Transcript of Master Production Scheduling (MPS)
![Page 1: Master Production Scheduling (MPS)](https://reader036.fdocuments.in/reader036/viewer/2022082813/58f2b6ca1a28ab42558b45f1/html5/thumbnails/1.jpg)
MPSBy:
Pankil Shah
![Page 2: Master Production Scheduling (MPS)](https://reader036.fdocuments.in/reader036/viewer/2022082813/58f2b6ca1a28ab42558b45f1/html5/thumbnails/2.jpg)
MPS(Master Production Schedule)
Master Production Schedule – States the requirements for individual end items by date and quantity -APICS
MPS…
o Breaks down or disaggregates the production plan into product families
o Promotes valid order promiseso Provides a communication medium between
Marketing/Sales and Operationso Proactively control ability to deliver goods to customerso Resource availability controlo Proactively control inventory levelso The Sales and Operations Plan is broken into smaller
product families
![Page 3: Master Production Scheduling (MPS)](https://reader036.fdocuments.in/reader036/viewer/2022082813/58f2b6ca1a28ab42558b45f1/html5/thumbnails/3.jpg)
MPS Rules1) Rule C2) Rule F3) Rule of Look Ahead Duration
![Page 4: Master Production Scheduling (MPS)](https://reader036.fdocuments.in/reader036/viewer/2022082813/58f2b6ca1a28ab42558b45f1/html5/thumbnails/4.jpg)
1) Rule C
Available-300MPS Size-500 Week 1 Week 2 Week 3
Forecast 400 500 600
Customer Order 200 100 0
Projected OH 400 400 300
MPS 500 500 500
ATP 800 900 900
![Page 5: Master Production Scheduling (MPS)](https://reader036.fdocuments.in/reader036/viewer/2022082813/58f2b6ca1a28ab42558b45f1/html5/thumbnails/5.jpg)
Available-300MPS Size-500 Week 1 Week 2 Week 3
Forecast 400 500 600
Customer Order 200 100 0
Projected OH 200 100 0
MPS 500 500 500
ATP 800 700 600
2) Rule F
![Page 6: Master Production Scheduling (MPS)](https://reader036.fdocuments.in/reader036/viewer/2022082813/58f2b6ca1a28ab42558b45f1/html5/thumbnails/6.jpg)
Available-300 Week 1 Week 2 Week 3
Forecast 400 500 600
Customer Order 200 100 0
Projected OH 1400 900 300
MPS 1500 0 0
ATP 1800 1400 900
3) Rule of Look Ahead Duration - 2 weeks