MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations...

22
1 MELBOURNE METRO RAIL PROJECT: Noise (Construction) & Vibration (Construction & Operation) Expert Witness Conclave Environmental Performance Requirements CONFIDENTIAL & PRIVILEGED [UPDATED - 29/08/2016 10:42:00 AM] Item No. EPR Current EPR (IAC Version 1) Proposed or Revised EPR (italics = comment / recommendation; standard text = proposed wording) Agreed or Not Agreed Discussion 01 EM2 Prepare and implement an Environmental Management System that is certified to ISO 14001:2015 Environmental Management Systems – requirements with guidance for use for construction and operation. Prepare a Construction Environmental Management Plan (CEMP), Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance Requirements and as relevant to any stage of the project. The CEMP should be prepared in accordance with EPA Publication 480, Environmental Guidelines for Major Construction Sites (EPA 1996). EPR should be updated to cross reference New NVB (CNVMP) and relevant EPRs. Agreed (DA) No specific EWS recommendations. 02 EM3 Appoint an Independent Environmental Auditor (for PPP contract only) to undertake environmental audits of compliance with the approved CEMP, Environmental Performance Requirements and approval conditions. EPR should be updated to allow the Independent Auditor access to all materials required to conduct a complete review, including where necessary for sample verification work, access to modelling files, measurement data and supporting test documentation relied upon in the development of design mitigation measures. Agreed An Independent arbiter for noise and vibration should be required. Agreed This is addressed in NV14. 03 B3 Following consultation with potentially affected businesses and prior to main works or shaft construction commencing, prepare management plans to minimise dust, noise and vibration impacts during construction, as per AQ1, NV1 and NV4. EPR should be updated to require a timeline to implement mitigation strategies in sufficient time to enable identified strategies (e.g. 4-6 months) Agreed (DA) Refer to New NVB. 04 SC2 Prior to main works or shaft construction in areas affected, develop a relocation management framework that responds to the Residential Impact Mitigation Guidelines to ensure allows for a uniform approach across the project for the voluntary (temporary) relocation of households subject to: Construction activities likely to unduly affect their amenity (e.g. out of hours works or sustained loss of amenity during the day for shift workers) Loss of access. Consideration to be given to redefining residential as hotels, commercial residences, residential type uses, hospitals and other spaces used for sleep and rest etc. It is recommended that the RIMG be revised and updated following revision of the other EPRs relevant to construction noise and vibration. Agreed (DA) Refer to New NVB. Subject to review of RIMG. (All) There is concern with the current draft of the RIMG. It is not considered adequate or appropriate.

Transcript of MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations...

Page 1: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

1

MELBOURNE METRO RAIL PROJECT: Noise (Construction) & Vibration (Construction & Operation) Expert Witness Conclave –

Environmental Performance Requirements

CONFIDENTIAL & PRIVILEGED [UPDATED - 29/08/2016 10:42:00 AM] Item No.

EPR Current EPR (IAC Version 1) Proposed or Revised EPR (italics = comment / recommendation; standard text = proposed wording)

Agreed or Not Agreed

Discussion

01 EM2 Prepare and implement an Environmental Management System that is certified to ISO 14001:2015 Environmental Management Systems – requirements with guidance for use for construction and operation. Prepare a Construction Environmental Management Plan (CEMP), Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance Requirements and as relevant to any stage of the project. The CEMP should be prepared in accordance with EPA Publication 480, Environmental Guidelines for Major Construction Sites (EPA 1996).

EPR should be updated to cross reference New NVB (CNVMP) and relevant EPRs. Agreed (DA) No specific EWS recommendations.

02 EM3 Appoint an Independent Environmental Auditor (for PPP contract only) to undertake environmental audits of compliance with the approved CEMP, Environmental Performance Requirements and approval conditions.

EPR should be updated to allow the Independent Auditor access to all materials required to conduct a complete review, including where necessary for sample verification work, access to modelling files, measurement data and supporting test documentation relied upon in the development of design mitigation measures.

Agreed

An Independent arbiter for noise and vibration should be required. Agreed This is addressed in NV14.

03 B3 Following consultation with potentially affected businesses and prior to main works or shaft construction commencing, prepare management plans to minimise dust, noise and vibration impacts during construction, as per AQ1, NV1 and NV4.

EPR should be updated to require a timeline to implement mitigation strategies in sufficient time to enable identified strategies (e.g. 4-6 months)

Agreed (DA) Refer to New NVB.

04 SC2 Prior to main works or shaft construction in areas affected, develop a relocation management framework that responds to the Residential Impact Mitigation Guidelines to ensure allows for a uniform approach across the project for the voluntary (temporary) relocation of households subject to:

Construction activities likely to unduly affect their amenity (e.g. out of hours works or sustained loss of amenity during the day for shift workers)

Loss of access.

Consideration to be given to redefining residential as hotels, commercial residences, residential type uses, hospitals and other spaces used for sleep and rest etc. It is recommended that the RIMG be revised and updated following revision of the other EPRs relevant to construction noise and vibration.

Agreed (DA) Refer to New NVB. Subject to review of RIMG. (All) There is concern with the current draft of the RIMG. It is not considered adequate or appropriate.

Page 2: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

2

05 SC3 Prior to main works or shaft construction, develop and implement a Community and Business Involvement Plan to engage potentially affected stakeholders and advise them of the planned construction activities and project progress. This plan should integrate all project activities that potentially impact on community and business operations and provide for a well- coordinated communication and engagement process. The plan must include:

Measures to minimise impacts to the development and/or operation of existing facilities

Measures for providing advance notice of significant milestones, changed traffic conditions, changed access and parking conditions, periods of predicted high noise and vibration activities

Measures for communicating the design and results from environmental monitoring programs (e.g. vibration, noise, dust, ground movement).

Process for registering and management of complaints

Measures to address any other matters which are of concern or interest to them. The plan would consider each precinct and station location in detail. Stakeholders to be considered in the plan include (but are not limited to):

Municipalities

Potentially affected residents

Potentially affected businesses

Recreation, sporting and community groups and facilities

Royal Melbourne Hospital, Victorian Comprehensive Cancer Centre, Peter Doherty Institute and other health and medical facilities

The University of Melbourne

RMIT

Melbourne Grammar

Fawkner Park Children’s Centre and Kindergarten

South Yarra Senior Citizens Centre

Other public facilities in proximity.

To be amended to require that the Residential Impact Management Guidelines (RIMG) are finalised and implemented for the Project. See discussion comment in relation to the RIMG EPR should be updated with a timeline to implement mitigation strategies in sufficient time to enable identified strategies (e.g. 4-6 months) – cross-reference to NV5; Consider adding St Pauls.

