Mechanical Completion
-
Upload
sreeram4160 -
Category
Documents
-
view
581 -
download
18
description
Transcript of Mechanical Completion
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 1/49
PREPARED
BYNA
PTT PUBLIC COMPANY LIMITEDCHECKED
BY ONSHORE COMPRESSOR STATION 4
PROJECT
APPROVED
BY
CERTIFIED
(PTT)NA
REV.
NO.
DATE REVISED
BY
APPROVED
BY
DESCRIPTION
D1 18-Feb-08 NA ISSUED FOR ITB
D2 11-Jun-08 NA REVISION ISSUED FOR ITB
SPECIFICATION FOR
MECHANICAL COMPLETION
COMMISSIONING
AND 30 DAY CONTINUOUS OPERATION
SPC-0804.02-99.88 REV. D2
TOTAL 49 PAGES
AREA CODE OF SITE LOCATION
GENERAL AREA: 010
.
PTT PLC. CONTRACT NO. PTT PLC. PROJECT NO.
0804.02
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 2/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 2 OF 49
REV: D2
CONTENTS
SECTION
1.0 SCOPE .................................................................................................... 3
2.0 ACTIVITIES.............................................................................................. 3
3.0 CHECKLISTS, FORMS, AND LOGBOOKS ..................................................... 8
4.0 SCHEDULE............................................................................................... 9
5.0 VENDOR REPRESENTATIVES ..................................................................... 9
6.0 COMPLETION OF WORK...........................................................................10
MECHANICAL COMPLETION FORMS....................................................................34
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 3/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 3 OF 49
REV: D2
1.0 SCOPE
This Specification describes and clarifies the requirements for mechanical
completion, commissioning, 30 day continuous run and provides a format for
the Contractor to carry out these activities. It is intended to expand and
supplement, but not to supersede the general terms and conditions of the
Contract concerning Completion, Commissioning, 30 Day Continuous
Operation and Acceptance by PTT.
2.0 ACTIVITIES
2.1 Mechanical Completion and Precommissioning
Mechanical Completion and Precommissioning means fabrication,
construction, physical installation, testing, inspection, and system verification
is complete, such that the Facilities are ready for introduction of product.
Activities associated with the term precommissioning are included in
mechanical completion activities and shall not be described separately.
Mechanical Completion shall also mean that all requirements have been met
to begin Commissioning activities, including submittal of commissioning plans
and documentation. In general, Mechanical Completion shall include the
activities listed below. More detailed activities are included in the attached
checklists.
• All civil work shall be complete, including fencing, final grading, and
surface preparation.
• Piping systems shall be checked against designs, cleaned, tested for
pressure ratings and tightness, dried, inerted, and restored to tight
condition in readiness for operation.
• All equipment shall be installed, assembled, inspected, calibrated,
adjusted, cold-aligned, tested, lubricated, and cleaned as necessary to be
ready for operation.
• Elements such as strainers, temporary strainers, and filters shall be
installed, cleaned or replaced so that a clean element is in place for
commissioning.
• All electrical systems shall be installed, energized, and tested for
continuity, insulation resistance, ground fault, and operational functions.
• All instrumentation shall be installed, loop checked, set to proper set-
points, and calibrated.
• Instrumentation loop checks to the DCS, SIS, UCP, MPC, Load sharing&
anti surge controller and other control systems shall be completed.
• Probes, coupons, samplers, and other consumables shall be installed
• Utility and safety systems shall be commissioned and demonstrated to be
operational
• All painting, coating, and insulation work shall be completed
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 4/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 4 OF 49
REV: D2
• All changes and modifications shall be incorporated
• All functional tests and Site Acceptance Test of individual systems shall
be performed.
• All work shall be verified to be in accordance with the related
Specifications, Drawings (PTT and vendor), codes, and standards
• Deficiencies identified during Mechanical Completion activities shall be
remedied prior to the commencement of Commissioning
• Mechanical Completion documentation shall be completed and signed
2.2 Commissioning
2.2.1 General
The commissioning of the facilities follows Mechanical Completion and
encompasses the purging of nitrogen from the system, initial filling with gas,
pressurisation, full system function test at the operating condition, start-up of
the unit and guarantee run for the machines and equipments
The contractor shall be responsible for commissioning all Facilities included in
the Scope of Work.
Commissioning shall take place in the presence of PTT and Contractor
representatives together with PTT approved third party. Operating troubles,
defects and reasons, if any, occurring during the Commissioning shall benoted in a log book and signed by the authorised representatives of both
parties. All such troubles or defects shall be corrected by Contractor prior to
the completion of Commissioning.
All utilities required for commissioning shall be provided by contractor.
All cost associated with the utilities such as electricity, water, nitrogen, and
communication etc. shall be the responsibility of the contractor whether the
compressed gas is sent to the customer.
2.2.2 Commissioning Activities
Commissioning activities shall include the initial filling with gas, function andperformance test of the facilities in sections and related support systems,
start up and the Guarantee run. In accordance with applicable specifications
and procedures the following commissioning activities shall be performed as
minimum.
• Prerequisite for the introduction of gas into the system is that all utilities,
safety, and support systems shall be successfully Mechanically Completed
and are in operation.
• Initial gas filling including provision and installation of temporary
connections, bypasses, filters/separators and, if required, gas heater and
blow down and/or flare facilities.
• Pressurizing of piping sections and related equipment on a section by
section basis including checking for leaks, PTT may request the leak
checking to be performed with inert gas where possible.
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 5/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 5 OF 49
REV: D2
• Procedure for jumpering (bypassing) instrumentation, if required.
• Flowing of gas including functional testing of equipment, instrumentation
and controls and performance of the overall station at the designed
operating condition.
• Full functional tests for all control systems under normal operating
pressure in the system.
• Full functional tests for the SIS and other package equipment shutdown
systems under normal operating pressure in the system
• Seat leak test for all ball valves at the designed operating pressure.
• Performance of Guarantee Run
2.2.3 Guarantee Run
The Guarantee Run shall proof
A) the performance of each individual compressor train
• Start of individual compressor train
• Surge line verification and Anti surge function test
• Function test for all fall back strategies for anti surge control
system
• Demonstration of performance for varied set points
• Shut down procedure (normal and ESD)
• Performance Test in accordance with ASME PTC 10 (compressors)
and ASME PTC Check test requirement for the motor
• Each motor proofing of
a) Power under specified operating conditions
b) Adequacy of essential protective devices.
c) handling characteristics (i.e. starting characteristics, time of
loading)
• Each Gas Compressor proofing of
The polytrophic efficiency, the thermodynamic properties of the
compressor (power, discharge pressure, etc)
• Each Motor Driven-Compressor Package proofing of
Vibrations
Noise level
The operation of standby and emergency equipment.
Five day continuous reliability test run after the successful of theperformance test
• Gas Coolers proofing of
Performance
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 6/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 6 OF 49
REV: D2
Noise level
B) the total operability of the Compressor Station
• Sequential start of compressor trains from stand still until full load
is achieved
• Operation under varied load requirements (variation of set points for
flow, suction pressure, discharge pressure)
• Load sharing operation and function test for all fall back strategies.
• Shutdown, Stand-by (Recycling Mode) and Restart of individual
compressor trains
• Shutdown of total Compressor Station
• Pressure drop in the piping at the full load condition
• Performance of the inlet filter separator in term of liquid droplet and
solid particle filtering for the entire operation range.
• Noise level of the station
All noise level and vibration test mentioned in this section shall be
performed during the equipment running at the design condition.
Details about the tests shall be agreed between PTT and Contractor.
Contractor shall submit all test procedures for PTT’s review andapproval sixty days prior the test.
Before the contractor can proceed with the thirty day continuous
operation, the contractor shall submit the check list and the result of
each test for PTT to sign off and all major punch list shall be cleared
and signed off
2.3 Thirty Day Continuous Operation
The Contractor shall demonstrate to the PTT that the OCS 4 station meet the
PTT specifications and operating requirements during a 30 day continuous
testing period to be performed under normal operating conditions. The testing
period shall begin after PTT has accepted the completion of commissioningactivities and the scheduled start date for the testing period. The 30 day
testing period shall be continuous 24 hours per day at normal operating
conditions without major modifications or failures. Should a major error occur,
the test shall be stopped, the error corrected, and the thirty day test restarted
at day one.
