Metrado Edificio de 4 Pisos

28
PARTIDA DESCRIPCIÓN UNID 1 TRABAJOS PRELIMINARES 1.1 Limpieza del terreno natural 1.2 Trazo, Replanteo y Nivelación 2 MOVIMIENTO DE TIERRAS 2.1 Excavaciones 2.1.1 Cimiento Corrido EJE A EJE B EJE 1 EJE 2 2.1.2 ZAPATAS Z1 2.2 RELLENOS (material propio) 2.2.1 Cimiento Corrido EJE A TRAMO 1 EJE A EJE B TRAMO 1 EJE B EJE 1 EJE 2 AREA 1 AREA 2 Z1 C1 C2 C3 C4 2.2 RELLENOS (material de préstamo) AREA 2.5 Eliminación de Material Excedente Volumen Eliminado = ( Volumen Excavado - Volumen de Relle ESPONJAMIENTO 25% Volumen Excavado = 26.77 Volumen Relleno material propio= 17.54 Esponjamiento = 25.00 m 3 m 3 m 3

Transcript of Metrado Edificio de 4 Pisos

Page 1: Metrado Edificio de 4 Pisos

PARTIDA DESCRIPCIÓN UNID CANT MEDIDAS

LARGO

1 TRABAJOS PRELIMINARES1.1 Limpieza del terreno natural 1 15.781.2 Trazo, Replanteo y Nivelación 1 15.782 MOVIMIENTO DE TIERRAS

2.1 Excavaciones2.1.1 Cimiento Corrido

EJE A 1 11.18EJE B 1 11.18EJE 1 1 7.1EJE 2 1 5.15

2.1.2 ZAPATASZ1 6 1.5

2.2 RELLENOS (material propio)

2.2.1 Cimiento CorridoEJE A TRAMO 1 1 5.18

EJE A 1 6EJE B TRAMO 1 1 5.18

EJE B 1 6EJE 1 1 7.1EJE 2 1 5.15

AREA 1 1 51.73AREA 2 1 4.55

Z1 6 1.5C1 6 0.5C2 5 0.25C3 1 0.25C4 1 0.15

2.2 RELLENOS (material de préstamo)AREA 1 79.0385

2.5 Eliminación de Material Excedente Volumen Eliminado = ( Volumen Excavado - Volumen de Relleno ) x ( 1 + % Esponjamiento)

ESPONJAMIENTO 25%

Volumen Excavado = 26.77

Volumen Relleno material propio= 17.54Esponjamiento = 25.00 %

m²m²

m3

m3

m3

m3

m3

Page 2: Metrado Edificio de 4 Pisos

MEDIDAS PARCIAL TOTALANCHO ALTO

7.10 112.04 112.047.10 112.04 112.04

26.77

20.770.6 1 6.710.6 1 6.710.6 1 4.260.6 1 3.09

6.001.2 1 6.00

17.54

17.540.35 0.1 0.18130.35 0.4 0.840.35 0.1 0.18130.35 0.4 0.840.6 0.1 0.426

0.35 0.4 0.72151.73 0.2 10.3464.55 0.1 0.455

1.2 0.4 4.320.5 0.4 0.6

0.25 0.4 0.1250.35 0.4 0.0350.2 0.4 0.012

7.9079.0385 0.1 7.90385

11.53

Page 3: Metrado Edificio de 4 Pisos

PARTIDA DESCRIPCIÓN UNID CANT

3.0 CONCRETO SIMPLE3.1 CIMIENTO CORRIDO 1:10 C:H + 30% P.G.

EJE A 1EJE B 1EJE 1 1EJE 2 1

3.3 FALSO PISO: e=0.1 mAREA 1

MUROS 1C1 6C2 5C3 1C4 1

3.4 SOBRECIMIENTO UNID CANTConcreto

S1 1Encofrado

S1 13.4 SOLADO (E=10 CM) UNID CANT

ZAPATAS m2Z1 6

4.0 CONCRETO ARMADO4.01 ZAPATAS UNID CANT

ConcretoZ1 6

DESCRIPCIÓN # n° varillas φ

Acero

Z1 8 6 1/2"10 16 1/2"

