MERSEY GATEWAY BRIDGE PROJECT MERSEYLINK CONSTRUCTION METHOD REPORT SECTION 7 WESTON LINK MARCH 2015 MER-CJV-REP-TMP-06-510131

Transcript of MERSEY GATEWAY BRIDGE PROJECT · 2015. 3. 12. · MER-CJV-REP-TMP-07-510131 1 12 MARCH 2015 1...

  • MERSEY GATEWAY BRIDGE PROJECT

    MERSEYLINK CONSTRUCTION METHOD REPORT SECTION 7 WESTON LINK MARCH 2015

    MER-CJV-REP-TMP-06-510131

  • Construction Method Report Section 7 – Weston Link

    FORWARD POINT OFFICE

    Document Control Sheet Rev. Status Revision History Date By Check Approved

    - PD For Planning Discharge 12 MAR 2015 MM TG SG

    Merseylink CJV Forward Point Tanhouse Lane Widnes Cheshire WA8 0SL Tel: +44 (0)1928 785700

  • Construction Method Report Section 7 – Weston Link

    FORWARD POINT OFFICE

    Table of Contents

    1 Introduction ............................................................................................................. 1

    1.1 Introduction ................................................................................................................. 1

    2 Description Of The Works ...................................................................................... 1

    2.1 Road Works ................................................................................................................ 1

    2.2 Structures ................................................................................................................... 2

    Figure 1 Ineos Chlor Retaining Wall ..................................................................................... 2

    Figure 2 Equestrian Bridge .................................................................................................. 5

    3 Site Access .............................................................................................................. 5

    4 Site Clearance .......................................................................................................... 6

    5 Utilities Diversions .................................................................................................. 6

    6 Construction Vehicles And Numbers .................................................................... 6

    7 Traffic Management ................................................................................................ 7

    8 Environmental Issues ............................................................................................. 8

    8.1 Construction Environmental Management Plan .......................................................... 8

    Appendix A – Support Documents ................................................................................. 9

  • Construction Method Report Section 7 – Weston Link

    MER-CJV-REP-TMP-07-510131 1 12 MARCH 2015

    1 Introduction

    1.1 Introduction

    1.1.1 This report describes the construction methods that Merseylink will adopt in order to

    construct the new works within Section 7 Weston Link. This will include major elements

    such as the contiguous piled retaining wall, an equestrian bridge, associated footpaths

    and a new on-slip merge lane within. It will also outline the proposals for the partial

    demolition of the existing western expressway over-bridge (Rocksavage West Bridge) at

    this junction.

    1.1.2 The report augments the information contained in the Construction Methods Report (ref

    MER-CJV-REP-TPL-00-5100011) for the entire Project which has already been partially

    approved by the local planning authority.

    2 Description of the Works

    2.1 Road works

    2.1.1 Section 7 includes the Western Point Expressway, Western Link (Northbound link) and

    the Western Point Expressway junction.

    2.1.2 The road works include the construction of a new Western Point Expressway; west to

    north bound link slip road; and amendments to the existing Western Point south to north

    bound link road. These works include all roadway merge and diverge arrangements to

    meet current geometric standards.

    2.1.3 The new Western Link road will be constructed to allow a left hand merge and result in

    the removal of the existing right hand side merge to the existing Western Link.

    2.1.4 The links will be accommodated by single lane slip roads. These works will comprise

    modifications to the earthworks and highway alignments and the construction of a new

    retaining wall to accommodate the new link road.

    2.1.5 The outline construction process is as follows:

    Complete main utility water main diversions.

  • Construction Method Report Section 7 – Weston Link

    MER-CJV-REP-TMP-07-510131 2 12 MARCH 2015

    Construct new contiguous piled retaining wall (known as the Ineos Chlor Retaining

    Wall)

    Construct new equestrian footbridge

    Complete new earthworks and associated road works with the slip roads.

    Demolish part of the existing Rocksavage West Bridge

    Demolish the old western to Central link –(South bound)

    Construct a new ramped footpath – equestrian way

    2.2 Structures

    2.2.1 Section 7 includes two new structures, Ineos Chlor Retaining Wall and the Equestrian

    Bridge.