Should any abnormal event occur during the thirty day test, the contractor
shall immediately investigate the event to determine a cause, correct the fault
and submit a report to PTT. The report shall state whether in the opinion of
the contractor the event is a major error or not, and the reasons for such a
conclusion.
During investigation of any abnormal event the Contractor shall continue to
operate the station as in the normal operation, if possible. The report shall be
submitted to PTT within three calendar days of the event. Failure to submit a
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 7/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 7 OF 49
REV: D2
report within the required time shall result in the event being declared a majorerror.
PTT will respond to an abnormal event report within three days; either
accepting the report, requesting additional information, or rejecting it.
Rejection of a report shall result in the event being declared a major error.
The contractor shall not make any major modification to the system during
this period. Such modification shall be considered the major error.
For the minor error, the 30 day continuous clock shall stop. The contractor
shall fix the problem and submit report for PTT to review. Upon the
satisfaction of the report, PTT shall allow the contractor to continue with the
test and the clock shall be resumed.
The Contractor shall prepare and submit test plan(s) for the PTT to review
and give permission to proceed at least 30 days prior to the scheduled start
date. At a minimum, the test plan(s) shall include.
• The verification for the operation of DCS, SIS, compressor control and
other control systems.
• Alarm and event log verification.
• The Switching over of the main and stand by equipments.
• The Switching over of the equipment trains.
• Testing procedures and schedule
• Test data to be collected, how the tests will be performed and a
comparison of test results to applicable specifications.
The contractor shall submit the daily report which include the activity log, the
test data and the result of any verification
During this period, the PTT shall have the full access to all systems in the
OCS4 and operate the facility under the supervision and responsibility of the
contractor. The contractor shall provide the qualify supervisor and field
support operator to cover the 24 hour operation
PTT will act in good faith not to delay the above mentioned activities;
however, interruptions to normal operations caused by PTT or third parties
shall halt the 30-day clock. Standby expenses during the interruption shall be
to Contractor's account. Once the source of the interruption is removed and
Contractor resumes normal operation, the 30-day clock shall also resume
such that the Contractor demonstrates a net 30 days of normal operations. In
the unlikely event that an interruption beyond the Contractor's control
extends for more than 30 days, or multiple such interruptions occur,
Contractor shall meet with PTT to determine the best course of action to
provide relief to the Contractor and assurance to PTT that the Facilities are
operable on a long-term basis.
Upon completion of the 30 day continuous test, the Contractor shall notify
the PTT in writing stating that the 30 day test period is complete. Upon PTT
concurrence, the PTT will issue a “Certificate of Start of Regular Operations”
to the Contractor.
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 8/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 8 OF 49
REV: D2
PTT will the initial acceptance certificate to the contractor after all majorpunch lists are cleared and signed off.
3.0 CHECKLISTS, FORMS, AND LOGBOOKS
3.1 General
Mechanical Completion, Commissioning and 30 day continuous operation
checklists and forms shall be used for all significant items to be erected,
installed, and/or modified under the Contract. Contractor shall prepare these
checklists and forms following the general format of the attached samples
(mechanical completion only - Contractor to generate forms and checklists forcommissioning and 30 day continuous operation), modified as necessary for
individual equipment and systems. Contractor shall submit these forms for
PTT approval at least sixty days prior to initiating the inspection, test, and
verification activities covered by the checklists and forms. Checklists and
forms required for Commissioning activities shall be submitted with the
Commissioning procedure plan at least sixty days prior to Mechanical
Completion.
Contractor shall prepare and use logbooks for all activities carried out during
Commissioning and 30 day continuous operation. At a minimum, Contractor
shall maintain a general logbook noting for each shift the personnel onsite,
events, activities, process conditions and changes, and results of any tests or
inspections. Contractor shall also maintain records of system status (such as
valve position and equipment hand-off-auto position) and temporary
conditions (such as jumpers installed/removed and valves out of service). To
allow accurate reconstruction of events in the case of an upset condition,
Contractor shall have available onsite a camera and film and shall record
instrument readings, control panel readings, and other relevant information.
3.2 Procedure
The checklists and forms prepared by the Contractor and as approved by PTT
shall be used as sign-off sheets for the permanent record of inspections,
tests, and mechanical completion activities. These shall be signed by
Contractor, PTT’s representative, and any Subcontractors or Vendors as
applicable. No system or unit shall be considered mechanically complete if any
items included in the checklists or forms are not fully signed.
Checklists, forms, reports, or other special documentation required by
Vendors or PTT shall be completed and considered a part of mechanical
completion in the same manner as above. Copies of these documents shall be
reproduced by the Contractor in as many copies as required and shall become
part of the permanent project records.
3.3 Introduction of Product
Contractor shall recognize that the introduction of product to any portion of
the Work is a hazardous activity requiring the full knowledge and approval of
all parties involved, including Contractor’s staff, PTT and PTT’s
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 9/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 9 OF 49
REV: D2
representatives, and the owners of the existing facilities. In addition, thefollowing criteria shall be met for introduction of natural gas:
• The unit shall be mechanically complete, with any exceptions approved by
PTT as described above
• All utility and safety systems, such as firewater, vent and flare, closed
drains, instrument air, and electrical, shall be completed and operational
• The work area around the unit is safe, secure, and clean of all debris,
unnecessary equipment, and excess materials
• A work permit system for hot work, cold work, vessel entry, etc shall be
in force• Detailed emergency and evacuation procedures shall be approved by PTT
for such events as fire, loss of power, loss of instrument air, overpressure,
and excessive condensate buildup
• Procedures for shutdown and standby shall be approved by PTT
In the case of a threat to the safety of personnel or equipment during c
commissioning, PTT may require Contractor to halt activities, place the
Facilities in a safe condition, and remedy the cause of the threat if within the
power of the Contractor. If product has been introduced, such work may
include depressurization and/or purging to render the Facilities safe.
4.0 SCHEDULE
Contractor shall prepare complete schedules for mechanical completion and
commissioning activities.
5.0 VENDOR REPRESENTATIVES
5.1 Installation, Mechanical Completion and Commissioning
Contractor shall schedule vendor representatives to be onsite to aid inmechanical completion and commissioning activities as necessary. As
minimum, the following vendor representatives shall be on site for the
installation, pre commissioning and commissioning activities.
Compressor package vendors, this shall include subsystem vendors such as
motor driver, gearbox and anti surge valve vendors.
DCS, SIS, PIMS and PRM
Machine Monitoring System
Fire and Gas control panels
MPC, load sharing and anti surge controllers
Switchgears and MCCs
Emergency diesel generator
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 10/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 10 OF 49
REV: D2
Instrument air package
Communication systems
Transformers
Inlet filter scrubber
Fire water pumps
The contractor shall make an arrangement for the local vendor representatives
to be on site for the required services such as installation, commissioning and
warranty work. The vendor representative outside of Thailand shall be
allowed only if the service from the local representative is not available.
During the 30 day continuous operation, the contractor shall determine for
which systems require the vendor representatives to be on site in order to
minimize the downtime for minor or major problems rectification.
6.0 COMPLETION OF WORK
Completion of the Work and the sequence of Notice and Acceptance shall be
as defined in the Contract. Contractor shall remain fully responsible for the
Facilities and all expenses incurred between the Start of Regular Operations
and PTT’s issuance of the Certificate of Initial Acceptance. The following
conditions for completion shall be met, at a minimum:
• Facilities shall be mechanically and structurally complete, inspected,
tested, commissioned, and operable at full design pressure
• Facilities shall be in a tight and clean condition, and otherwise prepared as
described in the Contract
• All checklists and documentation related to Commissioning and 30 day
continuous operation shall be complete and signed
• Contractor shall have issued the Notice of Start of Regular Operations to
PTT
• All required manuals, accounting records, quality control reports and
documents, as-built data, and other documents shall have been prepared
and delivered in accordance with the Contract.
• All deficiencies identified by PTT shall have been remedied
• Any disturbed land and facilities shall have been appropriately restored and
all required landscaping shall be complete
• All required training shall have been completed
• All required authorized inspection certification by law such as overhead
crane shall be completed and signed.
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 11/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 11 OF 49
REV: D2
Mechanical Completion
TO: DATE :
UNITS :
SUBJECT: Mechanical Completion and
Acceptance
ATTN: REF NO:
Gentlemen:
In accordance with the Contract, the following item(s) is (are) ready for commissioning:
ITEMS
EXCEPTIONS
Please sign and return two copies in acknowledgement of your acceptance.
