    Manufacturers Data Report (MDR) - Plant Projects

    EP-08-030-37

    Version No. 5.0 Page 1 of 13

    Document last modified: 15 July 2009. PDF Created: 22 January 2010.

    This is a Controlled Document that complies with CSBP Limited formatting and Quality

    Control guidelines. Please check that this is the latest available version before use.

    Title: MANUFACTURERS DATA REPORT (MDR) - PLANT

    PROJECTS

    Number: EP-08-030-37

    Owner: David Zacher

    Authoriser: David Zacher

    Version Details: Owner/Authoriser changed - was Phil Talbot.

    No changes to document.

    TABLE OF CONTENTS

    1. INTRODUCTION .................................................... ........................................................... ...... 2

    2. PURPOSE ....................................................... ........................................................... ................ 2

    3. RELATED STANDARDS AND GUIDES .............................................................................. 2

    4. MDR PREPARATION AND SUBMISSION ......................................................................... 3

    5. MDR FORMAT ....................................................... ........................................................... ...... 4

    6. MDR CONTENTS ................................................... ........................................................... ...... 4

    6.1 SCOPE OF WORK ........................................................ ....................................................... 56.2 SECTION 1 - DESIGN ............................................................ ............................................. 56.3 SECTION 2 - OFF SITE FABRICATION............................................................................ 56.4 SECTION 3 - SITE CONSTRUCTION AND INSTALLATION ........................................ 66.5 SECTION 4 - COMMISSIONING .................................................... ................................... 76.6 SECTION 5 - EQUIPMENT TECHNICAL DATA ....................................................... ...... 76.7 SECTION 6 - DRAWINGS ..................................................... ............................................. 8

    6.8 SECTION 7 - STATUTORY APPROVALS, REGISTRATION AND CERTIFICATES... 8

    APPENDIX 1 - MDR CONTENTS CHECK LIST........................................................... ................ 9

    SCOPE OF WORK........................................................... ........................................................... ...... 9SECTION 1 - DESIGN.... ........................................................... ....................................................... 9SECTION 2 - OFF SITE FABRICATION..................................................... ................................... 9SECTION 3 - ON SITE CONSTRUCTION AND INSTALLATION ............................................ 10SECTION 4 - COMMISSIONING....................................................... ........................................... 11SECTION 5 - EQUIPMENT TECHNICAL DATA.......................................................... .............. 11SECTION 6 - DRAWINGS........................................................ ..................................................... 12SECTION 7 - STATUTORY APPROVALS, REGISTRATION & CERTIFICATES ................... 12

  • 8/11/2019 MDR Manufacturers Data Report Info

    2/13

    Manufacturers Data Report (MDR) - Plant Projects

    EP-08-030-37

    Version No. 5.0 Page 2 of 13

    Document last modified: 15 July 2009. PDF Created: 22 January 2010.

    1.

    INTRODUCTION

    The Manufacturers Data Report (MDR) is the compilation of all the technical details and recordsof activities performed by a contractor as part of an engineering construction or modification

    project. This may include any of the following activities.

    a. Design

    b. Supply of materials, proprietary plant and equipment

    c. Off site fabrication, surface treatment, assembly

    d. On site construction, assembly, erection and installation of plant and equipment

    e. Inspection, testing, and commissioning.

    The MDR is provided by a Contractor to the Superintendent on completion of the Work under theContract, usually as a precondition to the issue of the Certificate of Practical Completion.

    The primary purpose of the MDR is to provide CSBP with the information required to safely

    operate the plant and equipment provided under the contract and to service and maintain the

    equipment to achieve reliable operation over its expected life.

    The MDR also serves as a historical record and can be useful in helping to identify the cause of

    problems with quality, performance or reliability of the plant and equipment later in its life.

    2.

    PURPOSE

    The purpose of this procedure is to define the requirements for preparation and submission of a

    MDR, and to provide a contents checklist for typical engineering projects.

    This document is focussed primarily to mechanical engineering contracts which include design,

    supply of equipment, off site fabrication, site installation and commissioning of mechanical

    equipment and piping. It is also relevant to civil, structural, electrical and instrumentation works,

    and should be used as a guide to format the MDR for these works.

