Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as...

35
Transportation Committee Item 7 | July 19, 2019 1 Transportation Committee Item 7 | July 19, 2019 Proposed FY 2020 Program Budget Amendment: Fiber Optic Information Network Gap Closure Project Memorandum of Understanding Interagency Fiber Optic Cable Sharing Agreement 2

Transcript of Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as...

Page 1: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 7 |  July 19, 20191

Transportation Committee Item 7 | July 19, 2019

Proposed FY 2020 Program Budget Amendment: Fiber Optic Information Network Gap Closure Project

Memorandum of Understanding Interagency Fiber Optic Cable Sharing Agreement

2

Page 2: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 7 |  July 19, 20192

Escondido Gap ClosureI-15 to NCTD SPRINTER ConnectionPlanned as part of NCTD’s PTC and SANDAG Toll Reserve funds

Caltrans Hub 3 to MTS/Caltrans Interface cabinet at Imperial Ave. finished as part of TransNetFasTrak I-15 Funds

Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds

3

Benefits

4

Page 3: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 7 |  July 19, 20193

Recommendation

The Transportation Committee is asked to recommend that the Board of Directors approve an amendment to the FY 2020 Program Budget to:

1. create a new Capital Improvement Program (CIP) Project to establish the Fiber Optic Information Network Gap Closure Project (CIP Project No. 1131500);

2. transfer $430,000 of SANDAG toll funds; and

3. accept $90,000 from the North County Transit District to fund this work.

5

Page 4: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 8 |  July 19, 2019 1

Proposed FY 2020 Program Budget Amendment: El Portal Undercrossing on LOSSAN Rail Corridor 

Transportation Committee Item 8 | July  19, 2019

LOSSAN Undercrossings in Encinitas

1. Santa Fe Drive undercrossing 

• Constructed by SANDAG 2012 ‐ 2013

2. El Portal undercrossing

• Design approaching 100% by City of Encinitas

• Construction funding ATP grant  

• City requesting SANDAG oversee construction phase

2

Page 5: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 8 |  July 19, 2019 2

Santa Fe Drive Undercrossing(Saturday 9/8/2012 at 11 a.m.)

3

Santa Fe Drive Undercrossing(Saturday 9/8/2012 at 11 p.m.)

4

Page 6: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 8 |  July 19, 2019 3

Santa Fe Undercrossing (Today)

5

Santa Fe Undercrossing (Today) 

6

Page 7: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 8 |  July 19, 2019 4

Project Area: Leucadia in Encinitas

7

El Portal UndercrossingPlan View After Streetscape

8

Page 8: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 8 |  July 19, 2019 5

Recommendation 

The Transportation Committee is asked to recommend that the Board of Directors approve an amendment to the FY 2020 Program Budget to:

1. create a new Capital Improvement Program (CIP) Project to establish the El Portal Undercrossing Project (CIP 1146900); and 

2. accept $8.937 million in funding from the City of Encinitas and State Active Transportation Program to fully fund construction of the project, in substantially the same form as shown in Attachment 1. 

9

Page 9: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 10 |  July 19, 2019 1

REGIONAL BIKEWAY PROGRAM UPDATE

Transportation Committee Item 10 | July 19, 2019

2GObyBIKEsd.com

EARLY ACTION PROGRAM

• $200 million in TransNet funds

• Builds 77 linear miles of bikeways

• 70 of 77 miles either open or under design

• 8.8 miles open to date

• 3/4 of investment in City of San Diego

Page 10: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 10 |  July 19, 2019 2

3GObyBIKEsd.com

BIKEWAY PROGRAM STATUS

70 of 77 Miles Open or Under Development

11.8

43.9

6.4 7.5

0

5

10

15

20

25

30

35

40

45

50

PE/Environmental Final Design Construction Open To Public

April 2019

4GObyBIKEsd.com

BIKEWAY PROGRAM STATUS

70 of 77 Miles Open or Under Development

3.8

45.4

11.68.8

0

5

10

15

20

25

30

35

40

45

50

PE/Environmental Final Design Construction Open To Public

July 2019

Page 11: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 10 |  July 19, 2019 3

RECENT PROGRESS

5

6GObyBIKEsd.com

COASTAL RAIL TRAIL: ENCINITAS

Page 12: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 10 |  July 19, 2019 4

7GObyBIKEsd.com

COASTAL RAIL TRAIL: ENCINITAS

8GObyBIKEsd.com

COASTAL RAIL TRAIL: ENCINITAS

Page 13: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 10 |  July 19, 2019 5