Very truly yours,
CONTRACTOR CERTIFICATE OF ACCEPTANCE
(Mechanical Completion)
PTT
BY
DATE
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 12/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 12 OF 49
REV: D2
Notice of Completion
TO: DATE :
UNITS :
SUBJECT: Completion of Construction
and Acceptance
ATTN: REF NO:
Gentlemen:
Work has been completed on the item(s), unit(s), facility(ies), or plant(s) listed below. This
Work is in accordance with all plans, specifications, and official instructions from PTT and
articles of the Contract.
ITEMS
EXCEPTIONS
Please sign and return two copies in acknowledgement of your acceptance.
Very truly yours,
CONTRACTOR CERTIFICATE OF ACCEPTANCE
PTT
BYDATE
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 13/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 13 OF 49
REV: D2
MECHANICAL COMPLETION CHECKLIST OUTLINE
I. PIPING
Check list against Piping and Instrumentation Diagrams
II. ELECTRICAL
A. Area Classification
B. Service Conditions
C. Circuit Breakers, Switchgear and Motor Control Center
D. Main Power Supply
E. Auxiliary Power Supplies
F. Wire and Cable
G. Conduit Systems
H. Electronic Instrument Loops
I. Ground System
J. Transformer or Generator Neutral Resistance Ground
K. Lighting
L. Control Stations
M. Cathodic Protection
III. INSTRUMENTATION
A. General Check List
B. Inspection and Calibration of Instruments1. Manufacturer's Check Lists
2. Differential Pressure Type Flow Meters
3. Orifice Plates
4. Differential Level Transmitters
5. Level Switches
6. Flow Switches
7. Pressure Switches
8. Temperature Switches
9. Miscellaneous Switches
10. Gage Glasses
11. Pressure Gages
12. Pressure Instruments13. Temperature Instruments
14. Control Valves
15. Safety and Relief Valves
16. Regulators
17. Instrument Piping and Tubing
18. Analytical Instruments and Specialties
19. Receiver Instruments and Control Panel
20. Annunciators
21. Annubars
22. Detection and Safety Devices
23. Interface to SCADA
IV. EQUIPMENT
A. Vessels, Tanks and Drums
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 14/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 14 OF 49
REV: D2
V. FLUSHING AND CLEANING
VI. OTHER FACILITIES
A. Safety and Fire Protection
B. Concrete Placement and Testing
C. Roads, Fences and Gates
D. Soil Compaction
E. Waste Disposal
F. Documentation
THIS MECHANICAL COMPLETION CHECK LIST IS INTENDED TO ASSIST CONTRACTOR TO
DEVELOP THE DOCUMENTATION REQUIRED TO PREPARE THE WORK FOR COMMISSIONING.
ITEMS NOT EXPLICITLY LISTED BUT REFLECTED IN SPECIFICATIONS OR ON DRAWINGS SHALL
FORM PART OF THE SCOPE OF THIS ACTIVITY. CONTRACTOR SHALL BE RESPONSIBLE TO
ENSURE THAT ALL COMPONENTS AND SYSTEMS SHOWN ON THE VARIOUS CONTRACT
DOCUMENTS ARE PROPERLY VERIFIED AFTER INCORPORATION INTO THE WORK TO THE
ULTIMATE SATISFACTION OF THE OWNER.
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 15/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 15 OF 49
REV: D2
I. PIPING
Prior to hydrostatic test of plant piping, it is
necessary to check the plant for complete
conformance with the final piping and
instrumentation diagrams. The final inspection
must include the PTT operations representatives.
It may be a combined operations, contractor and
engineering effort. This check will help to reveal
any errors and prevent retest of the piping in case
omissions and errors are found and corrections
have to be made. A thorough check must be
made of all piping supports, spring hanger settingsand spring support settings, anchors and welded
attachments. If any welded attachments are found
to be incorrect and must be changed, or if some
have been omitted and have to be added, this
should be done prior to hydrostatic testing if
possible. If this is not possible, the welding
performed after pressure test must be thoroughly
supervised and carefully inspected after
completion.
A. All piping systems must be checked for proper
venting and draining. Check for proper slope
where required.
B. Is there any configuration not previously
observed or corrected likely to result in
hydraulic shock (water hammer), slug flow or
vapor binding?
C. Check accessibility of all operating valves.
D. Check all valves for correct body material, trim
and packing.
E. Check pipe valves and fittings for specification
material, correct size, type, pipe schedule,
flange rating, and metallurgy.
F. Check all bolted joints for proper studding,
bolt length and gasket material.
G. Check for expansion and vibration. Check for
adequate, proper and safe supports, undue
stresses and alignment.
H. Operate all hand valves. Check for chain
wheels where required, platforms and ladders.
Grease all stems and handwheels.
I. Check all check valves for proper flow
direction.
J. If internal lining or sleeves are specified, are
they in place? Any wear plates left out?
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 16/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 16 OF 49
REV: D2
K. Has stress relief been performed where
required? If cold springing specified, has this
been checked?
L. Check connections and branch piping for
proper reinforcement.
M. Check to see that unusual or excessive piping
loads and temperature strains have not been
imposed on pump flanges.
N. Check all lubricated valves for proper
lubrication as recommended by themanufacturer for the service in which the valve
is to function. Verify standardization with
depot personnel.
O. Check installation and stroke of valve
operators and their lubrication and limit
settings.
P. Check motor valve settings for proper support
accessibility.
Q. Blank off all relief valves prior to testing piping
systems.
R. Hydraulically or hydrostatically test all pipe in
accordance with applicable codes and
specifications and complete PTT Form TR-1.
Provide hydrostatic test record, such as form
TR-2 to supplement PTT form, properly
witnessed by PTT. Do not test through
instruments or rotating equipment.
S. Perform any special tests and special chemical
cleaning or pickling required by the Contract
specifications or drawings. Complete any
required records.
T. Has blowing and/or flushing been performed?
Most debris and dirt should have been
routinely removed during construction. Avoid
flushing dirt and debris from one section to
another where it may become lodged. Do not
flush into instrument take-offs. (See Flushing
and Cleaning, Section V).
U. After flushing is complete and piping
reassembled, check for installation of start-up
strainers on pumps as specified by the
drawings and specifications. Strainers must be
in place before equipment has final alignmentcheck. Check and remove any blinds used
during construction and test.
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 17/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 17 OF 49
REV: D2
V. Check to see that proper orifice plates,
pressure gauges, sample valves, thermowells
and other such accessories are installed as per
drawings and specifications. Orifice plates
should be installed after prestart flush.
W. Check to see that all insulation, whether for
process, noise, or personnel protection
required at start-up, is installed.
X. Is all sentinel drilling (tell-tale holes) complete?
Y. Special procedures are required when air or
moisture must be removed or excluded. Hasthis work been performed?
Z. Check if Stamp and data reports that are
required for API 5L Piping Standards are in
place. Check if ASTM data reports that are
required are in place.
AA. Make the necessary tie-ins at the unit limits
as required by the drawings and
specifications.
BB. Prepare operating (live) systems for safe tie-
ins.
CC. Install car seals or locks on valves designated
as car sealed or locked valves. Check and
record position of all car sealed or locked
valves.
II. ELECTRICAL
Contractor shall prepare a comprehensive
Mechanical Completion form for each set of
electrical connections and electrical loops to
supplement: instrument data sheets, including
electrical wiring and electrical connections toequipment furnished for the Work.
Contractor shall follow the requirements in the
Electrical Installation Specification, Vendor supplied
instructions, instruction provided in this section
and directions received from PTT.
A. Area Classification
Check that all equipment is suitable for the
relevant area classification.
B. Service Conditions
Check that all material meets the conditions
specified in the plan drawings.
C. Circuit Breakers, Switchgear and Motor
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 18/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 18 OF 49
REV: D2
Control Centers
1. Equipment shall be visually inspected for
damage and missing parts, and
thoroughly cleaned of any dirt, debris or
foreign material accumulated during
construction.
2. All field wiring shall be checked for
connection to proper terminals.
3. All components shall be megger tested
(600-volt megger) minimum reading to
be one (1) megohm, before being
energized.
