MATS Timeline for Compliance

20
MATS Timeline

description

Utilities must comply with the new Mercury and Air Toxics Standards by April 16, 2015. This presentation discusses some of the upcoming milestones for compliance.

Transcript of MATS Timeline for Compliance

Page 1: MATS Timeline for Compliance

MATS Timeline

Page 2: MATS Timeline for Compliance

For most U.S. utilities, the compliance date for the Mercury and Air Toxics Standards (MATS)

is April 16, 2015

Page 3: MATS Timeline for Compliance

THAT’S LESS THAN 8 MONTHS AWAY

Page 4: MATS Timeline for Compliance

The compliance requirements are spelled out in Subpart UUUUU of 40 CFR Part 63

Page 5: MATS Timeline for Compliance

About 460 plants will be affected by these requirements

Page 6: MATS Timeline for Compliance

Compliance with the rule begins next April. Plants can demonstrate compliance through stack testing up to 12 months prior to this date, or….

Page 7: MATS Timeline for Compliance

They will have 180-days after 4/16 to demonstrate that they are meeting the

new emissions limits and work practices.

Page 8: MATS Timeline for Compliance

Unless they have filed for and weregranted a one-year extension.

In that case, the dates move to 2016.

Page 9: MATS Timeline for Compliance

There is a lot of work that needs to happen prior to next April. For example, utilities need to…

Page 10: MATS Timeline for Compliance

Submit the overall site-specific Monitoring Plan at least 60 days prior to any compliance tests or CEMS performance tests.

Example compliance test date of June 9-10

Page 11: MATS Timeline for Compliance

Submit a mercury CEMS Monitoring Plan by March 26, 2015.

Page 12: MATS Timeline for Compliance

Submit a CEMS QA/QC Plan prior to beginning any monitor certification tests.

Page 13: MATS Timeline for Compliance

Submit a site-specific Performance Evaluation Plan at least 60 days prior to any compliance or CEMS performance tests.

Page 14: MATS Timeline for Compliance

Notify the agency of compliance or CEMS performance test dates at least 60 days in advance.

Page 15: MATS Timeline for Compliance

Some compliance tests will consist of a 30-day performance test using the plant’s CEMS (or STMS) data.• Hg• PM• HCl

Page 16: MATS Timeline for Compliance

These CEMS must be certified PRIOR to that performance test.

RATA

Page 17: MATS Timeline for Compliance

Plants may opt to demonstrate ongoing PM and HCl compliance through quarterly testing instead of CEMS.

Page 18: MATS Timeline for Compliance

In those cases, the first quarterly test must be done within 180 days of the compliance deadline…

Page 19: MATS Timeline for Compliance

And must consist of three runs while the unit is operating at 90-110% of design capacity (or at maximum normal operating load).

Page 20: MATS Timeline for Compliance

For more information on MATS and MATS compliance

testing, contact CleanAir today.800-991-3300

[email protected]

Thanks!