9GObyBIKEsd.com

COASTAL RAIL TRAIL

10GObyBIKEsd.com

COASTAL RAIL TRAIL: ROSE CREEK BIKEWAY

Page 14: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 10 |  July 19, 2019 6

11GObyBIKEsd.com

COASTAL RAIL TRAIL: ROSE CREEK BIKEWAY

12GObyBIKEsd.com

COASTAL RAIL TRAIL: ROSE CREEK BIKEWAY

Page 15: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 10 |  July 19, 2019 7

13GObyBIKEsd.com

COASTAL RAIL TRAIL: ROSE CREEK BIKEWAY

14GObyBIKEsd.com

COASTAL RAIL TRAIL: ROSE CANYON BIKEWAY

Page 16: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 10 |  July 19, 2019 8

15GObyBIKEsd.com

INLAND RAIL TRAIL: COUNTY OF SAN DIEGO AND CITY OF VISTA

16GObyBIKEsd.com

INLAND RAIL TRAIL: COUNTY OF SAN DIEGO AND CITY OF VISTA

Page 17: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 10 |  July 19, 2019 9

17GObyBIKEsd.com

INLAND RAIL TRAIL: COUNTY OF SAN DIEGO AND CITY OF VISTA

18GObyBIKEsd.com

INLAND RAIL TRAIL: COUNTY OF SAN DIEGO AND CITY OF VISTA

Page 18: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 10 |  July 19, 2019 10

19GObyBIKEsd.com

CITY OF SAN DIEGO URBAN BIKEWAYS

• Opened bids from contractors for North Park | Mid-City Bikeways, Landis and Georgia-Meade, in June 2019

• Uptown Bikeways: Fourth/Fifth Avenue approved in June 2019, plans to advertise in July 2019

• Pershing, Imperial Avenue, and Bayshore Bikeway Barrio Logan currently under review

20GObyBIKEsd.com

NEXT STEPS

• Continue progress on 24 EAP projects in FY 20 Program Budget

• Provide regular program status updates

Page 19: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 1

Transportation Committee Item 11 | July 19, 2019

PROJECT OVERVIEW• 11-mile extension

of the Blue Line Trolley

• Old Town Transit Center to University City

• Nine new stations (five with parking)

• 36 Trolley cars

• Revenue service begins in fall 2021

• $2.17 billion (52% TransNet, 48% FTA)

2

Page 20: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 2

MID-COAST CONSTRUCTION SCHEDULE

60% DONE

3

CONSTRUCTION SCHEDULE

Milestone Baseline May 2019 UpdateHeavy Construction Duration 56 months 57.2 months

Reach 14 Track Const. Complete August 2020 October 2020

Start MTS Pre-Revenue Testing April 2021 May 2021

Final Completion by MCTC July 2021 August 2021

Revenue Service Date September 2021 November 2021

4

Page 21: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 3

MID-COAST CONSTRUCTION PROGRESS

5

MID-COAST DBE UTILIZATION

6

0.04% 0.23%0.57%

1.05%1.65%

2.46%

3.22%

4.01%

4.92%

5.79%

6.66%

7.46%

8.23%

9.01%

9.76%10.35%

10.76%11.07%11.25%

11.28%

0.04% 0.22%0.62%

1.23%

2.04%

3.09%

3.97%

4.74%

5.86%6.47%

7.00%

0.00%

2.00%

4.00%

6.00%

8.00%

10.00%

12.00%

14.00%

MID‐COAST LRTProjected vs. ActualDBE Goal 11.3%

Projected Attainment Realized Attainment To Date Linear (Projected Attainment)

Page 22: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 4

DBE SUCCESS STORY

Lucas Builders, Inc.

• Engineering utility contractor• Established in 2004• DBE certified in 2013• Mid-Coast Project success: Contract value grew from $36,000 to $15.5

million Grew from 35 to 54 employees on this project Able to purchase three trucks and plans to