Agreed (DA) Refer to New NVB

Page 3: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

3

06 NV1 Manage construction noise in accordance with EPA Publication 1254 Noise Control Guidelines. A number of strong arguments were presented to replace EPA 1254 with

alternative guidelines that prescribed construction noise limits for all time periods, including daytime. The conclave agreed that noise limits recommended in Department of Environment and Climate Change NSW Interim Construction Noise Guidelines (ICNG) or the City of Melbourne Noise and Vibration Management Guidelines (MCC) should be considered. There also needs to be consistency in defining the day, evening and night period. The panel should consider this issue in detail and update the EPR accordingly.

Agreed (TM) In regards to early works, what guidelines, standards etc. are applicable? (SM) Intention of noise limits is to design mitigation to achieve the limit prior to commencing the activities. Facilitates proactive mitigation rather than reactive mitigation. (DA) EPA codes in connection with a framework (e.g. RIMG) provide assurance that all practical measures would be implemented. What is the gap that numerical limits would fill? It would be consistent with Vic practice to retain EPA guidelines. (MSh) (SM) requires numerical criteria, otherwise an impact is not defined. RIMG is irrelevant as works would be programmed during normal working hours or considered unavoidable works where EPA1254 and RIMG do not apply. (MSh) Issue with EPA is it gives a loophole for unavoidable works and subsequent impact to receivers. Does not address the amenity impacts. (PF) (TM) In terms of accountability and impact, it is critical to adopt ICNG or MCC guidelines. (MSt) Adoption of criteria for daytime and UW is important to define unreasonable impact. (TM) biggest concern is definition of UW under EPA 1254. (MDA) The construction plan should also define:

The working periods for key activities that will result in high noise exposure, the measures that have been adopted to limit the duration of these periods, and how working periods will be monitored to avoid unnecessary prolongation of exposure to high noise levels

The measures that will be adopted for the control of impacts related to offsite construction vehicle movements, particularly during the night at site access and departure points in the vicinity of sensitive locations

A clear framework for the implementation of any off-site mitigation measures proposed, prior to commencement of the construction activity in question. This shall included details of consultations and investigations with the affected locations, and verification of the feasibility of implementing the measures proposed.

A program of monitoring to confirm adherence to the plan (WMG) Concern regarding repeated reference to EPA 1254 and allowance for Unavoidable Works to continue without noise restriction. There are no described trigger levels in the EES that would determine when alternative accommodation would be implementation. (TM) Concern regarding the project delays creating impacts outside of permitted hours

Page 4: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

4

07 NV2 For construction works conducted between CBD South station and Domain station, comply with the requirements of the Notification of Referral Decision for the Melbourne Metro Rail Project (EPBC 2015/7549, dated 22 September 2015) under the EPBC Act for vibration monitoring and measurement, as follows:

Conduct pre-construction dilapidation surveys of the nearest Commonwealth Heritage listed structures to the construction activity, including the Former Guardhouse (Block B), to record structural condition and structural integrity prior to commencement of tunnelling

Conduct vibration monitoring at the commencement of tunnelling in geological conditions that are similar to those at Victoria Barracks in order to quantify the actual tunnel boring machine vibration characteristics (level and frequency) for comparison to the values derived from the literature and the German DIN (DIN 4150) target

Conduct continuous vibration monitoring at the nearest Victoria Barracks heritage structures to the construction activity, including the Former Guardhouse (B Block), to assess the actual tunnelling vibration for acceptability, taking into account both the vibration frequency and condition of structures, until monitoring of vibration at the Former Guardhouse (B Block) shows measurements equivalent to preconstruction vibration readings at the Former Guardhouse (B Block)

If monitoring conducted according to the above demonstrates the condition of heritage structures may be degraded as a result of vibration, ground vibration must be reduced by adjusting the advance rate of the tunnel boring machine until monitoring of vibration at the Former Guardhouse (B Block) shows consistent measurements equivalent to preconstruction vibration readings at the Former Guardhouse (B Block).

EPR should to be addressed in the CNVMP as per New EPR NVB.

Agreed (MDA) Prior to commencement of the construction works, a vibration monitoring plan should be submitted for review and approval by the relevant authority. This should include full details of:

vibration measurement methodologies to be adopted for monitoring both baseline and construction levels. This shall include details of the parameters to be obtained, the measurement equipment, parameters to be recorded and relevant standards that shall be adhered to for the collection and analysis of data

baseline and construction vibration monitoring locations

the most critical periods, whether determined by separating distance or ground conditions, and the duration of the monitoring periods.

The requirement of NV2 is also recommended to be extended to apply to Melbourne Town Hall, Melbourne City Baths and St Paul’s Cathedral (AM) The Project should include requirements for a pre-construction condition / dilapidation survey of heritage buildings and potentially vibration sensitive structures at MGS.

Page 5: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

5

08 NV3 Appoint an acoustic and vibration consultant to predict construction noise and vibration (through modelling) and update the modelling to reflect current construction methodology, site conditions and specific equipment noise and vibration levels (this will require noise and vibration measurements). The model would be used to determine appropriate mitigation to achieve the Environmental Performance Requirements.

The acoustic and vibration consultant will also be required to undertake noise and vibration monitoring to assess levels with respect to Guideline Targets specified in the Environmental Performance Requirements. Where monitoring indicates exceedances of Guideline Targets, apply appropriate management measures as a soon as possible.

The findings of the modelling and mitigation investigation shall be documented in a Construction Noise and Vibration Assessment Report, which shall provide the basis for the development of the construction management plan required under NV1. The report shall be reviewed by the Independent Auditor (see separate recommended NV concerning the establishment of an Independent Auditor). The report shall implement any recommendations arising from the review prior to being finalised. The EPR should be changed to refer to a “suitably experienced and qualified person”, rather than an “acoustic and vibration consultant”. With respect to the reference to ‘Guideline Targets specified in the Environmental Performance Requirements’ it is recommended that the panel note the comments and recommendations in relation to NV1 regarding strong support for adoption of alternative guidelines for airborne construction noise.

Agreed

(AM) The Project should include requirements for pre-construction background noise monitoring at MGS. (MSh) Noise 1. Noise monitoring during the demolition and construction phases should be conducted throughout the project to confirm both internal and external noise level criteria are achieved. 2. Monitoring should commence prior to commencement of demolition and construction activities to confirm existing base-line noise levels internally and externally. 3. Continuous noise monitoring throughout the demolition and construction phases should be undertaken at the Westin in both hotel and residential apartments as: a. The site is clearly identified as a noise sensitive receivers b. Incorporates both residential and hotel guests c. The proximity of the site to the proposed demolition and construction site d. Assessment and modelling has been based on the proposed acoustic shed being installed. 4. Any monitoring undertaken should be undertaken both internally and externally to confirm compliance with noise criteria given construction works will occur at night. 5. Monitoring should be undertaken within both the residential and hotel room levels closest to the construction site. 6. Noise and vibration monitoring should be undertaken by an independent suitably qualified company at the cost of the Melbourne Metro and provided to the Westin Hotel. 7. An independent review of the design of the acoustic shed should be undertaken prior to finalisation and approval due to the proximity to the Westin and ensuring compliance with acoustic assessment criteria 8. Prior to commencement of 24-hour construction activities located within the acoustic shed it is recommended that a review of the proposed detailing and construction of acoustic enclosure be conducted by an independent suitably qualified acoustic consultant. The review shall confirm that in principle the enclosure will ensure compliance with noise criteria. 9. If noise monitoring during construction indicates that noise emissions exceed nominated noise criteria, then work associated with that activity should cease where practicable and an alternative method of construction be selected prior to the activity re-commencing. If no other option for that specific activity can be undertaken, then hours of operation should be reviewed to minimise impact on residents and hotel guests.

