Meeting Punch List 08-10-14 TG Hall Piping

29
1 2 3 5 1 2 3 4 5 6

description

punchlista

Transcript of Meeting Punch List 08-10-14 TG Hall Piping

FEED WATER SYSTEMFEED WATER SYSTEM DATE 08-10-20141MANUAL VALVE ERECTED IN PLACE OF MOV IN REHEAT DESUPER HEATING LINE FROM BFP-ATo check with Krishnan sir2MANUAL VALVE ERECTED IN PLACE OF MOV IN REHEAT DESUPER HEATING LINE FROM BFP-BTo check with Krishnan sir3MANUAL VALVE ERECTED IN PLACE OF MOV IN REHEAT DESUPER HEATING LINE FROM BFP-CTo check with Krishnan sir5BOILER FILL LINE SAFETY VALVE NOT ERECTEDC & I1BFP A NDE side bearing temperature RTD broken2Pressure Gauge nor provided in the Pump & Pipe line33 Way valve yet to be calibrated4HP heater 1,2, 3 TI & PI gauge to be erect5For all HP heater cascade line TP to be erect6On HP heater 2 to 3 cascade line CV cabling to be donecabling completed, termination to be done

FEED WATER INSTRUMENTRKM COMMISSIONING - Feed Water System 20-9-2014InstrumentLocationKKSErection StatusRemarks9/15/1410/8/14InstrumentCablingDeaerator to Booster PumpTemperature point suction of BP 'A'TP-10LAB10CT901NANAStub PresentStub PresentRequired at the time of PG testTemperature point suction of BP 'B'TP-10LAB50CT901NANAStub PresentStub PresentRequired at the time of PG testTemperature point suction of BP 'C'TP-10LAB80CT901NANAStub PresentStub PresentRequired at the time of PG testTemperature indicator suction of BP 'A'TI-10LAB10CT301CompletecompletedcompletedTemperature indicator suction of BP 'B'TI-10LAB50CT301CompletecompletedcompletedTemperature indicator suction of BP 'C'TI-10LAB80CT301CompletecpmpletedcompletedPressure Indicator *Inlet of BP 'A' suction Strainer PI-10LAB10CP501Not CompleteNATapping Point not PresentTapping Point Presenterected at the time of startsPressure Indicator *Inlet of BP 'B' suction Strainer PI-10LAB50CP501Not CompleteNATapping Point not PresentTapping Point Presenterected at the time of startsPressure Indicator *Inlet of BP 'C' suction Strainer PI-10LAB80CP501Not CompleteNATapping Point not PresentTapping Point Presenterected at the time of startsPressure difference alarm (H)Across suctio strainer BP 'A' InletPDA-10LAB10DP201CompleteImpules Pipe not CompleteImpules Pipe not CompletecompletedPressure difference alarm (H)Across suctio strainer BP 'B' InletPDA-10LAB10DP201CompleteImpules Pipe not CompleteImpules Pipe not CompletecompletedPressure difference alarm (H)Across suctio strainer BP 'C' InletPDA-10LAB10DP201CompleteImpules Pipe not CompleteImpules Pipe not CompletecompletedPressure Indicator Transmittersuction of BP 'A'PI(T)-10LAB10CP001CompletecompletedPressure Indicator Transmittersuction of BP 'B'PI(T)-10LAB50CP001CompletecompletedPressure Indicator Transmittersuction of BP 'C'PI(T)-10LAB80CP001CompletecompletedPressure Indicator *suction of BP 'A'PI-10LAB10CP502Not CompleteNAcompletedPressure Indicator *suction of BP 'B'PI-10LAB50CP502Not CompleteNAcompletedPressure Indicator *suction of BP 'C'PI-10LAB80CP502Not CompleteNAcompletedTemperature indicator *suction of BP 'A'TI-10LAB10CT801Not CompleteNAcompletedTemperature indicator *suction of BP 'B'TI-10LAB10CT801CompleteNAcompletedTemperature indicator *suction of BP 'C'TI-10LAB10CT801CompleteNAcompletedInstrumentLocationKKSErection StatusRemarksRemarksInstrumentCablingBooster Pump to Boiler Feed PumpPressure Indicator * BP 'A' dischargePI-10LAB15CP501Not CompleteNAerected at the time of startsPressure Indicator *BP 'B' dischargePI-10LAB55CP501Not CompleteNAerected at the time of startsPressure Indicator * BP 'C' dischargePI-10LAB85CP501Not CompleteNAerected at the time of startsPressure Indicator & Control BP 'A' dischargePIC-10LAB15CP001CompletecompletedPressure Indicator & ControlBP 'B' dischargePIC-10LAB55CP001CompletecompletedPressure Indicator & Control BP 'C' dischargePIC-10LAB85CP001CompletecompletedTemperature indicator & control BP 'A' dischargeTIC-10LAB15CT301Not CompleteInstrument erection completedcompletedTemperature indicator & controlBP 'B'dischargeTIC-10LAB55CT301Not CompleteInstrument erection completedcompletedTemperature indicator & control BP 'C' dischargeTIC-10LAB85CT301Not CompleteInstrument erection completedcompletedFlow Indicator & Control * BP 'A' dischargeFIC-10LAB15CF001CompleteImpules Pipe not CompleteImpules Pipe not Complete - 19-09-14completedFlow Indicator & Control*BP 'B'dischargeFIC-10LAB55CF001CompleteImpules Pipe line welding not completedImpules Pipe