Meeting Indonesia’s Energy Needs. Geothermal Development in Indonesia: Challenges and...
-
Upload
kenneth-sparks -
Category
Documents
-
view
217 -
download
0
Transcript of Meeting Indonesia’s Energy Needs. Geothermal Development in Indonesia: Challenges and...
Meeting Indonesia’s Energy Needs
Geothermal Development in Indonesia: Challenges and Opportunities for Scaling-Up the World ‘s Largest Reserves
Migara JayawardenaSenior Infrastructure SpecialistEAP Infrastructure UnitSustainable Development Department
February 28, 2011Knowledge Series – Emerging IndonesiaWashington DC
Key Challenges Facing Indonesia’s Power Sector
200928 GW
201987 GW
Looming power shortages in face of growing economy Momentous investment needs of $4-$5 billion annually to meet
demand Lack of clear vision due to legal, policy and regulatory uncertainties Only 70% of population with formal access to electricity Sub-optimal power generation mix is dominated by fossil fuels - with
heavy reliance on diesel and substantial expansion of coal underway with significant environmental impact
Geothermal3.2%
Geothermal7.0%
In 2006/07 Indonesia embarked on its 1st 10,000 MW Crash Program based on coal-fired power generation
Coal was seen at the time as the most readily available and least-cost option to
• Reduce reliance on fuel oils (replace high cost generation units)
• Increase supply at affordable price, and reduce the subsidy burden
HOWEVER, this poses substantial impact on local environment, contribute to more greenhouse gas emissions
THEREFORE, the GoI, for its 2nd 10,000 MW Crash Program, included a substantial amount of renewable energy, particularly geothermal.
GoI is taking action to scale up generation capacity
Geothermal Provides one of the best options for Improving Base Load Power Mix
I. ENVIRONMENT BENEFITS OF UTILIZING CLEAN ENERGY SOURCE
Reduction in harmful local pollutants (such as TSP, NOx, SO2)
Reduction in Greenhouse Gases (GHGs)
II. ENERGY SECURITY BY UTILIZING ABUNDANT NATIONAL RESOURCE
Enhance energy security by exploiting dependable indigenous (non-tradable) resource
III. HEDGE AGAINST VOLATILE PRICES FOR FOSSIL-FUELS
Geothermal “fuel” price does not fluctuate (once developed) unlike fossil fuels, providing a natural hedge in managing Indonesia’s energy portfolio
No.Major
Islands
Geothermal Potential (MW)
Speculative /Hypothetic
Probable(w/ detailed
surveys)
1 Java 9,671 3,086
2 Bali & NT 1,676 871
3 Sumatra 13,416 5,433
4 Kalimantan 45 -
5 Sulawesi 1,907 721
6 Maluku 734 142
7 Papua 50 -
TOTAL 27,499 10,027
Filename/RPS Number
How does geothermal work?
Drill “wells: to expose high temperature underground water reservoirs and extract steam under high pressure (production well)
The steam is then used to operate turbines that generate electricity After power generated, the steam is condensed back to water and reinjected into
ground, and cycle repeated (making it renewable!)
SteamSeparator
TurbineCondensor/
Cooling Tower
Barriers to developing geothermal in Indonesia
The financial cost of geothermal development is higher than the cost of developing an equivalent base-load substitute (i.e. coal), particularly when environmental impacts are not considered.
Incremental Costs
There are indications that Indonesia’s geothermal resource risk is not excessive, but it is something inherent in the sector worldwide
Resources Risks
The PLN credit/off-take risks due to its heavy reliance on GoI is seen as a considerable risk to all IPPs, including geothermal
Off-Take Uncertainty
Limited government experience in conducting credible competitive tenders in a transparent manner as per Geothermal Law. As a result, no geothermal tender has reached financial closure thus far
Domestic capacity for conducting credible transactions
These barriers make it a challenge to mobilize momentous investment requirements of $10-$12
billion for achieving GoI target
These barriers make it a challenge to mobilize momentous investment requirements of $10-$12
billion for achieving GoI target
World Bank Group Support to Indonesia Geothermal Development Program
Geothermal Sector Reform
Geothermal Sector Reform
Carbon Finance and Climate Change
Carbon Finance and Climate Change
Investment Lending to Strengthen Institutions
Investment Lending to Strengthen Institutions
GEF Grant (under implementation)
Enhance policy framework by:• Pricing & Incentives• Upstream Risk Mitigation• Legal & policy review and
amendments
Transactions to tender projects for development
Long-term domestic capacity building
Also supported by funding from PPIAF, ASTAE,
ESMAP, INIS (AusAID), IDF
GEF Grant (under implementation)
Enhance policy framework by:• Pricing & Incentives• Upstream Risk Mitigation• Legal & policy review and
amendments
Transactions to tender projects for development
Long-term domestic capacity building
Also supported by funding from PPIAF, ASTAE,