Page 6: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

6

(MSh) Vibration 1. Continuous vibration monitoring during the demolition and construction phases in our opinion should be undertaken and in particular it is recommended that monitoring be undertaken at the Westin due to a. The site is clearly identified as a sensitive receiver b. Incorporates both residential and hotel guests c. The proximity of the site to the proposed demolition and construction site d. Assessment and modelling has been based on the proposed acoustic shed being installed. 2. Any monitoring undertaken should be undertaken both internally and externally to confirm compliance with criteria given construction works will occur at night. 3. Monitoring should be undertaken within both the residential and hotel room levels closest to the construction site. 4. Noise and vibration monitoring should be undertaken by an independent suitably qualified company at the cost of the Melbourne Metro and provided to the Westin Hotel. 5. If vibration monitoring (both tactile and ground borne noise) during construction is found to exceed nominated criteria then work associated with that activity should cease where practicable and an alternative method of construction be selected prior to the activity re- commencing. If no other option for that specific activity can be undertaken then hours of operation should be reviewed to minimise impact on residents and hotel guests.

09 NV4 Develop and implement a communications plan to liaise with potentially affected community stakeholders and land owners regarding potential noise and vibration impacts. The plan shall include procedures for complaint management.

As a minimum the communications plan should be developed in consultation with City of Melbourne, City of Stonnington, City of Port Phillip and the EPA Victoria. The plan should also specify precinct-specific community consultations that will be conducted as part of developing, and prior to finalising, the Construction Noise and Vibration Management Plan required under NV-1. Intent of NV4 should be included in New NVB.

Agreed (DA) Refer to New NVB, also EPR B3 and SC3 (AM) The project should include requirements Consultation with MGS in the development of construction noise and vibration mitigation and management measures.

10 NV5 Airborne Construction Noise Guideline Targets (Internal)

Implement management actions if construction noise exceeds the internal noise levels below for Highly Sensitive Areas (based on AS/NZS 2107:2000) and a noise sensitive receptor is adversely impacted.

Highly Sensitive Area

Maximum Internal Construction Noise Level LAeq, 15 mins

Intensive Care Wards 45

Operating Theatres 45

Surgeries 45

Wards 40

A number of strong arguments presented to add consideration to additional sensitive uses. The panel should consider this issue in more detail and provide recommendation in the form of an updated EPR.

Agreed (MDA) This is the only proposed EPR which presently includes proposed Airborne Construction Noise Guideline Targets, However, this EPR does not address external noise levels or residential receiver locations. This EPR should therefore be modified to include Guideline Targets that will apply in accordance with EPA 1254 (i.e. evening and night periods), and should also include recommended Guideline Targets for work during normal hours which would be referenced as part of any requirement to monitor the noise of day-time construction work (see recommended modifications to EPR numbers NV1 and NV3). In relation to the Guideline Targets derived in accordance with EPA 1254, the nominated values must be derived on the basis of the background noise level (LA90 as specified in EPA 1254) in lieu of the higher ambient levels (LAeq) that have been referenced in the EES. Further to the above, the proposed internal targets are not considered suitable for prolonged periods of exposure. AS

Page 7: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

7

2107 is primarily concerned with less intrusive types of noise sources such as road traffic. Mitigation measures should therefore be directed at achieving the lower values outlined in AS 2107, Any instances where this cannot be met may be permitted to extend to the upper values that have been presently nominated. It is however expected that concessions to work to the upper levels of AS 2107 would be limited to brief/essential working periods and would need to be clearly identified in the Construction Noise and Vibration Assessment Report recommended in relation to EPR number NV3. The internal targets should also be extended to all other types or relevant non-residential sensitive uses such as offices, schools and hotel accommodation.

Page 8: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

8

(MSt) Educational institutions require noise levels be met within occupied spaces such that those spaces can continue reasonably function. (MSH) should include residential receivers. (TM) should this EPR consider all receiver types? (MSt) Proposed Revision Airborne Construction Noise Guideline Targets (Internal) Implement management actions if construction noise exceeds the internal noise levels below for Highly Sensitive Areas (based on AS/NZS 2107:2000) and a noise sensitive receptor is adversely impacted.

Highly Sensitive Area Maximum Internal Construction Noise level LAeq, 15 mins

Intensive Care Wards 45

Operating Theatres 45

Surgeries 45

Wards 40

Educational institutions (including teaching, research, academic and support spaces)

AS/NZS 2107:2000 satisfactory level plus 5 dB

Notes: 1 The duration of construction noise shall be considered. Acceptable impacts shall be agreed with stakeholders. Mitigation shall be provided in the form of shielding for construction activity and/ or façade improvements where maximum noise levels are expected to be exceeded. 2 Specialist spaces and specific acoustic requirements of spaces shall be addressed depending on their specific requirements. 3 Mitigation to be applied at source in the first instance and then at sensitive receivers where source treatment is not possible. (AM) The airborne construction noise limits recommended by the NSW INCG should be adopted for teaching spaces and office areas within MGS. Specifically, the following noise limits should be applied: i. 45 dB(A) LAeq,15min inside classrooms, teaching spaces and music rooms. ii. 70 dB(A) LAeq,15min outside offices.

11 NV6 Vibration Guideline Targets for Structures

Implement management actions if due to construction activity, the following DIN 4150 Guideline Targets for structural damage

EPR should be updated to require a review of guideline targets following site specific surveys to confirm whether guideline targets are appropriate or require adjustment. The results of the survey need to refine the vibration criteria, where

Agreed (MDA) Measurement of ground propagation characteristics are recommended to improve the confidence of predictions and to ensure that ground settling does not

Page 9: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

9

to buildings (for short-term vibration or long-term vibration) are not achieved.

Short-term vibration on structures

Type of structure

Vibration at the foundation, mm/s (Peak Component Particle Velocity)

Vibration at horizontal plane of highest floor

at all frequencies

1 to 10 Hz

10 to 50 Hz

50 to 100 Hz

1

mm/s (Peak Component

Particle Velocity)

Type 1: Buildings used for commercial purposes, industrial buildings and buildings of similar design

20 20 to 40

40 to 50

40

Type 2: Dwellings and buildings of similar design and/or occupancy

5 5 to15 15 to 20

15

Type 3: Structures that have a particular sensitivity to vibration e.g. heritage buildings

3 3 to 8 8 to 10 8

Notes

1 At frequencies above 100 Hz, the values given in this column may be used as minimum values.

2 Vibration levels marginally exceeding those vibration levels in the table would not necessarily mean that damage would occur and further investigation would be required to determine if higher vibration levels can be accommodated without risk of damage.