4. Make continuity checks of all circuits
simulating actual operating conditions as
far as possible without energizing
equipment.
5. Verify that instruments, instrument
transformers, relays, fuses and other
devices are of proper type, size and
rating, in accordance with relay and fuse
coordination information provided.6. With breaker in test position, test
operation with local, remote and manual
operation.
7. Secure approval of PTT to energize
equipment.
8. Induction type relays and other
protective devices shall be set and tested
per manufacturer's recommendation.
9. All seals in conduit shall be checked to
determine if installed correctly and
properly filled with approved sealing
compound.
10. Fences and other enclosures for high
voltage apparatus must be complete and
locks installed on gates.
D. Main Power Supply
1. Before closing main breaker, check phase
rotation and voltage.
2. Energize feeders.
E. Auxiliary Power Supplies
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 19/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 19 OF 49
REV: D2
1. Check battery and charger for damage
and check electrolyte for level and
specified gravity. Follow manufacturer's
precommissioning instructions.
2. Check emergency generator and
automatic transfer equipment for
automatic starting, generation and
transfer with simulated loss of normal
power.
3. Check UPS static "no-break" power
system for AC and DC input voltage and
check that output is "no-break" by
simulating loss of AC supply and loss of
battery.
F. Wire and Cable
1. 600-volt wiring and cable shall be
inspected for mechanical defects at time
of installation. Wire with damaged or
non-concentric insulation shall not be
used. All 600-volt wire shall be tested
with a megger and shall show minimum
reading as indicated in (2) to ground or
between each wire and all others in acommon conduit or raceway.
2. The insulation resistance will vary with
conditions; the following should serve as a
guide:
Wire Size Insulation Resistance
#12 & smaller (4mm2) 1 megohm
#10 to #8 (6/10mm2) 500,000 ohms
#6 to #2 (16/35 mm2) 400,000 ohms
#1 to #4/10 (50/95 mm2) 300,000 ohms
250thru 750 MCM (120/300 mm2) 200,000 ohms
3. All high voltage cables (above 600 volts)shall be given a high potential test
according to manufacturer's instructions.
This test shall be at a voltage not less than
IPCEA or AEIC standard voltage test.
Cable shall be tested on reel as soon as
possible after delivery and again after
installation (DC Volt to be applied 10
min.).
4. Cable runs shall be tested with a megger
prior to high-potential test.
5. All potheads or cable terminations installedon the site shall be given the same high
potential test as the cable to which it is
attached.
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 20/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 20 OF 49
REV: D2
6. Complete Form EE-2 (typical) where
applicable.
G. Conduit Systems
1. Underground – Check for compliance with
construction drawings.
2. Above Ground - Check for compliance with
detailed design drawings and the
construction specification.
H. Electronic Instrument Loops
1. Check all terminations for proper and tightconnections, check loops for continuity
and accidental ground.
2. Inspect all terminal boxes for drains, cable
seals and moisture.
3. Check for proper type RTD wire. Use
Form EE-2 (typical) if necessary.
4. Check power supply and fuses at control
board, control loops and field instruments.
Use Form TR-4 (typical).
I. Ground System
1. The ground system should be inspected for
defective or incomplete connections.
2. Measure actual resistance to ground at the
ground loop or grid with a ground
resistance megger.
3. Check resistance to ground of all
equipment and tanks that connect to
individual ground rods. Each ground
should test 5 ohms or less.
4. Verify integrity of separate "instrumentground" needs.
5. Complete Form TR-3 (typical).
J. Transformer or Generator Neutral Ground
1. For resistance grounding: Check grounding
transformer, resistor, current transformer,
and relay for size and rating.
2. Set relay in accordance with relay
coordination settings.
K. Lighting
1. All light fixtures and convenience outlets
shall be checked for proper voltage and
operation.
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 21/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 21 OF 49
REV: D2
2. Floodlights shall be checked at night and
directed to obtain correct lighting design
illumination levels.
3. Verify all illumination levels.
L. Control Stations
1. Check out manual control stations.
M. Cathodic Protection
1. Check continuity of system.
2. Turn on and adjust current as appropriate
before piping is placed in service.
3. Balance CP circuits after piping is put in
service with pipeline CP.
III. INSTRUMENTATION
Contractor shall prepare a comprehensive
Mechanical Completion form to supplement each
instrument data sheet furnished for the Work
Contractor shall follow the requirements in the
applicable Specifications, Vendor supplied
instructions, instructions provided in this section
and directions received from PTT.
A. General Check List
1. Check to see that specification materials
have been used in the installation of
instrument distribution piping, connecting
tubing, and fittings.
2. Check all instrument loops for proper
installation in accordance with the latest
approved drawings.
3. Check to see that all parts are accessible.
4. Check to see that control lines are not in
contact with hot lines or equipment.
5. Check to see that instrument air dryers and
filters are working properly.
6. Check to see that all parts, including
instrument piping and tubing, are properly
supported and protected from possible
damage due to operating or maintenance
activities in the area.
7. Check to see that the power to valves and
gas to instruments supplied with air bylateral lines or tubing is ready to be filled
with air.
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 22/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 22 OF 49
REV: D2
8. Warning - Isolate instruments during
hydrotest.
9. All piping and tubing is to be cleaned by
disconnecting at both ends and blowing
out. All instrument air distribution piping
shall require a pneumatic test with air.
Tubing shall be tested for leaks with an air
bubbler in accordance with ISA standards.
10. After lines are cleaned and tested, they
should be immediately capped or
connected to the instrument to prevent
any contamination or water from entering.
The loop drawings should be used to
record this test and cleaning. Complete
Form TR-6 (typical).
11. Check to see that lighting is adequate for
operations and maintenance. Check at
night.
B. Inspection and Calibration of Instruments
1. Manufacturer's Check List
a. Calibrate instrument and control
system in accordance withmanufacturer's information and
instrument data sheets.
b. All instrument elements should be
checked against design data for
correctness of location, connection,
labelling, and range of measurement.
c. Check to see that all measuring
elements, control valves, or other
instruments removed for the flushing
and cleaning operation are replaced
and connected.
d. Operate all hand valves including
instrument air supply valves.
e. Check to see that all electrical circuits
are tested. Grounding for safety and
shielding is to be checked.
f. Control valves should be tested for
proper response to their control
devices and for proper action on signal
failure.
g. Alarm devices and automatic safetyswitches are tested. Shutdown
systems are to be checked. Set all
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 23/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 23 OF 49
REV: D2
switches in accordance withinstrument data sheets.
h. Maintain a log of instrument
calibrations.
i. The calibration of transmitters,
controllers, etc., shall be checked to
comply and meet manufacturer's
guaranteed accuracy’s.
j. Each control valve shall be checked by
local pressure reduction to comply
with and meet manufacturer's
guaranteed accuracy’s.
k. Set all controllers with preliminary
modes per Vendor's documentation.
l. Complete Form IE-1 (typical) as
required.
m. All thermocouples and RTDs are to be
checked in a single operation from the
thermocouple to the indicator at the
panel board. After disconnecting the
wires from the element, the calibration
of the indicator is to be checked atthree points or more by the use of a
potentiometer.
n. Install seal fluids where required.
Properly seal instruments.
2.. Differential Pressure Type Flowmeter
a. Bench calibrate against a standard
water column manometer at three
points (zero, line 5 and line 9).
b. Use a precision output meter or gage
to monitor output on transmitters.c. Complete manufacturer's check list.
3.. Orifice Plates
a. Check nameplate data.
b. Check for an upstream sharp edge.
c. Measure and record bore with inside
micrometer to ensure compliance with
specifications.
d. Check material.
4. Differential Pressure Type LevelTransmitter
a. Bench calibrate against a standard
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 24/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 24 OF 49
REV: D2
water column manometer at threepoints.
b. Use a precision output meter or gage
to monitor output.
c. Fill seal legs.
d. Complete manufacturer's check list.
5. Level Switches
Check mechanical movement against
output on float or displace types. No
calibration required.
6. Flow Switches
a. Check and set differential pressure
types using standard water column
manometer.
b. Mechanically check only - through-flow
types.
7. Pressure Switches
a. Check using a hydraulic or dead-
weight test and set to the required
alarm and/or trip point.
b. Set receiver types to the required trip
point using a precision pressure gage.