ESMAP, INIS (AusAID), IDF
Lahendong II CDM Transaction
(under implementation) Purchase CER from PLN for
20 MW geothermal project
Carbon Finance Framework for
Geothermal(under preparation)
Support the provision of wholesale access to carbon revenues for geothermal
Lahendong II CDM Transaction
(under implementation) Purchase CER from PLN for
20 MW geothermal project
Carbon Finance Framework for
Geothermal(under preparation)
Support the provision of wholesale access to carbon revenues for geothermal
Investment Loan to PGE (under preparation)
Immediately scale-up investment
Blended concessional financing from IBRD and CTF (up to $350 million)
Institutional capacity building
IFC financing for Private Developers
(under identification) $4 mil. early-stage risk capital Collaboration w/ regional and
international developers
Investment Loan to PGE (under preparation)
Immediately scale-up investment
Blended concessional financing from IBRD and CTF (up to $350 million)
Institutional capacity building
IFC financing for Private Developers
(under identification) $4 mil. early-stage risk capital Collaboration w/ regional and
international developers
Pertamina Geothermal Energy (PGE): Geothermal Clean Energy Investment Project
PGE’s Ambitious Investment Plan Aims for a Four-Fold Increase in its Geothermal Capacity
PGE is the leading geothermal developer undertaking a quarter (1000 MW) of GoI’s geothermal program
PGE is the leading geothermal developer undertaking a quarter (1000 MW) of GoI’s geothermal program
Proposed Project Description
OPTIONAL: Component BTechnical Assistance for
Capacity Building (US$7 million)
OPTIONAL: Component BTechnical Assistance for
Capacity Building (US$7 million)
• strengthening the capacity of PGE to undertake its geothermal development program.
• Already mobilized $2.5 million grant for FS, ESIA
• In discussions with donors re: grant funding for $7 million
• strengthening the capacity of PGE to undertake its geothermal development program.
• Already mobilized $2.5 million grant for FS, ESIA
• In discussions with donors re: grant funding for $7 million
Component AInvestment in Geothermal
Power Generation Capacity (US$580.2 million)
Component AInvestment in Geothermal
Power Generation Capacity (US$580.2 million)
• Investment in drilling, SAGS, and Power Plants
• Ulubelu (Units 3 & 4) - 110 MW • Lahendong (Tompaso) (Units 5
& 6) - 40 MW
• Investment in drilling, SAGS, and Power Plants
• Ulubelu (Units 3 & 4) - 110 MW • Lahendong (Tompaso) (Units 5
& 6) - 40 MW
IBRD/CTF Loan/Grant ($587.2 million) to PGEIncrease renewable generation capacity and mitigate impact of
local and global pollution
IBRD/CTF Loan/Grant ($587.2 million) to PGEIncrease renewable generation capacity and mitigate impact of
local and global pollution
FINANCING• Pertamina/PGE own funds: $ 280 million, equity return of 14%• IBRD: $175 million, LIBOR + 0.48%, 9 year grace, 24.5 year tenor• CTF: $125 million, 0.25%, 10 year grace, 40 year tenor• Grant: $7 million
FINANCING• Pertamina/PGE own funds: $ 280 million, equity return of 14%• IBRD: $175 million, LIBOR + 0.48%, 9 year grace, 24.5 year tenor• CTF: $125 million, 0.25%, 10 year grace, 40 year tenor• Grant: $7 million
12
Key Indicators CTF/IBRD ProjectPGE’s Scale-Up
Program
Government Long-Term Program
New geothermal power generation capacity 150 MW 1,000 MW 9,500 MW
Additional power generation (kWh per year ) 1,209 million 8,059 million 76,562 million
Avoided CO2
- tonnes per year- lifetime (tonnes/30 years)
880,000;26 million
5.9 million;176 million
55.8 million;1,673 million
Environmental co-benefits in terms of avoided local pollution (tonnes per year)
NOx - 3,000;
SO2 - 3,900;
TSP - 1,800
NOx - 26,100;
SO2 - 20,100;
TSP - 12,500
NOx - 248,200;
SO2 - 191,400;
TSP - 118,600
Public health benefits from avoided local pollution US$45 million US$241 million US$ 2,293 million
Project Impact and Transformational Potential
PV of Economic CostsGeothermal vs. Coal(at 10 % social discount rate)
Is CTF/IBRD Concessional Financing Necessary and Justified?
10/16/08
Financial NPVof geothermal project
(with tariff at 6.4 US cents/kWh, 14% rate on equity)
Some Additional Value-Added Aspects of World Bank Engagement
BACK-UP SLIDES
Incremental Costs and Risks make development more costly (compared with coal)
Benchmark Price (Coal)
Benchmark Price (Coal) + Local Environmental Costs
Benchmark Price (Coal) + Local & Global Environmental Costs
Incremental Costs
*Based on data from 49 geothermal fields from JICA StudyAlthough about 10 GW may be economically justified (including externality), the associated financial incremental costs could be between IDR 6-9 trillion per year!
Although about 10 GW may be economically justified (including externality), the associated financial incremental costs could be between IDR 6-9 trillion per year!
