Method Statement
&
Risk Assessment
Project Name: CRAIGENDORAN RISING MAIN
Location of the Works:
CRAIGENDORAN, HELENSBURGH.
Title of method statement:
ENVIRONMENTAL PROTECTION PROCEDURES DURING PIPE LAYING AT CRAIGENDORAN RISING MAIN.
Scope of works The task involves the installation of HDPE Rising Main and includes the following works:
Re-Fuelling.
Fuel Storage.
Plant Precaution.
De-Watering Procedures.
Reference: Date: 01-04-2016
Prepared By: D Fall Rev: 00
![Page 2: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/2.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 2 of 17
1. Record of revisions/additions
Rev: Date: 01 - 04 - 2016 Details of revision:
00 Original Document
2. Parties to the Contract
Client: Scottish Water
PSDP: ABV
Principal Contractor: Cleantech Civils
Contractor
Sub-Contractor
Site Management
Name Company Job Title Contact
Killian Smith Cleantech Civils Contracts Director
Darren Fall Cleantech Civils Contracts Manager
Teresa Mylott Cleantech Civils EHS Manager
Paul Cusack Cleantech Civils Site Foreman
Site Engineer
3. Personnel Protective Equipment Required:
Name any other:
Hi-Viz Vest/Jacket
Safety Boots
Hard Hat Cover Alls
Safety Gloves
Hearing Protection
Eye Protection
Respiratory Protection
No rigger
boots allowed
Task
Dependent
Task
dependent
Task
dependent
Task
dependent
4. Labour Requirements:
3 x General Operative (trained DD operators)
Site Foreman (With CAT & JENNY
Engineer
1 x Dumper Driver
3 x Machine Driver
1 x Trained Butt Fusion & Electrofusion Welder
5. Plant & Equipment Required:
Safety Barriers
3 x 360 Excavator
1 x Submersible Pump & Generator
Traffic management equipment (barriers; signs; cones; etc…)
1 x Plate Compactor
Goal posts & bunting
1 x Track dumper
Cat & Jenny
1 x Road Saw
Butt Fusion Welder
Vacuum Pipe Lifter
6. Training
CPCS Training
Appropriate CPCS Training for operating the required plant
CAT & Jenny Sigma Training Street Works Training TM installers
Manual Handling Training Full Driving Licences
Abrasive wheel training
7. Permits
Permit to Dig Road Opening Licence
![Page 3: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/3.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 3 of 17
![Page 4: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/4.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 4 of 17
8. COSSH & Chemicals
Concrete
Diesel
Petrol
Plasticiser
Plant oils and lubricants
9. Emergency Procedures
First Aiders: Paul Cusack Location of First Aid Box: Site Office; Mobile Welfare Units & Vans Location Of the nearest hospital: The Victoria Infermatory, Helensburgh. Location of Fire Extinguishers: Site Office; vehicles & excavators Location Of Assembly Point: Site Works Entrance Emergency Site Evacuation: In the event of a fire/site evacuation, alarm area will be sounded. Upon hearing the alarm, all persons are to stop work immediately and assemble at the assembly point at the works entrance.
Excavation collapse:
The person discovering the incident must raise the alarm.
Contact First Aiders (if necessary), and members of the Site Safety, Health & Environmental Team, or a member of Site Management by mobile phone or in person to raise the alarm.
Give clear and concise information on the nature and location of the incident and other relevant details (e.g. injuries sustained/buried personnel).
Under no circumstances is the person discovering the incident to risk his/her own personal safety by attempting to deal with the situation alone. If trained/competent help is in the area and there are trapped/injured personnel requiring immediate attention/rescue and it is safe to do so, then help may be given until members of the emergency response team arrive or the emergency services.
In the event of a trench collapse where no injuries are involved, necessary remedial works may be carried out to make the area safe but only with authorisation from Site Management Team
In consultation, with the Site Manager, the nature, location and level of the Emergency will be defined.
Emergency Services shall be notified (if required)
General Operative may be assigned to prevent any unauthorised access by other site personnel into the area of the incident (if required) until the Emergency Services arrive/the IP is secured and transferred to the compound/the incident scene is made safe.
The site personnel in the vicinity of the incident scene shall be evacuated from the immediate area and instructed to report to the site assembly point (if necessary).
