Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

22

Click here to load reader

description

Half of the Honoré Mercier Bridge will be closed for seven weeks from Friday, June 20, at 9:00 p.m. to Monday, August 11, at 5:00 a.m. One lane will be open per direction while work takes place. During this period, major work will take place day and night to replace a section of the deck on the federal portion of the Honoré Mercier Bridge, as well as to replace expansion joints and bridge bearings, and to carry out paving and marking work.

Transcript of Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

Page 1: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

REHABILITATION OF THE HONORÉ MERCIER BRIDGE

FEDERAL SECTION

WORK PLAN

2014

Page 2: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

FOLLOW UP ON THE PROJECT

Page 3: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

3

Pier 14

Ramp 4139 SLABSINSTALLED

Ramp 2188 SLABSINSTALLED

Ramp 3120 SLABSINSTALLED+ 73 FOR THE BIKE PATH

FEDERAL SECTIONWORK COMPLETED

Pier 32

Maline Island East Side Montréal Direction116 SLABSINSTALLED

Page 4: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

FEDERAL SECTION2/3 OF THE WORK COMPLETED BEFORE 2014

SUMMARY OF THE WORK BEFORE 2014

636 SLABS REPLACED

346 SLABSTO BE INSTALLED

Page 5: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

WORK PLANNED IN 2014

Page 6: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

6

XX

X

Pier 14

Pier 27

2014 WORK120 SLABS TO INSTALL+ 73 SLABSFOR THE BIKE PATH

X

ONE LANE / DIRECTION

Work zone

WORKDAY AND NIGHTSEVEN WEEKSSUMMER 2014

Page 7: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

7

MALINE ISLAND SECTION

SEAWAY SECTION

CONVERGENCE SECTION

2014

Page 8: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

8

LASALLElSOUTH-SHOREl

MALINE ISLAND SECTIONTOWARDS THE SOUTH-SHORE

ONE LANE OPEN PER DIRECTION

Page 9: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

WORK SCHEDULE

Page 10: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

Honoré Mercier Bridge

2014 WORK SCHEDULESEVEN CONSECUTIVE WEEKS

APRIL MAY JUNE

JULY AUGUST SEPTEMBER

Page 11: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

OVERVIEW OF WORK TO COME

Page 12: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

SLABS CUT AND REMOVED

Page 13: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

INSTALLATION OF THE NEW CONCRETE DECK SLABS

Page 14: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

INSTALLATION OF THE NEW CONCRETE DECK SLABS

Page 15: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

NEW VS OLD DECK

NEW

OLD

Page 16: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

SLABS ANCHORERD TO STEEL STRUCTURE

Page 17: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

HIGH LEVEL OF PRECISION DURING THE INSTALLATION

Page 18: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

INSTALLATION OF NEW BEARING DEVICES

Page 19: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

INSTALLATION OF NEW EXPANSION JOINTS

Page 20: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

POST-TENSIONING OF THE DECK SLABS (INSTALLATION OF STEEL CABLES)

Page 21: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

INSPECTION AND FINAL PAVING OF THE BRIDGE

Page 22: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

22

MERCIERBRIDGE.CA