Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

46
Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee New Champlain Bridge Corridor Project Centre Saint-Charles – April 7, 2016

Transcript of Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

Page 1: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee New Champlain Bridge Corridor Project Centre Saint-Charles – April 7, 2016

Page 2: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project 2

Verdun Philippe Dubeau Hubert Fortin Anne-Marie Gagné François Labelle Seraya Speer Billy Walsh – Business Community Daniela Villatora – Community Organizations Sud-Ouest Natacha Alexandroff Daniel Brasseur Sarah Chouinard Michael Ryan Wiseman – Business Community Marie-Josée Béliveau – Community Organizations Partners Dan Genest - Signature on the Saint-Laurent Jean-François Parenteau – Borough of Verdun Benoît Dorais - Sud-Ouest Borough James Byrns - Ville de Montréal Vincent Jarry - Infrastructure Canada

Committee Members

Page 3: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

1. To inform you about completed, ongoing and future construction work between now and June, 2016.

2. To discuss major upcoming traffic obstructions during the summer of 2016.

3. To present progress in urban integration.

4. To answer questions, identify solution paths, and discuss.

Objectives of the meeting

3

Page 4: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Agenda

4

Series Item Duration Time 1. Opening 10 min 7:00 to 7:10 p.m.

2.

Completed, ongoing and future work • Atwater Interchange and LaSalle Blvd. • Gaétan Laberge sector and Wellington St. • Nun’s Island

30 min 7:10 to 7:40 p.m.

3. Questions from the Committee 10 min 7:40 to 7:50 p.m.

4. Update on other major projects 10 min 7:50 to 8:00 p.m.

5. Mobility: Obstruction to come in the Gaétan Laberge sector

10 min 8:00 to 8:10 p.m.

6. Urban integration: LaSalle Overpass and May St. sector

20 min 8:10 to 8:30 p.m.

7. Questions from the Committee 10 min 8:30 to 8:40 p.m.

8. Miscellaneous 10 min 8:40 to 8:50 p.m.

9. Questions from the general public 20 min 8:50 to 9:10 p.m.

10. Closure: next meetings and themes 5 min 9:10 to 9:15 p.m.

Page 5: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Work completed in recent months in Verdun / Sud-Ouest

Page 6: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

• Prefabrication facilities on western jetty: 8 (of 38) footings cast.

• Drilling and concreting of caissons for western landing of new Champlain Bridge.

• Demolition of old Nun’s Island Bridge is essentially finished: completion projected for mid-April.

• First reconfiguration of Atwater Interchange: A15 South feeder.

• A15 lane width reduction and route reconfiguration between Gaétan Laberge and Atwater.

Overview of completed work

6

Page 7: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

• Generally very few complaints during the period.

• Old Nun’s Island Bridge demolition: 11 complaints associated with noise from November 2015 through April 2016, but the thresholds allowed under the agreement with Infrastructure Canada were never exceeded.

• A15 route reconfiguration: no incidents.

Completed work: comments

7

Page 8: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Complaint management (January 29 to April 6, 2016)

Theme

Sector

Total Atwater / LaSalle Gaétan Laberge / Wellington Nun’s Island

Closed Open Total Closed Open Total Closed Open Total

Noise - - - - 1 1 5 - 5 6

Air quality - - - - - - - 1 1 1

Traffic - 2 2 - - - - - - 2

Vibrations - 1 1 - - - - - - 1

Light - - - - - - - - - -

Other 1 - 1 - - - 2 - 2 3

Total 1 3 4 0 1 1 7 1 8 13

8

Page 9: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Major priorities for coming months in Verdun / Sud-Ouest

Page 10: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

1 2 3

Location of sectors Verdun / Sud-Ouest

Gaétan Laberge and Wellington

Nun’s Island

Atwater and LaSalle

10

Page 11: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Construction on new A15S structures, walls and roadbeds

Overall Plan:

Spring 2016 through Fall 2017

Demolition of existing A15S structures, walls and roadbeds

Construction of Gaétan-Laberge Blvd.