    Note: It is usual for special equipment items such as pumps, control valves, and relief valves to

    be purchased by CSBP's Project Responsible Officer and free-issued to the contractor for

    installation. The technical data for these free-issued items will be assembled by the CSBP

    Responsible Officer and passed on to Reliability Support and to the CSBP Customer in

    the form of an MDR as described in this document.

    3.

    RELATED STANDARDS AND GUIDES

    The following CSBP documents shall form the basis of MDR requirements.

    a. Technical Data Requirements for Plant and Equipment (GM-05-043-01)

    b. Equipment Numbering System (ES-14-101-06)

  • 8/11/2019 MDR Manufacturers Data Report Info

    3/13

    Manufacturers Data Report (MDR) - Plant Projects

    EP-08-030-37

    Version No. 5.0 Page 3 of 13

    Document last modified: 15 July 2009. PDF Created: 22 January 2010.

    c. Technical Data Sheets - Mechanical, Electrical and Instrumentation (ES-14-101-12).(These

    sheets should be provided to the Contractor early in the project to ensure standardisation of

    presentation of information)

    d.

    Fabrication and Installation of Piping (ES-14-602-01)

    e. Inspection and Testing of Piping Systems (ES-14-602-02)

    f. CSBP Stage 1 Commissioning Inspection Report and Stage 2 Commissioning Test Report

    forms.

    Note: These forms are available in Dom.doc in Business Support - Engineering -

    Engineering Forms - Commissioning Reports

    g. Repairs and Minor Alterations to Existing Pressure Equipment, Piping and Tanks(DP-05-

    095-06)

    h.

    Major Alterations and Replacement to Existing Pressure Equipment, Piping and Tanks

    (DP-05-095-08)

    i. Testing and Commissioning of Electrical and Instrumentation Installations (ES-14-902-02).

    4.

    MDR PREPARATION AND SUBMISSION

    The Contractor shall compile an MDR for the contract work in the format detailed in 5. below. For

    large complex projects, the MDR may be submitted in several parts, for example, MDR for off-site

    manufacture and supplied equipment, MDR for on-site installation, erection and

    pre-commissioning; MDR for commissioning;

    For larger, multi discipline projects, separate MDRs may be produced for each discipline eg MDR

    for Civil Works, MDR for equipment supply/fabrication/assembly, MDR for mechanical

    installation, MDR for Electrical Installation.

    The Contractor and the Superintendent will review the check list provided in Appendix 1 at an

    early stage of the contract to agree the content of the MDR.

    The MDR shall be progressively compiled during the course of the work and kept up to date as the

    work progresses so that delivery of the MDR is not delayed at the completion of the work.

    Presentation of the required number of copies of a full and comprehensive MDR at the conclusion

    of construction is a contractual requirement under all CSBP engineering contracts and, unless

    specifically stated otherwise in the contract, is a precondition for the issue of the Certificate ofPractical Completion to the Contractor.

    The MDR shall be presented to the Superintendent for review upon request to ensure compliance to

    the Contract requirements and to ensure that progressive compilation is being maintained.

    Initially, a single draft copy shall be submitted for review and approval by the Superintendent.

    MDRs covering fabrication, welding, heat treatment and testing of pressure piping or pressure

    equipment shall be submitted to and approved by the CSBP Senior Inspector before final

    acceptance by the Superintendent.

  • 8/11/2019 MDR Manufacturers Data Report Info

    4/13

    Manufacturers Data Report (MDR) - Plant Projects

    EP-08-030-37

    Version No. 5.0 Page 4 of 13

    Document last modified: 15 July 2009. PDF Created: 22 January 2010.

    On approval of the draft copy of the MDR, two final copies of the MDR shall be prepared and

    submitted by the contractor. An additional copy of Sections 5, 6 and 7, as described in 6.6, 6.7and

    6.8shall also be supplied by the Contractor.

    The final copies of the MDR shall be distributed by the CSBP Responsible Officer as follows.

    - One complete copy to CSBP Customer

    - One complete copy retained in the CSBP Project File

    - Copy of Sections 5, 6 and 7 to Reliability Support

    5. MDR FORMAT

    The MDR shall be prepared by the Contractor in one or more hard cover, A4 size, loose leaf, lever

    arch binders, with file separators clearly segregating each section. The MDR shall have a detailed

    table of contents at the front of each of the binders.