4.01 COLUMNAS f´c= 210 kg/cm²

5.6.1UNID CANT

Concreto Primer pisoC1 6C2 5

CONCRETO EN COLUMNAS EN PRIMER, SEGUNDO, TERCER Y CUARTO PISO

Page 4: Metrado Edificio de 4 Pisos

C3 1C4 1

Concreto Segundo Piso m³C1 6C2 0C3 0C4 0

5.6.1UNID CANT

Encofrado Primer Piso m²C1 6C2 5C3 1C4 1

Encofrado Segundo Piso m²C1 6C2 0C3 0C4 0

DESCRIPCIÓN # n° varillas φ

Acero primer piso

C16 4 3/4"6 8 5/8"6 25 E3/8"

C25 3 1/2"5 3 1/2"5 25 E3/8"

C31 4 1/2"1 4 1/2"1 25 E3/8"

C41 2 1/2"1 2 1/2"1 25 E3/8"

DESCRIPCIÓN # n° varillas φ

Acero segundo piso

ENCOFRADO EN COLUMNAS EN PRIMER, SEGUNDO, TERCER Y CUARTO PISO

Page 5: Metrado Edificio de 4 Pisos

C16 4 3/4"6 8 5/8"6 25 E3/8"

C20 3 1/2"0 3 1/2"0 25 E3/8"

C30 4 1/2"0 4 1/2"0 25 E3/8"

C40 2 1/2"0 2 1/2"0 25 E3/8"

4.7. VIGAS f´c= 210 kg/cm²

CONCRETO ENVIGAS DE PRIMER, SEGUNDO, TERCER Y CUARTO PISO UNID CANTConcreto Primer piso

VA (.25 X .25)-EJE A 1VA (.25 X .25)-EJE B 1VA (.25 X .25)-EJE 1 1VS (.25x.35) - EJE A 1VS (.25x.35) - EJE B 1VP (.30x.50) - EJE 2 1VP (.30x.50) - EJE 3 1VP (.30x.50) - EJE 4 1

Concreto Segundo PisoVA (.25 X .25)-EJE A 0VA (.25 X .25)-EJE B 0VA (.25 X .25)-EJE 1 0VS (.25x.35) - EJE A 1VS (.25x.35) - EJE B 1VP (.30x.50) - EJE 2 1VP (.30x.50) - EJE 3 1VP (.30x.50) - EJE 4 1

5.6.1 ENCOFRADO EN VIGAS EN PRIMER, SEGUNDO, TERCER Y CUARTO PISOUNID CANT

Encofrado Primer PisoVA (.25 X .25)-EJE A 1VA (.25 X .25)-EJE B 1VA (.25 X .25)-EJE 1 1VS (.25x.35) - EJE A 1VS (.25x.35) - EJE B 1VP (.30x.50) - EJE 2 1VP (.30x.50) - EJE 3 1VP (.30x.50) - EJE 4 1

Encofrado Segundo PisoVA (.25 X .25)-EJE A 0

Page 6: Metrado Edificio de 4 Pisos

VA (.25 X .25)-EJE B 0VA (.25 X .25)-EJE 1 0VS (.25x.35) - EJE A 1VS (.25x.35) - EJE B 1VP (.30x.50) - EJE 2 1VP (.30x.50) - EJE 3 1VP (.30x.50) - EJE 4 1

DESCRIPCIÓN # n° varillas φ

Acero primer piso

EJE A

1 2 1/2''

1 2 1/2''

1 2 1/2''

1 3 5/8''

1 3 5/8''

1 1 5/8''

1 40 EST-3/8''1 56 EST-3/8''

EJE B

1 2 1/2''

1 2 1/2''

1 2 1/2''

1 3 5/8''

1 3 5/8''

1 1 5/8''

1 40 EST-3/8''1 56 EST-3/8''

EJE 1

1 23/4''1 2

1 21 2

5/8''1 21 21 38 EST-3/8''

EJE 2

1 23/4''1 2

1 21 2

5/8''1 21 21 38 EST-3/8''

EJE 3

1 23/4''

Page 7: Metrado Edificio de 4 Pisos

EJE 3

1 2 3/4''