Resource risks make it more challenging to mobilize investments particularly for new (green) fields
Uncertainties associated with geothermal field conditions and resource characteristics during the initial stages of field development will cause developers to require a price premium for taking on this risk
It is only after considerable drilling that the success rate stabilizes and become predictable
It is only after considerable drilling that the success rate stabilizes and become predictable
Data based on over 200 geothermal wells drilled in Indonesia
INDONESIA: UPPER CISOKAN PUMPED STORAGE HYDRO POWER PROJECT
Dejan Ostojic, Sector Leader (Energy)East Asia and Pacific Region, The World Bank
February 28, 2011Knowledge Series – Emerging IndonesiaWashington DC
Background
Indonesia has 75GW of hydropower potential
Yet only 4 percent has been exploited to date
The Government has embarked upon a low carbon development growth initiative
New and renewable energy constitutes 50 percent of the Government’s 10,000 MW crash program (Phase 2)
PLN has indicated their intention to build 3,835 MW of hydropower, with IPPs planning to build another 905 MW by 2018
PLN has also indicated their intention to build 70 MW of mini hydro with another 122 MW of mini hydro to be developed by IPPs by 2018
Hydropower can play an important role in Indonesia’s energy mix
Background
Electricity consumption in the Java Bali power system grew by 35 percent from 2003 to 2009;
The installed capacity grew by less than 23 percent over the same period
The system load factor has increased from 72 percent in 2003 to 78 percent in 2009 indicating significant suppressed demand
Demand is seriously underserved especially during the peaking hours
As a result, load shedding has reappeared sporadically across Java Bali
Quality of system frequency has worsened especially during the peaking hours
With a difference in peak and off-peak of over 6,000 MW each day, the peaking demand is supplied by oil-fired gas turbines, increasing the fuel cost which is already a large portion of PLN’s operating costs
Least cost and flexible peaking generation capacity is urgently needed
Filename/RPS Number
How does hydropower pumped-storage work?
Water is pumped during off-peak hours from lower to upper reservoir Hydroelectricity is produced during peak hours Hydroelectric units are fast-responding and quick-starting and therefore suitable for
rapid response during load changes in the power grid, as well as “black-start” facility after system black-outs
Filename/RPS Number
How does hydropower pumped-storage work?
Over 127 GW of pumped storage plants in operation around the world,
about 1% of the total power generation capacity installed
Developed countries' capacity (2004)
Pumped storage capacity, MW
% of country's total installed capacity
OECD Total 79013 3.29%
EU-25 31515 4.47%
Japan 24689 8.97%
United States 19569 1.86%
Switzerland 1655 8.64%
OECD installed PSP capacity (1970-2004), MW
0
10000
20000
30000
40000
50000
60000
70000
80000
90000
1969 1974 1979 1984 1989 1994 1999 2004
Recent surge in new projects related to facilitation of renewable (wind and solar) power generation
Strategic Context – Project Contribution
The project will: reduce the operating cost of PLN by substituting oil-based generation during peaking hours and reducing “cycling” of coal-fired power plants; and provide over 1,000 MW of peaking capacity and fast-responding reserve contributing to frequency control and emergency reserve capacity in the Java-Bali system;Therefore, the project will help improve the overall security, efficiency and reliability of electricity supply in Java-Bali
Project Development Objectives
The project will be the first pumped storage and largest hydropower generation facility in Indonesia
The project development objectives are to:
significantly increase peaking capacity of the power generation system in Java-Bali in an environmentally and socially sustainable way
strengthen PLN’s institutional capacity in hydropower planning, development, and operation
The project will contribute to higher level objectives by:
improving the business climate by better meeting the increasing demand for electricity in Java-Bali
strengthening the technical, managerial and operational capacity of PLN to implement large scale investment projects
Project Description
The project consists of three components
Development of the 1,040 MW Upper Cisokan Pumped Storage Power Plant
Social and environmental impact management
Land acquisition, resettlement, and livelihoods restoration
Environmental management
Institutional capacity building and preparation of feasibility study and basic design for the Mattengeng Pumped Storage Project
The project will be located in West Java in the catchment of the Upper Cisokan river, 150 km west of Jakarta, and 30 km from Bandung
Annex
Key sector challenges
The Java-Bali power system will face acute peaking and supply reliability risks without sufficient increase of flexible peaking capacity in the medium-term
Electrification ratios remain low, while robust and sustained economic growth is driving the demand for electricity to grow at an annual rate of over 7 percent
Sub-optimal generation fuel mix and low electricity price leading to large Government subsidies to state-owned power utility, PLN
Frequent restructuring of PLN in the past two decades has weakened its capacity to efficiently operate and expand a large and modern power system
Key sector challenges – World Bank response
The Bank is supporting a large investment lending program to finance:
public sector power infrastructure projects, especially renewable energy, to sustain economic growth
development policy lending programs to support GoI’s efforts to establish a sustainable policy environment for infrastructure project development and move the energy sector towards a low-carbon development path
technical assistance to rationalize the electricity tariff and subsidy regime, establish incentives for geothermal resource development, and strengthen the capacity of national state-owned companies in the energy sector