11

Construction of new Nun’s Island Bridge

Page 12: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

A15

• Relocate some utilities, including aqueducts

• Begin construction of new Nun’s Island Bridge

• Partially demolish A15S overpasses and roadbed

• Begin construction of new A15S overpasses

• Start of construction for Gaétan Laberge Blvd. reconfiguration.

New Champlain Bridge

• Footing prefabrication (and start of pilings) on western jetty

• River excavations

• River transport operations between Port of Montreal and site

• Opening of the industrial catamaran and crane barges (used to install footings, piles, portals and superstructure).

Verdun / Sud-Ouest Priorities: April to June, 2016

12

Page 13: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Activity description Approximate duration of work Projected timeframe of work

Legend: Work and impacts

• Traffic: • Residence proximity: • Public transit: • Cycling paths:

Minor impact Moderate impact

Major impact

Indication by level colour code

13

Page 14: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Key current and upcoming activities Atwater and LaSalle Boulevard interchange

Design and scheduling are in development so changes are possible

Page 15: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Objective: Widen Highway 15 and reconfigure Atwater-LaSalle Blvd. interchange

Ongoing and future construction:

• Excavation of soil containing asbestos between Atwater and Wellington

• Relocation of water mains between LaSalle and Wellington, and Atwater sector

• Partial demolition and partial reconstruction of Atwater, LaSalle and Gibbons overpasses and part of A15S

Approach:

• Daytime work, whenever possible, when the impacts, especially in terms of noise levels, are high.

• Nighttime work, whenever possible, when the impact on daytime traffic would be too high.

Atwater and LaSalle sector

15

Page 16: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Work and impacts: Atwater and LaSalle sector

Excavation of soil containing asbestos (possibly in other sectors)

Duration: one month Projected timeframe: late March to late April

Best practices • Notices to residents and Web broadcast • Security fence • Appropriate signage • Certified workers • Personal protective equipment required • Decontamination trailer • Disposal of soil in a site authorized by

the MDDELCC • Air quality monitoring

16

Page 17: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Work and impacts: Atwater and LaSalle sector

Relocation of aqueduct conduit between LaSalle and Wellington

Duration: five months Projected timeframe: March to July

17

Some work will be done 7 days a week from

7:00 a.m. to 7:00 p.m.

Page 18: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Work and impacts: Atwater and LaSalle sector

Preparatory work for widening of A15 between LaSalle and Wellington

Duration: 7 ½ months Projected timeframe: May to mid-December

18

• Dewatering work • Earthworks • Demolition of retaining walls and

existing roadbed

Page 19: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Partial demolition of Atwater, LaSalle and Gibbons overpasses Duration: 2 ½ months

Projected timeframe: mid-March to May

Work and impacts: Atwater and LaSalle sector

Closure of Atwater Ave. and one lane of the A15S

Weekend of April 22 to 25

Atwater Ave. detour

19

Opening of a temporary entrance and deviation of A15 northbound lanes as of March.

Duration: 18 months

Closure of LaSalle St. and one lane of the A15S

Weekend of May 6 to 9 (TBC)

Gibbons

Page 20: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Partial construction of Atwater and LaSalle overpasses Duration: seven months

Projected timeframe: May to November

Work and impacts: Atwater and LaSalle sector

Closure of Atwater Ave. One weekend in July

Atwater Ave. detour

Opening of temporary entrance and deviation of A15

northbound lanes from mid-March on. Duration: 18 months

Closure of LaSalle St. One weekend in August

20

Page 21: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Work and impacts: Atwater and LaSalle sector

Relocation of aqueduct in Atwater sector Duration: two months

Projected timeframe: May to June

Page 22: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Key current and upcoming activities Gaétan Laberge sector and Wellington St.

Design and scheduling are in development so changes are possible

Page 23: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Gaétan Laberge sector and Wellington

Objective: Widen Highway A15 and reconfigure Wellington St. and the Gaétan Laberge Sector

Ongoing and future work:

• Water main relocation

• Partial demolition and reconstruction of Wellington and Gaétan Laberge overpasses and part of A15S

• Start of construction for reconfiguration of Gaétan Laberge Blvd.

