METHOD STATEMENT for INSTALLATION of PVC Conduits and Accessories in the Concrete Slabs, Columns,...
-
Upload
richard-leong -
Category
Documents
-
view
797 -
download
74
description
Transcript of METHOD STATEMENT for INSTALLATION of PVC Conduits and Accessories in the Concrete Slabs, Columns,...
-
STATE OF KUWAIT KUWAIT UNIVERSITY
ELECTRICAL METHOD STATEMENT
TENDER NO.
KU/KUCP/C0251/10-11
Page 1 of 6
METHOD STATEMENT FOR INSTALLATION OF INSTALLATION OF PVC CONDUITS AND
ACCESSORIES IN THE CONCRETE SLABS, COLUMNS, BLOCK WORKS AND CONCRETE
WALLS
0 Issued for Review & Comments
Rev.
Date
Description
Eng. A.H Prepared by
Checked by Approved by
-
STATE OF KUWAIT KUWAIT UNIVERSITY
ELECTRICAL METHOD STATEMENT
TENDER NO.
KU/KUCP/C0251/10-11
Page 2 of 6
REVISION CONTROL SHEET
REV. NO.
DATE
PAGE NO.
DESCRIPTION
-
STATE OF KUWAIT KUWAIT UNIVERSITY
ELECTRICAL METHOD STATEMENT
TENDER NO.
KU/KUCP/C0251/10-11
Page 3 of 6
TABLE OF CONTENTS
1 Purpose.. 4 2 Scope of Work.. 4 3 Responsible Personnel on Site.. 4 4 Storage.. 4
5 Pre-Installation 4
6 Installation 5
7 Reference Documents. 5
8 Safety 6
-
STATE OF KUWAIT KUWAIT UNIVERSITY
ELECTRICAL METHOD STATEMENT
TENDER NO.
KU/KUCP/C0251/10-11
Page 4 of 6
1. Purpose
This method of statement covers the in-site installations of Installation of PVC Conduits and Accessories in the Concrete Slabs, Columns, Block Works And Concrete Walls as defined in the General Specification.
2. Scope of Work
This procedure will define the method to be used to ensure that the PVC Conduits and Accessories installations, on-site assembly, final connection and workmanship are acceptable, correct, safe and conforms the Contract Documents and Specification.
3. Responsible Personnel on Site
3.1. Construction Manager 3.2. Electrical Field Engineers 3.3. Safety Officer 3.4. QA/QC Engineer 3.5. Electrical Supervisors
4. Storage
4.1 Deliver PVC Conduits and Accessories to site, completely identified in accordance with shop and certified drawings prepared for this work.
4.2 Store in accordance with the manufacturers instructions, above ground, properly
protected from the weather and construction activities.
4.3 Make sure that the storage area is safe.
5. Pre-Installation
5.1 All materials and documentation relevant to this particular section of works shall be checked prior to installation.
5.2 Ensure that the location wherein the PVC Conduits and Accessories were installed are
accessible, clean and free of debris and foreign materials and suitable for installations.
-
STATE OF KUWAIT KUWAIT UNIVERSITY
ELECTRICAL METHOD STATEMENT
TENDER NO.
KU/KUCP/C0251/10-11
Page 5 of 6
6. Installation
6.1 During the course of the installation of the conduit system, procedures for working and dressing the installation as recommended shall be employed.
6.2 All bends and sets shall be in accordance with regulation and specifications formed with
the aid of a helical spring fitted internally, with if necessary, the conduit warmed sufficiently for it to move without avoidable wall thinning of the out side of the bend.
6.3 Joints between PVC conduit + fittings shall be made with suitable adhesive, but
expansion couplings shall be installed where any length of conduit , inclusive of draw in boxes etc, exceeds five meters in length.
6.4 Conduits in floors shall be routed and installed so as to avoid the fixings of floor
standing equipment to be installed on the floor.
6.5 The conduits shall be adequately fixed to prevent excessive movement and damage during the pouring and setting of concrete and shall be protected from mechanical damage. Check there is no damage before screed / concrete is poured. Unless otherwise indicated to cast in conduits shall not be less than 30mm.cores to plastered over conduits shall not be less than 5mm.
6.6 Where conduits are left "open ended" prior to wiring they shall be protected by caps or
plugs to prevent the ingress of building material.
6.7 All conduits runs must be designed to permit wiring to be readily installed after the complete erection of the conduits through the available draw-in, accessory and luminary suspension boxes.
6.8 Where surface mounted equipment (other than luminaries) is specified, all concealed
conduits shall be terminated and an adaptable box installed recessed into the wall at every surface mounted equipment position.
6.9 Where conduits pass through an external wall/roof the conduit box shall be fitted on the
side and after wiring filled with an inert, permanently plastic compound having a high insulation value.
6.11 Make provision in conduit and trunking, installation where building expansion joints are
crossed or settlement is likely.
6.12 Ensure conduits are not concealed until works has been inspected and approved. Ensure that conduit and fittings buried in concrete or behind plaster are protected against corrosion or electrolytic action prior to rendering.
.
-
STATE OF KUWAIT KUWAIT UNIVERSITY
ELECTRICAL METHOD STATEMENT
TENDER NO.
KU/KUCP/C0251/10-11
Page 6 of 6
7. Reference Documents 7.1 Approved Electrical Shop Drawings 7.2 Approved Material Submittals for PVC Conduits and Accessories 7.3 Approved QA/QC Installation and Test Plan
7.4 Approved Material Inspection Report 7.5 Approved Safety Plan
8. Safety
8.1 All safety precautions shall be followed as per approved safety plan & procedure. Ensure all involved persons are aware of the same.
8.2 Ensure that tradesman will keep their working places clean, tidy and free from
rubbish.
------------------------ Procedure End----------------------