Recommendation for Block Cipher Modes of Operation: Methods for ...
Methods of Block Working
-
Upload
paul-durai -
Category
Documents
-
view
217 -
download
0
Transcript of Methods of Block Working
-
8/14/2019 Methods of Block Working
1/19
Basics of Signalling
Methods of Block Working
-
8/14/2019 Methods of Block Working
2/19
Key Statistics
Route Kms : 63,028
Number of Stations : 6,853
Passenger Kms : 457,022m
Tonne Kms : 312,371m
Employees : 1,545.3m Revenue :Rs. 348,805m
Expenditure :Rs. 346,673m
Up-to 31.3.2001
-
8/14/2019 Methods of Block Working
3/19
Systems of working
Chapter VII of GR describes the Systems of
working.
Systems of working: The Absolute Block System,
The Automatic Block System,
The Following Trains System,
The Pilot Guard System,
The Train-staff and Ticket System, and
The One Train Only System.
-
8/14/2019 Methods of Block Working
4/19
Systems of working
The Following Trains System
Trains are despatched from one station to the next in
succession in the same direction on the same line, witha time interval
Station Master of next station will ensure that no train
leaves his station towards the station in rear until all
trains have reached his station and a fresh Direction of
Traffic has been esteblished
All trains should run at the same speed not exceeding
25 kmph
-
8/14/2019 Methods of Block Working
5/19
Systems of working
The Pilot Guard System
Trains are piloted by the Pilot Guard who shall travel
on the foot plate of the EngineNo train shall leave a stationwithout the Pilot Guard
All trains should run at the same speed not exceeding
25 kmph and with a time interval of minimum 15
minutes
-
8/14/2019 Methods of Block Working
6/19
Systems of working
The Train-Staff and Ticket System
Trains may be worked under this system between two
stations a single Train-Staff shall be kept at one of the stations
Train shall not start from a station unless the Train-
Staff has been handed over or shown to the driver
Driver must be in possession of either Train-Staff orTrain-Staff Ticket
All trains should run at the same speed not exceeding
25 kmph and with a time interval of minimum 15
minutes
-
8/14/2019 Methods of Block Working
7/19
Systems of working
The One Train Only System
Trains may be worked under this system on short
terminal branch lines on single line Only one Train shall work in the section, at any time
If the train becomes disabled and requires assistance,
the same will be arranged by the Station Master of the
Base Station, after observing laid down precautions Guard of the disabled train will be responsible for safe
working till normal working is restored
-
8/14/2019 Methods of Block Working
8/19
The Absolute Block System
Essentials:
No train shall leave a Block Station unless LC has
been received from Block Station in advance
On double line, such LC shall not be given unless
the last preceding train has arrived complete and
signals have been put back to on behind the said train line is clear up-to FSS plus adequate distance
-
8/14/2019 Methods of Block Working
9/19
The Absolute Block System
Essentials:
On single line, such LC shall not be given unless
the last preceding train has arrived complete and
signals have been put back to on behind the said train
line is clear up-to FSS plus adequate distance AND it is clear of trains running towards the station to
which LC is being given.
-
8/14/2019 Methods of Block Working
10/19
The Absolute Block System
Block Section
Stn A Stn B
Overlap
-
8/14/2019 Methods of Block Working
11/19
The Absolute Block System
Points to remember:
Adequate distance is 400m for 2 aspect signals &
180m for multi aspect signalsArrival of whole train is manually checked by
verifying Tail Board / Lamp and exchange of
Alright signal with Guard. It can also be done by
Axle Counters or track circuits.
Putting back of signals and clearance of overlap is
checked by circuits
-
8/14/2019 Methods of Block Working
12/19
The Automatic Block System
Essntials for double line:
Line must be continuously track circuited
Line between stations is divided into Automatic
Block Signalling Sections
Entry into each Section is controlled by MACL
stop signals
Track Circuits control the aspect of signals OFF aspect only when line is clear up-to next signal
plus overlap (120 m)
Automatic replacement to ON with passage of train
-
8/14/2019 Methods of Block Working
13/19
The Automatic Block System
Essntials for single line:
Line must be continuously track circuited
Direction of traffic only after LC has been
obtained from stn in advance
Train to start from the stn only after direction of
traffic has been esteblishedLC shall not be granted unless line is clear up-
to FSS plus overlap (180m)
-
8/14/2019 Methods of Block Working
14/19
The Automatic Block System
Essntials for single line:
Line between stations is divided into Automatic
Block Signalling SectionsEntry into each Section is controlled by MACL
stop signals in the direction of traffic
Signals against the direction of traffic at ONTrack Circuits control the aspect of signals
OFF aspect only when line is clear up-to next signal
If next signal is manual, then overlap (180m) is also
required
-
8/14/2019 Methods of Block Working
15/19
The Automatic Block System
Aspect Control: Yellow when one signalling section plus overlap is
clear Green when two signalling sections plus overlap is
clear (in 3 aspect territory)
Double Yellow when two signalling sections plus
overlap is clear (in 4 aspect territory) Green when 3 signalling sections plus overlap is
clear (in 4 aspect territory)
3 Aspect Signals 4 Aspect Signals
http://c/My%20Documents/acosoa1111.exehttp://c/My%20Documents/Acosoa22.exehttp://c/My%20Documents/Acosoa22.exehttp://c/My%20Documents/acosoa1111.exe -
8/14/2019 Methods of Block Working
16/19
The Automatic Block System
Minimum equipment of signals
Manual stop signals at stations
a Home
a Starter
an Automatic stop signal in rear of Home signal
of the station one or more additional auto signals in
between block stations
-
8/14/2019 Methods of Block Working
17/19
The Automatic Block System
Conditions for taking OFF manual signals
in auto territories:
Home signal except at terminal station Line to be clear upto Starter plus overlap (120m)
Last stop signal
Direction of Traffic has been esteblished Line is clear upto next signal (automatic) or
Line is clear upto next signal (manual) plus overlap
(180m)
-
8/14/2019 Methods of Block Working
18/19
The Automatic Block System
What happens if an Automatic signal isdefective:Signal can be at ON due to TC failure or some
other defectDriver should stop and wait in rear of signal one minute during DAY
Two minutes during NIGHT
If signal remains ON, inform Guard by whistlecode & hand signal and proceed at restrictedspeed (15 kmph or less) till he reaches the nextsignal
Then be guided by the aspect of next signal
-
8/14/2019 Methods of Block Working
19/19
The Automatic Block System
Points to remember:
Track is continuously track circuited
Signals diplay Off aspect normally when there
are no trains
Signals are replaced automatically to On with
the passage of trains past themDrivers are authorised to pass automatic signals
after observing certain precautions