8. Temperature Switches
a. Bench check using a controlled
temperature bath.
b. Set to required alarm and/or trip point.
9. Miscellaneous Switches - Solenoid valves,
electrical relays, timers, pushbuttons, etc.
shall be checked for proper operation.
10. Gage Glasses
a. Install as received.
b. Clean and check illuminators and
check protectors and other
accessories.
c. Do not replace any broken glasses
without proper instruction and torque
wrenches. Clean broken glass from
piping.
11. Pressure Gages
a. Gages are subject to construction
damage and should not be installed
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 25/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 25 OF 49
REV: D2
until immediately prior tocommissioning.
b. Do not calibrate direct connected,
bourbon-tube type gages, but where
required zero instrument prior to
installation.
c. Receiver-type pressure gages shall be
three-point calibrated using a precision
pressure gage and precision air
regulator.
d. Draft gages, diaphragm type shall be
three-point calibrated using a water
column manometer.
e. Glass tube manometers and draft
gages shall be filled with the proper
fluid and properly zeroed.
12. Pressure Instruments
a. Pressure and pressure differential
transmitters and transducers shall be
three-point bench calibrated using a
hydraulic or dead weight tester prior to
installation. A precision output meteror gage shall be used to monitor the
output.
b. Complete manufacturer's check list.
13. Temperature Instruments
a. Gages are subject to construction
damage and should not be installed
until immediately prior to
commissioning.
b. Prior to installation, filled system
instruments shall be three-point bench
calibrated using a controlled
temperature bath.
c. Thermocouple transducers shall be
calibrated using a portable precision
potentiometer in place in the racks.
d. The multi-point temperature indicator
calibration shall be checked using a
portable precision potentiometer.
e. Temperature recorder calibration shall
be checked using a portable precision
potentiometer.
f. Complete Form IE-2 (typical) and
manufacturer's check list as needed.
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 26/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 26 OF 49
REV: D2
g. Bi-metallic dial thermometers shall not
be calibrated but the dial or the pointer
reset shall be set to the known
ambient temperature before installing.
h. Thermocouples shall be checked for
type, polarity, double reversals,
shielding, and proper point
identification.
14. Control Valves
a. All diaphragm and piston-operated
control valves shall be pneumaticallystroked using a pressure regulator and
pressure gage against the spring range
shown on the nameplate. Mechanical
seating and travel shall be checked
against the nameplate. It is desirable
that this check be made in the shop
prior to installation.
b. Valve positioners shall be calibrated on
the control valve in accordance with
the instrument specifications. Split
range positioners shall not have
bypasses and shall be carefullychecked.
c. Prior to installation, electropneumatic
valve transducers shall be bench
calibrated with a portable or bench
power supply and meter and output
gage. If transducers are received
mounted on valves, calibration should
be done in place.
d. Control valve accessories, such as
handwheels, booster relays, etc., shall
be operationally checked.
e. All control valves shall be carefully
checked by nameplate data and
specifications and lubricated as
required.
f. Butterfly valves shall be carefully
checked to see that the vane moves
freely into the upstream and
downstream piping. Throttling
butterfly valves shall be set for
maximum travel in accordance with
the vendor's data.
15. Safety and Relief Valves
a. Check all safety valves for proper
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 27/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 27 OF 49
REV: D2
nameplate setting as per the valve andinstrument specifications.
b. Test all relief and safety valves for
proper relieving pressure and possible
leakage before installation. This test
shall be performed by a qualified
person. Qualified person is one who
as attended a school of instruction or
received training pertinent to the
equipment involved.
c. Where seals are found broken on relief
valves, the relief valve is to be retestedand resealed in accordance with plant
safety practice.
d. Where block valves are permitted
under the relief valve, they shall be full
line size and locked in the open
position.
e. Where rupture discs are used to isolate
the safety valve from process fluid,
their pressure rating is to be checked.
f. Conduct all operating tests required by
code, law and insurance.
g. Complete Form TR-5.
16. Regulators
a. Install self-contained pressure and
temperature regulators as received.
b. Check inlet and outlet ports and
nameplate data.
17. Instrument Piping and Tubing
a. Check against specifications.
b. Verify correct installation.
18. Analytical Instruments and Specialties
a. Calibrate analyzers and sampling
systems, using product samples where
furnished.
b. Check recording, peak-picking, alarm
interrupt circuitry. (Manufacturer to
calibrate after installation.)
c. Package instrument systems shall be
carefully checked and calibrated to
vendor's specifications.
19. Receiver Instruments and Control Panels
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 28/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 28 OF 49
REV: D2
a. Check all instrument nameplates, both
front and rear, and all panelboard
nameplates for tag number, service,
location, and proper spelling.
b. Install and check all charts and scales
for range in accordance with
specification.
c. Calibrate all principal front-of-panel,
rear-of-panel, and rack mounted
instruments in accordance with
manufacturer's instructions.
d. Panel instrument calibration test
instruments shall be precision devices
and shall be the standard for loop
matching.
e. Check loop matching, such as zeroing
transmitter to receiver.
f. Pressure test all signal air lines to
ensure leak tightness.
g. Check all wiring for continuity.
h. Perform megger tests for propergrounding and no shorts. Use Form
TR-3 (typical).
20. Annunciators
a. Check nameplates for engraving,
spelling, and proper location.
b. Check operation and point continuity
by mechanically actuating all trouble
contacts for low-high-deviation alarm
operation, auxiliary contact operation
and sequence. Use Form EE-3.
21. Check operation and calibration of all
annubars
22. Check all detection and safety devices.
Are they property calibrated? Do they
initiate the proper alarms and shutdowns
upon activation?
23. Interface to SCADA
a. Check transfer of digital inputs from
field to SCADA display screen.
b. Check 0, 25, 50, 75, and 100% risingand falling levels for each analog input
to SCADA display screen.
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 29/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 29 OF 49
REV: D2
c. Check frequency inputs at 10 Hz and
maximum frequency to SCADA
display screen.
d. Check control outputs from SCADA
command to end device in field.
e. Check analog setpoints from SCADA
output to end device. Verify that
feedback of setpoint is correctly
shown on SCADA display with
controller in local and remote.
IV. EQUIPMENT
Contractor shall prepare a comprehensive
Mechanical Completion form for each unit shown
in the Equipment List as furnished for the Work.
Contractor shall pre-plan and notify PTT in advance
when manufacturer's representatives or service
engineers are to be present at the job site to
implement the Mechanical Completion program.
Contractor shall follow the requirements in the
applicable Specifications, Vendor supplied
instruction, instructions provided in this section,
and directions received from PTT.A Vessels, Tanks and Drums
Contractor shall verify under this section:
Completeness of gas dehydrators, dryers, filters,
flame arrestors and silencers.
1. Internal Inspection
Before the final bolting of cover plates on
manways, the interiors of the vessels must be
inspected for cleanliness, completeness, and
proper installation of internal components.
Metallurgy of internals and interior claddingmust be checked. Measurements and locations
of internals must be verified as to drawings and
specifications. This check shall be a joint
inspection with PTT. A more detailed check list
is given below.
a. Are all nozzles. Pipes. And internals installed
at proper location with correct orientation
and clearances as shown on the drawings
and called for in the vessel specification ?
b. Are all internals fabricated of proper
materials as per the vessel specifications?Are cladding. lining. And wear plates
installed as specified and of proper
metallurgy ?
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 30/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 30 OF 49
REV: D2
c. Check tightness of all bolting, fitting, and
positioning of vessel internals.
d. Are all thermowells in correct position and
of correct alloy and length? Are level
control or indicator floats of proper size and
free to move, with stilling wells were
specified?
2. External Inspection
a. Are all specified nozzles and other
connections installed at proper location?
b. Are all valve connections for sampling or
pressure installed and at correct locations?
c. Are all thermowells installed?
d. Are all ladders and platforms installed? Are
there any safety hazards such as piping,
valves, conduits too close to ladder rungs
and rails?
e. connected piping, has this been done?
Complete From TR-2 (typical).
f. Are all required pressure relief valves
installed? Do nameplate pressure settings
agree with specifications? If the assignment
includes testing, has this been done?
g. Is all lifting gear, such as davits, etc., in
place? (As per drawings)
h. Are adequate vents and drains provided?
