PROVIDING RENEWABLE ENERGY
AND FOOD IN PAPUA
MERAUKE PROJECT - MEDCOGROUP
FACTS ON INDONESIA RICE INDUSTRYRice Production and Import Historical Rice Price
Indonesia Food Imports
• Rice is main staple food in Indonesia• People of Indonesia eat rice frequently
(3 times per day on average).• Low income people spend 70% of their
income on rice
MEDCOGROUP FOOD ZONE AND ENERGYFOREST DEVELOPMENT
ADOPT A CIRCULAR ECONOMYBUSINESS MODEL
ENERGY FOREST
POWER PLANT FOOD ESTATE
Integrated Food and
Energy Business
LIVESTOCK
ORGANIC FERTILIZER
WOODPRODUCT
THE OBJECTIVES AND PROGRAMS
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
WHY MERAUKE - PAPUA ?
•
•
•
•
•
•
•
•
Power Plant 3
Food Estate
Buepe Industrial
Complex (Power
plant, Food and
Pellet industry)
Food Estate
Food Estate
Wapeko
Industrial
Complex (Power
plant and food
industry)
EnergyForest
Energy Forest
Energy Forest
New regulation of Indonesian Forest Ministry allowing HTI concession (Forest Plantation) to allocate20-30% of its land for food/rice
OUR CONCESSION OF APRROX. 275,000 HA
Putting the right plant, in the right place, for the right purpose!
Medco implemented Agroforestry practices to
optimize benefits from forest development
1. FOOD ZONE (RICE)
Paddy field ResultJOKOWIPICTURE
President Jokowi visited 425 ha pilot project of modern rice farming and announced Merauke as National Rice Estate to support the country’s food self-sufficiency program
Paddy field Result
MERAUKE RICE DEVELOPMENT AREA
CURRENT STAGE AND TARGET
ALREADY PLANTED/ DEVELOPED
TARGET
ENERGY FOREST3,000 HA 100,000 HA
FOOD ESTATE (RICE) 1,000 HA 50,000 HA
BIOMASS POWER PLANT7 MW 50 MW
WOOD INDUSTRY
WOOD PRODUCTS(500,000 TON/YR)
WOOD PRODUCTS(700,000 TON/YR)
FACTS ON ELECTRICITY IN PAPUA REGION
45.93%Electricity Ratio Papua Province
65.6%Electricity Ratio West Papua Province
•
•
•
•
ELECTRICITY FACTS IN PAPUA & MERAUKE
Papua’s electricity reserve margin is 9%,
lower than PLN’ standards of 25% - 30%
About 2 million Papua people are yet to
receive electricity supply
Merauke ‘s electricity demand grows
2.75% per year
Merauke electricity ratio is 43.04%.
Lower than 100% target
Merauke &
Wapeko are
the right
locations
9,000 Ha modern rice farm in Wapeko
require additional electricity supply
Power plants in Merauke dominated by fuel
2. ENERGY FOREST & WOOD PRODUCTS INDUSTRY
We have constructed a woodchip mill with capacity of 600,000 ton/year.
Our target is to build wood pellet mill with capacity of 500,000 ton/year combined with Torre faction system.
Nursery produces 120,000 seeds/month 3,000 Ha planted 200 KM main and secondary road
3. BIOMASS POWER PLANT
Debarker Machine
We have constructed 7 MW biomass power plant in our site and currently is constructing our second plant (3.5 MW) in Wapeko. Next plant will be 10 MW in Merauke
7 MW power plant
Most of cities in Papua are still powered by diesel Power Plant with cost of more than USD 0.25 / KWh. Our Biomass power plant could cost as low as USD 0.17/KWh.
Therefore, there are opportunities to build similar power plants in other cities in Papua.
BIOMASS UTILIZATION FOR POWER PLANT
Powerpack is the Solution
Roadmap to 50 MW Target
Thank You