MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

24

Transcript of MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

Page 1: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP
Page 2: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

MEASURE TWICE, CUT ONCE:BUILDING A BETTER PSAP

Page 3: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

SHERRI BUSH, ENPSENIOR CONSULTANT

FEDERAL ENGINEERING

Page 4: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

ERNIE OLDS, AIAVICE PRESIDENT

BECKER MORGAN GROUP

Page 5: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

SITE SELECTIONLET’S DISCUSS…

• Land Development Principles• PSAP Survivability• Future Proofing

Page 6: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

LAND DEVELOPMENTJust 5.8% of all land in the lower 48 states is developed, …but that area accounts for more than 50% of the total land value.

Page 7: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

LAND DEVELOPMENTPopulation growth is uneven and density varies greatly, meaning…

Presenter
Presentation Notes
As land management becomes a bigger issue in growth regions, the comm center planners need to think more like real estate investors and less like public servants.
Page 8: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

LAND DEVELOPMENT

Median land price was $7,700 in 1980 is now $58,800 – over 760% increase!!

Page 9: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

LAND DEVELOPMENTLand costs per acre –2009, varies greatly with location

Page 10: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

LAND DEVELOPMENT

0%

10%

20%

30%

40%

50%

60%

70%

80%

NH ME RI VT PA NY MA CT NJ WI IL IA KS MO OH NE IN MN MI SD ND WV OK AL MS KY LA AR TX TN GA FL NC SC VA DE MD AK NM AZ MT WY ID UT NV CO WA OR CA HI

Land Costs as a Share of Total

Costs of Construction by Region

Presenter
Presentation Notes
Land costs as a share of construction have increased from an avg of 22% in 1980 to 33% in 2016 Means that land went from 25% of cost of structure to 49% of cost of structure
Page 11: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

LAND DEVELOPMENTLand development cost components• Land value – proximity to

housing, work, shopping, schools, amenities, transportation

• Physiography – soils, vegetation, water

• Infrastructure – access, utilities

Page 12: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

LAND DEVELOPMENTHow much land do I need?• Start with 500sf to 1000sf per position• Add a 25m (82ft) standoff• Parking can be placed outside that point• Allow space to manage storm water• Give the generator/utilities access• Connect parking to your roadway• Buffer for privacy and security as needed• Fence the property

350 FT x 300 FT = 105,000 SF or 2.4 acres

Page 13: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

PSAP SURVIVABILITYSTRUCTURAL ATTRIBUTES• Natural Hazards…

Page 14: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

PSAP SURVIVABILITYSTRUCTURAL ATTRIBUTES• Other Threats…

Page 15: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

PSAP SURVIVABILITYINFRASTRUCTURE• Power• Data• HVAC• Sewer / Water• Food / Rest

Page 16: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

PSAP SURVIVABILITYACCESSIBILITY• Single vs Multi-

Point• Rural vs Urban

Page 17: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

PSAP SURVIVABILITYSECURITY• Perimeter• Internal

Page 18: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

PSAP SURVIVABILITYINTERNAL CRISIS• Loss of power, data,

a fire…

Page 19: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

PSAP SURVIVABILITYEXTERNAL CRISIS• When YOU are in the storm…

Page 20: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

FUTURE PROOFINGChange in land values,

Change in population,Change in technology

Page 21: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

FUTURE PROOFINGPlanning for the Future• Building for the Future

Page 22: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

SITE SELECTIONSUMMARY

1. Understand that land has value2. Improving land for a PSAP is expensive3. Your decisions can save or cost you money

for years4. Done correctly you will be set for the future!

Page 23: MEASURE TWICE, CUT ONCE: BUILDING A BETTER PSAP

SITE SELECTIONQuestions & Answers

Sherri Bush – Federal Engineering Ernie Olds – Becker Morgan [email protected] [email protected]