3 For civil engineering structures (e.g. with reinforced concrete constructions used as abutments or foundation pads) the values for Type 1 buildings may be increased by a factor of 2.

4 Short-term vibration is defined as vibration which does not occur often enough to cause structural fatigue and which does not produce resonance in the structure being evaluated.

Long-term vibration on structures

Type of Structure

Vibration Velocity, mm/s (Peak Component

Particle Velocity) in horizontal plane at all

frequencies

necessary. The Independent Auditor should be responsible for approving with input from the stakeholder.

occur particularly in the vicinity of St Paul’s Cathedral, Melbourne Town Hall, Melbourne City Baths, RMIT, UoM.

Page 10: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

10

Buildings used for commercial purposes, industrial buildings and similar design

10

Dwellings and buildings of similar design and/or occupancy

5

Structures that have a particular sensitivity to vibration, e.g. heritage buildings

2.5

Notes

1 Vibration levels marginally exceeding those in the table would not necessarily mean that damage would occur and further investigation is required would be required to determine if higher vibration levels can be accommodated without risk of damage.

2 Long-term vibration means vibration events that may result in a resonant structural response.

12 NV7 Undertake condition assessments of above and below ground utility assets and establish construction vibration limits with asset owners.

Monitor vibration during construction to demonstrate compliance with agreed vibration guideline targets. Take remedial action if limits are not met.

Update EPR to include condition assessment and monitoring of vibration during construction at Arden Street Bridge, Swanston Street brick drain, Flinders Street drains, Princes Bridge, Melbourne Town Hall, Melbourne City Baths, St Paul’s Cathedral and utilities (authority and privately owned)

Agreed

13 NV8 Vibration Guideline Targets for Underground Infrastructure

Implement management actions if the following DIN 4150 Guideline Targets for buried pipework/underground infrastructure from construction are not achieved.

Pipe material Vibration Velocity,

mm/s (PPV)

Steel 100

Clay, concrete, reinforced concrete, prestressed concrete, metal

80

Masonry, plastic 50

Notes

1 These values may be reduced by 50% when evaluating the effects of long-term vibration on buried pipework.

2 It is assumed pipes have been manufactured and laid using current technology (however it is noted that this is not the case for the majority of buried pipework potentially affected by Melbourne Metro).

3 Compliance with is to be achieved with asset owner’s Utility Standards.

Update EPR to include specific vibration targets for Swanston Street brick drain and Flinders Street drains in consultation with the responsible authority. Discussions must be undertaken with the asset owner.

Agreed

Page 11: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

11

14 NV9 Vibration Dose Values (VDVs) (Human Comfort)

Implement management actions if the following Guideline Targets (VDVs) (based Table 1 in BS6472-1:2008) for continuous (as for TBMs and road headers), intermittent, or impulsive vibration are not achieved.

Location

VDV (m/s1.75

)

Day 7:00am to 10:00pm

Night 10:00pm to 7:00am

Preferred Value

Maximum Value

Preferred Value

Maximum Value

Residences 0.20 0.40 0.10 0.20

Offices, schools, educational institutions, places of worship

0.40 0.80 0.40 0.80

Workshops 0.80 1.60 0.80 1.60

Notes

1 The Guideline Targets are non-mandatory; they are goals that should be sought to be achieved through the application of feasible and reasonable mitigation measures. If exceeded then management actions would be required.

2 The VDVs may be converted to PPVs within a future noise and vibration construction management plan

EPR to be updated to refer to the relevant Vibration Criteria (VC) presented in ISO Standard 10137:2007 Basis for design of Structures: Serviceability of buildings and walkways against vibration.

Agreed (TM) Reference to VC enables prompt response to exceedances, ID of sources and facilitates rapid action to rectify any exceedance or non compliance, unlike the situation if VDV measured or used

Page 12: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

12

15 NV10 Vibration-sensitive Equipment Guideline Targets

Implement management actions if the following ASHRAE equipment vibration Guideline Targets or measured background levels (whichever is higher) are exceeded for vibration-sensitive equipment during construction and operation at Parkville and CBD North stations.

Equipment requirements Curve

Bench microscopes up to 100x magnification; laboratory robots

Operating Room

Bench microscopes up to 400x magnification; optical and other precision balances; co-ordinate measuring machines; metrology laboratories; optical comparators; micro electronics manufacturing equipment; proximity and projection aligners, etc

VC-A

Microsurgery, eye surgery, neurosurgery; bench microscope at magnification greater than 400x; optical equipment on isolation tables; microelectronic manufacturing equipment such as inspection and lithography equipment (including steppers) to 3mm line widths

VC-B

Electron microscopes up to 30,000x magnification; microtomes; magnetic resonance images; microelectronics manufacturing equipment such as lithography and inspection equipment to 1mm detail size

VC-C

Electron microscopes at magnification greater than 30,000x; mass spectrometers; cell implant equipment; microelectronics manufacturing equipment such as aligners, steppers and other critical equipment for phot-lithography with line widths of ½ micro m; includes electron beam systems

VC-D

Unisolated laser and optical research systems; microelectronics manufacturing equipment such as aligners, steppers and other critical equipment for photolithography with line widths of ¼ micro m; includes electron beam systems

VC-E

Notes

1 The proponent may undertake consultation with the users and agree alternative Guideline Targets.

In respect to Note 5, the EPR should be updated to include:

A requirement that the design assessment for operational vibration compliance incorporate ground vibration propagation measurements at key locations along the alignment, using a suitable method such as the transfer mobility method described in the FTA Transit Noise and Vibration Impact Assessment Manual (2006).

A requirement that a 5dB safety factor be included in the design assessment for noise and vibration.

A requirement to incorporate a track-form consistent with the Very High Attenuation track described in the EES at locations near vibration sensitive equipment in Parkville and near the RMIT campus at CBD North. The extent of this track-form should address, to the extent that can reasonably be determined at the time of detailed design, the location of future vibration sensitive equipment and activities at the Parkville campus of the University of Melbourne. Sensitive Equipment Guideline Targets Implement management actions if the following ASHRAE equipment vibration Guideline Targets or measured background levels (whichever is higher) are expected to be exceeded for vibration-sensitive equipment during construction and operation for example around the Parkville and CBD North stations.