purchase four pieces of equipment New work with City of LA, LA Metro, and LA

County Sanitation District

Leadership, Reliability, Quality & Safety

7

CONSTRUCTION LABOR – May 2019

0 200 400 600 800 1000 1200

Brick Layer

BCI/FSMT

Carpenter

Cement Mason

Electrician

Surveyor

Ironwrkr

Laborer

Operating Eng

Painter

Plumber

Teamster

BrickLayer

BCI/FSMT CarpenterCementMason

Electrician Surveyor Ironwrkr LaborerOperating

EngPainter Plumber Teamster

Cumulative 8 164 308 68 137 38 360 885 746 27 60 278

May‐19 0 42 186 22 31 13 77 225 127 4 24 29

NUMBER OF WORKERS BY TRADE

8

Page 23: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 5

CONSTRUCTION ACCOMPLISHMENTS

• Placed final Genesee girder on April 19, 2019

• Placed final LRT flyover girder on May 23, 2019

• I-5 Voigt and Nobel LRT Bridges

• Bike path opened on July 3, 2019

• Navy fuel line relocation

• Settled three additional properties

• First Mid-Coast vehicles delivered

9

CONSTRUCTION UPDATE

10

Tecolote Creek Bridge and Navy Fuel Line (NFL) heroes

Page 24: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 6

CONSTRUCTION UPDATE

11

Rail welds near Morena Boulevard and Signal House installation

12

Trolley track installation at Clairemont Drive Station

CONSTRUCTION UPDATE

Page 25: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 7

CONSTRUCTION UPDATE

13

Rose Creek North LRT Bridge

CONSTRUCTION UPDATE

14

LOSSAN LRT Flyover

Page 26: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 8

CONSTRUCTION UPDATE

15

Rose Canyon Bike Path final location

CONSTRUCTION UPDATE

16

Trolley Underpass at Gilman Drive / La Jolla

Colony Drive

Page 27: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 9

17

CONSTRUCTION UPDATE

Trolley Overcrossing south ofNobel Drive and Nobel Drive Station

CONSTRUCTION UPDATE

18

UC San Diego Viaduct – Rail Construction

Page 28: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 10

CONSTRUCTION UPDATE

19

Pepper Canyon Station at UC San Diego

CONSTRUCTION UPDATE

20

UC San Diego – Pedestrian Bridge to Preuss School,Scripps Medical Center

Page 29: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 11

CONSTRUCTION UPDATE

21

Rail at Voigt Drive Station and

Deck Placement Genesee Avenue

CONSTRUCTION UPDATE

22

UTC Terminus Formwork and Concrete Placement

Page 30: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 12

PROJECT RISKS

Risk Item Potential Impact

Right of Way Cost – Mediations, Settlements, Trials Cost

Right of Way - Goodwill Claims Cost (no federal participation)

Fez Street Substation Schedule, Redesign, Cost

Construction Cost, Provisional Sums Cost (if above current estimates)

Construction Unknowns Schedule and Cost (diminishing)

23

RIGHT OF WAY

Mid-Coast Project Acquisitions

Total Property Owners 43

Available for Construction (Possession) 40

Needed Possessions for Construction 3

Acquisitions Settled 35

Under or Pending Negotiation 8

Potential Hearings of Necessity 2

Risks• Settlements, trial, legal, goodwill exposure exceeds budget• 1 - 5 properties go to trial

24

Page 31: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 13

LIGHT RAIL VEHICLES

25

• First Mid-Coast car arrived April 4, 2019

• Three more Mid-Coast cars arrived May 7, May 17, and May 31, 2019

SAN DIEGO RIVER BRIDGE

26

Two LOSSAN complete bridge structures, one is operational

Page 32: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 14

ELVIRA TO MORENA DOUBLE TRACK

27

Bridge and Trackwork

ROSE CREEK BIKEWAY

28

Santa Fe Street andTrail Area Work

Page 33: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 15

GILMAN DRIVE BRIDGE

29

Gilman Drive BridgeUp Lighting

• Stakeholder Outreach – Community Planning Groups

– Monthly Council briefings

– Construction notices

– Shift San Diego

• Community Events– UC San Diego Pepper Canyon

Designathon

– Pure Water open house

– UC Fourth of July celebration

• Media Events– Rose Canyon Bike Path opening

• Public Inquiries and Comments

30

PUBLIC OUTREACH

Page 34: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 16

• Project Tours– Nine tours conducted (April-June)

– Participating elected officials included:• Councilmember Monica Montgomery

• Mayor Mary Salas

• Councilmember Jill Galvez

• Councilmember Ronn Hall

• Councilmember Jennifer Campbell

• Social Media MID‐COAST TROLLEY FACEBOOK PAGE

April‐June Stats Overall Likes (City) Overall Likes (Country)

Impressions: 52,738 San Diego: 1,495 United States: 2,079

Video Views: 4,297 Los Angeles: 32 Mexico: 36

Engaged Visitors: 2,857 Chula Vista: 28 United Kingdom: 6

Tijuana: 25 Italy: 5

Oceanside: 24 Taiwan: 3

31

PUBLIC OUTREACH

[email protected]

(877) 379-0110

KeepSanDiegoMoving.com/MidCoast

Mid-Coast Trolley @MidCoastTrolley

Contact Us

32

Page 35: Memorandum of Understanding Interagency Fiber Optic Cable ... · Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds 3 Benefits

Transportation Committee Item 11 |  July 19, 2019 17

33

Questions?