Measure M2 Performance Assessment March 31, 2011

description

Measure M2 Performance Assessment. March 31, 2011. The End of One Era – M1 Sunsets. Measure M1 - approved November 1990 Collection of tax sunsets March 31, 2011 More than $4 Billion in improvements Widened almost all freeways, improved many streets and roads, and brought - PowerPoint PPT Presentation

Transcript of Measure M2 Performance Assessment

Page 1: Measure M2   Performance Assessment

Measure M2 Performance Assessment

March 31, 2011

Page 2: Measure M2   Performance Assessment

2

The End of One Era – M1 Sunsets

Measure M1 - approved November 1990 Collection of tax sunsets March 31, 2011 More than $4 Billion in improvements Widened almost all freeways,

improved many streets and roads, and brought Metrolink to OC

Page 3: Measure M2   Performance Assessment

3

The Beginning of a New Era – M2

Built on success of M1 30-year plan approved November 2006 Collection begins April 1, 2011 Revenue forecast - $ 15 billion Five-year Action Plan jump-started many

projects Plan of Finance to advance projects

Page 4: Measure M2   Performance Assessment

4

M2 – Action Plan Progress Report

Freeways SR-91, SR-57 and I-5

Streets & Signals Call For Projects

Transit Quiet Zones, ARTIC and Community Circulators

Environmental Property Acquisition; Water Quality Grants

Page 5: Measure M2   Performance Assessment

5

2006 - 09 Performance Assessment

Included in M2 Ordinance No. 3 as a safeguard Must be conducted every three years Evaluates:

efficiency , effectiveness, economy, & program results of OCTA in satisfying requirements

OCBC/Oftelie Company conducted first assessment covering 2006 to 2009 Completed in December 2010

Page 6: Measure M2   Performance Assessment

6

Assessment Parameters

Progress of OCTA against nine objectives Changed economic conditions since 2007

Action Plan adoption Management & oversight OCTA’s ability to deliver

promises made in Action Plan through 2011

Page 7: Measure M2   Performance Assessment

7

Key Findings

OCTA’s aggressive early steps have been successful

Substantial progress made in achieving the Action Plan’s 9 objectives

Navigated constantly shifting economy

18 comments on appropriateness of actions or recommendations

Page 8: Measure M2   Performance Assessment

8

Comments

Financing Consider other financing sources if appropriate Focus of necessary size of borrowing

Transparency Regular reporting Measure M web portal

Project Controls Dashboard

Page 9: Measure M2   Performance Assessment

9

Comments

Delivery of major projects I-405, Orangethorpe Grade Separations

Improved Internal Controls M Program Management Office Project Cost accounting

Timing of future Triennial Performance Assessments

Page 10: Measure M2   Performance Assessment

10

Next Steps

Incorporating comments into M2 implementation

Tracking progress with OCTA’s Transportation 2020 Committee

Releasing RFP for 2009-12 assessment by spring 2012