Equipment requirements Curve

Bench microscopes up to 100x magnification; laboratory robots

Operating Room

Bench microscopes up to 400x magnification; optical and other precision balances; co-ordinate measuring machines; metrology laboratories; optical comparators; micro electronics manufacturing equipment; proximity and projection aligners, etc

VC-A

Microsurgery, eye surgery, neurosurgery; bench microscope at magnification greater than 400x; optical equipment on isolation tables; microelectronic manufacturing equipment such as inspection and lithography equipment (including steppers) to 3mm line widths

VC-B

Electron microscopes up to 30,000x magnification; microtomes; magnetic resonance images; microelectronics manufacturing equipment such as lithography and inspection equipment to 1mm detail size

VC-C

Electron microscopes at magnification greater than 30,000x; mass spectrometers; cell implant equipment; microelectronics manufacturing equipment such as aligners, steppers and other critical equipment for phot-lithography with line widths of ½ micro m; includes electron beam systems

VC-D

Unisolated laser and optical research systems; microelectronics manufacturing equipment such as aligners, steppers and other critical equipment for photolithography with line widths of ¼ micro m; includes electron beam systems

VC-E

Equipment specific noise (airborne and structure borne) specifications for sensitive equipment shall be met during construction and operation at Parkville and CBD North stations. Implement management actions (to stakeholder approval) where

Agreed (MDA) Micro and nano scale electron-microscopes at Melbourne University and RMIT University are required to operate continuously. Consideration should be given to reducing risk of disruption to experiments by providing secondary vibration isolation to the equipment and adopting sensitive equipment.

(MSt) Sensitive equipment is generally vibration, noise and EMI sensitive. Equipment specific requirements shall be adopted (including testing methodology) where appropriate. A testing and compliance process should be adopted to ensure limits are achieved.

(DA) better to be done as a performance outcome rather than a specification. A modern system should be able to achieve a good outcome with floating track slab in some areas but not all.

(TM) Should have floating track slab throughout the CBD. MDA have done some checks, and with floating track slab there is risk of exceedance at some receivers, within RMIT. Assessment has not used the detailed FTA method.

(TM) RMIT should be included in Note 5, and consistent with the UoM view that the VC’s should be regarded as limits not to be exceeded rather than guideline targets. Issue of secondary isolation should be considered if the criteria cannot be achieved. (JH) Limits should be relevant to the time of use

(MSt) suggest to remove table and refer to standards for VC curves (ASHRAE 2015 handbook).

Page 13: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

13

specifications are expected to be exceeded. Notes 1 The proponent may undertake consultation with the users and agree alternative Guideline Targets. 2 Equipment manufacturer environmental specifications shall be adopted where available, the appropriateness should consider the time of use and background vibration. 3 Background vibration and noise shall be measured in accordance with equipment environmental test requirements. The duration of any periods of higher background shall be considered and not only the highest period. 4 During the construction phase a continuous monitoring program shall be adopted (to stakeholder approval) with online stakeholder access to all monitoring data using a 75% alert and not to exceed limit approach. Monitoring may be carried out at derived locations to agreement with stakeholders to minimise chance of false alerts. 5 Best available track form vibration isolation to adopted to allow future flexibility at the University of Melbourne.

Page 14: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

14

16 NV11 Ground-borne (internal) Noise Guideline Targets for Amenity

Implement management actions as determined in consultation with potentially affected land owners to protect amenity at residences, sleeping areas in hospital wards, student accommodation and hotel rooms where the following ground-borne noise Guideline Targets (from the NSW Interim Construction Noise Guideline) are exceeded during construction.

Time Period Internal LAeq,15min, dB

Evening, 6pm to 10pm 40

Night, 10pm to 7am 35

Notes

1 Levels are only applicable when ground-borne noise levels are higher than airborne noise levels.

2 The noise levels are assessed at the centre of the most affected habitable room.

3 Management actions include extensive community consultation to determine acceptable level of disruption and provision of respite accommodation in some circumstances.

Ground-borne (internal) Noise Guideline Targets for Amenity Implement management actions as determined in consultation with potentially affected land owners to protect amenity at residences, sleeping areas in hospital wards, student accommodation and hotel rooms where the following ground-borne noise Guideline Targets (from the NSW Interim Construction Noise Guideline) are exceeded during construction. Implement management actions where ground-borne noise levels unreasonably limit usage in educational institutions such as lecture theatres. Notes 1 Levels are only applicable when ground-borne noise levels are higher than airborne noise levels. 2 The noise levels are assessed at the centre of the most affected habitable room. 3 Management actions include extensive community consultation to determine acceptable level of disruption and provision of respite accommodation in some circumstances.

Agreed (MDA) The proposed EPR conflicts with the NV1 which commits to manage construction noise in accordance with EPA Publication 1254 Noise Control Guidelines. While EPA 1254 does not explicitly address ground-borne intrusion paths, the advice it provides in relation to night-time work and airborne intrusion paths is to achieve inaudibility within affected receiver locations. For context, ground-borne noise is generally considered more intrusive then airborne noise; this is evident from the lower targets that have been proposed for operational noise intrusion that is dominated by ground-borne noise. It therefore follows that for consistency with NV1 and EPA 1254, the intrusion targets for ground-borne construction noise at night should also be based on achieving inaudibility. If this cannot be practically achieved, alternative limits must be specified in terms of both the duration of the period of exposure as well as intrusion levels set at significantly lower thresholds than have been presently nominated. In terms of the evening Guideline Targets, there is no direct advice in EPA 1254 with respect to internal noise levels. However, while the Guideline Targets for the evening are consistent with the alternative reference guidance in the NSW Interim Construction Noise Guidelines, prolonged construction noise exposure at an internal level of 40 dB LAeq represents a significant risk. Accordingly, ground-borne noise intrusion at the proposed evening level, if permitted, should be specifically restricted to limited periods (e.g. less than 1 week). (AM) ground-borne construction noise limit of 40 dB(A) LAeq,15min should be adopted for teaching spaces and office areas. This aligns with the evening period noise limit for ground-borne construction noise recommended by the NSW INCG. The Project should also include the likely ground-borne construction noise levels at MGS to be determined and appropriate mitigation measures to be implemented. (MSt) Educational institutions require noise levels be met within occupied spaces such that those spaces can continue reasonably function.

17 NV12 Blasting

Comply with Australian Standard AS2187.2-2006, Explosives – Storage and use Part 2 – Use of explosives for all blasting

For Highly Sensitive Areas, hospital wards, operating theatres and Bio-resources and areas with vibration-sensitive equipment which are not covered in AS2187.2-2006, develop a plan in

Blasting Comply with Australian Standard AS2187.2-2006, Explosives – Storage and use Part 2 – Use of explosives for all blasting For Highly Sensitive Areas, hospital wards, operating theatres and Bio-resources and areas with vibration-sensitive equipment which are not covered in AS2187.2-2006, develop a plan in consultation with facilities owners that: • Avoids damage to vibration-sensitive equipment

Agreed (MSt) Risks associated with Bio-resources mean that mitigation and control require a precautionary approach given the extreme difficulty with mitigation and the lack of consultation options.

Page 15: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

15

consultation with facilities owners that:

Avoids damage to vibration-sensitive equipment

Minimises adverse impact on Highly Sensitive Areas and Bio-resources.

