Measurement validation peak load reduction

19
Measurement & Validation of Peak Load Reduction Jeremy Carden, P.E. Lead Volt/VAR Engineer Duke Energy Dragan Popovic, Ph.D. Executive Vice President – Smart Grid IT Schneider Electric 1 February 4, 2015

Transcript of Measurement validation peak load reduction

Measurement & Validation of Peak Load Reduction

Jeremy Carden, P.E.

Lead Volt/VAR Engineer

Duke Energy

Dragan Popovic, Ph.D.

Executive Vice President – Smart Grid IT

Schneider Electric

1

February 4, 2015

Presentation Summary

Introduction to Duke’s DSDR system

Implementation Details

Duke’s M&V Approach

Benefits to Duke

Productizing the Solution

Conclusions

Duke Energy Progress – Distribution System Demand Reduction (DSDR)

Peak demand reduction through VVO

Deployed on entire distribution grid

Controllable load: 8,400 MW at peak

315 substations

1,160 feeders

1.5 million customers

34,000 square miles of service area

3

DSDR Implementation Details

Centralized Distribution Management System (DMS)

Integrated with several business applications (GIS, OMS, CIS, EMS, etc.)

Model-based with near real-time measurement input from the grid

7 Million GIS assets

400,000 SCADA points

90,000 SCADA measurements used as part of state estimation process

IP-based, two-way communications

800 substation voltage regulators

415 substation capacitor banks

Over 10,000 feeder devices

2,900 voltage regulators

2,900 capacitor banks

1,500 medium voltage sensors

3,000 low voltage sensors

850 reclosers

4

M&V Approach for DSDR

Post-activation analysis developed by Duke in 2013

Creates a baseline estimate by applying a polynomial regression to pre-activation load measurements

Primarily evaluated at the system level

Performed on data captured directly from DMS (before/during/after)

Data requirements

Frequent sample rate (typically 30 seconds)

3 – 6 hours of pre-activation data (winter vs. summer peak)

5 – 13 hours of total data (winter vs. summer peak)

5

M&V Approach for DSDR

Strengths

Relatively simple and practical (in comparison to others)

Created from actual load measurements

Statistically based

Results fall within in recommended confidence intervals

Favorable results when compared to other methods

Weaknesses

Relatively new

Not an actual load curve

Manual and can be time extensive

Unreasonable baselines for particular days

6

2014 Polar Vortex Example

7

2014 Summer Example

8

Results/Benefits

Validation of 316 MW of peak demand reduction

Avoided peak energy production cost estimates

DSDR business case deferred construction of two peaking CT generation units

Validation of 178 MW of peak spinning reserves (non-optimized voltage reduction)

Avoided energy production cost estimates

Validation of benefit from emergency voltage reduction activations

Example is 2014 Polar Vortex that helped DEP avoid shedding firm load

Development of hourly forecast models

Aids in planning and economical dispatch order of resources

9

Conclusions

Continual application and refinement is a necessity

Compare and contrast against other methods

Duke has utilized 3 different methods

Provides validation of results

Data, Data, Data

Need the tools and resources to collect, extract, and retain

Not only for benefit but also for system performance (identifying issues)

Visibility into the state of the grid during activation

Availability of resources (circuits and devices)

Communications status

Event/command logs

10

Productization – ADMS

●Software solution that integrates SCADA/DMS/OMS/DSM into one product – IT/OT

convergence

●Managing one network model for all operations based on the GIS

●One user interface familiar to all users within utility

●One data base and one security

●Functionality

● Network monitoring and management

● Improved management of alarming, tagging and history

● Validation of switching operations

● Basic calculations (load flow, state estimation) and network optimization applications

● Closed loop execution (VVO, FLISR)

● Distribution training simulator (DTS)

● Distribution network planning and design tool

Productization – ADMS

Realtime Bus (DNP3, ICCP)

Utility Management Systems

DMSSCADA OMS

Control

Center

Switching

and

Logging

EMS

Simulation Modeling

DEMAsset

Mngmt

Mobility

Feeder Automation Substation Automation Transmission

Enterprise Bus (IEC CIM)

ER

P

En

erg

y

Ma

rke

t

GIS

Ne

two

rk

Ma

na

ge

me

nt

AM

I

We

ath

er

MD

M

Be

hin

d

the M

ete

r

UMS Common Platform

Productization – VVO Closed loop

●Configuration

●Profiles – presets of VVO configuration managed by grid engineers

●Control & Monitoring

●24/7 operation control

●Automatic verification of command execution

●Overview of devices availability and commanding

●Modes: Loss Optimization, DSDR, Emergency, Storm

●Manual execution on request

●Off-line and real-time analysis of VVO decisions

Productization – VVO Closed Loop

DMS

Distribution Management System

1. Field data collecting

2. Real-time analysis

3. Decision making

4. Commands executing

Regulator Capacitor

SUB

DSCADATap Lines

Phase Additions

Sensors

AMI

Productization – VVO & DSDR

●VVO optimizes network state in all load conditions

● Normal load

●Reduces losses, provides VAR support

●Energy savings vs. energy charging

● Heavy load

●Peak load shaving

●Avoids high cost of peak spinning reserves

●Avoids load shedding in emergency situations

●Achieved benefits

● Loss Optimization – continuous VAR support for transmission needs

● DSDR – 250 MW demand reduction benefit – summer 2014

● Emergency – level 2 implements 250 MW reduction during cold wave – January 2014

Productization – VVO & DSDR

WP Losses

WP Benefits

Achieved

Productization – Network model data challenge

●Quality of calculated state depends on accuracy of GIS data

●Good quality of calculated state needed for VVO multi-objective decisions (LO,

DSDR)

●To include more VVO single objective approaches based on basic network model &

topology, SCADA measurements, smart meters

● Implementation of VVO in phases, on different parts of network

●Gaining benefit in earlier phases prior to data improvement

●To support automatic detection of parts of network ready for multi-objective VVO with

full benefit

Productization – Conclusions

● ADMS – comprehensive, real-time solution for network management and design

● Productization of ADMS with VVO Closed Loop – DSDR

● VVO – continuous process that optimizes power grid 24/7

● DSDR project – measurable and verified benefits of implementation of VVO

● Loss Optimization/VAR support

● DSDR – peak shaving

● Emergency

● New ideas for software solution from DSDR project

● Automatic support for different quality of network model data

● New ways of calculating and reporting benefit

18

19

Jeremy D. Carden, P.E.

[email protected]

Dragan Popovic, Ph.D.

[email protected]