Megaprojects - New Psychiatric hospital in Slagelse
Presentation 03.12.2015 by Henrik Bendix Olsen
Hospital projects in Denmark
The kvalitetsfond
constructions are partly
funded by the government
with 60% and regional
funded with 40%.
16 projects with a total cost
of 42 billion ddk.
Hospitals in Region SealandKvalitetsfond projects
Slagelse acute department
Hospital floor space: 11.000 m²
Beds: 85 total consisting of: 50 acute beds, 15
intensive beds and 20 cardiac monitoring beds.
Projekt sum: 0.315 billion ddk.
Occupancy of the hospital – late 2013
Slagelse psychiatric hospital
Hospital floor space: 44.000 m²
Site size: 158.463 m²
Beds: 194 total consisting of: 114 general
psychiatric beds, 50 forensic psychiatric beds
and 30 beds in a high secure ward.
Employees: approx. 650
Projekt sum: 1.2 billion ddk.
Occupancy of the hospital – late 2015
Koege University hospital
Hospital floor space: 189.000 m²
Site size: 275.000 m²
Beds: 900 total
Employees: approx. 4130
Projekt sum: 4 billion ddk.
Occupancy of the hospital – 2022
Special kvalitetsfond demands
Control manual
- Organisation
- Risk management
- Controlling
3D project, IKT
- New technology
Fixed bottomline
- Large reserves
- Change request lists
Networking
- Quarterly rapports
Innovation
Organisation diagram
Advisors
Building owner:
Region Sjælland
Architect (Lead consultant):
Karlsson arkitekter / VLA i/s
Advisors (architect):
Schønherr
Moe
NNE Pharmaplan
Cenergia Energy Consultants
Bartenbach Light Design
Signal
Advisor (building owner):
Kuben Management A/S
Construction/site management:
Rambøll
Security:
Molter Consult
External controlling:
Arkitema Architects
7
Kvalitet og Udvikling – KU Byg – Alleen 15 – 4180 Sorø
7
New Psychiatric hospital in SlagelseTime schedule
Activity Time
General planning (Mangor & Nagel) 2008 to 2009
Advisor to the building owner (Kuben) Primo 2010
Lead consultant choosen by competition (Karlsson architects og Vilhelm Lauritsen architects)
Ultimo 2010
Usergroups, temp. Building program & Kvalitetsfond-application (Karlsson architects and Vilhelm Lauritsen architects)
Primo2011
Kvalitetsfond accept Ultimo2011
Usergroups & planning finished - Ultimo2012
Construction management (Rambøll) Ultimo 2012
Licitation - building Nov. 2012
Construction site and excavation Ultimo2012
Building period 2013 - 2015
Contractor hand over & operation start up Medio 2015
Hand over to psychiatry 1. August 2015
Arial photo 12. november 2015
Main entrance – office building
Entrance area
Office building - atrium
Sports and exercise centre
Patient area
Garden - patient area
Multistimuli-area, General psychiatric
HIS, General psychiatric
17
GAPS – LED lightThe most advanced system in the world
17
LED light:
Dynamic light with the ability to control each roomseparatly.
18
Building integrated art / colours
18
Painter: Malene Landgreen
Author:Ursula Andkjær Olsen
19
Psychiatric bed
19
Billedkunstner: Malene Landgreen
Forfatter:Ursula Andkjær Olsen
LED-belysning indgår som en del af kunststrategien
20
DGNB – pre-certification
20