Approach:

• Daytime work, whenever possible, when the impacts, especially in terms of noise levels, are high.

• Nighttime work, whenever possible, when the impact on daytime traffic would be too high.

23

Page 24: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Gaétan Laberge sector and Wellington St.

Partial demolition of Wellington and Gaétan Laberge overpasses

Duration: two months Projected timeframe: June to July

Closure of Wellington St. One weekend in June

Closure of Gaétan Laberge Blvd.

One weekend in July

24

Page 25: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Work and impacts: Gaétan Laberge sector and Wellington St.

Aqueduct conduit relocation Duration: three months

Projected timeframe: April to June

25

Page 26: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Work and impacts: Gaétan Laberge sector and Wellington St.

Gaétan Laberge Blvd. reconfiguration Duration: 12 months

Projected timeframe: July 2016 to July 2017

26

Page 27: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Key current and upcoming activities Nun’s Island

Design and scheduling are in development so changes are possible

Page 28: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Nun’s Island

28

Objective: Construction of western approach to the new Champlain Bridge, the new Nun’s Island Bridge and the road link between them.

Ongoing and future construction:

• Reconfiguration work for overpass adjoining Nun’s Island Bridge • Drilling of caissons for new Nun’s Island Bridge • Footing prefabrication. Approach:

• Daytime work, whenever possible, when the impacts, especially in terms of noise levels, are high.

• Nighttime work, whenever possible, when the impact on daytime traffic would be too high.

Page 29: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Demolition of the old Nun’s Island Bridge and construction of the new bridge

29

Phase 3: Reconfiguration of overpass (in progress)

Phase 4: Construction of new bridge (in progress)

Phase 2: Demolition of piles and abutments (essentially

finished)

Phase 1: Demolition of bridge superstructure (completed)

Page 30: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Work and impacts: Nun’s Island

Construction of new Nun’s Island Bridge

Duration: 19 months Projected timeframe: March 2016 to Sept. 2017

30

• Caisson drilling (in progress) • Piles and abutments • Superstructure

Page 31: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Overpass reconfiguration Duration: six months

Projected timeframe: April to September

Work and impacts: Nun’s Island

31

Page 32: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Anticipated Impacts

Page 33: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Anticipated Impacts

• Traffic • Noise • Air quality • Light • Vibrations

33

Page 34: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Traffic

• Reduced lane widths and reconfiguration of A15 route

• Closures for one weekend, respectively Atwater: late April and July LaSalle: early May and August Wellington: June Gaétan Laberge: July

• Major changes in road user routines beginning June / July 2016, primarily in the Gaétan Laberge sector.

34

Page 35: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project 35

M1: Sud-Ouest / Argenson M2: Sud-Ouest / Butler et Charlevoix M3: Verdun I1: Sax I2: Pointe-Nord I3: Cours des Fougères

Noise management Ambient noise level in (May 2015) / Estimated (March 2016)

Sect

or

Activity Period Exposed

sensitive area

Ambient noise in

dBA

Criteria in dBA

Estimated noise in dBA

Measures required D / E / N

Atw

ater

and

LaS

alle

Soil excavation - asbestos D M3 61 75 75 Monitoring required

Partial demolition of overpasses D M1 / M2 66 / 64 75 69/67 No D M3 61 75 83 Yes

Debris collection E / N M3 60 / 59 65 / 64 Later Later

Overpass construction D M1 / M2 66 / 64 75 69/67 No J M3 61 75 83 Yes

Preparatory work for widening J M2 64 75 66 No M3 61 75 87 Yes

Aqueduct relocation J M3 61 75 90 Yes

Noise-sensitive areas

Page 36: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project 36

M1: Sud-Ouest / Argenson M2: Sud-Ouest / Butler et Charlevoix M3: Verdun I1: Sax I2: Pointe-Nord I3: Cours des Fougères

Noise management Ambient noise level in (May 2015) / Estimated (March 2016)

