Master Scheduling and Rough-Cut Capacity Planning ISQA 459/559 Mellie Pullman.
-
Upload
rogelio-cresap -
Category
Documents
-
view
219 -
download
4
Transcript of Master Scheduling and Rough-Cut Capacity Planning ISQA 459/559 Mellie Pullman.
Master Scheduling and Rough-Cut Capacity Planning
ISQA 459/559
Mellie Pullman
Page 2
Learning Objectives
• Explain the role & objectives of a master production schedule
• Explain the organizational links to master production scheduling
• Develop a master production schedule• Explain rough-cut capacity planning• Calculate available-to-promise quantities • Describe time fence policies
Page 3
Role of the MPS
• Aggregate plan:– Specifies the resources available (e.g.: regular
workforce, overtime, subcontracting, allowable inventory levels & shortages)
• Master production schedule:– Specifies the number & when to produce each end
item (the anticipated build schedule)– Disaggregates the aggregate plan
Page 4
Business Planning Hierarchy
Page 5
Planning Links to MPS
Page 6
Objectives of MPS
• Maintain the desired customer service level
• Utilize resources efficiently
• Maintain desired inventory levels
Page 7
Developing an MPS:
• Assume:– Make-to-stock environment– Production is in fixed quantities of 125
(MPS)– 110 units in beginning inventory (BI)
forecast - MPS BI available Projected
Page 8
Sample Problem
• We start with 110 units in Beginning Inventory• Projected Available: How many units are available at the end of each time
period? • MPS: Replenishment Shipments that need to arrive at the beginning of the
time period
Projected Available =BI + MPS - Forecast
Period 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Projected
Available 110
MPS
Page 9
Step 1
• Find first negative “projected available”Week BI 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Projected available 110 60 10 -40
MPS
We start with 110 units in Beginning InventoryProjected Available: How many units are available at the end
of each time period? (safety stock criteria could be in place > 5)
MPS: Replenishment Shipments that need to arrive at the beginning of the time period
Page 10
Schedule Production
Week BI 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Projected available 110 60 10 85 35 -40
MPS 125
Page 11
Repeat
Week BI 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Projected available 110 60 10 85 35 85 10 -65
MPS 125 125
Page 12
Continue, Until Complete
Week BI 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Projected available 110 60 10 85 35 85 10 60 110 60 10 85 35
MPS 125 125 125 125 125
Page 13
Evaluating the MPS
• Customer service issues:– Does “available-to-promise” inventory
satisfy customer orders?– What new orders can we take from
customers and when?
Page 14
Available to Promise
• When a customer places an order, they do not expect immediate delivery (negotiable).
• The product will delivered by some later date.
• ATP = how many uncommitted units the company has available at a given time
Page 15
New Calculation for Projected Available
Projected Available =
BI + MPS – Max (Customer Orders ; Forecast)
Period 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Customer Orders 35 25 25 20 0 15 0 0 10 0 0 10
Projected
Available 110
Available to Promise
MPS
Page 16
Available-to-Promise“Action Bucket”
• “Action Bucket” = the current period• Only calculate ATP during in Action Bucket and when
MPS occurs
ATP action bucket = BI +MPS-customer orders before next replenishment110 + 0 – (35+25) = 50
Period 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Customer Orders 35 25 25 20 0 15 0 0 10 0 0 10
Projected
Available 110
60 10 85 35 85 10 60 110 60 10 85 35
Available to Promise 50
MPS 125 125 125 125 125
Page 17
Available-to-Promise“Replenishment periods”
• ATP for replenishment periodsATP = MPS - customer orders between current MPS
and next scheduled replenishment
ATP period 3 = 125 – (25 + 20)= 80
ATP period 5 = 125 – (0 + 15)= 110
Period 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Customer Orders 35 25 25 20 0 15 0 0 10 0 0 10
Projected
Available 110
60 10 85 35 85 10 60 110 60 10 85 35
Available to Promise 50 80 110 125 115 115
MPS 125 125 125 125 125
Page 18
New Order
• Suppose we get an order for 200, can we accept this for delivery in period 5?
Page 19
Worksheet for New Order for 200
Fit in the order for 200 (can’t change MPS)
Period 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Customer Orders 35 25 25 20 200 15 0 0 10 0 0 10
Projected
Available 110
60 10 85 35
Available to Promise 50 80
MPS 125 125 125 125 125
Page 20
New Order for 200
• Negative number in Projected Available = might be a problem in the future
• Negative number in Available to Promise= always a problem
Solution?
Period 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Customer Orders 35 25 25 20 200 15 0 0 10 0 0 10
Projected
Available 110
60 10 85 35 -40 -115 -65 -15 -65 -115 -40 -90
Available to Promise 50 80 -90 125 115 115
MPS 125 125 125 125 125
Page 21
Split up New Order for 200
Check to see if this is OK
Period 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Customer Orders 45 25 105 20 110 15 0 0 10 0 0 10
Projected
Available 110
Available to Promise
MPS 125 125 125 125 125
Page 22
Can you now take 2 more orders?
Period 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Customer Orders 45 25 105 20 110 15 0 50 10 0 0 40
Projected
Available 110
60 10 30 -20 -5 -80 -30
Available to Promise 40 0 0
MPS 125 125 125 125 125
• 50 units to be delivered in Period 8• 30 units to be delivered in Period 12
Page 23
Time Fences
Page 24
• Frozen: no changes are possible with a certain period of time (i.e. 8 weeks)
• Time Fence (length of period schedule is frozen, liquid, etc.)
• Demand Fence: MPS numbers do not change and focus is on orders not forecast
• Planning Fence: Master Production Scheduler is planning more MPS.
Page 25
Rough-cut capacity planning
• An estimate of the plans’ feasibility
• Given the demonstrated capacity of critical resources (e.g.: direct labor & machine time), have we overloaded the system?
Page 26
Rough-Cut Capacity Planning
• Determine required resources & proposed workload:
Planning Factors Model W Model M
Direct labor 0.40 0.30
Machine time 0.12 0.08
MPS QRT 1 QRT 2 QRT 3 QRT 4 Total
Model W 6,000 5,500 9,500 6,500 27,500
Model M 10,000 12,000 7,500 10,100 39,600
Hours/unit
Page 27
Calculate RequiredLabor Hours
• Compare with hours available
Model Labor Factor QRT 1 QRT 2 QRT 3 QRT 4 Total
MPS Quantity 6,000 5,500 9,500 6,500 27,500
Hours Required 1,800 1,650 2,850 1,950 8,250
MPS Quantity 10,000 12,000 7,500 10,100 39,600
Hours Required 4,000 4,800 3,000 4,040 15,840
24,090Labor Capacity Required
Model M
0.30
0.40
Model W
Page 28
Calculate RequiredMachine Hours
Model Machine Factor QRT 1 QRT 2 QRT 3 QRT 4 Total
MPS Quantity 6,000 5,500 9,500 6,500 27,500
Hours Required 480 440 760 520 2,200
MPS Quantity 10,000 12,000 7,500 10,100 39,600
Hours Required 1,200 1,440 900 1,212 4,752
6,952Machine Capacity Required
Model M 0.12
Model W 0.08
• Compare with hours available