Plugs or valves installed? Make check for
plastic shipping plugs that must be removed
and replaced with specification steel plugs
for vessel rating and service.
i. Are plugs removed from “tell-tale” holes inreinforcing pads? Pipe vent outside
insulation using ¼” open end pipe.
j. Is electrical grounding system complete?
k. Is painting required before start-up is
complete?
l. Special procedures are required when air or
moisture must be removed or excluded. Has
this work been done?
m. Check adequacy of lighting. This should be
done at night with cooperation of PTT.3. Complete typical Forms ME-1
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 31/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 31 OF 49
REV: D2
V. FLUSHING AND CLEANING
A. All piping and vessels should be thoroughly
cleaned of loose scale and internal debris that
accumulates during construction. Flush or
blow lines to remove the bulk of this loose
material. A large part of this flushing can be
accomplished by removing water from lines
and equipment after hydrotesting or during the
run-in of pumps. During test and flushing
operations all lines and systems must be
checked for proper drainage and venting.
Most of the process and auxiliary lines may beflushed through established circuits from
vessels, which are filled with water for that
purpose. A single filling of a vessel may not
provide adequate water for flushing all lines for
which it is a reservoir, in which case a
continuous or intermittent flow of water into
the vessel should be maintained. Water may
be admitted to most vessels via temporary
connection to a nozzle on the bottom outlet
line. If washing of the vessel itself is a primary
object, introduce water into the top of the
vessel by hose connection or by other means.
Overhead lines may be flushed by overflowing
the related vessel. When washing lines from a
vessel always be certain that the vessel is
adequately vented to prevent a vacuum
condition. Verified?
B. In any system to the greatest extent possible,
flush downward or horizontally, and out at low
points. The low point discharge openings will
usually be temporary openings made by
disconnecting flanges or fittings; normal drains
may be used for flush outlets provided they are
equal to line size or nearly so. For best results,there should be no restriction at the outlet or
any other point in a line undergoing cleaning;
where it is necessary to throttle the flushing
flow, do so at the supply end.
The higher the velocity of flushing, the more
thoroughly a line will be cleaned. With a
limited supply of flushing medium, do not flush
through too many circuits or openings
simultaneously. Flush through all vents, drains
and other side connections. Flush by-passes
alternately with their main channels. Try to
avoid flushing line debris into equipment whereit may become lodged or trapped. This is
particularly important when washing towers
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 32/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 32 OF 49
REV: D2
containing perforated trays. So far as it can bedone conveniently and economically, divert the
initial flow ahead of, or around such equipment
until lines upstream are clean, and then flush
into or through the item concerned. Verified?
C. When flushing of the lines is finished, drain
water from the system as completely as
possible. Provide ample top venting of all lines
and vessels during the draining operation and
drains must be provided in all low spots of the
system to ensure removal of all flushing water
or media. Blow lines with air to effect further
water removal. Done?
D. At the conclusion of flushing any system,
check carefully to see that normal alignments
are restored, temporary connections broken,
temporary breaks reconnected, check valve
flappers and/or cover plates replaced, orifices
installed, etc. Start-up strainers are to be
installed for pump and alignment of equipment
checked after piping has been bolted in place.
Completed and checked?
E. Special instructions shall be issued outlining
cleaning procedures for units or sections wheremoisture cannot be tolerated due to process
considerations. Done?
VI. OTHER FACILITIES
Contractor shall prepare a comprehensive
Mechanical Completion form for each facility
installed as shown on drawings.
Contractor shall follow the requirements in the
applicable Specifications, Vendor supplied
instructions, instructions provided in this section
and directions received from PTT.
A. Safety and Fire Protection
1. Are all systems operable? All components
tested "end-to-end," verified and working?
2. Ladders and platforms are installed for safe
operation and access.
3. Any safety hazards? Identify and describe.
B. Concrete Placement and Testing
1. Were all concrete tests completed? Arelaboratory and field reports on file?
2. Verify that minimum strength has been
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 33/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 33 OF 49
REV: D2
achieved for all pours.
3. Has all concrete work been inspected for
cracks? Make necessary repairs.
C. Roads, Fences and Gates
1. Verify all new road surfaces suffered no
damage and all damages have been
repaired. The repairs have been accepted?
2. Verify all new and/or relocated gates
operate properly.
3. Verify all fencing materials suffered no
damage and all damages have been
repaired to PTT satisfaction.
4. Verify all new road culverts and headwalls
suffered no damage and all damages have
been repaired to PTT satisfaction.
5. Have security fences, gates, and guard
houses been completed?
6. Has construction equipment such as
cranes, welding machines, etc., no long
being used, been removed from operation
areas?
D. Soil Compaction
1. Has test been conducted, results
documented and degree of compaction
accepted?
2. If treatments to accelerate process were
used, describe and verify acceptance.
E. Waste Disposal
1. Have required governmental approvals
been obtained?
2. Do all underground drains flow freely?
Have seals been established where
required?
3. Are outfall lines, ditches, etc., ready for
use?
F. Documentation
1. Complete all work shown on drawings and
verify all check lists are complete.
2. Have required identifying markers and
signs been installed?
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 34/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 34 OF 49
REV: D2
MECHANICAL COMPLETION FORMS
The sample forms on the following pages may be used for recording field inspection
results and tests. The list is not necessarily complete and the specific requirements for
each facility or system must be a matter of agreement between Contractor and PTT.
FORM NO.
Test and Record Forms:
TR-1, p. 1 Piping Strength Test Pressure Report (Page 1)
TR-1, p. 2 Piping Strength Test Pressure Report (Page 2)
TR-2 Hydrostatic Test Record
TR-3 Megger Readings - Ground Resistance RecordTR-4 Electrical Test Record
TR-5 Safety and Relief Valve Record
TR-6, p. 1 Instrument Test Record (Page 1)
TR-6, p. 2 Instrument Test Record (Page 2)
Mechanical Equipment Check List
ME-1 Vessels
Electrical Equipment Check List
EE-1 Circuit Breakers
EE-2 Lighting Panels, Insulation Resistance, and Remote Terminal Display (RTD)
EE-3 Alarm Circuit Operation Test
Instrument Check List
IE-1 Controllers
IE-2 Direct Connected Recorders and Recorder Controllers
IE-3 Electronic Controllers, Recorders & Indicators
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 35/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 35 OF 49
REV: D2
FORM TR-1
PIPING LEAK AND STRENGTH PROOF TEST REPORT (Page 1)
Onshore Compressor Station 4 Project
FORM TR-1
LEAK AND STRENGTH PROOF TESTREPORT (Page 1 of 2)
DEPARTMENT CONDUCTING TEST REPORT DATE
REASON FOR TEST: NEW CONSTRUCTION EXISTING FACILITY STOCK PIPE
1. LOCATION:
Facilities in GSP
(Name.________________)
Natural Gas Piping
LPG Piping
NGL Piping
Oil/Water/Other Piping
Metering Station
(Name.________________)
Pipeline “A”
“B”
Milepost to ____
Station to ____
DRAWING REFERENCES:
2. PIPE DATA AND TEST PRESSURE REQUIREMENTS
a. Size b. Wall c. Spec d. Material e. Min. Test
Pressure
f. Min. Test
Time
g. Footage
Tested
Columns a. through f. need to be completed and approved prior to test.
3. TEST MEDIUM INFORMATION
Water Natural Gas Nitrogen Other:____________________________________
If water is to be used, the following must be completed:
Source____________________________ Sample Analysis______________________________________
Agency How to beConsulted_________________________ Disposed____________________________________________
ENGINEERING
APPROVAL BY:__________________________________________________________DATE: _________________
4. TEST INSTRUMENTS AND EQUIPMENT:
Type Make Range Serial No. Date LastCalibrated
PressureRecorder
TemperatureRecorder
Dead WeightTester
Others:
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 36/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 36 OF 49
REV: D2
FORM TR-1
PIPING LEAK AND STRENGTH PROOF TEST REPORT (Page 2)
Onshore Compressor Station 4 Project
FORM TR-1
LEAK AND STRENGTH PROOF TEST REPORT
Page 2 of 2
5. PROFILE DATA:
ELEVATION PRESSURINGPOINT
LOCATION OF
DEAD WEIGHT TESTER
Survey Station
Elevation
6. FIELD TEST PRESSURE DATA:
Date of Test Time Test Began Date & Time Test Ended Weather:
1.ClockTime
2.Press.Point(psig)
3.Min.
