REHABILITATION OF THE HONORÉ MERCIER BRIDGE
FEDERAL SECTION
WORK PLAN
2014
![Page 2: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/2.jpg)
FOLLOW UP ON THE PROJECT
![Page 3: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/3.jpg)
3
Pier 14
Ramp 4139 SLABSINSTALLED
Ramp 2188 SLABSINSTALLED
Ramp 3120 SLABSINSTALLED+ 73 FOR THE BIKE PATH
FEDERAL SECTIONWORK COMPLETED
Pier 32
Maline Island East Side Montréal Direction116 SLABSINSTALLED
![Page 4: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/4.jpg)
FEDERAL SECTION2/3 OF THE WORK COMPLETED BEFORE 2014
SUMMARY OF THE WORK BEFORE 2014
636 SLABS REPLACED
346 SLABSTO BE INSTALLED
![Page 5: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/5.jpg)
WORK PLANNED IN 2014
![Page 6: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/6.jpg)
6
XX
X
Pier 14
Pier 27
2014 WORK120 SLABS TO INSTALL+ 73 SLABSFOR THE BIKE PATH
X
ONE LANE / DIRECTION
Work zone
WORKDAY AND NIGHTSEVEN WEEKSSUMMER 2014
![Page 7: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/7.jpg)
7
MALINE ISLAND SECTION
SEAWAY SECTION
CONVERGENCE SECTION
2014
![Page 8: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/8.jpg)
8
LASALLElSOUTH-SHOREl
MALINE ISLAND SECTIONTOWARDS THE SOUTH-SHORE
ONE LANE OPEN PER DIRECTION
![Page 9: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/9.jpg)
WORK SCHEDULE
![Page 10: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/10.jpg)
Honoré Mercier Bridge
2014 WORK SCHEDULESEVEN CONSECUTIVE WEEKS
APRIL MAY JUNE
JULY AUGUST SEPTEMBER
![Page 11: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/11.jpg)
OVERVIEW OF WORK TO COME
![Page 12: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/12.jpg)
SLABS CUT AND REMOVED
![Page 13: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/13.jpg)
INSTALLATION OF THE NEW CONCRETE DECK SLABS
![Page 14: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/14.jpg)
INSTALLATION OF THE NEW CONCRETE DECK SLABS
![Page 15: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/15.jpg)
NEW VS OLD DECK
NEW
OLD
![Page 16: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/16.jpg)
SLABS ANCHORERD TO STEEL STRUCTURE
![Page 17: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/17.jpg)
HIGH LEVEL OF PRECISION DURING THE INSTALLATION
![Page 18: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/18.jpg)
INSTALLATION OF NEW BEARING DEVICES
![Page 19: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/19.jpg)
INSTALLATION OF NEW EXPANSION JOINTS
![Page 20: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/20.jpg)
POST-TENSIONING OF THE DECK SLABS (INSTALLATION OF STEEL CABLES)
![Page 21: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/21.jpg)
INSPECTION AND FINAL PAVING OF THE BRIDGE
![Page 22: Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite](https://reader038.fdocuments.in/reader038/viewer/2022102316/559281501a28ab33678b45db/html5/thumbnails/22.jpg)
22