The Site Manager or delegate performs a roll call in conjunction to ensure all personnel are present and accounted for.
No unauthorised personnel will be allowed enter the area while remedial works/rescue operation is taking place.
Any vehicles obstructing emergency access to be removed.
A member of the site emergency response team will be allocated at the site entrance to meet the emergency services upon their arrival on site and direct them to the incident scene (if required).
Upon arrival at the scene the emergency services will be briefed and they will take control of the incident scene.
All resources available on site will be at the disposal of the emergency services.
The incident is investigated and those actions deemed appropriate by CLEANTECH HSE Management
Electrical Emergencies {Electric Shock or Contact with Electricity}
When the alarm is raised. Staff will call the emergency services. (Phone number 999 or 112) to notify fire brigade and ambulance if appropriate, and give details and location of the accident / Incident. o The machine driver should be instructed to stay in the cab of the machine and to not touch any part of the
machine. o If you come across an incident in which you suspect that a victim has been electrocuted, never touch or
move the person. o If casualty is still in contact with the cable, use something rubber to break the connection between the
casualty and the live cable/wire.
![Page 5: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/5.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 5 of 17
The site manager will co-ordinate crowd control, they shall be helped in this task by any two General operatives as appointed by the site manager.
The site manager will arrange to have a General Operative wait at the site entrance so to direct the Emergency services to the site of the Accident / Incident.
The trained first aiders will assess the situation and will administer first aid treatment if required he/she will also co-ordinate if necessary the rescue operations and will establish the details of injury etc.
When the emergency services arrive they will take over co-ordination of the rescue aided by the First Aiders.
The site manager will contact the casualty’s next of kin.
The emergency coordinator will appoint a person to go to the hospital if a casualty or casualties are taken there and will keep the Site Manager informed.
The site manager will contact the next of kin.
The site manager will inform Head office immediately of the situation.
The area is to be cordoned off until the investigation has been completed.
![Page 6: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/6.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 6 of 17
10. Methodology
Pre-start 1. Permit to Dig Register & Permits in place prior to any ground penetration, Ground surveyed by a CAT 5 &
trained Sigma Permit authoriser communicated to operators & services clearly marked on the ground 2. Assume all lines and services are live. 3. All site personnel entering site will receive a site specific induction, all necessary paperwork will be
completed such as manual handling training records, CPCS and CPCS or equivalent and will be recorded on site.
4. All site specific rules must be adhered to by all operatives at all times including wearing the mandatory PPE (hard-hat, high-vis vest, steel-toe cap boots).
5. Prior to construction works beginning all necessary control measures will be put in place to safe guard the health & safety of all employees of Cleantech Construction, and members of the public.
6. Leave emergency equipment (First Aid, Extinguisher, Spill Kit) out near the works area ensure that a copy of the emergency procedures plan is on site and located in a known location
7. Site Supervisor to ensure that everybody is completely aware of the scope of works and have read this method statement and are familiar with the reporting and emergency procedures
8. All supporting documentation should be read prior to works i.e. Method Statement, JSSP, Construction Drawings etc.
9. Erect all necessary signage to serve notification that construction work, particularly excavation work is in progress in accordance with chapter 8
10. Ensure safe access is provided to the work area; keep all public areas free of obstructions. 11. Drawings must be present on site for all utilities including electrical; telecom; fibre optic; water & foul.
Machinery required for works under overhead services shall be height restricted – equipment with potential to exceed 8metre in height. Excavator shall be restricted by raising of jib to permitted height, key on control system switched on to engage the height limiter on the machine.
10.1. Initial Stage
1. All on site must complete CLEANTECH site safety induction.
2. Works to be supervised by CLEANTECH site management.
3. All operatives to have read and signed this Method Statement
4. All underground services to marked and depths determined. Route of the proposed excavation to be determined
5. Reflective Signage will be erected on the approaches to the works in accordance with street works to an approved traffic management plan. The Traffic Management plan; barriers; cones; signs; traffic signals is put in place by a competent traffic management company. A safety at road works operator will be present at the works zone at all times. All traffic management equipment will be in accordance with street works. Formal inspections of the traffic management plan is carried out twice daily.
6. Prior to excavating a permit to dig will be completed by the Approved Permit Authoriser and signed off by the excavator drivers and ground workers; excavation controls with respect to underground services are as follows:
Obtain up to date exiting services drawings;
The area is surveyed by a trained sigma location of underground services permit authoriser using a calibrated Cat 4 +Cat & Genny Locator.
