    MINUTES OF MEETINGDATE: 15/02/2013TIME: 1300 - 1500VENUE: SIM HQ ANNEX

    PRESENT: KHOO JUN XIANG (Leader)

    ANG WEN CAN STEPHENGOH KHENG SIANG JOEL

    LIM SING HUI

    LOW JIA HUI JETHRO

    OPENING:Sing Hui recorded the minutes.AGENDA:

    1. Brief Introduction of Agenda2. Actions from last minutes

    3. Implementation

    4. Current Situation

    5. Update Summary

    6. Arrangement of Next Meeting

    7. Any other matters

    8. End of Meeting

    Items Actions to be taken

    1

    Presentation Of Agenda

    Jun Xiang addressed the group with current progress. All to note

    2 Actions from last minutesSubmission of User Manual Preliminary on 9t Feb 2013. All to note

    3 ImplementationAll Single Tables queries are workable.

    Difficulty encountered for users who have no knowledge in making

    an SQL statement. The How To guide function has been

    progressing well with research on the internet on the steps and

    formats to guide the users.

    Export Report is installed and workable.

    Changes need to make for View Report. Reports displayed in

    View Report are not based on role privileges. All report is

    displayed instead.

    All to note

  • 7/29/2019 Meeting Minutes 15feb2013

    2/3

    4 Current SituationUnit Testing Report

    - On-going testing with capturing of screenshots and codes for

    testing of the program.

    Design

    -User page is finalised.

    There are bugs found in Generate Report tab, correction of errors

    need to be done.

    All to take note

    5 Update SummaryNil All to take note

    6 Arrangement of Next MeetingNext meeting will be held on Monday, 18/02/2013

    Location: SIM Annex

    Time: 1300

    Members must inform

    group leader to requestfor change of date

    and/or timing.

    7 Any other mattersNil Nil

    8 End of MeetingThe meeting ended at 15:00

    Item Action Item Date Added Assigned To Date Due StatusA1-01 Project Diaries 20/10/2012 Everyone On-going Open

    A1-02 Members Profile 20/10/2012 Everyone 08/11/2012 Close

    A1-03 Literature review on proposal 20/10/2012 Everyone 04/11/2012 Close

    A1-04 Development of Project Website 30/10/2012 Joel 04/11/2012 Close

    A1-05 Proposal Draft 1 20/10/2012 Everyone 26/12/2012 Close

    A1-06 Introduction, Project Scope 08/11/2012 JunXiang 23/11/2012 CloseA1-07 Stakeholder, Development Methodology 08/11/2012 SingHui 23/11/2012 Close

    A1-08 Project Team, Project Website 08/11/2012 Stephen 08/11/2012 Close

    A1-09

    Control Records, Test Plan 08/11/2012

    Joel

    23/11/2012

    Close

    A1-10 Introduction of Requirement Specification 08/11/2012 JiaHui 23/11/2012 Close

    A1-11 Update Objective, Scope and Problem Limitation 23/11/2012 Everyone 26/11/2012 Close

    A1-12 Project Proposal 20/10/2012 Everyone 08/12/2012 Close

    A1-13 Introduction & Glossary 08/12/2012 JiaHui 25/12/2012 Close

    A1-14 General Description 08/12/2012 JiaHui 25/12/2012 Close

    A1-15 Requirements Definition 08/12/2012 Everyone 25/12/2012 Close

    A1-16 Main Constraints 08/12/2012 Everyone 25/12/2012 Close

    A1-17 Proofread all the documents 26/12/2012 Everyone 29/12/2012 Close

    A1-18 Redo of prototype 26/12/2012 Everyone 29/12/2012 Close

    A1-19

    Review on feedbacks from Accessor on29/12/2012 prototype demonstration

    30/12/2012

    Everyone

    10/01/2013

    Close

    A1-20 Download QT creator from website

    - Understand the basics usage of QT creator

    30/12/2012 Everyone 30/12/2012 Close

  • 7/29/2019 Meeting Minutes 15feb2013

    3/3

    A1-21 Implement codes and establish connection 30/12/2012 Jia Hui, Jun Xiang 10/01/2013 Open

    A1-22 Design UI interface 30/12/2012 Sing Hui 10/01/2013 Open

    A1-23 Research on System Test Plan 30/12/2012 Joel, Stephen 10/01/2013 Close

    A1-24 Progression of prototype 30/12/2012 Everyone 30/02/2013 Open

    A1- 25 Drafting out System Test Plan 10/01/2013 Joel, Stephen 14/01/2013 Close

    A1-26 Finalized on System Test Plan 17/01/2013 Joel, Stephen 18/01/2013 Close

    A1-27

    Proofread the System Test Plan, Minutes andProject Diaries

    17/01/2013

    Everyone

    18/01/2013

    Close

    A1-28 On-going unit testing report 25/01/2013 Joel, Stephen 18/02/2013 Open

    A1-29 Drafting of preliminary User Manual 25/01/2013 Joel, Stephen 09/02/2013 Close

    A1-30 Design and GUI finalised 15/02/2013 Jun Xiang,Sing Hui

    18/02/2013 Open