line welding not completed - 19-09-14completedFlow Indicator & Control* BP 'C' dischargeFIC-10LAB85CF001CompleteFlow meter not erected & Impules Pipe not CompleteFlow meter erected & Impules Pipe not Complete - 19-09-14completedPressure Indicator *Inlet of BFP 'A' suction Strainer PI-10LAB15CP502Not CompleteNApr. Gauge erected at the time of startsPressure Indicator *Inlet of BFP 'B' suction Strainer PI-10LAB55CP502Not CompleteNApr. Gauge erected at the time of startsPressure Indicator *Inlet of BFP 'C' suction Strainer PI-10LAB85CP502Not CompleteNApr. Gauge erected at the time of startsPressure difference alarm (H)Across suctio strainer BFP 'A' InletPDA-10LAB15DP201CompleteImpules Pipe not CompleteImpules Pipe Complete. Manifold to be fixedcompletedPressure difference alarm (H)Across suctio strainer BFP 'B' InletPDA-10LAB55DP201CompleteImpules Pipe not CompleteImpules Pipe Complete. Manifold to be fixedcompletedPressure difference alarm (H)Across suctio strainer BFP 'C' InletPDA-10LAB85DP201Not CompleteImpules Pipe not CompleteInstrument fixed. Impules Pipe Complete. Manifold to be fixedcompletedPressure indicator & switch (L)*Suction of BFP 'A' PIS-10LAB15CP201CompleteImpules Pipe not CompleteImpules Pipe Complete.Manifold to be fixedcompletedPressure indicator & switch (L)*Suction of BFP 'B' PIS-10LAB55CP201CompleteImpules Pipe not CompleteImpules Pipe Complete.Manifold to be fixedcompletedPressure indicator & switch (L)*Suction of BFP 'C' PIS-10LAB85CP201CompleteImpules Pipe not CompleteImpules Pipe Complete.Manifold to be fixedcompletedpressure indicator & switch(LLL) Suction of BFP 'A' PIS-10LAB15CP202CompleteImpules Pipe not CompleteImpules Pipe Complete.Manifold to be fixedcompletedpressure indicator & switch(LLL) Suction of BFP 'B' PIS-10LAB55CP202CompleteImpules Pipe not CompleteImpules Pipe Complete.Manifold to be fixedcompletedpressure indicator & switch(LLL) Suction of BFP 'C' PIS-10LAB85CP202CompleteImpules Pipe not CompleteImpules Pipe Complete.Manifold to be fixedcompletedPressure Indicator *Suction of BFP 'A' PI-10LAB15CP503Not CompleteNAcompletedPressure Indicator *Suction of BFP 'B' PI-10LAB55CP503Not CompleteNApr. Gauge erected at the time of startsPressure Indicator *Suction of BFP 'C' PI-10LAB85CP503Not CompleteNApr. Gauge erected at the time of startsInstrumentLocationKKSErection StatusRemarksRemarksInstrumentCablingBFP Discharge Piping To Three Way ValvePressure Indicator * BFP 'A' DischargePI-10LAB20CP501Not CompleteNANot CompletecompletedPressure Indicator *BFP 'B' DischargePI-10LAB60CP501Not CompleteNANot Completepr. Gauge erected at the time of startsPressure Indicator *BFP 'C' DischargePI-10LAB90CP501Not CompleteNANot Completepr. Gauge erected at the time of startsPressure point BFP 'A' DischargePP-10LAB20CP901NANARequired at the time of PG testPressure point BFP 'B' DischargePP-10LAB60CP901NANARequired at the time of PG testPressure point BFP 'C' DischargePP-10LAB90CP901NANARequired at the time of PG testPressure Indicator & alarm BFP 'A' DischargePIA-10LAB20CP001CompletecompletedPressure Indicator & alarmBFP 'B' DischargePIA-10LAB60CP001CompletecompletedPressure Indicator & alarmBFP 'C' DischargePIA-10LAB90CP001CompletecompletedTemperature Indicator & Alarm BFP 'A' DischargeTIA-10LAB20CT301Not Complete9/19/14completedTemperature Indicator & Alarm BFP 'B' DischargeTIA-10LAB60CT302Not Complete9/19/14completedTemperature Indicator & Alarm BFP 'C' DischargeTIA-10LAB90CT303Not Complete9/19/14completedPressure pointBFP Common Discharge linePP-10LAB25CP901NARequired at the time of PG testPressure indicatorBFP Common Discharge linePI-10LAB25CP501NAerected at the time of startsPressure indicator alarmBFP Common Discharge linePIA-10LAB25CP001CompletedcompletedPressure indicator alarmBFP Common Discharge linePIA-10LAB25CP002CompletedcompletedTemperature point BFP Common Discharge lineTP-10LAB25CT901NARequired at the time of PG testInstrumentLocationKKSErection StatusRemarksRemarksInstrumentCablingThree way valve at HP Heater 3 inlet to EconomiserPressure indicator *HP Heater #3 inlet10LAB25CP502Not CompleteNAstub presentInstrument erection completedcompletedTemperature indicator & alarm HP Heater #3 inlet10LAB25CT301Complete CompletecompletedTemperature indicator*HP Heater #3 inlet10LAB25CT801CompleteNARequired at the time of PG testTemperature point HP Heater #3 inlet10LAB25CT902NANAStub PresentRequired at the time of PG test