Any existing services identified, appropriate depths ascertained and marked on drawings
Information communicated to operatives via the permit to dig form.
Hand digging to take place close to services
Special care is taken when using picks & crow-bars; they must be of nonconductive material
Hand-tools are used within 0.5 m of a buried service
Services are never used as hand or foot holds & are supported if exposed. Extreme care is taken if joints are exposed.
An emergency plan is in place should any damage occur to an underground service. Approved code of practice for avoiding underground services and avoid danger from overhead services is adhered to at all times
7. Goal posts bunting and signage erected where necessary.
10.2. Protection of the Environment during the works laying the 710mm Pipe in Craigendoran
![Page 7: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/7.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 7 of 17
8. All fuel containers to be marked up and stored on a bunded area in a locked container.
9. All small plant and stationary equipment to be placed on plant nappies at all times.
10. Spill Kits are to be made available in designated areas of the site and their locations highlighted with signage and details of the location included in the site induction.
11. All fuel for the plant to be stored in a double skinned bunded fuel bowser and placed in a designated location in the site compound.
12. Fire extinguishers to be placed in areas of suitable access in close proximity to the fuel storage location.
13. The location of all extinguishers to be made available in designated areas of the site and their locations highlighted with signage and details of the location and correct usage to be included in the site inductions.
14. The re-fulling will take place at the designated fuel bowser location. The bowser will not be brought out to fuel the machines from its location and at no time shall the bowser be brought to the shore/Beach.
15. All items of plant to have biodegradable oil only. Plant operators will be provided with all necessary information for the correct use of plant containing biodegradable oil and details about the oil type will be included in the site inductions.
16. All plant will be provided with spill kits and checked regularly to ensure there is an adequate supply available.
17. As the works will be in tidal conditions, de-watering will not be effective when the water is in the immediate area of the works. Pipe laying can commence after the water has drained naturally from the area to be excavated.
18. Localised pumping may be required for areas of construction or pipe laying. A pump can only be used with the outfall hose connected into a plant nappy functioning as a settlement area and assist with the removal of hydrocarbons if present.
19. All Pumps will be seated on bunded plant nappies at all times.
20. A temporary settlement bund can be set up at the compound area for any dewatering requirements or with the assistance of concrete trucks and will be maintained at regular intervals as necessary.
21. All plant inspections will be made on a daily basis, any leaks or concerns will be brought to the managers attention and the plant will be excluded from any further works until repaired.
22. The inductions will include a dedicated section to protection of the surrounding environment and regular tool box talks will include information on environmental protection.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
![Page 8: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/8.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 8 of 17
44.
11. Environmental
1. Waste Management
A waste management plan will be prepared for the project and available at the site office for inspection
Waste shall be controlled and managed at all times
Waste shall be transferred by appropriately registered carriers and only removed to licensed sites
Wastes shall be kept in a secure manner, suitably contained and labeled
Hazardous wastes shall be kept separately and securely labeled containers for the task and disposed of in accordance with the Hazardous Waste Regulations
2. Waste minimization CLEANTECH shall endeavor to minimize waste streams in line with the principles of the waste hierarchy
Avoidance of waste at source
Reduction of waste volumes
Re-use of uncontaminated spoil within the works
Arrange for recycling of the waste
Disposal as a last option
3. Operations of vehicles and plant To ensure minimal impact from the operation of vehicles and plant, operators shall give due regard and implement the following
Minimize route and journey mileage to and from and around site
Prevent nuisance to the community caused by parking, spoil from vehicle movements, noise and access restrictions
Ensure prevention of spillage of spoil, fuels, coolants, hydraulic oils and other vehicle fuels
Maintain vehicles
Ensure all vehicles and machinery are turned off when not in use
Ensure suitable control for the means of access and egress to public highway
4. Noise and nuisance Care shall be taken by the CLEANTECH Civil Works to ensure good image and relations with the local community by the following
The use of offensive language, behavior and or discourtesy to the public prohibited
Excessive noise from plant, equipment, vehicles and employees being monitored
Strict compliance with noise and working hour restrictions
Excessive emissions of dust, fumes and odors
CLEANTECH will ensure a high standard of housekeeping and litter control on all sites at all times 5. Water Protection:
Fuels, oils, greases and hydraulic fluids must be stored in bunded compounds a minimum of 50m from the watercourse.
