Transportation Committee Item 7 | July 19, 20191
Transportation Committee Item 7 | July 19, 2019
Proposed FY 2020 Program Budget Amendment: Fiber Optic Information Network Gap Closure Project
Memorandum of Understanding Interagency Fiber Optic Cable Sharing Agreement
2
Transportation Committee Item 7 | July 19, 20192
Escondido Gap ClosureI-15 to NCTD SPRINTER ConnectionPlanned as part of NCTD’s PTC and SANDAG Toll Reserve funds
Caltrans Hub 3 to MTS/Caltrans Interface cabinet at Imperial Ave. finished as part of TransNetFasTrak I-15 Funds
Oceanside Gap Closure Planned as part of NCTD’s positive train control (PTC), and SANDAG Toll Reserve funds
3
Benefits
4
Transportation Committee Item 7 | July 19, 20193
Recommendation
The Transportation Committee is asked to recommend that the Board of Directors approve an amendment to the FY 2020 Program Budget to:
1. create a new Capital Improvement Program (CIP) Project to establish the Fiber Optic Information Network Gap Closure Project (CIP Project No. 1131500);
2. transfer $430,000 of SANDAG toll funds; and
3. accept $90,000 from the North County Transit District to fund this work.
5
Transportation Committee Item 8 | July 19, 2019 1
Proposed FY 2020 Program Budget Amendment: El Portal Undercrossing on LOSSAN Rail Corridor
Transportation Committee Item 8 | July 19, 2019
LOSSAN Undercrossings in Encinitas
1. Santa Fe Drive undercrossing
• Constructed by SANDAG 2012 ‐ 2013
2. El Portal undercrossing
• Design approaching 100% by City of Encinitas
• Construction funding ATP grant
• City requesting SANDAG oversee construction phase
2
Transportation Committee Item 8 | July 19, 2019 2
Santa Fe Drive Undercrossing(Saturday 9/8/2012 at 11 a.m.)
3
Santa Fe Drive Undercrossing(Saturday 9/8/2012 at 11 p.m.)
4
Transportation Committee Item 8 | July 19, 2019 3
Santa Fe Undercrossing (Today)
5
Santa Fe Undercrossing (Today)
6
Transportation Committee Item 8 | July 19, 2019 4
Project Area: Leucadia in Encinitas
7
El Portal UndercrossingPlan View After Streetscape
8
Transportation Committee Item 8 | July 19, 2019 5
Recommendation
The Transportation Committee is asked to recommend that the Board of Directors approve an amendment to the FY 2020 Program Budget to:
1. create a new Capital Improvement Program (CIP) Project to establish the El Portal Undercrossing Project (CIP 1146900); and
2. accept $8.937 million in funding from the City of Encinitas and State Active Transportation Program to fully fund construction of the project, in substantially the same form as shown in Attachment 1.
9
Transportation Committee Item 10 | July 19, 2019 1
REGIONAL BIKEWAY PROGRAM UPDATE
Transportation Committee Item 10 | July 19, 2019
2GObyBIKEsd.com
EARLY ACTION PROGRAM
• $200 million in TransNet funds
• Builds 77 linear miles of bikeways
• 70 of 77 miles either open or under design
• 8.8 miles open to date
• 3/4 of investment in City of San Diego
Transportation Committee Item 10 | July 19, 2019 2
3GObyBIKEsd.com
BIKEWAY PROGRAM STATUS
70 of 77 Miles Open or Under Development
11.8
43.9
6.4 7.5
0
5
10
15
20
25
30
35
40
45
50
PE/Environmental Final Design Construction Open To Public
April 2019
4GObyBIKEsd.com