Temperature point HP Heater #3 outlet10LAB25CT903NANAStub PresentRequired at the time of PG testTemperature indicator & alarm HP Heater #2 inlet10LAB25CT302CompleteNot Complete9/19/14CompleteTemperature indicator *HP Heater #2 inlet10LAB25CT802CompleteNARequired at the time of PG testTemperature point HP Heater #2 inlet10LAB25CT904NANAStub PresentRequired at the time of PG test

Temperature point HP Heater #2 outlet10LAB25CT905NANAStub PresentRequired at the time of PG testTemperature indicator & alarm HP Heater #1 inlet10LAB25CT303CompleteNot Complete9/19/14completeTemperature indicator *HP Heater #1 inlet10LAB25CT803CompleteNARequired at the time of PG testTemperature point HP Heater #1 inlet10LAB25CT906NANAStub PresentRequired at the time of PG test

Pressure indicator *HP Heater #1 outlet10LAB25CP503Not CompleteNAnot completenot completeCompletedTemperature point HP Heater #1 outlet10LAB25CT907NANAStub PresentStub PresentRequired at the time of PG testTemperature indicator *HP Heater #1 outlet10LAB25CT804CompleteNAstub presentstub presentRequired at the time of PG test

After HP Heater Bypass Outlet to EconomiserPressure point10LAB25CP902NANATapping Present, incompleteTapping Present, incompleteIncompetePressure indicator & alarm10LAB25CP003CompleteCompletedTemperature point10LAB25CT908NANAStub PresentRequired at the time of PG testTemperature point10LAB25CT909NANAStub PresentRequired at the time of PG testTemperature indicator & control 10LAB25CT304To be checkedcompleted