• Minimises adverse impact on Highly Sensitive Areas and prevents impact on Bio-resources. Notes 1 A precautionary approach shall be taken for Bio-resources to ensure no impact from blasting. 2 Vibration at sensitive equipment shall be not exceed levels which would require recalibration.

18 NV13 To protect the amenity of Bio-resources and sensitive research during construction and operation, the following criteria apply:

Background noise should be kept below 50 dB and should be free of distinct tones (internal)

Short exposure should be kept to less than 85 dB (internal).

Notes

1 The levels above should take into consideration the frequency threshold for the Bio-resource under consideration.

2 Higher levels may be acceptable if it can be shown that the Bio-resource under consideration is exposed to higher levels and is not adversely impacted by them.

To protect the amenity of Bio-resources and sensitive research during construction and operation, the following limits apply: • Background noise should be kept below 50 dB Leq and should be free of distinct tones (internal) • Short exposure should be kept to less than 85 dB Lmax (internal). Notes 1 The levels above should take into consideration the frequency threshold for the Bio-resource under consideration. 2 Higher levels may be acceptable if it can be shown that the Bio-resource under consideration is exposed to higher levels and is not adversely impacted by them. 3 Noise includes airborne and structure borne. 4 A precautionary approach shall be taken for Bio-resources to ensure no impact from construction noise and vibration. 5 Background shall be measured in accordance with Bio-resource standards. The duration of any periods of higher background shall be considered and not only the highest period. 6 A continuous monitoring program shall be adopted (to stakeholder approval) with online stakeholder access to all monitoring data. 7 Consideration given to adopting a vibration limit in agreement with MMRA and stakeholders

Agreed (MDA) The proposed EPR is generally considered reasonably but should be clarified in terms of the measurement parameters and measurement durations that apply to background noise and short exposures, including citation of the relevant references for the selected thresholds. (MSt) Risks associated with Bio-resources mean that mitigation and control require a precautionary approach given the extreme difficulty with mitigation and the lack of consultation options. (MSt) Vibration levels shall be kept to less than 75 micro-m/s (VC-A plus 50%).

19 NV14 Appoint an acoustic and vibration consultant to predict noise and vibration and determine appropriate mitigation to achieve the Environmental Performance Requirements. The acoustic and vibration consultant would also be required to undertake commissioning noise and vibration measurements to assess levels with respect to the Environmental Performance Requirements.

The EPR should be updated to require that the noise and vibration consultant shall prepare the Construction and Operational Noise and Vibration Reports for review and approval by the Independent Auditor commissioned to review the predictions and proposed design mitigation measures.

Agreed (MDA) In contrast to the Governance Framework outlined in Chapter 23, the Independent Auditor should not be appointed jointly by the MMRA and PPP. It is recommended that the Independent Auditor should be selected and engaged by the Department of Transport, Planning and Local Infrastructure, with costs borne by the MMRA and/or PPP contractor. The Independent Auditor should also be granted access to all materials required to conduct a complete review, including where necessary for sample verification work, access to modelling files, measurement data and supporting test documentation relied upon in the development of design mitigation measures

20 NV15 Victorian Passenger Rail Infrastructure Noise Policy (PRINP)

Avoid, minimise or mitigate rail noise where the following PRINP (April 2013) Investigation Thresholds are exceeded during operation:

Time Type of Receiver Investigation Thresholds

Day (6am – 10pm)

Residential dwellings and other buildings where people sleep

65 dBLAeq and a change in 3 dB(A) or more

or

EPR to be updated to reflect the following comments: The proposed performance targets are considered appropriate, based on PRINP, subject to the inclusion of the appropriate internal noise targets to address the locations near the Eastern Portal that the EES proposes would be addressed through offsite mitigation (retrospective façade insulation measures) rather than barriers. Consistent with the EES proposed NV1, this EPR should also include requirements to document the proposed methods of achieving the targets. Specifically, the findings of all detailed modelling and mitigation assessments during the design development shall be documented in an Operational Noise and Vibration Assessment Report. The report shall be reviewed by the Independent Auditor (see separate MDA

Agreed

Page 16: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

16

including aged persons homes, hospitals, motels and caravan parks

Noise sensitive community buildings, including schools, kindergartens, libraries

85 dBLAmax and a change in 3 dB(A) or more

Night (10pm – 6am)

Residential dwellings and other buildings where people sleep including aged persons homes, hospitals, motels and caravan parks

60 dBLAeq and a change in 3 dB(A) or more

or

85 dBLAmax and a change in 3 dB(A) or more

Notes

1 If an investigation shows that the thresholds are not exceeded, then no further action is considered under the PRINP.

2 LAmax, is defined as maximum A-weighted sound pressure level and is the 95 percentile of the highest value of the A-weighed sound pressure level reached within the day or night.

3 For Melbourne Metro the location of assessment is at 1m from the centre of the window of the most exposed external façade.

comments for NV14 concerning the establishment of an Independent Auditor). The report shall implement any recommendations arising from the review prior to being finalised. An additional report shall be prepared documenting a proposed operational noise compliance monitoring plan, including details of monitoring locations and methodologies.

21 NV16 For operation, comply with State Environment Protection Policy (Control of Noise from Commerce, Industry and Trade) No. N-1 (SEPP N-1). This does not apply to trains and trams.

Consideration to be given to noise limits determined in accordance with SEPP N-1 ‘Day’ period requirements should be applied at the facade of the MGS buildings.

Agreed

For operation, comply with State Environment Protection Policy (Control of Noise from Commerce, Industry and Trade) No. N-1 (SEPP N-1). This does not apply to trains and trams. For sensitive usages not covered by SEPP N-1 noise levels within spaces shall comply with AS/NZS 2107:2000 satisfactory levels. Update EPR to consider outdoor guidelines for schools (AAAC guidelines).

Agreed (MSt) Expanded coverage to include non-residential receivers.

22 NV17 Ground-borne Noise Guideline Targets for Operation

Where operational ground-borne noise trigger levels are exceeded for sensitive occupancies as shown in the table below (trigger levels are based on the Rail Infrastructure Noise Guideline, 17 May 2013 (RING

(1)), assess feasible and reasonable

mitigation to reduce noise towards the relevant ground-borne noise trigger level.

Sensitive land use Time of day Internal noise trigger levels

Residential Day (7am-10pm)

40 dBLASmax and an increase in existing rail noise level by 3 dB(A)

EPR to be updated to reflect the following comments: As per MDA comments with respect to NV15, the findings of all detailed modelling and mitigation assessments during the design development shall be documented in an Operational Noise and Vibration Assessment Report. The purpose being to demonstrate how the completed project is proposed to adhere to the targets established in NV17. The report shall be reviewed by the Independent Auditor (see separate MDA comments for NV14 concerning the establishment of an Independent Auditor). The report shall implement any recommendations arising from the review prior to being finalised. An additional report shall be prepared documenting a proposed operational noise compliance monitoring plan, including details of monitoring locations and methodologies.

