![Page 1: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/1.jpg)
Master Plan Public WebinarMobile Downtown Airport
August 4, 2020
![Page 2: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/2.jpg)
2Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Welcome
▪ Mary Mullins Redditt, Outreach Coordinator and Webinar Facilitator
― [email protected] (include who you are)
▪ Meeting agenda and Zoom logistics
― One and one-half hours, Webinar format
― Mobile Airport Authority Staff and Consultant Planning Team Members
▪ Feedback
― Maamasterplan.com
― Click on “feedback” tab
![Page 3: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/3.jpg)
3Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Opening Remarks
▪ By Mobile Airport Authority President Chris Curry
![Page 4: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/4.jpg)
4Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Master Plan Video
Video available at http://www.mobairport.com/masterplan/
![Page 5: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/5.jpg)
5Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Background
▪ Airport Master Plan is a concept for long-term development
▪ Airport master plans are prepared to support the modernization or expansion of existing airports or the creation of a new airport
▪ The master plan is the sponsor’s strategy for the development of the airport
▪ The goal is to guide future airport development that will cost-effectively satisfy aviation demand, while considering potential environmental and socioeconomic impacts
VISION
• GOALS
• CHALLENGES
MASTER PLAN
• ACTIVITY FORECASTS
• DEMAND/CAPACITY ANALYSIS
• STRATEGIC ASSESSMENT
• FINANCIAL FEASIBILITY
• STAKEHOLDER INVOLVEMENT
ACTION PLAN
• IMPLEMENTATION
• DESIGN
• CONSTRUCTION
![Page 6: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/6.jpg)
6Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Master Plan Products and Outcomes
PRODUCTS
▪ Ultimate land use plan for the airport
▪ Sound and comprehensive development plan
― Schedule (Planning Activity Level)
― Capital improvement plan
▪ Business and financial plan
▪ Airport layout plan
OUTCOMES
▪ Stakeholder / community consensus
▪ Coordination with regional plans
▪ Foundation for ensuing efforts
― Federal Aviation Administration (FAA) approvals
― National Environmental Policy Act (NEPA)
― Others as required
![Page 7: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/7.jpg)
7Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Agenda
▪ Aviation Demand Forecasts
▪ Facility Requirements
▪ Key Airport Facilities
― Passenger Terminal and Landside (Ground Transportation and Parking)
― Airport and Airline Support (Air Traffic Control Facility, Aircraft Rescue and Firefighting Facility, Multi-Use Aviation Area)
― On-Airport Land Use Opportunities
― Airfield
▪ On-Airport Development Plan
▪ Environmental Overview
▪ Crepe Myrtle Trail Assessment
![Page 8: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/8.jpg)
Aviation Demand Forecasts
![Page 9: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/9.jpg)
9Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Aviation Demand Forecasts
▪ Report completed and approved by the FAA
▪ Forecasts future enplanements and aircraft operations (incl. passenger airline, cargo, general aviation, military) through 2040
▪ Does not take into account impact to the aviation industry caused by COVID-19
― No guidance yet from the FAA; actual future aeronautical activity will likely be less than forecast until the aviation industry recovers to pre-pandemic levels
▪ Forecasts are presented in planning activity levels (PALs)
― Recognizes uncertainties associated with forecasting
― Tied to milestone activity levels rather than arbitrary years
![Page 10: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/10.jpg)
10Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Aviation Demand Forecasts
a) Enplanements/operations are shown for both BFM and MOB to capture the total Mobile market demand
Source: Historical—Mobile Airport Authority; OAG Aviation Worldwide Ltd., OAG Analyser database, accessed August 2019.Forecast—LeighFisher, October 2019.
Existing (2018)
PAL 1(2025)
PAL 2(2030)
PAL 3(2035)
PAL 4(2040)
Enplaned Passengers
MOB (a) 303,871 - - - -
BFM - 523,000 588,250 614,500 640,750
Aircraft Operations
Commercial
MOB 13,986 - - - -
BFM 4,468 24,360 26,180 26,600 27,000
General Aviation
MOB 9,253 9,190 9,310 9,450 9,580
BFM 14,359 14,800 15,010 15,220 15,440
Military
MOB 48,373 49,970 49,970 49,970 49,970
BFM 45,267 43,670 43,670 43,670 43,670
Total Aircraft Operations
MOB 71,612 59,160 59,280 59,420 59,550
BFM 64,094 82,830 84,860 85,490 86,110
![Page 11: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/11.jpg)
Facility Requirements
![Page 12: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/12.jpg)
12Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Facility Requirements
▪ Requirements calculated for airfield, terminal, landside, and airport support facilities
▪ Documentation complete in draft form
▪ Requirements will guide development of new terminal and supporting facilities
▪ All requirements summarized represent the end of the planning period (PAL 4, 2040)
![Page 13: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/13.jpg)
13Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Airfield Requirements
▪ Critical Design Aircraft: Airbus A-300 (C-IV) for primary runway and associated facilities
▪ Hourly Weighted Runway Capacity: 88.6 operations/hour in visual meteorological conditions (VMC)
▪ Annual Service Volume (Capacity): 184,111 annual operations in PAL 4
▪ Runway Length: Sufficient
▪ Instrument Approach: Upgrade to Category II/III instrument landing system (ILS)
![Page 14: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/14.jpg)
14Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Terminal Requirements
▪ Total Number of Gates: 8
▪ Holdroom area: 7,500 sq. ft.
