Transcript of Measuring Results In Pay For Performance Cleanups Brian Dougherty Florida Department of...
Measuring Results InPay For Performance Cleanups
Brian Dougherty
Florida Department of Environmental Protection
Monitoring Cleanup
PFP Milestones Pre-determined events when payments are
made Usually based on a subset of the data
Cleanup Target Levels Satisfy state requirements for all contaminants
and all media
PFP Milestones
Typical Breakdown 45% System Startup 10% Contaminants reduced by 50% 10% Contaminants reduced by 75% 10% Contaminants reduced by 90% 10% Reach CTLs (all media and contaminants) 15% Hold CTLs and Close Site
??
??
Components of Monitoring PFP Cleanup Progress
Establish the baseline. Determine the endpoint. Select key monitoring wells. Specify perimeter wells. Calculate milestones. Provide for split sampling. Provide for verification wells and borings. Maintain cleanup levels.
Establish The Baseline
This is point from which all progress will be measured. Should be very recent data or first task in PFP
agreement, not based on previous data.
Sample several wells to get good snapshot of the site. Specify analyses and analytes of interest.
Determine the Endpoint
Strict Resource Protection. High cost, long duration but clean site.
Site Specific Target Levels. Lower cost, shorter duration. Monitoring period may extend cleanup.
Endpoint OptionsStrict resource protection.
High Cost, Clean Site.
Site Specific Levels with monitoring. Long term monitoring leads to delayed payment.
• Payment delay causes cost to increase.
• Natural attenuation not a performance issue.
Site Specific levels with no monitoring. Low cost, short duration. No assurance if site rebounds
Key Monitoring Wells
Milestone measurement points.Carefully choose a small, representative
number of wells. Consider how you will measure progress.
Clean wells don’t add to information.Allow for changes if site conditions change.
Corner Gas
Station
Key Monitoring Wells
Perimeter Wells
Important to make sure plume doesn’t move away.
Keep to a minimum. More wells may provide more comfort, but at a
higher price.
Corner Gas
Station
Perimeter Wells
Milestone MeasurementAverage of Key Monitoring Wells.
Sensitive to large change in single well. Less indicative if key wells differ widely in
contaminant levels.
CoC Reduction in each well. Precise measure of progress. Harder to make progress in well with low
contaminant levels.
Mass Reduction.
MMMWWW---111 MMMWWW---222 AAAvvveeerrraaagggeeeBBBttt===000 333,,,222000000 555000000 111,,,888555000BBBttt===mmm 111,,,333000000 444000000 888555000RRReeeddduuuccctttiiiooonnn 111,,,999000000 111000000 111,,,000000000
PPPeeerrrccceeennnttt 555111%%% 222000%%% 555444%%%
PPPaaayyymmmeeennnttt AAAllllll WWWeeellllllsss --- NNNooo YYYeeesss
Milestone Measurement
Split Sampling
Important for verifying progress and payments.
Require prior notice of any milestone sampling event.
Tie payment terms to agreement between split samples.
Verification Wells & Borings
Important to confirm site is clean and not just that certain wells are clean.
Withhold final payment pending results.Allow contractor to split samples.
Maintaining Cleanup Levels
Minimum time period (State Requirement.) Typically 6 to 12 months
Provision for spikes and rebounds. Resample to confirm? Require corrective action? Does monitoring period reset?
Pay For Performance Monitoring
Goal: Pay for Environmental Results. Measure real reductions in contaminant levels. Monitor cleanup progress. Confirm results.
Provide Defined Goals for: PFP Payments. Meeting State Standards.