    The outside front cover and spine of the binders shall be identified with:

    The name of the Project

    Manufacturer's Data Report for Manufacture (or installation, etc, as applicable)

    The description of the subject work

    The CSBP Contract or Purchase Order number

    All documents for inclusion in MDR shall be written in the English language, in SI units, shall be

    complete and shall be originals or clearly legible copies. Documents and drawings larger than A4

    size, which cannot be reduced clearly, shall be folded into A4 plastic pockets.

    MDRs shall be divided into the sections described below, as appropriate, and each section shall be

    divided by tabbed separator sheets. All of the separator sheet tabs shall carry the applicable section

    number and the title of the section. If a particular section is not applicable, the section may be

    omitted.

    6. MDR CONTENTS

    The MDR shall be divided into the sections described below, as appropriate to the scope of the

    contract.

    The check list attached as Appendix 1 should be reviewed to check that all relevant documents for

    each aspect of the work have been included in the relevant section of the MDR as detailed below

    and in Appendix 1.

    If not already covered in this procedure, MDRs shall also contain those documents identified in the

    approved Inspection and Test Plan / Inspection and Test Program for the subject work as well as

    those identified in Contract/Order and in the applicable codes, Standards and legislation.

  • 8/11/2019 MDR Manufacturers Data Report Info

    5/13

    Manufacturers Data Report (MDR) - Plant Projects

    EP-08-030-37

    Version No. 5.0 Page 5 of 13

    Document last modified: 15 July 2009. PDF Created: 22 January 2010.

    6.1 SCOPE OF WORK

    Insert as the front of MDR a brief description of the contract Scope of Work applicable to the

    MDR.

    6.2 SECTION 1 - DESIGN

    This section shall include all design calculations required to be submitted under the contract

    including design criteria, assumptions made and any references for design method selected.

    Calculations shall be sufficiently detailed to enable independent verification. Copies of all technical

    queries and their replies shall be included.

    Details of any authorised deviations from the contract specifications and the reasons for the

    deviations shall be included.

    Lists of all equipment, valves, pipelines and vessels provided by the contractor shall be includedfor reference.

    6.3 SECTION 2 - OFF SITE FABRICATION

    This section shall contain records of all activities associated with off site fabrication and assembly

    of materials and equipment to be incorporated into the works. The extent of the information to be

    included in the MDR will depend on the requirements of the contract.

    6.3.1 Material Certificates and Test Reports

    Where material traceability is required under the contract, this section shall contain an indexed list

    identifying material certificates and material test reports referenced to the locations of the materialsused by their part, piece or item number and the applicable drawing(s). The material certificates

    and traceability shall include welding consumables.

    A copy of the certificates and reports shall be included in this section of the MDR indicating the

    certificate or report number, Heat, lot, plate number, etc, and the name of Mill.

    For clarity, the section shall also contain a drawing of the equipment or piping marked up to show

    the certificate number and heat number for the materials used at each location.

    6.3.2 Weld Records

    Details of all welding procedures and qualifications relevant to the subject work, includingevidence of CSBP's approval, shall be included in this section.

    If more than one welder is used, then traceability sheets and / or marked up drawings, sketches or

    maps shall be included to identify the welder responsible for each weld, and what WPS was used.

    6.3.3 Non Destructive Examination (NDE)

    This section shall include a list of all NDE carried out on the subject works. The listing shall

    include for each test location, the type of NDE, the NDE procedure, the NDE report number and

    the result of the examination. The listing may be incorporated into the welding control and record

    sheets. The section shall include a marked up drawing, sketch or map to identify the NDE report

  • 8/11/2019 MDR Manufacturers Data Report Info

    6/13

    Manufacturers Data Report (MDR) - Plant Projects

    EP-08-030-37

    Version No. 5.0 Page 6 of 13

    Document last modified: 15 July 2009. PDF Created: 22 January 2010.

    numbers relevant to each test location together with a copy of all NDE certificates/reports in the

    order in which they are included in the above list.

    The section shall also include a list of all non-destructive testing personnel employed on the subjectwork and evidence of their qualifications.

    6.3.4 Heat Treatment

    If applicable, certificates and properly scaled furnace charts for all heat treatment performed shall

    be included. Charts shall include the complete heat treatment cycle including heating, soak period

    and cooling.

    The charts shall clearly show the calibrated temperature and time scales and provide a reference to

    the heat treatment procedure and to the specific item or weld that was heat treated.