    Ineos Chlor Retaining Wall:

    2.2.2 This new retaining wall will be constructed with contiguous piles to form a cantilevered

    wall. The wall will be faced with insitu concrete. This retaining wall will allow the new

    Western Point Expressway to Western Link Road to be constructed.

    Figure 1 Ineos Chlor Retaining Wall

  • Construction Method Report Section 7 – Weston Link

    MER-CJV-REP-TMP-07-510131 3 12 MARCH 2015

    2.2.3 The construction sequence is described below:

    i. Retaining Wall

    Prior to commencing construction of the new wall a pair of 400mm PE water mains

    will be directionally drilled from the north side of the wall beneath the existing Western

    Point Expressway and to the south side of Rocksavage viaduct.

    The water main will also include a section of conventional open cut pipe work to

    complete the diversion work. The final connection and transfer of the water supply

    from the existing main to the new diversion will be phased during the construction of

    the piled wall.

    The existing ground and existing northbound link will be filled with suitable material

    to form a piling platform to the south side of the retaining wall. The piling rig will be

    situated to the south side to ensure that no damage occurs to the existing 600mm

    water main and the newly diverted section.

    Piling works will commence at the western end of the piled wall and progress towards

    the existing water main located within the existing footpath to the south of the Mormon

    Church. Prior to continuing with the piling operations the new main will be connected

    once the first section of piling has passed the section of drilled pipework. At the time

    of writing this report United Utilities are investigating the possibility of making final

    connections prior to piling operations

    With the water main diversion completed the remaining section of the piling works

    can be completed.

    The new retaining wall also forms part of the Equestrian Bridge sub structure. With

    the substructure completed the new bridge deck can be cast.

    The main retaining wall is also clad with a new concrete face.

    Upon completion of the structures work the bulk earthworks and road works

    operations can commence.

    Equestrian Bridge

    2.2.4 The bridge is required to carry the existing bridleway over the new link road. The bridge

    will have a width of 3.5m to allow for combined pedestrian and equestrian use. The road

  • Construction Method Report Section 7 – Weston Link

    MER-CJV-REP-TMP-07-510131 4 12 MARCH 2015

    below will be a single lane urban all-purpose connector road comprising 2.5m west verge,

    3.3m hard shoulder, 3.7m carriageway, 0.3m hard strip and 2.5m east verge.

    2.2.5 In order to cross the proposed road, the structure will have a clear span of 12.2m, which

    is easily accommodated in a single span. The structure will be provided with a width of

    3.5m between parapets to allow for pedestrian and equestrian use. This relatively small

    span can be accommodated in a single span reinforced concrete deck founded on a

    contiguous piled wall foundation. As this bridge is located in a ‘green field’ site ‘top down’

    construction is adopted to minimise the risk of working at height (see 2.2.8 below).

    2.2.6 Either side of the west abutment the will be Ineos Chlor Retaining Wall, this will also be

    constructed using contiguous bored piling, and will be finished to match the Equestrian

    Bridge. Movement joints will be provided between the bridge and the retaining wall.

    2.2.7 The approaches to the bridge will generally be formed of earth slopes. However, local to

    the ends of the deck a reinforced concrete slab will be provided to act as the supports to

    the equestrian parapet. At the west end of the crossing the structure interfaces with the

    proposed new Ineos Chlor retaining wall.

    2.2.8 Construction of Structure

    As noted above, the structure can be constructed in a ‘green field’ site, so there is

    considerable flexibility in the construction sequencing. In order to eliminate the risks of

    working at height, ‘top down’ construction will be used. An outline sequence for the

    structure is as follows:

    Remove any soft areas in the existing made ground.

    Fill the location of the deck with structural backfill up to bridge soffit levels.

    Construct temporary piling platform for Ineos Chlor and Equestrian Bridge abutments.

    Install Ineos Chlor retaining wall.

    Install bridge abutment piles.

    Construct bridge deck.

    Carry out the bulk excavation for the link road cutting.

    Excavate below the bridge deck down to road finish level.

    Install wall facing construct capping beam.

  • Construction Method Report Section 7 – Weston Link

    MER-CJV-REP-TMP-07-510131 5 12 MARCH 2015

    Construct new bridleway route.