Excavators will be modified to operate with biodegradable hydraulic oil.
Diesel to be stored in double skinned tanks/diesel bowsers – refueling of plant to only take place if drip trays are in position
Refuelling of machinery will be carried out in bunded areas.
Runoff from machine service and concrete mixing areas must not enter the watercourse;
Stockpile areas for sands and gravel will be kept to a minimum size, 50m away from the watercourse;
Runoff from the above will only be routed to the watercourse via suitably designed and sited settlement
ponds/filter channels;
Settlement ponds should be inspected daily and maintained regularly;
Temporary crossings will be designed to the criteria laid down for permanent works;
Watercourse banks will be left intact if possible.
If they have to be disturbed, all practicable measures should be taken to prevent soils from entering the
watercourse.
![Page 9: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/9.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 9 of 17
12. Quality Controls
1. Work carried out in accordance with the specification documents.
2. Pipe welding test carried out in accordance with the specification
![Page 10: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/10.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 10 of 17
Risk Assessment Assessment Date: March 2016 Assessed by: Killian Smith Hazard No.
Task Hazard Identification and Foreseeable Risks
Risk Rating (Without Controls)
Control Measures Methods of Monitoring Control Measures
Risk Rating (with Controls)
1. Access /Egress
Unauthorised entry to site
Injury to public
Vehicle collision
High Banksman in place for any awkward reversing
Mandatory PPE worn
CLEANTECH induction complete
Driving with due care & attention
Adherence to site safety signage
Never block access and egress routes with materials and equipment
Site tidiness maintained by cleaning up during work, at end of day and(major) weekly to avoid slips and trips – Clean as you go.
No protruding nails allowed: all such nails must be clawed out or hammered flat so as to foot injuries
Routes delineated with barriers; barriers secured with sandbags where necessary
Excavations backfilled as soon as possible
Barriers erected around unattended excavations
Open excavations attended.
Access to the site must be controlled to ensure the safety of site employees and visitors.
Sign in sign out to take place
Ensure all plant is secured against unauthorised operation; removed the keys & prevent access to the cab
Checks by Supervisor
Low
3. Loading & Unloading
Falls from height
Crushing
High Safe lift plan in place for lifts by mobile crane.
Operator trained to the approved CPCS standard
Vehicles should never be overloaded. Loads should be evenly distributed, secured and not protruding beyond the sides or back of the vehicle.
Reverse beeper and flashing beacon fitted.
All guards and covers to be in position and secured.
Checks by supervisor GA3 inspections
Low
![Page 11: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/11.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 11 of 17
Windows, lights, mirrors and camera lens to be kept clean at all times.
The cab floor to be kept clean and free from any obstacles which may affect the safe operation of the Machine.
Ground workers to wear hi visibility vests at all times and hard-Hats.
Warning signs will be erected to alert pedestrians of Unloading/Loading Operations.
Ground workers to keep clear of plant at all times and not to approach until signalled to do so by the trained Operator while loading/unloading operations are underway.
All lifting equipment must be certified for its use and have proof of such inspections available to all supervisory staff. No work shall be carried out on site unless certification has been checked by Site Manager.
Loads to be tipped only on suitably level ground to prevent overturning.
All plant and equipment will be equipped with a Fire extinguisher.
Competent Garage Mechanics carry out servicing to plant as per the manufacturer’s instructions.
The use of mobile phones will be prohibited during lifting operations.
When mounting or dismounting the machine the handholds and steps must be used and must be maintained in safe condition.
Access roads will be damped down during fine weather periods to prevent dust from rising.
Where the operators direct field of vision is obstructed a banks man should be available to assist the operator, this person should be adequately trained.
4. Excavation of Trenches
Underground services - gas, electricity or water
Falling materials or plant
Falls of persons
Ingress of water
Collapse of sides
Weakening of adjacent structures
Noise
High
Ground conditions established by a survey to identify the type of ground in which the excavation is to be carried out; means of trench support confirmed upon completion of trial holes
Remember that even work in shallow trenches can be dangerous. You may need to provide support if the work involves bending or kneeling in the trench. No one should be in the trench unless it is safe to be there.