    The charts shall be dated and signed by the person responsible for verifying the correctness of theheating cycle.

    Traceability sheets and / or marked up drawings, sketches or maps shall be included to identify the

    heat treatment charts relevant to each weld or item being heat treated.

    6.3.5 Hydrostatic Testing

    Where required by the contract, records of hydrostatic testing performed offsite, along with

    supporting documentation such as NATA test certificates for test gauges, shall be included in this

    section of the MDR. Stage 1 Commissioning inspection report forms should be completed prior to

    the commencement of such tests, and be included in this section of the MDR, whether included in

    the ITP or not.

    6.3.6 Combination of Traceability Information

    The traceability sheets and drawings, sketches or maps for material certificates, welder

    identification, NDT and heat treatment may be combined partially, or fully, in a format to be

    approved by the Superintendent.

    6.4 SECTION 3 - SITE CONSTRUCTION AND INSTALLATION

    This section shall contain records of all activities associated with site fabrication, assembly,

    installation and construction and Stage 1 commissioning of materials, plant and equipment

    incorporated into the works.

    Material traceability information, weld records, non destructive examination records, heat

    treatments records, etc, as detailed in 6.2 above and in Appendix 1, when applicable to the work

    done on site, shall be included in this section of the MDR.

    This section shall contain a copy of the approved ITP with evidence that the Contractor has

    complied with the ITP. Evidence of compliance shall be by signature of the persons responsible for

    verifying satisfactory performance of the identified inspections and tests in the relevant spaces

    provided in the ITP. Where applicable, this shall include the Superintendent and the Owner's

    inspector.

  • 8/11/2019 MDR Manufacturers Data Report Info

    7/13

    Manufacturers Data Report (MDR) - Plant Projects

    EP-08-030-37

    Version No. 5.0 Page 7 of 13

    Document last modified: 15 July 2009. PDF Created: 22 January 2010.

    This section shall contain all those inspection and test records required by the ITP except for those

    that are identified for inclusion in other sections of the MDR.

    Where a standard CSBP Stage 1 Commissioning Inspection Report form is available for aparticular item of equipment, the form shall be completed and included in this section of the MDR,

    whether indicated in the ITP or not.

    The records shall be filed in this section in the order in which they are identified on the ITP, or in

    some other logical order, clearly referenced to the particular inspection or test stage identified on

    the ITP.

    6.5 SECTION 4 - COMMISSIONING

    This section shall contain records of all activities associated with Stage 2 and Stage 3

    commissioning.

    Where a standard CSBP Stage 2 Commissioning Test Report form is available for a particular item

    of equipment, the form shall be completed and included in this section of the MDR, whether

    indicated in the ITP or not.

    The records shall be filed in this section of the MDR in the order in which they are identified on the

    ITP, or in some other logical order, clearly referenced to the particular inspection or test stage

    identified on the ITP.

    6.6 SECTION 5 - EQUIPMENT TECHNICAL DATA

    This section shall contain technical information for all items of equipment supplied under the

    contract to allow ongoing operation, servicing and maintenance to be carried out. Information shallbe included in sufficient detail to enable CSBP to identify and purchase individual parts of

    equipment supplied and to enable those parts to be installed.

    A drawing shall be supplied for each item of equipment, showing a complete breakdown of all

    parts. Each drawing shall be accompanied by a complete parts list, indicating the quantity of each

    part required and the manufacturer's part number. Any specific overhaul / repair kit must also have

    a part number and identify the items comprising the kit.

    Dimensional details of all non-proprietary items shall be provided by the Contractor, to allow

    CSBP to source replacements at a competitive price e.g. bearings, gaskets, oil-seals, packing

    materials, etc.

    Detailed drawings for all purpose-built items, unavailable off-the-shelf, shall be included in this

    section, specifying materials and all dimensions required to manufacture a replacement. E.g.

    gaskets for heat exchanger end covers, non-standard pipework components, etc.

    Nozzle drawings, showing flange details, should also be included in this section, to assist in linking

    gaskets to items of equipment.

    Completed Data Sheets on the applicable CSBP standard form shall be provided for each

    equipment item. Technical data in this section should address service conditions and operating

    parameters, e.g. temperatures, pressures, etc.