1 21 2

5/8''1 21 21 38 EST-3/8''

EJE 4

1 23/4''1 2

1 21 2

5/8''1 21 21 38 EST-3/8''

DESCRIPCIÓN # n° varillas φ

Acero Segundo piso

EJE A

0 2 1/2''

0 2 1/2''

0 2 1/2''

1 3 5/8''

1 3 5/8''

1 1 5/8''

0 40 EST-3/8''1 56 EST-3/8''

EJE B

0 2 1/2''

0 2 1/2''

0 2 1/2''

1 3 5/8''

1 3 5/8''

1 1 5/8''

0 40 EST-3/8''1 56 EST-3/8''

EJE 1

0 23/4''0 2

0 20 2

5/8''0 20 20 38 EST-3/8''

EJE 2

1 23/4''1 2

Page 8: Metrado Edificio de 4 Pisos

EJE 21 2

3/4''

1 25/8''1 2

1 21 38 EST-3/8''

EJE 3

1 23/4''1 2

1 21 2

5/8''1 21 21 38 EST-3/8''

EJE 4

1 23/4''1 2

1 21 2

5/8''1 21 21 38 EST-3/8''

4.7. LOSA ALIGERADA f´c= 210 kg/cm²CONCRETO EN LOSA UNID CANTConcreto Primer piso

AREA 1 17AREA 2 17

Concreto Segundo pisoAREA 1 17AREA 2 17

LADRILLOS EN LOSA UNIDLadrillos Primer piso Und

34Ladrillos Srgundo piso Und

34

ENCOFRADO EN LOSA UNIDEncofrado Primer Piso

LOSA Ext 2.000Encofrado Segundo Piso

LOSA Ext 2.000

DESCRIPCIÓN # n° varillas φ

Acero primer piso

EJE A y B 17 1 1/2''

Page 9: Metrado Edificio de 4 Pisos

EJE A y B17 1

1/2''

DESCRIPCIÓN # n° varillas φ

Acero segundo piso

EJE A y B 17 1 1/2''17 1

PARTIDA DESCRIPCIÓN UNID CANTMEDIDAS

AREA

1 MUROS Y TABIQUES DE ALBAÑILERIA Muro de Ladrillo KK Tipo IV (e= 25 cm) m2

Primer piso

EJE A 1

EJE B 1

EJE 2 1

Segundo piso - Cuarto piso

EJE A 1

EJE B 1

EJE 2 1

Page 10: Metrado Edificio de 4 Pisos

MEDIDAS PARCIAL TOTALLARGO ANCHO ALTO

16.6111.18 0.6 0.8 5.3711.18 0.6 0.8 5.37

7.1 0.6 0.8 3.415.15 0.6 0.8 2.47

102.5915.78 7.10 112.0430.06 0.25 7.52

0.5 0.5 1.500.25 0.25 0.310.25 0.35 0.090.15 0.2 0.03

LARGO ANCHO ALTO PARCIAL TOTAL5.26

30.06 0.25 0.7 5.2636.072

30.06 1.2 36.07LARGO ANCHO ALTO PARCIAL TOTAL

10.801.5 1.2 10.80

LARGO ANCHO ALTO PARCIAL TOTAL6.48

1.5 1.2 0.6 6.48

LONGITUD PARCIALTOTAL (ml)

1/4'' 3/8'' 1/2'' 5/8'' 3/4''0.000 0.000 265.800 0.000 0.000

TOTAL (kg)1/4'' 3/8'' 1/2'' 5/8'' 3/4''

0.25 0.56 0.99 1.55 2.240 0 263.142 0 0

1.5 721.2 192

COLUMNAS f´c= 210 kg/cm²

LARGO ANCHO ALTO PARCIAL11.0957.044

0.5 0.5 3.65 5.480.25 0.25 3.65 1.14

Page 11: Metrado Edificio de 4 Pisos

0.25 0.35 3.65 0.320.15 0.2 3.65 0.11

4.0500.5 0.5 2.7 4.05

0.25 0.25 2.7 0.000.25 0.35 2.7 0.000.15 0.2 2.7 0.00

LARGO ANCHO ALTO PARCIAL 97.605

65.2052 3.45 41.401 3.45 17.25

1.2 3.45 4.140.7 3.45 2.42

32.4002 2.7 32.401 2.7 0.00

1.2 2.7 0.000.7 2.7 0.00

LONGITUD PARCIALTOTAL (ml)