Where possible ensure that all water sources are turned off before entering an excavation
Do not go into unsupported excavations that have not being battered to a suitable slope. Never work ahead of the support.
Permit to Dig AF3 Checks by supervisor
Low
![Page 12: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/12.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 12 of 17
Do not store spoil or other materials close to the sides of excavations. The spoil may fall into the excavation and the extra loading will make the sides more prone to collapse
Contaminants removed following a suitable risk assessment and method statement
Employees and Management must ensure no-one enters an unsupported unsafe trench
Support materials on site before excavation starts. Plant and materials kept away from the side of excavations to prevent
undue pressure or ingress of exhaust fumes. if the depth is a particular risk of anybody falling, suitable guard-rails
placed and suitable access arrangements, such as ladders or ramps, provided
If there is a risk of water ingress, suitable methods and/or equipment provided to either prevent the entry of water or to remove water, e.g. water pumps
If plant could fall into the excavation, baulks or earth bunds should Where excavations are dug next to structures, suitable preventative
measures established in case of collapse, subsidence or damage Inspections of excavations carried out prior to each shift, after any
event likely to affect strength or stability be provided. Record of inspections recorded on approved form AF3 daily Suitable personal protective equipment [PPE] The location of electric cables, drains, gas and water mains etc. will be
determined and marked prior to the commencement work. Local ESB Networks staff to be consulted on underground services. Local authorities and, where necessary, scanning are to be used to determine service locations.
It will be the liability of the contractor to make good any damage done to such services during excavation work, to render them safe and secure without undue delay.
Excavations or openings will be properly sloped or shored at all times. A competent person must approve trench designs prior to entry. Warning lamps must be used during hours of darkness or low visibility.
Excavations or openings in floors must be properly fenced at all times. During excavation work the surrounding areas must be maintained in
an orderly and tidy condition.
![Page 13: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/13.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 13 of 17
Where vehicles have to tip materials into excavations, stop blocks can be used to prevent them from over-running. Remember that the sides of the excavation may need extra support.
Always work outside the reach of an excavator bucket. Where this is not possible, use safe systems of work to prevent people being struck. Do not stand directly under the bucket.
Safe means of access will be provided to excavations. Ladders will be in good condition, extend 1 metre above the excavation edge and be secured.
Heavy vehicles are to be kept away from the edge of an excavation. At no time should materials be stored along the edge of an excavation.
Flooded trenches should be "de-watered" as quickly as possible. Once emptied the trench is to be fully inspected prior to entry.
All personnel on sites, where work at heights is being carried out, will wear safety helmets.
Appropriate safety equipment will be used when necessary
5. Laying of Pipes,
Entrapment due to fall/ roll of pipe.
Operators direct field of vision obscured by load leading to contact with other persons or plant.
Failure of lifting equipment.
Inadequate supervision.
Untrained Operatives
Use of mobile phones by operators.
Displacement of load
Person being struck by suspended pipe causing serious injury of harm.
Defective and broken skids causing crushing of limbs of entrapment of body parts.
Manual Handling.
High Operator trained to the Approved CPCS standard as per the Construction Regulations.
Vehicles should never be overloaded. Loads should be evenly distributed, secured and not protruding beyond the sides or back of the vehicle.
Reverse beeper, flashing beacon, CCTV and or mirrors fitted
Defective skids removed immediately from the line.
Heavy duty gloves to be worn by operatives handling skids.
All engines guards and covers to be in position and secured.
Windows, lights, mirrors and camera lens to be kept clean at all times
The cab floor to be kept clean and free from any obstacles which may affect the safe operation of the Machine.
Ground workers to wear Hi Visibility Vests at all times and Hard-Hats.
Warning signs will be erected to alert pedestrians of Unloading/Loading Operations.
Traffic management must be in place where loading/unloading is being carried out on public roads.
Loads to be tipped only on suitably level ground to prevent overturning of skip.
Permit to Dig AF3 Checks by supervisor
Low
6. Work at Height
Fall of a person a distance liable of causing personal injury
High Take into accounts the principles of prevention when working at heights.
Work at height must be adequately planned and supervised
GA3 Checks by supervisor
Low
![Page 14: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/14.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 14 of 17
Falls of persons off the edge of structures
Collective fall protection measures must be given priority –
Trench boxes must have guard and mid rails.