Press. @Max.Elev.(psig)
4.Max.
Press. @Min.Elev.(psig)
5. Amb.Temp.( F)
6.Test
MediumTemp.( F)
1.ClockTime
2.Press. Point
(psig)
3.Min.
Press. @Max.Elev.(psig)
4.Max.
Press. @Min.Elev.(psig)
5. Amb.Temp.( F)
6.Test
MediumTemp.( F)
Enter in column 2, the pressure reading from the dead weight tester. Columns 3 and 4 data may be calculated if accurate elevation information is available.
For piping in the GSP facility, furnish a field sketch if test layout differs from reference drawings.
Temperature and pressure recorder charts and gage calibration charts are to be attached to the original of thisreport together with the water analysis if such a test was necessary.
For mainline piping, furnish field profile sketch recording the pipeline length tested and the elevations and pressureas at high and low elevations. Existing bench marks & survey monuments shall be referenced in the test section.
TEST PERFORMED BY:
PTT By: _____________________________
Contractor (Firm) By: _____________________________
Subcontractor (Firm) By: _____________________________
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 37/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 37 OF 49
REV: D2
FORM TR-2
HYDROSTATIC TEST RECORD
Onshore Compressor Station 4 Project FORM TR-2
HYDROSTATIC TEST RECORD
TEST SECTION NO. ______________________________ (1)
PIPING SERVICE SYSTEM_________________________________ DATE OF TEST ________________________
METHOD OF TEST ___________________ TEST MEDIUM SOURCE ________________ COMPOSITION_________
AMBIENT TEMPERATURE __________________________ TEST MEDIUM TEMPERATURE ___________________
DESIGN PRESSURE ______________________________ TEST PRESSURE _______________________________
(2) Line Numbers Origin Destination Drawing No. ISO No.
TEST INSTRUMENTATION AND TEST RECORDS
READINGS THROUGH TEST PERIOD REMARKS
TIME PRESS. TEMP. LEAKS
TESTINSTRUMENTDESCRIPTION AND RANGE
CALIBRATIONDATE
1 2 3 1 2 3 1 2 3
DESCRIBE: FILL PUMP
PRESSURE PUMP
MAXIMUM PRESSURE
GPM MAX
GPM
GPM AT MAX
DEADWEIGHT TESTER
TEST HEADERS AND BLINDS ________________________________________________________
EQUIPMENT INCLUDED IN TEST EQUIPMENT EXCLUDED - SHOP TESTED
TAG NO. DESCRIPTION REMARKS TAG NO. DESCRIPTION REMARKS
NOTES: (1) Prepare documentation for each Test Section – include schematics, layout and periodic notes duringtest period.
(2) Use data from Project issued sheets
Accepted:
Subcontractor Date
PTT
LOCATION
Accepted:
Contractor Date
DATE
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 38/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 38 OF 49
REV: D2
FORM TR-3
MEGGER READINGS - GROUND RESISTANCE RECORD
Onshore Compressor Station 4 Project FORM TR-3
MEGGER READINGS -GROUND RESISTANCE RECORD
GROUNDSYSTEM TEST
LOCATION
SYSTEMNUMBER
RESIST.(OHMS)
AMB.TEMP.
WEATHER DATE TESTER'SINITIALS
EQUIPMENT
ACCEPTED __________________________________
SUBCONTRACTOR
DATE _______________________________________
ACCEPTED______________________________________
PTT
DATE __________________________________________
ACCEPTED __________________________________
CONTRACTOR
DATE _______________________________________
ACCEPTED _____________________________________
PTT
DATE___________________________________________
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 39/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 39 OF 49
REV: D2
FORM TR-4
ELECTRICAL TEST RECORD
Onshore Compressor Station 4 Project
FORM TR-4
ELECTRICAL TEST RECORD
SYSTEM DATE OF TEST
METHOD OF TEST
DESIGN VOLTAGE TEST VOLTAGE
CIRCUIT NUMBERS VOLTAGE ORIGIN DESTINATION RUN IN DRAWING NO.
EQUIPMENT INCLUDED IN TEST
ITEM NO. DESCRIPTION ITEM NO. DESCRIPTION
ACCEPTED ________________________________
SUBCONTRACTOR
DATE _____________________________________
ACCEPTED _______________________________________
PTT
DATE ____________________________________________
ACCEPTED ________________________________
CONTRACTORDATE _____________________________________
ACCEPTED _______________________________________
PTTDATE ____________________________________________
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 40/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 40 OF 49
REV: D2
FORM TR-5
SAFETY AND RELIEF VALVE RECORD
Onshore Compressor Station 4 Project
FORM TR-5
SAFETY & RELIEF VALVE RECORD
SAFETY VALVES
ITEMNUMBER
EQUIPMENT SIZE PRESSURE SETTINGTESTED
DATETESTED
INSTALLED OK
RELIEF VALVES
SYSTEM TEST
REMARKS:
ACCEPTED ________________________________
SUBCONTRACTOR
DATE _____________________________________
ACCEPTED _______________________________________
PTT
DATE ____________________________________________
ACCEPTED ________________________________
CONTRACTOR
DATE _____________________________________
ACCEPTED _______________________________________
PTT
DATE ____________________________________________
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 41/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 41 OF 49
REV: D2
FORM TR-6
INSTRUMENT TEST RECORD (Page 1)
Onshore Compressor Station 4 Project
FORM TR-6
INSTRUMENT BANK TEST AND
CALIBRATION RECORD
Sheet 1 of 2
TYPICAL FORM:
TITLE FROM INSTRUMENT INPUT/OUTPUT LIST
TAG NO. NAME (T)
(1)
(C)
(2)
INSTALLEDLOCATION
OK?
(3)
VERIFY (4) REMARKS
AND
OTHER
M I E W R S
NOTES: (1) Show date of bank test completed and accepted. Describe below test method used.
(2) Verify calibration of instrument and describe procedure followed. Include separately approved calibrationcertificate.
(3) Indicate compliance with drawings.
(4) M = mounting with all brackets and identifiers finished
I = installation complete ready for use
E = piping ends connected after piping test and cleaning
W = electrical wiring tested, passed and connections finished
R = recorders with printing media verified (inks, pens, paper, etc.); verify with data collected duringprecommissioning
S = remote receipt of data
ACCEPTED ________________________________
SUBCONTRACTOR
DATE _____________________________________
ACCEPTED _______________________________________
PTT
DATE ____________________________________________
ACCEPTED ________________________________
CONTRACTOR
DATE _____________________________________
ACCEPTED _______________________________________
PTT
DATE ____________________________________________
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 42/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 42 OF 49
REV: D2
FORM TR-6
INSTRUMENT TEST RECORD (Page 2)
Onshore Compressor Station 4 Project
FORM TR-6
INSTRUMENT BANK TEST AND
CALIBRATION RECORD
Sheet 2 of 2
SYSTEM DATE OF TEST
METHOD OF TEST
DESIGN CRITERIA TEST CRITERIA
LOOP NUMBERS INSTRUMENT NO. RANGE DRAWING NO.
EQUIPMENT INCLUDED IN TESTS
ITEM NO. DESCRIPTION ITEM NO. DESCRIPTION
NOTES:
ACCEPTED ________________________________
SUBCONTRACTOR
DATE _____________________________________
ACCEPTED _______________________________________
PTT
DATE ____________________________________________
ACCEPTED ________________________________
CONTRACTORDATE _____________________________________
ACCEPTED _______________________________________
PTTDATE ____________________________________________
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 43/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 43 OF 49
REV: D2
FORM ME-1
VESSELS
Onshore Compressor Station 4 Project
FORM ME-1
FIELD INSTALLATION CHECK LIST
VESSELS
EQUIPMENT NO. SERVICE
FABRICATOR P.O. NUMBER
TYPE CODE
MATERIAL
THICKNESS DATE RECEIVED
ITEM TO CHECK REMARKS/OK DATE TESTED
CONDITION WHEN RECEIVED?
ERECTION
ALIGNMENT, ELEVATION & PLUMBGROUNDING STRAP INSTALLED?
