MINUTES OF MEETINGDATE: 07/02/2013TIME: 1300 - 1500VENUE: SIM HQ ANNEX
PRESENT: KHOO JUN XIANG (Leader)
ANG WEN CAN STEPHENGOH KHENG SIANG JOEL
LIM SING HUI
LOW JIA HUI JETHRO
OPENING:Sing Hui recorded the minutes.AGENDA:
1. Brief Introduction of Agenda2. Actions from last minutes
3. Implementation
4. Current Situation
5. Update Summary
6. Arrangement of Next Meeting
7. Any other matters
8. End of Meeting
Items Actions to be taken
1
Presentation Of Agenda
Jun Xiang addressed the group with current progress. All to note
2 Actions from last minutesProgression with Integration Test and producing of finalised User
Manual.
- Generate Report page and the report output are done which can
be displayed.
All to note
3 Implementation- The report generated cannot be exported to excel as the
installation of library is not successfully done.
- Joint table has yet implemented as all the Single Tables queries
must be workable before proceeding to joint tables problem.
Encountered a difficulty:
Users who have no knowledge in making an SQL statement in our
program (through Generate Report tab). To conveniently catered tosuch users, would be good to have a How To guide for them.
All to note
-
7/29/2019 Meeting Minutes 07feb2013
2/3
4 Current SituationUnit Testing Report
As the implementers are having continuous edit of codes, the unit
test cases have to make amendments accordingly.
User Manual
User Manual is halfway completed as joint tables has not
implement yet. In the midst of preparation for submission of
preliminary user manual.
All to take note
5 Update SummaryDeliverable: User Manual Preliminary (9 February 2013). All to take note
6 Arrangement of Next MeetingNext meeting will be held on Friday, 15/02/2013
Location: SIM Annex
Time: 1300
Members must informgroup leader to request
for change of date
and/or timing.
7 Any other mattersNil Nil
8 End of MeetingThe meeting ended at 15:00
Item Action Item Date Added Assigned To Date Due StatusA1-01 Project Diaries 20/10/2012 Everyone On-going Open
A1-02 Members Profile 20/10/2012 Everyone 08/11/2012 Close
A1-03 Literature review on proposal 20/10/2012 Everyone 04/11/2012 Close
A1-04 Development of Project Website 30/10/2012 Joel 04/11/2012 Close
A1-05 Proposal Draft 1 20/10/2012 Everyone 26/12/2012 Close
A1-06 Introduction, Project Scope 08/11/2012 JunXiang 23/11/2012 CloseA1-07 Stakeholder, Development Methodology 08/11/2012 SingHui 23/11/2012 Close
A1-08
Project Team, Project Website
08/11/2012
Stephen
08/11/2012
Close
A1-09 Control Records, Test Plan 08/11/2012 Joel 23/11/2012 Close
A1-10 Introduction of Requirement Specification 08/11/2012 JiaHui 23/11/2012 Close
A1-11 Update Objective, Scope and Problem Limitation 23/11/2012 Everyone 26/11/2012 Close
A1-12 Project Proposal 20/10/2012 Everyone 08/12/2012 Close
A1-13 Introduction & Glossary 08/12/2012 JiaHui 25/12/2012 Close
A1-14 General Description 08/12/2012 JiaHui 25/12/2012 Close
A1-15 Requirements Definition 08/12/2012 Everyone 25/12/2012 Close
A1-16 Main Constraints 08/12/2012 Everyone 25/12/2012 Close
A1-17 Proofread all the documents 26/12/2012 Everyone 29/12/2012 Close
A1-18
Redo of prototype
26/12/2012
Everyone
29/12/2012
Close
A1-19 Review on feedbacks from Accessor on
29/12/2012 prototype demonstration
30/12/2012 Everyone 10/01/2013 Close
-
7/29/2019 Meeting Minutes 07feb2013
3/3
A1-20 Download QT creator from website- Understand the basics usage of QT creator
30/12/2012 Everyone 30/12/2012 Close
A1-21 Implement codes and establish connection 30/12/2012 Jia Hui, Jun Xiang 10/01/2013 Open
A1-22 Design UI interface 30/12/2012 Sing Hui 10/01/2013 Open
A1-23 Research on System Test Plan 30/12/2012 Joel, Stephen 10/01/2013 Close
A1-24 Progression of prototype 30/12/2012 Everyone 30/02/2013 Open
A1- 25 Drafting out System Test Plan 10/01/2013 Joel, Stephen 14/01/2013 Close
A1-26 Finalized on System Test Plan 17/01/2013 Joel, Stephen 18/01/2013 Close
A1-27 Proofread the System Test Plan, Minutes and
Project Diaries
17/01/2013 Everyone 18/01/2013 Close
A1-28 On-going unit testing report 25/01/2013 Joel, Stephen 18/02/2013 Open
A1-29 Drafting of preliminary User Manual 25/01/2013 Joel, Stephen 09/02/2013 Close