BIKEWAY PROGRAM STATUS
70 of 77 Miles Open or Under Development
3.8
45.4
11.68.8
0
5
10
15
20
25
30
35
40
45
50
PE/Environmental Final Design Construction Open To Public
July 2019
Transportation Committee Item 10 | July 19, 2019 3
RECENT PROGRESS
5
6GObyBIKEsd.com
COASTAL RAIL TRAIL: ENCINITAS
Transportation Committee Item 10 | July 19, 2019 4
7GObyBIKEsd.com
COASTAL RAIL TRAIL: ENCINITAS
8GObyBIKEsd.com
COASTAL RAIL TRAIL: ENCINITAS
Transportation Committee Item 10 | July 19, 2019 5
9GObyBIKEsd.com
COASTAL RAIL TRAIL
10GObyBIKEsd.com
COASTAL RAIL TRAIL: ROSE CREEK BIKEWAY
Transportation Committee Item 10 | July 19, 2019 6
11GObyBIKEsd.com
COASTAL RAIL TRAIL: ROSE CREEK BIKEWAY
12GObyBIKEsd.com
COASTAL RAIL TRAIL: ROSE CREEK BIKEWAY
Transportation Committee Item 10 | July 19, 2019 7
13GObyBIKEsd.com
COASTAL RAIL TRAIL: ROSE CREEK BIKEWAY
14GObyBIKEsd.com
COASTAL RAIL TRAIL: ROSE CANYON BIKEWAY
Transportation Committee Item 10 | July 19, 2019 8
15GObyBIKEsd.com
INLAND RAIL TRAIL: COUNTY OF SAN DIEGO AND CITY OF VISTA
16GObyBIKEsd.com
INLAND RAIL TRAIL: COUNTY OF SAN DIEGO AND CITY OF VISTA
Transportation Committee Item 10 | July 19, 2019 9
17GObyBIKEsd.com
INLAND RAIL TRAIL: COUNTY OF SAN DIEGO AND CITY OF VISTA
18GObyBIKEsd.com
INLAND RAIL TRAIL: COUNTY OF SAN DIEGO AND CITY OF VISTA
Transportation Committee Item 10 | July 19, 2019 10
19GObyBIKEsd.com
CITY OF SAN DIEGO URBAN BIKEWAYS
• Opened bids from contractors for North Park | Mid-City Bikeways, Landis and Georgia-Meade, in June 2019
• Uptown Bikeways: Fourth/Fifth Avenue approved in June 2019, plans to advertise in July 2019
• Pershing, Imperial Avenue, and Bayshore Bikeway Barrio Logan currently under review
20GObyBIKEsd.com
NEXT STEPS
• Continue progress on 24 EAP projects in FY 20 Program Budget
• Provide regular program status updates
Transportation Committee Item 11 | July 19, 2019 1
Transportation Committee Item 11 | July 19, 2019
PROJECT OVERVIEW• 11-mile extension
of the Blue Line Trolley
• Old Town Transit Center to University City
• Nine new stations (five with parking)
• 36 Trolley cars
• Revenue service begins in fall 2021
• $2.17 billion (52% TransNet, 48% FTA)
2
Transportation Committee Item 11 | July 19, 2019 2
MID-COAST CONSTRUCTION SCHEDULE
60% DONE
3
CONSTRUCTION SCHEDULE
Milestone Baseline May 2019 UpdateHeavy Construction Duration 56 months 57.2 months
Reach 14 Track Const. Complete August 2020 October 2020
Start MTS Pre-Revenue Testing April 2021 May 2021
Final Completion by MCTC July 2021 August 2021
Revenue Service Date September 2021 November 2021
4
Transportation Committee Item 11 | July 19, 2019 3
MID-COAST CONSTRUCTION PROGRESS
5
MID-COAST DBE UTILIZATION
6
0.04% 0.23%0.57%
1.05%1.65%
2.46%
3.22%
4.01%
4.92%
5.79%
6.66%
7.46%
8.23%
9.01%
9.76%10.35%
10.76%11.07%11.25%
11.28%
0.04% 0.22%0.62%
1.23%
2.04%
3.09%
3.97%
4.74%
5.86%6.47%
7.00%
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
12.00%
14.00%
MID‐COAST LRTProjected vs. ActualDBE Goal 11.3%
Projected Attainment Realized Attainment To Date Linear (Projected Attainment)
Transportation Committee Item 11 | July 19, 2019 4
DBE SUCCESS STORY
Lucas Builders, Inc.
