![Page 1: Maximum Temperatures and Pressures to Run](https://reader034.fdocuments.in/reader034/viewer/2022051501/589bdead1a28aba5108b5273/html5/thumbnails/1.jpg)
10-12-2011_PCC Pilot PlantLinde AG Engineering Division 1
Pipe Stress Analysis of Reformer R-101
By: E. Perez
![Page 2: Maximum Temperatures and Pressures to Run](https://reader034.fdocuments.in/reader034/viewer/2022051501/589bdead1a28aba5108b5273/html5/thumbnails/2.jpg)
10-12-2011_PCC Pilot PlantLinde AG Engineering Division
Pipe Stress Analysis of Reformer R-101Maximum Temperatures to Run. Allowable Stresses of Incoloy 800HT at 10,000 hrs.
2 By: E. Perez
1870°F
![Page 3: Maximum Temperatures and Pressures to Run](https://reader034.fdocuments.in/reader034/viewer/2022051501/589bdead1a28aba5108b5273/html5/thumbnails/3.jpg)
10-12-2011_PCC Pilot PlantLinde AG Engineering Division
Pipe Stress Analysis of Reformer R-101Maximum Pressures to Run. Allowable Stresses of Incoloy 800HT at 10,000 hrs.
3 By: E. Perez
![Page 4: Maximum Temperatures and Pressures to Run](https://reader034.fdocuments.in/reader034/viewer/2022051501/589bdead1a28aba5108b5273/html5/thumbnails/4.jpg)
10-12-2011_PCC Pilot PlantLinde AG Engineering Division
Pipe Stress Analysis of Reformer R-101Model Nodes
4 By: E. Perez
![Page 5: Maximum Temperatures and Pressures to Run](https://reader034.fdocuments.in/reader034/viewer/2022051501/589bdead1a28aba5108b5273/html5/thumbnails/5.jpg)
10-12-2011_PCC Pilot PlantLinde AG Engineering Division
Pipe Stress Analysis of Reformer R-101Model Nodes
5 By: E. Perez
Coil ACoil B
Coil A
![Page 6: Maximum Temperatures and Pressures to Run](https://reader034.fdocuments.in/reader034/viewer/2022051501/589bdead1a28aba5108b5273/html5/thumbnails/6.jpg)
10-12-2011_PCC Pilot PlantLinde AG Engineering Division
Pipe Stress Analysis of Reformer R-101Model Nodes
6 By: E. Perez
Coil A Coil A
![Page 7: Maximum Temperatures and Pressures to Run](https://reader034.fdocuments.in/reader034/viewer/2022051501/589bdead1a28aba5108b5273/html5/thumbnails/7.jpg)
10-12-2011_PCC Pilot PlantLinde AG Engineering Division
Pipe Stress Analysis of Reformer R-101Model Nodes
7 By: E. Perez
Coil A
![Page 8: Maximum Temperatures and Pressures to Run](https://reader034.fdocuments.in/reader034/viewer/2022051501/589bdead1a28aba5108b5273/html5/thumbnails/8.jpg)
10-12-2011_PCC Pilot PlantLinde AG Engineering Division
Pipe Stress Analysis of Reformer R-101Model Nodes
8 By: E. Perez
![Page 9: Maximum Temperatures and Pressures to Run](https://reader034.fdocuments.in/reader034/viewer/2022051501/589bdead1a28aba5108b5273/html5/thumbnails/9.jpg)
10-12-2011_PCC Pilot PlantLinde AG Engineering Division
Pipe Stress Analysis of Reformer R-101Model Nodes
9 By: E. Perez
Coil B Coil B
![Page 10: Maximum Temperatures and Pressures to Run](https://reader034.fdocuments.in/reader034/viewer/2022051501/589bdead1a28aba5108b5273/html5/thumbnails/10.jpg)
10-12-2011_PCC Pilot PlantLinde AG Engineering Division
Pipe Stress Analysis of Reformer R-101Model Nodes
10 By: E. Perez
Coil B Coil B