1/4'' 3/8'' 1/2'' 5/8'' 3/4''0.000 405.000 176.400 201.600 100.800

TOTAL (kg)

1/4'' 3/8'' 1/2'' 5/8'' 3/4''

0.25 0.56 0.99 1.55 2.240 226.8 174.636 312.48 225.792

4.2 100.80 | 369.6 174.636 550.56 397.8244.2 201.601.7 255.004.2 63.004.2 63.00

0.85 106.254.2 16.804.2 16.801.1 27.504.2 8.404.2 8.40

0.65 16.25

LONGITUD PARCIALTOTAL (ml)

1/4'' 3/8'' 1/2'' 5/8'' 3/4''0.000 255.000 0.000 153.600 76.800

TOTAL (kg)1/4'' 3/8'' 1/2'' 5/8'' 3/4''

0.25 0.56 0.99 1.55 2.240 142.8 0 238.08 172.032

Page 12: Metrado Edificio de 4 Pisos

3.2 76.803.2 153.601.7 255.003.2 0.003.2 0.00

0.85 0.003.2 0.003.2 0.001.1 0.003.2 0.003.2 0.00

0.65 0.00

LARGO ANCHO ALTO PARCIAL9.390

5.2455.8 0.25 0.25 0.365.8 0.25 0.25 0.366 0.25 0.25 0.388 0.25 0.35 0.708 0.25 0.35 0.70

6.1 0.3 0.50 0.916.1 0.3 0.50 0.916.1 0.3 0.50 0.91

4.1455.8 0.25 0.25 0.005.8 0.25 0.25 0.006 0.25 0.25 0.008 0.25 0.35 0.708 0.25 0.35 0.70

6.1 0.3 0.50 0.916.1 0.3 0.50 0.916.1 0.3 0.50 0.91

LARGO ANCHO ALTO PARCIAL 77.460

45.3305.8 0.25 0.50 4.355.8 0.25 0.50 4.356 0.25 0.50 4.508 0.25 0.50 6.008 0.25 0.50 6.00

6.1 0.3 0.80 6.716.1 0.3 0.80 6.716.1 0.3 0.80 6.71

32.1305.8 0.25 0.50 0.00

Page 13: Metrado Edificio de 4 Pisos

5.8 0.25 0.50 0.006 0.25 0.50 0.008 0.25 0.50 6.008 0.25 0.50 6.00

6.1 0.3 0.80 6.716.1 0.3 0.80 6.716.1 0.3 0.80 6.71

LONGITUD PARCIALTOTAL (ml)

1/4'' 3/8'' 1/2'' 5/8'' 3/4''0.000 407.600 89.160 241.500 167.200

TOTAL (kg)

1/4'' 3/8'' 1/2'' 5/8'' 3/4''

0.25 0.56 0.99 1.55 2.240 228.256 88.2684 374.325 374.528

6.51 13.02 0 389.816 88.2684 701.84 655.4246.76 13.529.02 18.049.25 27.759.55 28.653.95 3.950.80 32.001.10 61.606.51 13.026.76 13.529.02 18.049.25 27.759.55 28.653.95 3.950.80 32.001.10 61.607.20 14.406.55 13.107.15 14.307.15 14.303.95 7.904.00 8.001.45 55.107.20 14.406.55 13.107.15 14.307.15 14.303.95 7.904.00 8.001.45 55.107.20 14.40

Page 14: Metrado Edificio de 4 Pisos

6.55 13.107.15 14.307.15 14.303.95 7.904.00 8.001.45 55.107.20 14.406.55 13.107.15 14.307.15 14.303.95 7.904.00 8.001.45 55.10

LONGITUD PARCIALTOTAL (ml)

1/4'' 3/8'' 1/2'' 5/8'' 3/4''0.000 288.500 0.000 211.300 125.400

TOTAL (kg)