Agreed

Page 17: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

17

or more

Night (10pm-7am)

35 dBLASmax and an increase in existing rail noise level by 3 dB(A) or more

Schools, educational institutions, places of worship

When in use 40-45 dBLASmax and an increase in existing rail noise level by 3 dB(A) or more

Hospitals(bed wards and operating theatres)

24 hours 35 dB(A) LASMax

Offices When in use 45 dB(A) LASMax

Cinemas and Public Halls

When in use 30 dB(A) LASMax

Drama Theatres When in use 25 dB(A) LASMax

Concert halls, Television and Sound Recording Studios

When in use 25 dB(A) LASMax

Notes

1 RING provides trigger levels for residential and schools, educational institutions and places of worship, but does not provide guidance on acceptable ground-borne noise levels for other types of sensitive receivers. Ground-borne noise trigger levels for other types of sensitive occupancies have been devised based on RING and industry knowledge.

2 Specified noise levels refer to noise from heavy or light rail transportation only (not ambient noise from other sources).

3 Assessment location is internal near to the centre of the most affected habitable room.

4 LASmax refers to the maximum noise level not exceeded for 95% of the rail pass-by events.

5 For schools, educational institutions, places of worship the lower value of the range is most applicable where low internal noise levels is expected.

6 The values for performing arts spaces may need to be reassessed tohe specific requirements of a venue.

The wording of EPR NV17 should be strengthened to make the proposed target criteria for operational ground-borne noise and vibration mandatory.

Page 18: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

18

23 NV18 Vibration Guideline Targets for Operation

During operation, achieve the Guideline Targets (based on Table 1 in BS6472-1:2008) or background levels (whichever is higher) for vibration as follows:

Location

VDV (m/s1.75

)

Day 7:00am to 10:00pm

Night 10:00pm to 7:00am

Preferred Value

Maximum Value

Preferred Value

Maximum Value

Residences 0.20 0.40 0.10 0.20

Offices, schools, educational institutions, places of worship

0.40 0.80 0.40 0.80

Workshops 0.80 1.60 0.80 1.60

Notes

1 The Guideline Targets are non-mandatory; they are goals that should be sought to be achieved through the application of feasible and reasonable mitigation measures.

2 Compliance with these values implies no structural damage due to operation.

EPR to be updated to reflect the following comments: As per MDA comments with respect to EPR numbers NV15 and NV17, the measures to achieve compliance with these targets should be documented in an Operational Noise and Vibration Compliance Report for review by the independent Auditor. The wording of EPR NV18 should be strengthened to make the proposed target criteria for operational ground-borne noise and vibration mandatory. Update EPR to delete Note 1.

Agreed

(TM) Comment re: best possible trackforms see NV10 Note 5

24 New NVA

Establish a Parkville Reference Group comprising of relevant government agencies including MMRA, PTV, VicRoads, The Victorian Department of Health and Human Services, Ambulance Victoria, Yarra Trams, and key institutions in the Parkville Precinct.

Consideration to be given to strengthening this EPR to align with NV and other EPR requirements.

Agreed

25 New NVB

Construction Noise and Vibration Management Plan

Develop and implement a Construction Noise and Vibration Management Plan (“CNVMP”) in consultation with EPA Victoria and the relevant councils key stakeholders. The CNVMP must be informed by the modelling undertaken by the acoustic and vibration consultant in accordance with NV3 and must include (but not be limited to):-

General

(1) identification of sensitive receivers along Melbourne Metro’s alignment;

(2) details of construction activities and an indicative schedule for construction works, including the identification of key noise and/or vibration generating construction activities (based on representative construction scenarios, including at ancillary facilities) that have the potential to generate noise and/or vibration impacts on surrounding sensitive receivers.

Further consideration should be taken into account to update the EPR, including the following:

The purpose of the CNVMP shall include: o To allow detailed independent review and approval o To provide a comprehensive and self-contained document o To provide the basis for informing the community about the

impacts and how they will be managed

The CNVMP shall cover: o Acoustic Terminology / Glossary o Location of works and site plan o Applicable criteria o Details of contractor o Description of works, including programme o Work methods o Hours (including the need for any works carried out outside of

normal working hours) o Number, type and make of construction plant & equipment and

Agreed (SM) Content required is vague and content would vary on whether it would be a public or private document. Purpose of the plan should be defined, who is being communicated with and for what purpose.

Consensus – Documentation needs to be produced that is informative to the impacted receivers. CNVMP should facilitate community notification.

(TM) (AM) reference to councils is not relevant in the CNVMP, replace reference to Councils with key stakeholders (1

st sentence, 1

st para). Approval should

be sought from the Independent Auditor.

(JH) Methodology for conditions surveys should be incorporated into the CNVMP. Requirement that there

Page 19: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

19

associated noise and vibration source levels o Ambient Noise and Vibration Monitoring: methodology,

locations, analysis and resultsPredicted noise and vibration levels. All noise and vibration predictions are to be presented (as a minimum) as facade noise maps for a distance of at least 300 m in all directions from each work site / project area under assessment.

o Summary of noise and vibration impacts, including consideration of cumulative impacts

o Proposed steps to reduce noise and vibration o Proposed noise and vibration monitoring regime

Consideration should be given to a range of uses (daytime), not just residential.

New NVB to be updated to reflect any recommended changes to EPRs.

should be a conditions survey should be captured by another EPR (consider modifying NV7)

(SM) CNVMP should be revisited each time the nature of the works has changed or 6 monthly during construction.

26 New NVB (cont’d)

Airborne Noise

(3) identification of reasonable and practicable measures to be implemented to manage construction noise impacts in accordance with with reference to:

(i) EPA Publication 1254 Noise Control Guidelines as specified in NV1, and

(ii) the airborne construction noise guideline targets (internal) specified in NV5

(4) any management actions to be implemented if predicted noise levels exceed, for an extended period of time, the guideline targets specified in NV1 or NV5;

(5) any measures to be implemented in accordance with the MMRA Residential Impact Mitigation Guidelines

Pending resolution of NV1 in relation to EPA 1254, clause 3(i) may need to be revised.

Agreed (MSt) Update to recognise specific requirements raised elsewhere.

(TM) Should address impacts to amenity and sleep for construction activities at night.

27 New NVB (cont’d)

Vibration: Structures

(6) a description of the condition of all above- and below-ground utility assets assessed in accordance with NV7

(7) identification of reasonable and practicable measures to be implemented to manage construction vibration impacts in accordance with the:

(i) vibration guideline targets for structures specified in NV6

(ii) construction vibration limits for above and below ground utility assets determined in accordance with NV7

(iii) vibration guideline targets for underground infrastructure specified in, or as otherwise determined in accordance with NV8

(8) any management actions to be implemented if predicted vibration levels exceed, for an extended period of time, the guideline targets specified in NV6, NV7, or NV8

(9) specific heritage measures where relevant in accordance with CH2.