Sect

or

Activity Period Exposed

sensitive area

Ambient noise in

dBA

Criteria in dBA

Estimated noise in dBA

Measures required D / E / N

Wel

lingt

on

Partial demolition of overpasses D M1 / M2 66 / 64 75 69/67 No D M3 61 75 83 Yes

Debris collection E / N M3 60 / 59 65 / 64 Later Later Overpass construction D M3 61 75 83 Yes

Preparatory work for widening D M3 61 75 87 Yes

Aqueduct relocation D M3 61 75 90 Yes

G-L

Partial demolition of viaducts D M3 61 75 69 No

Overpass construction D M3 61 75 74 Monitoring required

Areas sensitive to noise Noise-sensitive areas

Page 37: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project 37

M1: Sud-Ouest / Argenson M2: Sud-Ouest / Butler and Charlevoix M3: Verdun I1: Sax I2: Pointe-Nord I3: Cours des Fougères

Noise management Ambient noise level in (May 2015) / Estimated (March 2016)

Sect

or

Activity Period Exposed

sensitive area

Ambient noise in

dBA

Criteria in dBA

Estimated noise in dBA

Measures required D / E / N

Nun

’s Is

land

West jetty – Footing prefabrication

D I2 / I3

64 / 57 75 64 Monitoring required E 59 / 52 64 / 57 60

N 57 / 52 62 / 57 58

New bridge construction D I1 57 75 63 No

Access ramp construction D I1 57 75 69 No

Preparatory work for overpass D I1 57 75 69 No

Noise-sensitive areas

Page 38: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Air Quality Management

• No expected impact on sensitive areas

• Monitoring, mainly for demolition activities • Dust blanketing using water cannons • Use of dust control liquid.

38

Page 39: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Light Management

39

• Problem essentially limited to site trailers and parking on western jetty: largest worksite facilities for the project are near the Pointe-Nord on Nun’s Island

• Two areas impacted: Evolo 2: adjustments made René Lévesque Blvd. (toward Pointe-Nord): new challenge

• Human health and safety imperative and operational

security.

Page 40: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Vibration Management

40

• Continuous seismographic monitoring: an alert is received if the 25mm/s criterion is exceeded; adjustments are then made to work methods in order to remain within the criterion.

• The 25 mm/s criterion is based on a low probability of cosmetic damage (e.g., cracks in gypsum) and is recognized by the MTQ for residential buildings.

• Protective cushions are used to dampen debris impact shocks during

demolition.

• Visual assessment prior to construction and re-assessment afterwards.

Page 41: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Follow-up of actions from Last Meeting

Page 42: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Action follow up

42

SSL • West jetty site luminosity: adjustments made. • Possibility of having a noise abatement wall between Sud-Ouest and the railroad: acoustic

analysis is ongoing. • Removal of buildings from May St. and the effect on neighbourhood tranquility, plus

concerns expressed with regard to bringing the A15 closer to the Poudrière sector: Temporary noise abatement walls will be installed between LaSalle and Wellington Permanent noise abatement walls to be erected later.

INFC • Environmental compensation for the project as a whole (i.e. GGs: discussions ongoing • Possibility of a 4th lane on the Nun’s Island Bridge linking Nun’s Island to Verdun:

discussions ongoing. • Conversion of temporary Nun’s Island Bridge into park: under review.

Ville de Montréal • Access to Nun’s Island channel for Pointe-Saint-Charles: under review.

Page 43: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

Next meetings

Page 44: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

• Public information meeting: May 11 on Nun’s Island. • Good Neighbourly Relations Committee: June 8 (TBC) in Verdun

Theme 1: Major traffic hindrances in 2016 Theme 2: Unban integration progress.

• Good Neighbourly Relations Committee: Sept. 14 (TBC) in Sud-Ouest

Theme: Your Suggestions.

Next meetings (for discussion)

44

Page 45: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project

• Newsletter: sign up on the Website.

• Leaflets delivered to doors, if required, and notices in local newspapers.

• Subscribe / contact us: Website: www.newchamplain.ca E-mail: [email protected] Telephone: 514-876-1020 Twitter: @NEW_CHAMPLAIN

Communications

45

Page 46: Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - April 7, 2016

New Champlain Bridge Corridor Project