Venturi(flow meter)10LAB25BP001After alkali flushingReheater Desuper Heating Spray linePressure indicator*PI-10LAB86CP501Not CompleteNATapping PresentTapping PresentPressure indicatorPI-10LAB86CP001Not CompleteNATapping PresentTapping Present

EXTRACTION SYSTEMEXTRACTION SYSTEM (19-9-2014)TARGET8-Oct1EXTRACTION -1 AFTER QC NRV 2nDRAIN LINESOLONIED VALVE LINE TO BE WELDEDcompleted2extraction -1 after QC NRV 2nd drain line MANUAL VALVE HAND WHEEL MISSINGnot completed3EXTRACTION-4 (DEAREATOR) QC NRV NO.-2 NOT ERECTEDnot completed4EXTRACTION-4 (DEAREATOR) AFTER MOV DRAIN LINE PNUMETIC VALVE NOT ERECTED AND ISOLATION VALVE ERECTED EXTRA9/15/14For smooth operation Pneumatic valve to be indented5EXTRACTION-4 (DEAREATOR) AFTER QC NRV NO.-1 DRAIN LINE PNUMETIC VALVE NOT ERECTED AND ISOLATION VALVE ERECTED EXTRAto be checked - 15-09-2014For smooth operation Pneumatic valve to be indented6ALL PNUMETIC VALVE AIR LINE TO BE CONNECTEDnot completed7PRESSURE TRANSMITTER TO BE INSTALLED FOR ALL EXTRACTION LINE not completed8TEMPRATURE SENSOR TO BE ERECTED not completed

condensate systemS.NOCondensate systemStatus as on 15-09-1410/8/141ON BOTH THE PUMPS SEAL WORK UNDER PROGRESS.completedcompleted2ON CEP -B RELIEF VALVE TO BE ERECTED.completed3STRAINER ALONG WITH MESH TO BE INSTALLED.completedcompleted4HOTWELL MAKE UP STATION CONTROL VALVE AIR LINE NOT CONNECTED.completedcompleted5ALL MOVS AND CONTROL VALVE TO BE CHECKED.c & icompleted50/84 hookup with dcs6VALUE REQUIRED FOR HOT WELL, DEAREATOR AND CEP HEADER LOW PRESSURE VALUES c & icompleted7CCCW MAKE UP INLET LINE CONTROL VALVE ON SERVICES.c & i10/10/148PUMP VIBRATION AND CEP MOTOR ARE NOT SHOWNED ON DCS. c & iunder progressampears should be incorporated in the dcsDevesh Agrawal9BELLOW IS IN LOCKED CONDITIONS .before start upcompleted10RELIEF VALVE SETTINGS TO BE DONE.commissioningcompleted11AT 18.6 MTRS CONDENSATE LINE FROM LPH-5 APPORACH REQUIRED FOR TO OPERATE ISOLATION VALVE.availablecompleted12 FUEL OIL ATTEMPERATION AND LP AUX ATTEMPERATION LINE HEADER END TO BE WELDED.completedcompleted13LP BYPASS ATEMPERATION LINE TO BE WELDED. completedcompleted14HOT WELL MAKE UP STATION CONTROL VALVE BEFORE AND AFTER FLANGE TO BE TIGHTNED9/15/14completed15HOT WELL MAKE LOAD TRAIL IS PENDING .Pump is not delivering the pressure under erection.under progress16AT 0 MTRS APPORACH REQUIRED TO OPERATE CEP Pump17Fuel oil automisation spray line isolation valve in jammed condition18IP to LP Header spray water line isolation valve in jammed condition19LP Turbine spray water line welding to be completed20CEP A & B Oil Cup Required21CEP B vent line isolation valve wheel required22Nitrogen line connected on Level Gauge point as per GA drawing there is no Nitrogen lineC & I1Deaerator overflow & bottom drain line TI to be erect2LP HEATERS3For all LP heater cascade line CV cabling to be done4on LP Heater 7 to 8 cascade line TP & TIC to be erect5LP Heater 8 Level Gauge Bottom flange to be erect6LP Heater 7 emergency drain line broken handwheel to be change7On LP heater 6 TI not erected8LP Heater 5 TI not erected9On LP Heater 5 to 6 cascade line TP, TIC, TI to be erect10On LP Heater 6 to 7 cascade line TP, TIC, TI to be erect11GSC Level Gauge to be erected