28 New NVB (cont’d)

Vibration and Ground-borne Noise: Human Comfort

(10) identification of reasonable and practicable measures to be

Update EPR to correct 10(i) to refer to RMS velocity, delete PPV reference. Agreed

Page 20: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

20

implemented to manage construction vibration and ground-borne noise impacts in accordance with the:

(i) vibration dose values for human comfort specified in NV9 (which may be expressed as peak particle velocity rates for the purposes of the CVNMP)

(ii) ground-borne (internal) noise guideline targets for amenity specified in NV11

(11) any management actions to be implemented if predicted vibration or ground-borne noise levels exceed, for an extended period of time, the guideline targets identified in NV9 or NV11

(12) any measures to be implemented in accordance with the Residential Impact Mitigation Guidelines

29 New NVB (cont’d)

Vibration and Ground-borne Noise: Sensitive Equipment and Bio-resources

(13) identification of reasonable and practicable measures, to be determined following consultation with the Parkville Reference Group, to be implemented to manage construction vibration and ground-borne noise impacts in accordance with the:

(i) vibration sensitive equipment guidelines specified in, or as otherwise determined in accordance with NV10

(ii) bio-resource guideline targets specified in, or as otherwise determined in accordance with NV13

(14) any management actions to be implemented if predicted vibration or ground-borne noise levels exceed, for an extended period of time, the guideline targets identified in NV10 or NV13

Consideration to be given to mandatory limits for Bio resources and sensitive equipment, not targets. Continuous noise and vibration monitoring at representative derived critical locations with transparent access to historical results to demonstrate compliance with limits. Alarm set at 75% of limit at which management action is required. Limits not to be exceeded.

Agreed (MSt) Update to recognise specific requirements raised elsewhere.

30 New NVB (cont’d)

Blasting

(15) if blasting is proposed, an assessment of the potential noise and vibration impacts associated with blasting activities, and the identification of measures to ensure compliance with Australian Standard AS2187.2-2006 as specified in NV12

(16) any measures to be implemented in accordance with the Residential Impact Mitigation Guidelines

Consideration should be given to a blasting exclusion zone for the Parkville Precinct.

Agreed

31 New NVB (cont’d)

Community Consultation

(17) details of all community consultation measures to be implemented in accordance with NV4 and SC2 including:

(i) any precinct-specific community consultation measures; and

(ii) the establishment of measures concerning complaints management.

32 New NVB (cont’d)

Haulage

(18) operational procedures and controls that minimise truck noise, including, but not limited to, consideration of the following:

(i) Where reasonable and practicable, limit heavy

Haulage

(18) operational procedures and controls that minimise truck noise, including, but not limited to, consideration of the following:

(i) Where reasonable and practicable, limit heavy construction vehicle movements to Normal Working Hours (as defined by the EPA) providing

Agreed

Page 21: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

21

construction vehicle movements to Normal Working Hours (as defined by the EPA) providing this limitation does not include vehicles essential to maintaining construction operations;

(ii) Where practical, select traffic routes with existing heavy vehicle usage and avoid local roads (e.g. residential streets), particularly 24-hour activities;

(iii) Install ‘no engine braking’ signs on designated routes;

(iv) Ensure trucks are fitted with mufflers that comply with the original equipment manufacturer specifications;

(v) Enforce speed restrictions on all construction vehicles;

(vi) Complete regular maintenance checks of road surfaces and trucks;

(vii) Implement temporary changes to traffic light sequences on designated routes to minimise trucks starting and stopping at junctions;

(viii) Monitor construction vehicle driver behaviour;

(ix) Identify locations for trucks to idle pending arrival at construction sites.

this limitation does not include vehicles essential to maintaining construction operations;

(ii) Where practical, select traffic routes with existing heavy vehicle usage and avoid local roads (e.g. residential streets), particularly 24-hour activities;

(iii) Install ‘no engine braking’ signs on designated routes;

(iv) Ensure trucks are fitted with mufflers that comply with the original equipment manufacturer specifications and relevant EPA in-service noise requirements;

(v) Enforce speed restrictions on all construction vehicles;

(vi) Complete regular maintenance checks of road surfaces and trucks;

(vii) Implement temporary changes to traffic light sequences on designated routes to minimise trucks starting and stopping at junctions;

(viii) Monitor construction vehicle driver behaviour;

(ix) Identify locations for trucks to idle pending arrival at construction sites. (x) minimise the need for trucks to reverse and mandate the use of broadband reverse alarms (xi) address noise from any truck wash required as vehicles leave site, particularly at night

33 New NVB (cont’d)

Monitoring

(19) mechanisms to ensure effective monitoring of noise and vibration associated with construction in accordance with NV3, including:

(i) vibration and noise measurement methodologies for monitoring both baseline and construction levels, including details of the parameters to be obtained, the measurement equipment, parameters to be recorded, and relevant standards to be adhered to for the collection and analysis of data;

(ii) baseline and construction noise and vibration monitoring locations;

(iii) the most critical periods, whether determined separating distance or ground conditions, and the duration of monitoring periods;

(iv) how the results of monitoring would be recorded, reported, and interpreted.

Refer to NV3 Agreed

34 New EM1

N/A Equipment specific electro-magnetic interference specifications for sensitive equipment shall be met during construction and operation at Parkville and CBD North stations. Implement management actions (to stakeholder approval) where specifications are expected to be exceeded.

N/A EM expertise was not represented at the conclave. (MSt) Sensitive equipment is generally vibration, noise and EMI sensitive. Equipment specific requirements shall be adopted (including testing methodology) where appropriate. A testing and compliance process should be adopted to ensure limits are achieved.

35 New EM2

N/A Best available electro-magnetic interference systems design (train and power system) to adopted to allow future flexibility at the University of Melbourne.

N/A As above

36 New EM3

N/A A continuous EMI monitoring program shall be adopted (to stakeholder approval) with online stakeholder access to all monitoring data.

N/A As above

37 New EPR

N/A Project requirement to use low-noise technology such as electrically powered cranes and other such equipment wherever possible, rather than simply accepting the way things have been done in the past. (HK notes for New NVB)

Addressed by other EPRs

Page 22: MELBOURNE METRO RAIL PROJECT: Noise …...Site Environment Implementation Plans, Operations Environmental Management Plan (OEMP) and other plans as required by the Environmental Performance

22

By Signing below, each named expert has endorsed that this document is a true summary of the discussion held and the points agreed or disagreed between the experts at the Conclave, held on Thursday 25 August 2016 at 6 Gipps Street, Collingwood Victoria 3066.

Peter Fearnside (PF) Timothy Marks (TM) Ross Leo (RL)

Andrew Mitchell (AM) Neville Goddard (NG) Matthew Stead (MSt)

Simon McHugh (SM) Matthew Shields (MSh) John Heilig (JH)

David Anderson (DA)