INTERNALS
INSULATION & FIREPROOFING
GROUTED
CLEANED
TESTED
LADDERS, PLATFORMS, DAVITS
CLOSED
REMARKS:
ACCEPTED ________________________________
SUBCONTRACTOR
DATE _____________________________________
ACCEPTED _______________________________________
PTT
DATE ____________________________________________
ACCEPTED ________________________________
CONTRACTORDATE _____________________________________
ACCEPTED _______________________________________
PTTDATE ____________________________________________
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 44/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 44 OF 49
REV: D2
FORM EE-1
CIRCUIT BREAKERS
Onshore Compressor Station 4 Project
FORM EE-1
FIELD INSTALLATION CHECK LIST
CIRCUIT BREAKERS
EQUIPMENT NO. SERVICE
MANUFACTURER INSTALLED BY
ITEM TO CHECK REMARKS/OK DATE TESTED
CONTACT PARTS CLEAN?
VISUALLY CLEAN? (NOT CORRODED)
NO MOISTURE PRESENT?
ENCLOSURE HAS BREATHER & DRAIN?
COVERS ON TIGHT?
SEALS FILLED?
INSTANTANEOUS TRIP SETTING: PHASE A
PHASE B
PHASE C
REMARKS:
ACCEPTED ________________________________
SUBCONTRACTOR
DATE _____________________________________
ACCEPTED _______________________________________
PTT
DATE ____________________________________________
ACCEPTED ________________________________
CONTRACTORDATE _____________________________________
ACCEPTED _______________________________________
PTTDATE ____________________________________________
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 45/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 45 OF 49
REV: D2
FORM EE-2
LIGHTING PANELS, INSULATION RESISTANCE, REMOTE TERMINAL DISPLAY (RTD)
Onshore Compressor Station 4 Project
FORM EE-2
ELECTRICAL TEST RECORD
TYPICAL FORM FOR: LIGHTING PANELS
INSULATION RESISTANCE
REMOTE TERMINAL DISPLAY (RTD)
CIRCUIT
NUMBER
WIRE
NUMBER
WIRE
SIZE
FROM TO MEGGER READING
(MEG OHM) @
DATE AMB.TEMP.
WEATHER
1 2 3
NOTE: @ MEGGER READINGS TO BE WITH WIRES COMPLETELY INSTALLED, CONDUIT FITTINGS CLOSED,SEALS FILLED, AND WITH THE CIRCUIT BREAKER OPEN
INSTALLED BY _________________________________________ DATE___________________________________
ACCEPTED ________________________________
SUBCONTRACTOR
DATE _____________________________________
ACCEPTED _______________________________________
PTT
DATE ____________________________________________
ACCEPTED ________________________________
CONTRACTOR
DATE _____________________________________
ACCEPTED _______________________________________
PTT
DATE ____________________________________________
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 46/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 46 OF 49
REV: D2
FORM EE-3
ALARM CIRCUIT OPERATION TEST
Onshore Compressor Station 4 Project
FORM EE-3
FIELD INSTALLATION
CHECK LIST
ALARM CIRCUIT OPERATION TEST
ALARM UNITNUMBER
EQUIPMENTLOCATION
TESTER'SINITIALS
DATE REMARKS
NOTE: EACH DEVICE SHOULD BE ACTUATED BY ACTUAL PRESSURE, TEMPERATURE, LEVEL, SPEED, FLOW,ETC. ALL ITEMS MUST BE SIGNED AS BEING IN SATISFACTORY CONDITION BEFORE OPERATION ISPERMITTED.
ACCEPTED ________________________________
SUBCONTRACTOR
DATE _____________________________________
ACCEPTED _______________________________________
PTT
DATE ____________________________________________
ACCEPTED ________________________________
CONTRACTORDATE _____________________________________
ACCEPTED _______________________________________
PTTDATE ____________________________________________
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 47/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 47 OF 49
REV: D2
FORM IE-1
CONTROLLERS
Onshore Compressor Station 4 Project
FORM IE-1
INSTRUMENT CHECK LIST
CONTROLLERS
INSTRUMENT NO.
MANUFACTURER
SERVICE
SERIAL NO.
ITEM TO CHECK DATE CHECKED
1. Blow air supply line at filter. Adjust air supply to specified pressure.
2. Align or synchronize controller so that when both process and set point are together near mid-range, the output air pressure does not drift. Observe for at least 2 minutes. Theproportional bank adjustment should be able to be moved through its full range (2 to 300%)without change in output pressure.
3. Check the tubing from output to valve or pneumatic set unit of another instrument. Thereshould be no restriction or leaks. Check stack for leaks - tighten bolts if necessary.(Bubble test should be used on all pneumatic controller systems.)
4. Controller is connected to proper valve and to proper connections.
5. Check manual control position. Put instrument on manual, adjust output to about 9 psig,move set point above and below process pen. No change in output air pressure shouldresult.
6. Check that controller output air action is correct for valve or instrument to which it isconnected. Control action is set "as process measurement increases" output air.(INCREASES for direct action and DECREASES for reverse action.)
7. Affix calibration sticker.
REMARKS:
ACCEPTED ________________________________
SUBCONTRACTOR
DATE _____________________________________
ACCEPTED _______________________________________
PTT
DATE ____________________________________________
ACCEPTED ________________________________
CONTRACTOR
DATE _____________________________________
ACCEPTED _______________________________________
PTT
DATE ____________________________________________
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 48/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 48 OF 49
REV: D2
FORM IE-2
DIRECT CONNECTED RECORDERS AND RECORDER CONTROLLERS
Onshore Compressor Station 4 Project
FORM IE-2
INSTRUMENT CHECK LIST
DIRECT CONNECTED RECORDERS AND RECORDER CONTROLLERS
INSTRUMENT NO.
MANUFACTURER
SERVICE
SERIAL NO.
ITEM TO CHECK DATE CHECKED
1. Remove all paper tags, strings, shipping stops, and install chart.
2. Check pen linkages for proper connection and freedom of movement.
3. Check calibration of recording pens at three points: 0, 50%, 100% of span; if not within
0.5% of span, recalibrate and report results on attached sheet.4. If instrument is a controller, synchronize and align controller. Blow air supply line and
adjust regulator to 20 psig before connecting controller to air supply.
5. Check output air tubing for leaks and connection to proper valve. Check that control actionis correct.
6. Fill pens with ink and see the ink flows freely.
7. Check that chart drive operates.
8. Check nameplates for correct identification.
9. Affix calibration sticker. Shut off chart drive. Leave instrument clean and neat, ready for operation.
REMARKS:
ACCEPTED ________________________________
SUBCONTRACTOR
DATE _____________________________________
ACCEPTED _______________________________________
PTT
DATE ____________________________________________
ACCEPTED ________________________________
CONTRACTORDATE _____________________________________
ACCEPTED _______________________________________
PTTDATE ____________________________________________
7/14/2019 Mechanical Completion
http://slidepdf.com/reader/full/mechanical-completion-56327ad8859c9 49/49
MECHANICAL
COMPLETION AND
COMMISSIONING
AND 30 DAY
CONTINUOUS OPERATION
PTT PUBLIC COMPANY LIMITED
ENGINEERING SPECIFICATION
SPC-0804.02-99.88
PAGE: 49 OF 49
REV: D2
FORM IE-3
ELECTRONIC CONTROLLERS, RECORDERS AND INDICATORS
ELECTRONIC CONTROLLERS, RECORDERS ANDINDICATORS
Onshore Compressor Station 4 Project
FORM IE-3
INSTRUMENT CHECK LIST
ELECTRONIC CONTROLLERS, RECORDERS AND INDICATORS
INSTRUMENT NO.
MANUFACTURER
SERVICE
SERIAL NO.
ITEM TO CHECK DATE CHECKED
1. Check continuity of wiring, location and value of dropping resistors, and verify service manual
feature (if provided) is disengaged.2. Turn on power supply and check voltage level and polarity.
3. Check and adjust input span and zero.
4. Set output signal limits. (High = 100%; Low = 0%)
5. Place controller in Automatic Mode and check alignment.
6. Transfer controller to the Manual Mode and check both up and down scale ramp rates.
7. Verify output signal action is correct for receiver.
"Output is to _______________ with input signal increase."
8. Check correct chart and scale ranges.
9. Install recorder ink capsules
10. Affix calibration sticker.
REMARKS:
ACCEPTED ________________________________
SUBCONTRACTOR
DATE _____________________________________
ACCEPTED _______________________________________
PTT
DATE ____________________________________________
ACCEPTED ACCEPTED