1/4'' 3/8'' 1/2'' 5/8'' 3/4''

0.25 0.56 0.99 1.55 2.240 161.56 0 327.515 280.896

6.51 0.006.76 0.009.02 0.009.25 27.759.55 28.653.95 3.950.80 0.001.10 61.606.51 0.006.76 0.009.02 0.009.25 27.759.55 28.653.95 3.950.80 0.001.10 61.607.20 0.006.55 0.007.15 0.007.15 0.003.95 0.004.00 0.001.45 0.007.20 14.406.55 13.10

Page 15: Metrado Edificio de 4 Pisos

7.15 14.307.15 14.303.95 7.904.00 8.001.45 55.107.20 14.406.55 13.107.15 14.307.15 14.303.95 7.904.00 8.001.45 55.107.20 14.406.55 13.107.15 14.307.15 14.303.95 7.904.00 8.001.45 55.10

LARGO ANCHO ALTO PARCIAL 6.732

3.3664.2 0.4 0.15 1.684.2 0.4 0.15 1.68

3.3664.2 0.4 0.15 1.684.2 0.4 0.15 1.68

952.000

476.0004.2 0.3 476.00

476.0004.2 0.3 476.00

110.88

55.4404.20 6.6 55.44

55.4404.20 6.6 55.44

LONGITUD PARCIALTOTAL (ml)

1/4'' 3/8'' 1/2'' 5/8'' 3/4''0.000 0.000 243.100 0.000 0.000

TOTAL (kg)

1/4'' 3/8'' 1/2'' 5/8'' 3/4''

0.25 0.56 0.99 1.55 2.240 0 240.669 0 0

5.15 87.55

Page 16: Metrado Edificio de 4 Pisos

9.15 155.55

LONGITUD PARCIALTOTAL (ml)

1/4'' 3/8'' 1/2'' 5/8'' 3/4''0.000 0.000 243.100 0.000 0.000

TOTAL (kg)

1/4'' 3/8'' 1/2'' 5/8'' 3/4''

0.25 0.56 0.99 1.55 2.240 0 240.669 0 0

5.15 87.559.15 155.55

MEDIDASPARCIAL TOTAL

LARGO ANCHO ALTO

150.300

75.150

13.78 2.5 34.45

13.78 2.5 34.45

2.5 2.5 6.25

75.150

13.78 2.5 34.45

13.78 2.5 34.45

2.5 2.5 6.25

Page 17: Metrado Edificio de 4 Pisos

PARTIDA N° ESPECIFICACIONES

01.00 SALIDAS PARA CONDUCTORES01.01.00 Salida Centro de Luz

Primer pisoSegundo piso

01.02.00 Salida para Tomacorrientes Bipolartes SimplesPrimer pisoSegundo piso

01.03.00 Salida para Tomacorrientes a prueba de aguaPrimer pisoSegundo piso

01.04.00 Salida para interruptor simplePrimer pisoSegundo piso

01.05.00 Salida para interruptor doblePrimer pisoSegundo piso

01.06.00 Salida para interruptor de conmutaciónPrimer pisoSegundo piso

02.00 SALIDA PARA COMUNICACIONES Y SEÑALES02.01 Salida de Telefono

Primer pisoSegundo pisoTercer pisoCuarto pisoAzotea

02.02 Salida de TV cablePrimer pisoSegundo pisoTercer pisoCuarto pisoAzotea

02.03 Salida para Intercomunicador Primer pisoSegundo pisoTercer pisoCuarto pisoAzotea

03.00 CANALIZACIONES Y/O TUBERIAS03.01 Tuberia Electrica PVC SEL 2"

Primer pisoMontante de cableMontante de telefonoMontante de intercomunicadorSegundo piso

Page 18: Metrado Edificio de 4 Pisos

Montante de cableMontante de telefonoMontante de intercomunicadorTercer pisoMontante de cableMontante de telefonoMontante de intercomunicadorCuarto pisoMontante de cableMontante de telefonoMontante de intercomunicador

03.02 Tuberia Electrica PVC SEL 3/4"Primer pisoTomacorrienteIntercomunicadorTeléfonoTVAlumbrado generalSegundo pisoTomacorrienteIntercomunicadorTeléfonoTVAlumbrado general