GLAND SEALINGRKM POWERGEN PVT. LTD. - COMMISSIONING DEPARTMENTDATE 19-9-2014SL NO.GLAND SEALING PIPING PUNCH LISTStatus on 19-09-14Status on 08-10-141Control valve not erected in line from main steam line for gland sealingnot erectedmaterial at visaz port waiting for material2Control valve not erected in line from CRH line for gland sealingnot erectedmaterial at visaz port waiting for material3Control valve not erected in line from AUX. Steam hdr for gland sealingAfter SBOmaterial at visaz port waiting for material4Control valve not erected in line from AUX. Steam hdr for gland sealingAfter SBOmaterial at visaz port waiting for material5HIP Turbine gland sealing line drain point is not erectedunder progress10/16/146HIP Turbine gland sealing line erection work is under progressunder progress10/16/147LP gland sealing line spray water line for desuper heating is not erectednot propercompleted8LP gland sealing line near the LP turbine is under progressunder progress10/16/149Leak off steam line for ES & Control valve is under progressunder progress10/13/1410Leak off steam line RES & Control valve is under progressunder progress10/13/1411HIP leak off steam line erection work is under progressunder progress10/14/14

CCCW&BOILER FILL PUMP

RKM COMMISSIONING - CCCW&BOILER FILL PUMP9/19/14S.No.DiscriptionLocationRemarkTargetCCCW PUMP PUNCH POINT1Booster Pump-1 Inlet & Outlet Flange.0 mtrHeavy Leakage & Bolt Missingcompleted2Booster Pump-2 Inlet & Outlet Flange.0 mtrHeavy Leakage & Bolt Missingcompleted3Booster Pump-3 Inlet & Outlet Flange.0 mtrHeavy Leakage & Bolt Missingcompleted4Boiler Feed Pump-2 Inlet & Outlet Flange.0 mtrMinor Leakagecompleted5Boiler Feed Pump-3 Inlet Isolation valve.0 mtrPassingcompleted7seal Oil System Air side Cooler-A&B 0 mtrLeakage Observed completed8seal Oil System Hydrogen Cooler-B 0 mtrLeakage Observed completed9CCCW PHE i/l & o/l Pressure Gauge 10CCCW PHE i/l & o/l Temperature GaugeBOILER FILL PUMP PUNCH POINT1Suction Strainer DP Gauge Requirednot completed2Disharge Pressure Gauge Not Installednot completed3Suction and Discharge Pipe Flange Bolt Tighting Required not completed4Suction and Dischartge Pipe Gasket Replacement Required.not completed

vaccum systemS.NO DESCRIPTION 9/15/1410/8/141ALL DRAIN AND VENTS LINE ARE TO BE DUMMIED FOR VACUUM PUMP SUCTION LINE .CompletedCompleted2SEPARATOR & VACCUM PUMP DRAIN LINE YET TO ERECTED.9/12/149/22/14Completed3FROM DM TRANSFER PUMP TO GAS SEPARATOR WATER FEEDING LINE YET TO BE CONNECTED.9/13/149/19/14Completed4ON GA DIAGRAM AIR EJECTOR LINE ONE CHECK VALVE GIVEN BUT IN FIELD NO CHECK VALVE.To be checkedTo be checked5STRAINER TO BE INTRODUCED FOR COMMISSIONING IN AIR SUCTION LINE9/13/149/19/14To be checked

ACW & CW PipelineCW PIPELINE PUNCH POINTSSL noWork Description1Condensor i/l & o/l line actuator to be erect2CT Blowdown pipeline to be erect3CT I/L 13th Cell Raiser to be completed4Condensor front side vent Isolation valve to be erect5All pump Oil Cup & Oil level Indicator to be installed6All Pump Discharge MOV to be installed7No provision for Rubber Ball cleaning device O/L to condensor I/L line 8Chemical lines (Dosing Lines) to be erected9Cooling Tower Motor cabling work to be completed10Hydraulic valve connections to be done (Electrical & C&I)11P&ID Drawing required for ACW Line12CW Pump House & Condensor Sump pump to be erected13Bolts to be erected & tightened for Condensor I/L & O/L Line14Proper approach required for CT inlet line15Barryguard required for ACW o/l & OCCW i/l junction at TG 0 mtr16Approach required for ACW o/l & OCCW i/l junction at TG 0 mtr

