Method statement for Room Control Unit.docx

18
CONTENTS: 1. Scope of Works 2. Project Organization for Health & Safety Control 3. Health & Safety Risk and Control 4. Access / Egress 5. Lighting 6. Plant & Equipment 7. Personnel Training Certificate 8. Hazardous Materials & Substances 9. Waste Management 10. Special Control Measures Appendixes Appendix 1: Checklist for Room Control Unit Appendix 2: Project Organization for Health & Safety control Appendix 3: Risk Assessment Appendix 4: Personnel Training Certificate

Transcript of Method statement for Room Control Unit.docx

Page 1: Method statement for Room Control Unit.docx

CONTENTS:

1. Scope of Works

2. Project Organization for Health & Safety Control

3. Health & Safety Risk and Control

4. Access / Egress

5. Lighting

6. Plant & Equipment

7. Personnel Training Certificate

8. Hazardous Materials & Substances

9. Waste Management

10. Special Control Measures

Appendixes

Appendix 1: Checklist for Room Control Unit

Appendix 2: Project Organization for Health & Safety control

Appendix 3: Risk Assessment

Appendix 4: Personnel Training Certificate

Page 2: Method statement for Room Control Unit.docx

1. Scope of Works

Scope of Activities

This scope defines the minimum standards to be adopted when installing Room Control Unit

in Hotel Guest Room. The RCU provides intelligent management of the guest room energy-

saving and control system like, Energy management of guest room status, lighting control,

guest amenities, central monitoring, and including precise temperature control for enhanced

guest comfort.

Site Procedure

Site mobilization shall be done with real time monitoring the conditions & progress of builder

works. Before commencement of the work, carry out examination of the physical condition of

the area. Photographs should be taken where necessary, prior to commencement and

during works.

Page 3: Method statement for Room Control Unit.docx

METHOD STATEMENT

I. Preparation stage

a. Factory visit and testing to be conducted before shipment to site.

b. Engineer in-charge shall check to ensure that the Room Control Unit manufacturing,

complies with specification and drawings.

c. Engineer shall check to ensure that the guest room architectural finishing work is

completed and any physical obstruction during the delivery RCU.

d. Ensure that the RCU design/equipment provided all are fully comply with the

specification.

e. Supplier shall deliver RCU unit to site and store it designated place.

f. Handle the RCU unit with care to avoid damage to components, frame and finish.

g. When the RCU unit is received, unpack it sufficiently to inspect it for concealed

damage to determine that the shipment is complete and correct.

h. If the RCU is to be stored prior to installation, replace the packing for protection

during that period. When conditions permit, leave the packing intact until RCU unit

are at their final installation location.

i. Protect the equipment against the dust and debris during construction period.

j. A trolley or pallet may offer a more convenient method of handling the RCU to shift

from one location to other.

Page 4: Method statement for Room Control Unit.docx

II. Installation stage

a. Site survey of the proposed RCU is based on approved CSD by foreman / sub-

contractor together with Engineer.

b. Installation must be carried out based on approved shop drawings & samples by

foreman / sub-contractor.

c. Install the RCU in its final position at guest room, progressively leveling each section

and bolting the frames together if they are separated.

d. Mark the exact position of the RCU panel using respective template.

e. Drill the anchor location and install the RCU.

f. Tightened all bolted connection in accordance with the manufacturer torque

specifications.

g. Fix all the incoming & outgoing power/control cable in the RCU unit.

Input / Output wiring of RCU panel

Page 5: Method statement for Room Control Unit.docx

h. Connect all input/output control cable for Door contact switch, lighting control

Thermostat, Fan Coil Unit, Motion detectors and the communication output to

Network Floor Bridge.

Thermostat

Door Contact Switch

Page 6: Method statement for Room Control Unit.docx

Door Bell

i. Name or label RCU unit for future reference.

j. After installation of RCU, Engineer-in-charge shall check the complete works and

complete the Inspection Checklist for Room Control Unit installation works.

( See Appendix 1)

k. Engineer-in-charge shall arrange and request for inspection with the Owner’s

representative Residential Technical Officer (RTO) using approved Main con

Request for Inspection (RIN) form.

III. Testing and Commissioning

Steps to be taken before energizing the RCU.

a. Qualified personnel should be present when the equipment is energized for

the first time.

Page 7: Method statement for Room Control Unit.docx

b. Tighten all accessible electrical connection to the manufacturer's torque

specification.

c. Check the enclosure to see that it is not been damaged in a manner as to

reduce electrical spacing.

d. Manually exercise all switches, circuit breakers, and other operating

mechanism to make certain that they operate freely.

e. Conduct and electrical insulation resistance test to ensure that the RCU panel

is free from short circuits and grounds.

f. Check electrical relays and instrumentation to determine that the connections

are made properly and the devices function properly.

g. After RCU energizing check all the loads are working according to the

program logic installed in RCU.

h. Check the function of DDC Thermostat functioning properly.

i. Check the function of Chime bell.

j. Check the dedicated switch function for Sub Master, Pendant, Head board,

Night light, Bathroom light, Luggage lights, Foyer switch, Card key switch.

k. Check the day light open and night light open.

l. The performance and requirement of RCU shall follow contract documents

( Part III: Page PS-5-98 to PS-5-100 ) or approved shopdrawing.

IV. Preferred Materials

RCU – Room Control

UnitBenalla

Page 8: Method statement for Room Control Unit.docx

2. Project Organization for Health & Safety Control

( See Appendix 2 )

3. Health & Safety Risks and Controls

( Please refer to attach Risk Assessment with respect to above scope of works – see

Appendix 3)

4. Access / Egress

Proper step ladders shall be provided for access and egress into Distribution board

as applicable.

5. Lighting

Adequate temporary/task lighting shall be provided if work to be carried at night or at

dark places.

Page 9: Method statement for Room Control Unit.docx

6. Plant & Equipment

S/N Description Unit

1 Center punch 1 lot

2 Brace 1 lot

3 Torque wrench 1 lot

4 Hammer 1 lot

5 Electrical drill (only for surface installation works) 1 lot

6 Diagonal-Cutting Pliers 1 lot

7 Wire Stripper/Cutter with Spring 1 lot

8 Side-Cutting Pliers 1 lot

9 Level 1lot

10 Shank Screwdriver 1 lot

11P.P.E. – Personal Protective Equipment (safety helmet, Boots, gloves & safety vest )

1 set per worker

*The above machinery & Equipment used quantity will be varied depending on site conditions and production rate.

7. Personnel Training Certificate

( see Appendix 4 )

8. Hazardous Materials & Substances

( Not applicable )

Page 10: Method statement for Room Control Unit.docx

9. Waste Management

The Rubbish which would be created from our scope of works will be disposed to the

designated dumping ground.

10. Special Control Measures

The following general control measures against Safety, Environment and Quality

shall be required for our scope of work and special control measures are not

applicable for us

Proper PPE must be worn at all time.

Permit to work at height > 2m where applicable

Lifting operation permit (using crane) where applicable.

Confined space permit where applicable.

Approved work method statement and risk assessment will be made available to

site. All workers doing the work shall be briefed on this method statement and

risk assessment.

Page 11: Method statement for Room Control Unit.docx

APPENDIX 1:

Checklist for RCU Installation

Page 12: Method statement for Room Control Unit.docx

APPENDIX 2:

Project Organizationfor Health & Safety

Control

Page 13: Method statement for Room Control Unit.docx

APPENDIX 3:

Risk Assessment

Page 14: Method statement for Room Control Unit.docx

APPENDIX 4:

Professional Training Certificate