  • 8/11/2019 MDR Manufacturers Data Report Info

    8/13

    Manufacturers Data Report (MDR) - Plant Projects

    EP-08-030-37

    Version No. 5.0 Page 8 of 13

    Document last modified: 15 July 2009. PDF Created: 22 January 2010.

    This information should contain sufficient detail to enable purchase of a replacement item able to

    perform the same function even if from another manufacturer. Name plate details for tanks, vessels,

    heat exchangers, etc., should also be included in this section of the MDR.

    Commissioning, Operating and Maintenance Manuals shall be included for all items provided

    under the contract in sufficient detail to enable CSBP to safely and reliably commission, start up,

    operate, service, maintain and overhaul the items supplied by the contractor.

    6.7 SECTION 6 - DRAWINGS

    6.7.1 Drawing List

    A complete list of all drawings including revision numbers produced by the Contractor for

    construction purposes, and which have been passed to CSBPs drawing office for electronic

    storage, shall be included in this section of the MDR.

    6.7.2 Vendor Drawings

    Paper copies of Vendor drawings including assembly and sectional drawings showing details of

    overall width, height, base-to-shaft centres, base plate holes, etc, shall be provided with the MDR.

    6.7.3 As-built Drawings

    As-built drawings shall be provided with the MDR. As-built details shall be marked up with a red

    pen onto a paper copy of the contract drawing to clearly show changes that were made during

    manufacture or construction and to record any particular details not included in the original

    drawings. In particular, the exact location of buried pipework or buried other services shall be

    accurately recorded.

    6.8

    SECTION 7 - STATUTORY APPROVALS, REGISTRATION AND

    CERTIFICATES

    This section shall list the various parts, equipment, materials and activities which require statutory

    approval and registration. Evidence of the required approval and compliance for each item shall be

    included in this Section.

  • 8/11/2019 MDR Manufacturers Data Report Info

    9/13

    Manufacturers Data Report (MDR) - Plant Projects

    EP-08-030-37

    Version No. 5.0 Page 9 of 13

    Document last modified: 15 July 2009. PDF Created: 22 January 2010.

    APPENDIX 1 - MDR CONTENTS CHECK LIST

    SCOPE OF WORKInsert a brief description of the contract Scope of Work applicable to the MDR at the front

    of MDR.

    SECTION 1 - DESIGN

    a. Design calculations

    b. Technical Queries

    c. Authorised Deviations

    d. Equipment lists

    e. Valve List

    f. Pipeline lists

    g. Pressure Vessel List

    h. Instrument List

    i. Motor List

    SECTION 2 - OFF SITE FABRICATION

    Fabrication and Welding of Pressure Vessels, Pipe Spools and Steelwork

    a. Signed off ITPs for each stage of the work

    b. Material Certificates, including all items directly welded to piping or pressure

    vessels

    c. Material and consumable map for traceability

    d. Consumables Certificates

    e. Weld Procedure Records (WPR)

    f. Weld Procedure Qualification Records (WPQR)

    g. Welder Qualification Records (WQR)

    h. Material Heat Traceability Records

    i. Inspection and Non Destructive Testing (NDT) Records

    j.

    Weld maps identifying NDT records against location

    k. Weld maps identifying welders and WPS used for each weld

    l. Hardness Test Records (to be included in NDT traceability)

    m. Heat Treatment Records

    n. Map for identifying heat treatment records against welds and/or location

    o. Pressure Test Records

    p. Pressure Test instrument calibration records (NATA)

    q. Stage 1 Pre-commissioning Inspection Reports completed prior to pressure tests

  • 8/11/2019 MDR Manufacturers Data Report Info

    10/13

    Manufacturers Data Report (MDR) - Plant Projects

    EP-08-030-37

    Version No. 5.0 Page 10 of 13

    Document last modified: 15 July 2009. PDF Created: 22 January 2010.

    r. Non-conformances, concessions and technical queries

    Valves

    a.

    Test Certificatesb. Material Certificates

    Surface Treatment and Protective Coatings

    a. Surface preparation Records

    b. Coating application and thickness records

    SECTION 3 - ON SITE CONSTRUCTION AND INSTALLATION

    Inspection and Test Plans (ITPs)

    a. Signed off ITPs for each stage of the work

    Civil Worksa. Earthworks

    1. Survey and set out records

    2. Backfill Checklist

    3. Compaction Checklist

    b. Concrete Works

    1. Formwork Inspection and Pre-Pour Records

    2. Concrete Placing Records

    3.