04.00 CONDUCTORES Y/O CABLES04.01 Cable 2-1 x 4 mm2 TW

Primer pisoTomacorrienteSegundo pisoTomacorrienteIluminacion escalera y áreas libres

04.02 Cable 2-1 x 2.5 mm2 TWPrimer pisoIluminacionIntercomunicadorSegundo pisoIluminacionIntercomunicador

04.03 Cable 2 x 16 mm2 TW + 1x 10mm2Primer pisoSegundo piso

05.00 CAJAS DE PASO05.01 Caja de paso con tapa ciega

Primer pisoSegundo piso

05.02 Caja de pase cuadrada metálicaPrimer pisoSegundo piso

Page 19: Metrado Edificio de 4 Pisos

06.00 TABLERO DE DISTRIBUCION06.01 Tablero de distribución general

Primer piso06.01 Subtablero de distribucion

Primer pisoSegundo pisoTercer pisoCuarto pisoAzotea

07.00 INTERRUPTORES THERMOMAGNETICOS07.01 Interruptor Thermomagnetico Monofasica 2x30A

Primer pisoSegundo pisoTercer pisoCuarto pisoAzotea

07.03 Interruptor Thermomagnetico Monofasica 2x20APrimer pisoSegundo pisoTercer pisoCuarto pisoAzotea

07.03 Interruptor Thermomagnetico Monofasica 2x15APrimer pisoSegundo pisoTercer pisoCuarto piso

08.00 SISTEMA DE POZO A TIERRA08.01 Pozo conexión a Tierra

09.00 ARTEFACTOS DE ILUMINACIÓN09.01.00 Equipo de luminarias

Primer pisoSegundo piso

Page 20: Metrado Edificio de 4 Pisos

UNDN° VECES MEDIDAS PARCIAL

TOTALLARGO PUNTO PZA/UND

pto 14pto 1 7 7pto 1 7 7pto 14pto 1 7 7pto 1 7 7pto 2pto 1 1 1pto 1 1 1pto 2pto 1 1 1pto 1 1 1pto 0pto 1 0 0pto 1 0 0pto 4pto 1 2 2pto 1 2 2

1pto 4pto 1 1 1pto 1 1 1pto 1 1 1pto 1 1 1pto 1 0 0pto 16pto 1 4 4pto 1 4 4pto 1 4 4pto 1 4 4pto 1 0 0pto 4pto 1 1 1pto 1 1 1pto 1 1 1pto 1 1 1pto 1 0 0

ml 32.4ml 8.1

1 2.7 2.71 2.7 2.71 2.7 2.7

ml 8.1

Page 21: Metrado Edificio de 4 Pisos

1 2.7 2.71 2.7 2.71 2.7 2.7

ml 8.11 2.7 2.71 2.7 2.71 2.7 2.7

ml 8.11 2.7 2.71 2.7 2.71 2.7 2.7

ml 94.54ml 47.27

1 23.37 23.371 01 01 01 23.9 23.9

ml 47.271 23.37 23.371 01 01 01 23.9 23.91

ml #REF!ml 23.37

1 23.37 23.37ml #REF!

1 23.37 23.371 #REF! #REF!

ml #REF!ml #REF!

1 #REF! #REF!1 0 0

ml #REF!1 #REF! #REF!1 0 0

ml 29.6ml 1 24ml 1 5.6 5.6

und 2und 1 1 1und 1 1 1und 11und 1 4 4und 1 7 7

Page 22: Metrado Edificio de 4 Pisos

1pza 1pza 1 1 1pza 5pza 1 1 1pza 1 1 1pza 1 1 1pza 1 1 1pza 1 1 1

1pza 6pza 1 2 2pza 1 1 1pza 1 1 1pza 1 1 1pza 1 1 1pza 20pza 1 5 5pza 1 4 4pza 1 4 4pza 1 4 4pza 1 3 3pza 8pza 1 2 2pza 1 2 2pza 1 2 2pza 1 2 2

glb 1 1 1

und 24und 1 13 13und 1 11 11