Karsten Liesenberg / AS-T
Visit NCSX engineers 11/12 October 2007
Max-Planck-Institut für Plasmaphysik
Final assembly of Stellarator W7-X in the torus-assembly hall
Karsten Liesenberg
Project Engineer / AS-T
Karsten Liesenberg / AS-T Visit NCSX engineers 11/12 October 2007 2
Final assembly of Stellarator W7-X
Max-Planck-Institut für Plasmaphysik
UnternehmungWENDELSTEIN 7-X
Overview mounting stands in torus-assembly hall
Mountingstand IIIa
Mountingstand IV
Machine base
Mountingstand IVa
Karsten Liesenberg / AS-T Visit NCSX engineers 11/12 October 2007 3
Final assembly of Stellarator W7-X
Max-Planck-Institut für Plasmaphysik
UnternehmungWENDELSTEIN 7-X
Mountingstand IVa (finished in 2005) Mountingstand IVa with outer vessel lower shell, magnet system and plasma vessel
In Mountingstand IVa, the outer vessel lower shell and the magnet system are put together.
Karsten Liesenberg / AS-T Visit NCSX engineers 11/12 October 2007 4
Final assembly of Stellarator W7-X
Max-Planck-Institut für Plasmaphysik
UnternehmungWENDELSTEIN 7-X
Machine base and temp. supports (finished in 2006)
Supporting structure (1 module) assembly phase
Supporting structure (1 module) operating phase
Machine base
Temp. supports
On the machine base and further temporary supports the stellarator (dead weight approx. 8000 kN ) is supportedduring the assembly phase and the operating phase.
Karsten Liesenberg / AS-T Visit NCSX engineers 11/12 October 2007 5
Final assembly of Stellarator W7-X
Max-Planck-Institut für Plasmaphysik
UnternehmungWENDELSTEIN 7-X
Mountingstand IV (finished in 2007)
Basis platform
Alignment system
Measuring column
Adjustment of 1 module in mountingstand IV
In mountingstand IV the final assembly of the stellarator will be done.All 5 modules are aligned with an accuracy by ≤1.5 mm in all directionsand afterwards welds or bolts with each other.
Module withcross beam
Karsten Liesenberg / AS-T Visit NCSX engineers 11/12 October 2007 6
Final assembly of Stellarator W7-X
Max-Planck-Institut für Plasmaphysik
UnternehmungWENDELSTEIN 7-X
Adjustment test in mountingstand IV (in 2007)
An adjustment test for 1 module was accomplished successfullywith a 100 t dummy load (accuracy ≤1.5 mm).
A further adjustment test takes place in November 2007. For a final adjustment of the module we want to test a movement in all directions with radius of 5 mmwith help of the sliding bearings and hydraulic cylinders in the temporary supports and the cryofeets.
Module withcross beam
Dummy load