    Concrete Delivery Dockets4. Reinforcing Schedule

    5. Coating record sheets

    c. Concrete Testing

    1. Compressive Strength Testing

    Structural Steel Erection

    a. Installation record sheets

    Mechanical Equipment Installation

    a.

    Pre-commissioning Inspection Reportsb. Pump alignment records

    Piping

    a. Approved repair procedure as per DP-05-095-06 for welded tie-ins to existing

    piping and equipment

    b. Welding Procedure Specifications / WPQR

    c. Welder Qualifications Records

    d. Material Heat Number Index

    e. Material Certificates

  • 8/11/2019 MDR Manufacturers Data Report Info

    11/13

    Manufacturers Data Report (MDR) - Plant Projects

    EP-08-030-37

    Version No. 5.0 Page 11 of 13

    Document last modified: 15 July 2009. PDF Created: 22 January 2010.

    f. Material and consumable map for traceability

    g. Weld Maps for welder, WPS and NDT traceability

    h.

    Weld & Material Heat Number Traceability Recordsi. Non Destructive Testing (NDT) Records

    j. Post Weld Heat Treatment (PWHT) Records

    k. PWHT traceability maps

    l. Hardness Test Records (include in NDT traceability)

    m. Pressure Testing Records and test packs, including NATA calibration certificates

    for test instruments

    n. Completed Punch-lists

    o. Non-conformances, concessions and technical queries

    p. Stage 1 Pre-commissioning Inspection Reports

    Insulation / Cladding Records

    Refractory Inspection and Test Records

    Electrical and Instrument installation records

    a. Commissioning Test Reports as detailed in CSBP Engineering Standard ES-14-902-

    02 Testing and Commissioning of Electrical and Instrumentation Installations

    b. Cable Test Result Sheets

    c. Instrument Calibration Record Sheets

    d.

    Loop Check Sheets

    e. Hazardous Area Check Sheets

    f. Trip Settings Record Sheets

    Miscellaneous Records

    a. Test equipment certificates

    SECTION 4 - COMMISSIONING

    a. Approved commissioning procedure

    b. Stage 2 Dry Commissioning Test Reports

    c.

    Stage 3 Wet Commissioning records

    d. Completed punchlists resulting from b and c.

    SECTION 5 - EQUIPMENT TECHNICAL DATA

    Vendor details

    a. Equipment number and description

    b. Vendor and Order number

    c. Vendor contact details (address, telephone number, fax number, email address,

    contact name)

  • 8/11/2019 MDR Manufacturers Data Report Info

    12/13

    Manufacturers Data Report (MDR) - Plant Projects

    EP-08-030-37

    Version No. 5.0 Page 12 of 13

    Document last modified: 15 July 2009. PDF Created: 22 January 2010.

    Technical Data

    a. Technical Data Sheets

    b.

    Name Plate Detailsc. Test certificates

    d. Calibration certificates

    Operating and Maintenance Information

    a. General Information

    b. Safety Precautions

    c. Assembly and Installation Instructions

    d. Start-up Procedures

    e.

    Maintenance and inspection requirements, intervals, checks, etcf. Lubrication schedules including grease and oil types, quantities

    g. Repair / Overhaul Procedures

    h. Assembly Torque settings

    i. Storage instructions

    j. Test Certificates

    k. Recommended Spare Parts Lists

    l. Calibration procedures

    SECTION 6 - DRAWINGSa. Drawing List including revision number

    b. General arrangement drawings

    c. Layout drawings

    d. Marking plans

    e. Vendor drawings

    f. Assembly drawings

    g. As-Built Drawings

    1.

    Piping isometrics and details2. Buried pipe and services

    3. Red pen markups to contract drawings

    SECTION 7 - STATUTORY APPROVALS, REGISTRATION & CERTIFICATES

    a. Pressure Vessel Design Registration details

    b. Lifting equipment certification

    c. Development approval and Building license

    d. Gas and electrical installation certificates

  • 8/11/2019 MDR Manufacturers Data Report Info

    13/13

    Manufacturers Data Report (MDR) - Plant Projects

    EP-08-030-37

    Version No. 5.0 Page 13 of 13

    e. Electrical equipment hazardous area rating certification

    f. Test certificates for pressure safety valves and bursting disks