    Figure 2 Equestrian Bridge

    2.2.9 Section 7 also includes the retention of the following existing structures: Rocksavage

    Viaduct and Rocksavage West Bridge. These structures are identified in Scheme Road

    Layout (sheet 25) - MER-DJV-DRA-HWY-07-301125 rev02. However, a section of

    Rocksavage West Bridge is also demolished once the new Western Point Expressway to

    Western Link North bound is completed. This existing structure will require careful and

    controlled demolition as part of the removal of the existing link road.

    2.2.10 Demolition of this and other existing bridge structures on the whole scheme will be

    covered in a specific Demolition of Structures CMR and will be issued at a later date.

    3 Site Access

    3.1.1 Site access will be from the existing carriageway. Safe entry and egress from the working

    areas is incorporated into the traffic management regime.

  • Construction Method Report Section 7 – Weston Link

    MER-CJV-REP-TMP-07-510131 6 12 MARCH 2015

    4 Site Clearance

    4.1.1 Site clearance will be required before starting the construction works. The site clearance

    is detailed on drawing MER-DJV-DRA-HWY-07-302011 rev03.

    4.1.2 At Weston Link Junction there will be a need to demolish part of the Rocksavage West

    Bridge.

    5 Utilities Diversions

    5.1.1 There are a number of existing services in the area which will require diverting or

    protection during the work. Details for the Ineos Chlor Retaining Wall services protection

    can be found in a separate report. (Ineos Retaining Wall Services Protection Report -

    MER-CJV-CAL-TMP-07-520388 rev-)

    5.1.2 A United Utilities asset, consisting of a 24’’ diameter clean water main must be diverted

    due to the re-alignment of the existing junction. A suitable diversion has been agreed with

    United Utilities.

    5.1.3 There is an existing 18” diameter brine main serving the Ineos Chlor site. Suitable

    protection, if required, will be agreed with Ineos Chlor.

    5.1.4 There is an existing 500mm (nominal) diameter National Grid high pressure gas pipeline.

    The retaining wall has been designed such that National Grid’s requirement for a minimum

    3m space between the wall and the pipe is maintained. Vibration from our operations will

    be monitored and recorded to ensure National Grid’s limit of 75 mm/s is not exceeded.

    6 Construction Vehicles and Numbers

    6.1.1 The execution of the Section 7 works will involve a number of wagon movements for both

    delivery of materials and plant as well as removal of surplus spoil. This will include

    materials to construct the retaining wall comprising:

    6.1.2 Approximately 66 HGV material deliveries movements: 2 HGV for drainage materials, 40

    concrete mixer trucks for pile installation, 1 HGV for hangers, 3 HGV for scaffolding, 8

  • Construction Method Report Section 7 – Weston Link

    MER-CJV-REP-TMP-07-510131 7 12 MARCH 2015

    trucks for formwork materials, 10 HGV for bent reinforcement, 2 HGV for barriers and

    finishings.

    6.1.3 Approximately 75 tipper HGV movements will be required for the delivery and collection

    of the following plant: 2 compaction equipment (15Tn), 2 piling equipment, 2 excavators,

    1 working platforms, 2 cranes, and 5 concrete pump. Approximately 10 vehicle

    movements will be required for the delivery and collection of small plant and machinery

    not covered above.

    6.1.4 For general earthworks there will be 2 excavators, 4 dumpers and approximately 500 HGV

    wagon movements for the removal of surplus spoil to adjacent fill areas within the project

    boundary.

    6.1.5 This section will require a workforce of approximately 35 operatives for the construction

    of the infrastructure, the operation to construct the equestrian bridge in its final position

    and finishing works. In addition four teams of workers will be needed for the assembly of

    the general infrastructure.

    6.1.6 A self-contained welfare unit will be provided within the site boundary for occasional use.

    Main welfare and messing facilities will be sited at the Vencroft site off Astmoor Road. The

    workforce will be bussed to the worksite at the start and finish of work and at main break

    times.