• Engineering utility contractor• Established in 2004• DBE certified in 2013• Mid-Coast Project success: Contract value grew from $36,000 to $15.5
million Grew from 35 to 54 employees on this project Able to purchase three trucks and plans to
purchase four pieces of equipment New work with City of LA, LA Metro, and LA
County Sanitation District
Leadership, Reliability, Quality & Safety
7
CONSTRUCTION LABOR – May 2019
0 200 400 600 800 1000 1200
Brick Layer
BCI/FSMT
Carpenter
Cement Mason
Electrician
Surveyor
Ironwrkr
Laborer
Operating Eng
Painter
Plumber
Teamster
BrickLayer
BCI/FSMT CarpenterCementMason
Electrician Surveyor Ironwrkr LaborerOperating
EngPainter Plumber Teamster
Cumulative 8 164 308 68 137 38 360 885 746 27 60 278
May‐19 0 42 186 22 31 13 77 225 127 4 24 29
NUMBER OF WORKERS BY TRADE
8
Transportation Committee Item 11 | July 19, 2019 5
CONSTRUCTION ACCOMPLISHMENTS
• Placed final Genesee girder on April 19, 2019
• Placed final LRT flyover girder on May 23, 2019
• I-5 Voigt and Nobel LRT Bridges
• Bike path opened on July 3, 2019
• Navy fuel line relocation
• Settled three additional properties
• First Mid-Coast vehicles delivered
9
CONSTRUCTION UPDATE
10
Tecolote Creek Bridge and Navy Fuel Line (NFL) heroes
Transportation Committee Item 11 | July 19, 2019 6
CONSTRUCTION UPDATE
11
Rail welds near Morena Boulevard and Signal House installation
12
Trolley track installation at Clairemont Drive Station
CONSTRUCTION UPDATE
Transportation Committee Item 11 | July 19, 2019 7
CONSTRUCTION UPDATE
13
Rose Creek North LRT Bridge
CONSTRUCTION UPDATE
14
LOSSAN LRT Flyover
Transportation Committee Item 11 | July 19, 2019 8
CONSTRUCTION UPDATE
15
Rose Canyon Bike Path final location
CONSTRUCTION UPDATE
16
Trolley Underpass at Gilman Drive / La Jolla
Colony Drive
Transportation Committee Item 11 | July 19, 2019 9
17
CONSTRUCTION UPDATE
Trolley Overcrossing south ofNobel Drive and Nobel Drive Station
CONSTRUCTION UPDATE
18
UC San Diego Viaduct – Rail Construction
Transportation Committee Item 11 | July 19, 2019 10
CONSTRUCTION UPDATE
19
Pepper Canyon Station at UC San Diego
CONSTRUCTION UPDATE
20
UC San Diego – Pedestrian Bridge to Preuss School,Scripps Medical Center
Transportation Committee Item 11 | July 19, 2019 11
CONSTRUCTION UPDATE
21
Rail at Voigt Drive Station and
Deck Placement Genesee Avenue
CONSTRUCTION UPDATE
22
UTC Terminus Formwork and Concrete Placement
Transportation Committee Item 11 | July 19, 2019 12
PROJECT RISKS
Risk Item Potential Impact
Right of Way Cost – Mediations, Settlements, Trials Cost
Right of Way - Goodwill Claims Cost (no federal participation)
Fez Street Substation Schedule, Redesign, Cost
Construction Cost, Provisional Sums Cost (if above current estimates)
Construction Unknowns Schedule and Cost (diminishing)
23
RIGHT OF WAY
Mid-Coast Project Acquisitions
Total Property Owners 43
Available for Construction (Possession) 40
Needed Possessions for Construction 3
Acquisitions Settled 35
Under or Pending Negotiation 8
Potential Hearings of Necessity 2
Risks• Settlements, trial, legal, goodwill exposure exceeds budget• 1 - 5 properties go to trial
24
Transportation Committee Item 11 | July 19, 2019 13
LIGHT RAIL VEHICLES
25
• First Mid-Coast car arrived April 4, 2019
• Three more Mid-Coast cars arrived May 7, May 17, and May 31, 2019
SAN DIEGO RIVER BRIDGE
26
Two LOSSAN complete bridge structures, one is operational
Transportation Committee Item 11 | July 19, 2019 14
ELVIRA TO MORENA DOUBLE TRACK
27
Bridge and Trackwork
ROSE CREEK BIKEWAY
28
Santa Fe Street andTrail Area Work
Transportation Committee Item 11 | July 19, 2019 15
GILMAN DRIVE BRIDGE
29
Gilman Drive BridgeUp Lighting
• Stakeholder Outreach – Community Planning Groups
– Monthly Council briefings
– Construction notices
– Shift San Diego
• Community Events– UC San Diego Pepper Canyon
Designathon
– Pure Water open house
– UC Fourth of July celebration
• Media Events– Rose Canyon Bike Path opening
• Public Inquiries and Comments
30
PUBLIC OUTREACH
Transportation Committee Item 11 | July 19, 2019 16
• Project Tours– Nine tours conducted (April-June)
– Participating elected officials included:• Councilmember Monica Montgomery
• Mayor Mary Salas
• Councilmember Jill Galvez
• Councilmember Ronn Hall
• Councilmember Jennifer Campbell
• Social Media MID‐COAST TROLLEY FACEBOOK PAGE
April‐June Stats Overall Likes (City) Overall Likes (Country)
Impressions: 52,738 San Diego: 1,495 United States: 2,079
Video Views: 4,297 Los Angeles: 32 Mexico: 36
Engaged Visitors: 2,857 Chula Vista: 28 United Kingdom: 6
Tijuana: 25 Italy: 5
Oceanside: 24 Taiwan: 3
31
PUBLIC OUTREACH
(877) 379-0110
KeepSanDiegoMoving.com/MidCoast
Mid-Coast Trolley @MidCoastTrolley
Contact Us
32
Transportation Committee Item 11 | July 19, 2019 17
33
Questions?