C & I1PG, PS to be erected2Flow transmitter to be erected3TG, TS to be erected4Level sensors to be erected

ct pumpRKM POWERGEN PRIVATE LIMITED (4*360)MW ,UCCHPINDA CONDENSATE TRANSFER PUMP AND LINE PUNCH POINTS S.NO DESCRIPTION Status as on 11-09-14Status as on 15-09-14status on 08-10-141HOT WELL MAKE UP PUMP SIDE SHAFT IS BEND (impeller side)To be checkedPump replacedCompleted2DISCHARGE PRESSURE GUAGE NOT ERECTED CompletedCompleted3HOT WELL MAKE UP CONTROL STATION CONTROL VALVE INSTRUMENT AIR LINE TO BE ERECTED CompletedCompleted4HOT WELL RECIRCULATION LINE ERECTION WORK UNDER PROGRESS CompletedCompleted5HOT WELL PUMP SUCTION AND DISCHARGE LINE TENSION CONDITIONS 9/15/14not completed

CONDENSATE CONDENSATE SYSTEM 20-09-2014S. No.Equipment DetailsKKS CodeErection StatusRemarksInstrumentCabling1Condenser to Condensate Extraction Pump- PipingLIC- Hot Well levelLIC-10MAG10CL001CompletedcompletedLIC- Hot Well levelLIC-10MAG10CL002completedcompletedLSA- Hot Well level (HH)LSA-10MAG10CL101completedcompletedLSA- Hot Well levelLSA-10MAG10CL102 completedcompletedLI- Hot Well level (LL)*LI-10MAG10CL501 completed completedTP10LCA10CT901CompletedWill be done at the time of PG testPDIA For Strainer A(H)PDIA-10LCA11CP201CompletedcompletedPDIA For Strainer B(H)PDIA-10LCA12CP201CompletedcompletedPI -Condensate Extraction Pump A InletPI-10LCA11CP501CompletedPI -Condensate Extraction Pump B InletPI-10LCA12CP501completed2Condensate Extraction Pump Oulet to Gland Seal Condenser- PipingPI*-Condensate Extraction Pump A OutletPI-10LCA21CP501 completedPI*-Condensate Extraction Pump B OutletPI-10LCA22CP501completedPI-Condensate Extraction Pump AMechanical Seal Quenching and Flushing InletPI-10LCA25CP001CompletedPI-Condensate Extraction Pump A Mechanical Seal Quenching and Flushing InletPI*-10LCA25CP501CompletedPI-Condensate Extraction Pump B Mechanical Seal Quenching and Flushing InletPI-10LCA24CP001CompletedPI-Condensate Extraction Pump B Mechanical Seal Quenching and Flushing InletPI*-10LCA24CP501CompletedPP-PP-10LCA30CP901CompletedPI-PI-10LCA30CP001CompletedcompletedPSA(L)-PSA(L)-10LCA30CP201CompletedcompletedTI-TI-10LCA30CT301Completednot requiredFIC-Across VenturiFIC-10LCA30CF001CompletedCompleted

Gland Seal CondenserTI-Gland Seal Condenser inletTI-10LCA40CT801completed

3Gland Seal Condenser to LP Heater No. 8 -pipingTI-Gland Seal Condenser outletTI*-10LCA40CT802 completed

PI-PI-10LCA40CP001completedcompletedTI- TI-10LCA40CT301completedcompletedC)To Condenser -pipingFIC Across Orifice10LCA43CF001Completedd)LP Heater 7&8 bypass -pipingPP10LCA51CP901Not completedWill be done at the time of PG testTP10LCA51CT901CompletedTI10LCA51CT301completednot done