    7 Traffic Management

    7.1.1 The construction of Section 7 works will require the closure of the existing slip roads and

    main carriageway in a phased and planned manner. Convenient diversion routes to

    facilitate the closures have been identified and agreed with the Traffic Manager. A strategy

    has been developed to ensure that the road user will not be required to divert from their

    route more than once in any direction of travel. This will ensure that traffic management

    arrangements in adjacent sections do not conflict.

    7.1.2 To construct the retaining wall and equestrian bridge, the earthworks material in the

    existing embankments will need to be excavated and re-used in fill areas on the south

    side of the river.

  • Construction Method Report Section 7 – Weston Link

    MER-CJV-REP-TMP-07-510131 8 12 MARCH 2015

    7.1.3 During installation of the piled retaining wall it is required to close the Weston Point

    Expressway eastbound off-slip toward the Weston Link in Phase 1, to provide working

    space. Phase 2 will require full closure of the Weston Link eastbound off-slip toward

    Rocksavage Expressway with a diversion for vehicles travelling toward the M56 using a

    new signalised junction at Rocksavage Way. This same diversion will be retained during

    Phase 3 works. Phase 4 works will only require single lane closures on the Rocksavage

    Expressway. These plans will be agreed through the Traffic Management Group within

    the agreed timescales.

    7.1.4 Some incidental localised Traffic Management may be required as the works progress in

    Phase 1, for such works as service diversions. These TM layouts will be agreed with the

    Traffic Manager. All notice periods will be adhered to for the approval of such works.

    7.1.5 Pedestrian Management – To construct Phase 1 and 2 of the works the equestrian

    bridleway/footpath will have to be temporarily closed since there is no viable alternative

    diversionary route. Any other localised temporary diversions of the footpaths will be

    surfaced, well maintained with signage and segregation barriers in place. Any diversion

    length will be kept to a minimum whilst ensuring the safety of pedestrians is maintained

    at all times. These, too, will be agreed with HBC highways authority in advance.

    Construction plant and pedestrians will be segregated at all times and warning signage

    displayed at all crossing points. Advance notices will be issued for any closure and will

    be planned in advance if required later in the construction period.

    8 Environmental Issues

    8.1 Construction Environmental Management Plan

    8.1.1 Environmental issues relating to the work in Section 7 are addressed in the individual

    CEMP documents previously submitted to the local planning authority. The following

    Management Plans are relevant to the construction activities identified.

    Pollution Prevention including Traffic Management and Water Quality

    Waste

    Biodiversity, (particularly Eco 8 Great Crested Newts)

    Noise and Vibration

    Air Quality

  • Construction Method Report Section 7 – Weston Link

    MER-CJV-REP-TMP-07-510131 9 12 MARCH 2015

    Appendix A – Support Documents

    General

    Site Clearance - MER-DJV-DRA-HWY-07-302011 rev03

    Retaining wall

    Ineos Chlor Retaining Wall – GA Sheet (1 of 3) - MER-DJV-DRA-STR-07-349101 rev07

    Ineos Chlor Retaining Wall – GA Sheet (2 of 3) - MER-DJV-DRA-STR-07-349102 rev06

    Ineos Chlor Retaining Wall – GA Sheet (3 of 3) - MER-DJV-DRA-STR-07-349103 rev04

    Equestrian Bridge

    Equestrian Bridge Abutment Details - MER-DJV-DRA-STR-07-346310 rev03

    Equestrian Bridge GA (sheet 1 of 2) - MER-DJV-DRA-STR-07-346101 rev06

    Equestrian Bridge GA (sheet 2 of 2) - MER-DJV-DRA-STR-07-346102 rev05

    Traffic Management

    Section 7 TM Phase 1 - MER-CJV-DRA-TRA-07-501336 rev-

    Section 7 TM Phase 2 - MER-CJV-DRA-TRA-07-501337 rev-

    Section 7 TM Phase 3 - MER-CJV-DRA-TRA-07-501338 rev-

    Section 7 TM Phase 4 - MER-CJV-DRA-TRA-07-501339 rev-

    Weston Point Diversion - MER-CJV-DRA-TMP-07-980712 rev-

    Weston Point Diversion Junction Details - MER-CJV-DRA-TMP-07-980711 rev-

    Services Protection Report

    Ineos Retaining Wall Services Protection Report - MER-CJV-CAL-TMP-07-520388 rev-