MC meeting Bucuresti 19-20 th of May, 2010
description
Transcript of MC meeting Bucuresti 19-20 th of May, 2010
![Page 1: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/1.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Advances in HOmogenisation MEthods for climate series
an integrated approach
COST ES0601 “HOME”
MC meeting Bucuresti
19-20th of May, 2010
![Page 2: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/2.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Agenda 19th morning
• Welcome of participants (09H30-10H00)• Adoption of minutes of last meeting• Adoption of Agenda• Presentation of new delegates• Matters arising• News from COST Office (Chandrasa)• Report from Grant Holder (Berta)• Status of Action
![Page 3: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/3.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Agenda 19th, afternoon
• Progress report of Wgs (14H00)– Bibliography (Enric)– Benchmark (Victor)– Practical recommandations (Ingeborg)– Daily data (Petr, Olivier)
![Page 4: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/4.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Agenda 20th Morning
• 09H00– Preparation of Annual Progress Conference
(Activity report)– Action planning– Action budget planning– Meeting plannings
![Page 5: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/5.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
20th Afternoon• 14H00
– planning of additional meetings and STSMs for period june 2010 – September 2010
– organization of R summer school– Preparation of year 4 workplan and budget
plan; next MC…– Constitution of WG5 : WG leader, volunteers– Vote for extension of the Action to additional 6
months (Training)– Publications…– AOB– Closing
![Page 6: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/6.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
MC opened
• Adoption of Agenda Y/N
• Adoption of minutes of last MCY/N
• Welcome to new delegates
• Matters arising Y/N
![Page 7: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/7.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Report from COST Office
• COST Office news
![Page 8: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/8.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Report from GH
• Status of budget
![Page 9: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/9.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Main achievements this year
• Bibliography
• Intercomparison simulations
• Benchmark experiment - and Mallorca meeting
• Practical recommandations
• Advances in Dailies
![Page 10: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/10.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
To be improved
• Unification of procedures
– Blocking point for software implementation
![Page 11: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/11.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
To be discussed
• WG 5 constitution (software)
• Additional 6 months (training)
![Page 12: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/12.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Progress Report
• WG1: Bibliography
– Enric, your turn…
• WG2/3 Benchmark results
– Victor….
![Page 13: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/13.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Progress Report
• WG2/3 Practical recommandations
– Inge…
![Page 14: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/14.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
News from WG3 (correction)
• From bibliography• Multivariate
–MASH–Caussinus Mestre–Mixed Linear Models
• Unification of the 3 models (Tamas, Anders, Olivier)
• March meeting did not occur (agenda) - discussions
• To be organized asap <> software
![Page 15: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/15.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
WG3 : UBRIS2 experiment
• Urban effect and homogenisation
Mestre, Böhm, Auer, Stepanek, – C&M correction model, modified to take into account
additional non-climatic trends, adapted to monthly scale– Tested on a set of 13 Viennese series, Bucuresti and
Praha series – Allowed testing significance of urban trends and
correction
![Page 16: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/16.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
WG4 : daily values
• Petr : your turn...
![Page 17: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/17.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Experiment on simulated data
• Great help from Christine Gruber STSM• Couple of series simulated according to a
bivariate AR(1) process• Allows control precisely temporal and
spatial correlations, as well as variance• Vincent, HOM and SPLIDHOM for various
correlations
![Page 18: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/18.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Added inhomogeneities
![Page 19: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/19.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Corrected vs Raw
![Page 20: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/20.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Corrected vs Raw
![Page 21: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/21.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
ACTION PLANNING
• Elaborated with care• As detailed as possible
![Page 22: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/22.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
ACTION PLANNING
• PRIORITIES
UNIFICATION OF PROCEDURES
FINAL BENCHMARK ANALYSIS
HOMOGENISATION OF BENCHMARK DAILY DATASET
CONSTITUTION OF WG5
![Page 23: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/23.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Suggestions for remaining budget
• Depending on actual MC expenses
• On a basis of 25k€ => 35k€ left– R summer school (already voted) ~12k€– 5 STSMs (1xUBRIS (?), 4x dailies~10k€– 1xEM (Paris, July, 4 persons) ~4k€– 1xEM (Zurich, september) ~2k€– 1xWG dedicated to Benchmark ~10k€
• VOTES
![Page 24: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/24.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Additionnal Votes…
• Preparation of Second Installment of the Grant (MC approval)
• Preparation of next year Grant (MC approval)
![Page 25: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/25.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
WG5
• Volunteer….
![Page 26: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/26.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
FUTURE
• Date, place next MC• Date, place final event• Vote in favor of 6 months extension
Training purposes
![Page 27: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/27.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Votes
• Remaining budget– STSMs– EMs– WG
![Page 28: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/28.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
THANKS SORIN!!!
![Page 29: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/29.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
![Page 30: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/30.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
European Added value
• Everybody is on board
• Large enough to interest other people
NOAA : Matt Menne
Canada : Lucie Vincent
Australia
![Page 31: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/31.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Coordination
• Action is large (26 countries)
• Relying more on small WG/expert meetings and STSMs
• Management Committee = Dissemination of the results to all partners
![Page 32: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/32.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Young people
• WG leaders and Chairman are not so old
• 2 STSMs (only), more in the future (6 planned next year)
Recall this is only our first year
![Page 33: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/33.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Non-COST
• Andorra– Active participation to the “Catalan
experiment”– Motivated people
• Australia : quite recent
![Page 34: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/34.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Dissemination
• homogenisation.org
![Page 35: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/35.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Conferences
• ECSN, November 2007, Vienna
• EGU, April 2008, Vienna
• 6th Seminar on homogenisation, May 2008, Budapest
![Page 36: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/36.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Articles
• At least 3 articles fully realized thanks to COST should be published in peer reviewed journals during year 2
• More articles written by COST members will acknowledge COST
![Page 37: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/37.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Problems
• Web site– Used to be quite empty (much improved now)– Forum had to be closed
• Administration– Thanks to Carine and Chandrasa– Sorry to always forget signing the attendance list– Plenty of (small?) mistakes
• Personal involvement of the Chair : too large!
![Page 38: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/38.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Further plans
• Large intercomparison experiment, based on the benchmark dataset
• Continue exploring mathematical procedures for detection
• Unifying correction procedures
• Encourage procedures for daily values
![Page 39: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/39.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Further plans
• More STSMs (at least 6)
• Improving the web
• Publications
![Page 40: MC meeting Bucuresti 19-20 th of May, 2010](https://reader035.fdocuments.in/reader035/viewer/2022081512/56814e04550346895dbb7288/html5/thumbnails/40.jpg)
ES0601 Action progress report
COST ES0601 MC5 Bucuresti, 19-20 May 2010
Thanks…
• To Sylvain and ESSEM DC, for having selected our Action
• To Carine & Chandrasa
• To the Action Rapporteur John Sweeney, who attended our last MC
(may we expect a milder review after that?)