Inspections on equipment carried out (i.e., crowd control barriers, harnesses, fall arrest devices etc)
Safe means of access to the work location provided using ladders
7. Manual Handling
Ligament strains. Muscle strains.
Fatigue.
Abdominal hernias. Prolapsed/herniated discs.
Paralysis.
Medium Full training and instruction provided in both induction and on- going safety training.
Design out the need for manual handling where possible
Mechanical aids used wherever possible
Workers adhere to guideline weights & to only lift what they are able to lift
Assess the load
Weights marked on all loads.
Lift smaller loads.
Cutting pipes to length
Mandatory PPE worn
Checks By Supervisor
Low
8. Unauthorised Access
Personal injury High Unauthorised entry to the working area to be reported to site management.
All barriers to be replaced to secure access
Checks By Supervisor
Low
9. Vehicle Fuels & chemicals & Dust
Fire
Explosion
Unintended release / spills
Environmental Pollution
High COSSH assessments complete and communicated to workers
Appropriate PPE worn
Ensure employees have a spill kit available and know how to use it.
Fuels stored in safe locations, away from sunlight and in a secure location
Water suppression used
Dust masks worn
Face fit testing complete
Checks By Supervisor
Low
10. Slips, Trips & Falls
Cuts and bruises
Laceration
Serious bodily injury
High Workplace tidiness maintained by cleaning up during work, at end of day to avoid slips and trips – Clean as you go.
Vigilance from employees as to the dangers from slips trips and falls.
Checks By Supervisor
Low
11. Working on or near roads,
Collision with plant or traffic
Traffic Accidents.
Inadequate Traffic Management Arrangements
Misleading signs
Close proximity of the public.
Collision with plant or traffic
Traffic management plan in accordance with chapter 8
Correct signing/coning/barriers in place for all roadwork’s and path works; including site entrance signage
Competent contractors implementing the TMP
Employees operating stop/go batten or maintaining the system to have safety at roadwork’s training
Longitudinal & size safety zones in place
General checks
by supervisors.
Recorded traffic management inspections
Low
![Page 15: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/15.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 15 of 17
Traffic Accidents.
Inadequate Traffic Management Arrangements
Misleading signs
Close proximity of the public
Tapering in accordance with chapter 8
Class 3 hi-vis worn by TM installers
Signs in place in accordance with chapter 8 & made stable by sandbags
Consultation to occur with the local authority; appropriate permits obtained & appropriate controls implemented
Safe access and egress for vehicles, plant and persons
Safe crossing of traffic lanes.
Traffic management equipment maintained clean
Traffic control supervisor appointed who inspects traffic management arrangements twice daily
All delivery drivers to adhere to the rules of the road.
Hard hats; Hi-visibility clothing & steel toe capped boots must be worn at all times
Safe access for vehicles, plant and persons
Safe crossing of traffic lanes by site workers
Employees set out signs before moving onto work site.
Trained employees, measure out the distance for the roadwork’s ahead signs/flashing warning signs as per traffic management plan, place signs on left hand side.
Trained employees, work back towards the site, placing signs as necessary.
All employees always stay on the verge if possible
Where there is two way traffic, repeat the procedure for traffic going in the opposite direction.
If portable traffic lights are to be used, Trained employees start using them before going in the opposite direction with signage & cones
Employees cone off the works area, always face the traffic when setting out cones for the lead in taper and always start from the verge.
Trained employees set up End of Roadwork’s sign to show that the road is clear in both directions.
When removing the signs, trained employees always reverse the procedure
Site or works entrance signs installed 100m before entrance.
Continual monitoring of work in progress and traffic control
![Page 16: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/16.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 16 of 17
Appendix 1 Trench support manufacturer’s guidelines
![Page 17: Method Statement Risk Assessment · method statement and are familiar with the reporting and emergency procedures 8. All supporting documentation should be read prior to works i.e.](https://reader034.fdocuments.in/reader034/viewer/2022050717/5e14a6cc07d4696f2e6b7b98/html5/thumbnails/17.jpg)
Name
Method Statement Form SF 25
Rev: 05
Page 17 of 17
Method Statement communication register The given talk is taken from the above method statement.
TALK BY:
DATE:
LOCATION:
Interpreter:
LIST OF ATTENDEES: I received and understood the above method statement. I will carry out work activities in accordance with CLEANTECH safety & environmental policies and procedures.