4LP Heater No. 8 & 7 to LP Heater No. 6 -pipingTPTP-10LCA51CT902CompletedTITI-10LCA51CT301 completednot donePI-PI-10LCA60CP001 completedTI-TI-10LCA60CT301completednot doneTP-TP-10LCA61CT901CompletedTI*TI*-10LCA61CT801 completedPI*-PI*-10LCA61CP501Not completedTo be checkedTI*-TI*-10LCA61CT802 completedTP-TP-10LCA61CT902Completed

5LP Heater No. 6 Outlet to Deaerator Inlet -pipingTP-LP Heater 5 Inlet10LCA71CT901CompletedTI*-LP Heater 5 Inlet10LCA71CT801Not completedWill be done at the time of PG testLP Heater No. 5PI*-LP Heater 5 outlet10LCA71CP501Not completedWill be done at the time of PG testTI*-LP Heater 5 outlet10LCA71CT802completedTP-LP Heater 5 outlet10LCA71CT902CompletedTo Recirculation Water Back Pipe While Unit Start Up piping- before Outlet Motorized Valve of LP Heater No. 5

PIC10LCA80CP001CompletedCompletedTIC10LCA80CT301CompletedCompletedGate Valve10LCA80AA101CompletedTo be checkedFIC-Across Venturi10LCA80CF001CompletedFIC-Across Venturi10LCA80CF002CompletedFIC-Across Venturi10LCA80CF003CompletedDeaerator10LAA10AC001CompletedTI*10LAA10CT801CompletedTI10LAA10CT301CompletednotdoneTo be checkedPI*10LAA10CP502CompletedLI*10LAA10CL501CompletedLI*10LAA10CL502CompletedLSA(LL)10LAA10CL103CompletedCompletedLSA(HH)10LAA10CL102CompletedCompletedLSA(HHH)10LAA10CL101CompletedCompletedLICA10LAA10CL001-003CompletedCompletedPIC10LAA10CP003CompletedCompletedPIC10LAA10CP002CompletedCompletedPIC10LAA10CP001CompletedCompleted

HVAC-CCR9/20/14RKM POWERGEN PVT LTD - HVAC SYSTEMSr. No Name of equipmentPending works1Water make-up tankErection of vent pipe, drain pipe, overflow pipe and pressure release pipe is pending.2Automatic water make-up unitPiping works started from 2nd automatic make-up water unit to cooling water line but not yet completed.3Chilled water distributorErection of gate valve in drain pipe is pending.Erection of gate valve in standby pipe is pending.4Chilled water collectorErection of gate valve in drain pipe is pending.Erection of gate valve in standby pipe is pending.5Cooling water pumpInsulation works going on but yet to be completed.6Chilled water pumpInsulation works going on but yet to be completed.7Absorption chillerPiping works pending from gas reheater to absorption chiller. Welding works in piping from absorption chiller to chilled water pump is going on.8Screw type water chillerWelding works in piping from screw type chiller to chilled water pump is going on.9Air washer unitPiping works and duct works yet to be started.10Air supply unitDuct works started but yet to be completed.11Fan coil (5 nos)Supply and return piping works from distributor and collector started but not completed. One of the fan coil unit is not erected.12Corossive proof fan coil (1 no)Supply and return piping works from distributor and collector started but not completed.13Closed cooling water tower1) Erection of make up water line is pending in all the three cooling towers.2) Erection of drain line in cooling tower is pending in all the three cooling towers.NOTE - Electrical cable laying works, C & I works, equipment and body earthing works, etc. yet to be started for the equipments involved in the entire HVAC system. In particular C&I PDP panels, VFD and control panels, electrical panels, and its cabling work are not yet started.

HVAC-TGDate - 27/06/14HVAC SYSTEM FOR TG BUILDING

Sr. No ElevationName of equipmentQtyStatus/Activities10 m levelAir washer unit42 out of 4 air washer units erected.Exhaust fan2Yet to be erected.Direct axial fan6Yet to be erected.Air supply unit2Yet to be erected.Exhaust axial fan8Yet to be erected.

26.3 m levelAir washer unit53 out of 5 Erection completedDirect axial fan7Yet to be erected.Exhaust axial fan5Yet to be erected.Air supply unit22 nos of air supply unit erected.

334.35 m levelAnti-explosion roof fan16 (14W+2S)Erection completed.