▪ Airline Check-in: 12 positions, 5,600 sq. ft.
▪ Security: 4 security lanes, 5,000 sq. ft.
▪ Baggage Claim: 2 claim devices, 12,000 sq. ft.
▪ Concessions: 10,000 sq. ft.
![Page 15: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/15.jpg)
15Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Ground Transportation and Parking Requirements
▪ Public, Employee, and Commercial Parking: 2,600 stalls (low), 3,500 stalls (high)
▪ Rental Car Facility: 108,000 sq. ft. (low), 192,000 sq. ft. (high)
▪ On-Airport Roadways: new roadway configuration to serve terminal
▪ Curbside: 375 linear ft. for arrivals, 350 linear ft. for departures
▪ Commercial Vehicle Hold Lot: 60 stalls, 22,000 sq. ft.
![Page 16: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/16.jpg)
16Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
General Aviation and Cargo
▪ Air Cargo Facilities: 2,895 sq. ft.
▪ General Aviation /Fixed Base Operator Facilities: 3 acres (parcel) / 13,346 sq. ft. (apron)
![Page 17: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/17.jpg)
17Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Airport Support Facilities
▪ Aircraft Rescue and Firefighting (ARFF): 9,000 sq. ft.
▪ Air Traffic Control: 135,500 sq. ft. (3 acres)
▪ Airport Administration: 26,908 sq. ft.
▪ Fuel Storage: 106,100 gallons (Jet-A) / 12,200 gallons (AvGas)
▪ Airline Maintenance Facility: 58 acres
▪ Ground Support Equipment Area: 28,285 sq. ft.
▪ Airport Maintenance Facility: 8,188 sq. ft. (maintenance building) / 20,204 sq. ft. (maintenance yard)
![Page 18: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/18.jpg)
Passenger Terminal and Landside
![Page 19: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/19.jpg)
19Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Planning Assumptions
▪ Maintain utilization of Interim Terminal (22,800 sf) and LCC/ULCC service at BFM
▪ Interim Terminal can be used as a transition facility for relocated and new carriers prior to the opening of the new terminal
▪ The timetable for new terminal development and Legacy airline relocation to BFM would require adoption of a schedule accommodating required planning, design, environmental and construction activities
![Page 20: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/20.jpg)
20Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Future Terminal Location Study Area
Airport boundary
Corridor 1
Terminal Study Area
![Page 21: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/21.jpg)
21Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Future Airport Access
PERIMETER RD
DAUPHIN ISLAND PKWYG
AT
OT
KO
CO
DR
Airport boundary
![Page 22: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/22.jpg)
22Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Existing Conditions
Terminal building (ft2) 22,800
Curb length (ft) 140
Gates 3
Parking (acre) 1.5
Parking (stalls) 176
Michigan AveA
ven
ue
M
Ave
nu
e O
Bro
ad S
t
Terminal building
Surface parking
![Page 23: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/23.jpg)
23Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
▪ Evaluated 5 options
▪ Conducted detailed evaluations
▪ Short listed 3 final options
▪ Recommending a preferred option for MAA approval
▪ Continued Planning for new terminal is a work in progress
New Terminal Options
![Page 24: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/24.jpg)
24Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Michigan Ave
Bro
ad S
tPreferred Terminal Option
Terminal building (ft2) 130,000
Curb length (ft) 530
Gates 8
Parking area (acre) 31.5
Parking capacity (stalls) 3,505
New apron (yd2) 35,500
Buildings affected* 9
* Exclude Existing FBO and small structures
Terminal building
Parking garage / Surface Parking
Apron
Rental car facility
![Page 25: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/25.jpg)
25Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Preferred Terminal Option (continued)
▪ Airport Access
― Ingress and Egress: New terminal access loop road north of current Penske property
▪ Terminal
― Situated to reduce the new apron construction and relocation of PetroClean and ASF on Perimeter Road at north of new terminal access loop road
― Moderate future expandability beyond planning period to east (1 gate) and west (1-2 gate)
▪ Airside
― Shorter taxilane to reach the farthest gate
▪ Landside
― New 5-level parking garage in front of the terminal; connected to the terminal by crosswalk
― New access road to existing terminal building area south of current Penske facility
― Michigan Avenue terminates at south of Avenue N
― New rental car facility at current Penske facility
▪ Least environmental impact of all options
![Page 26: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/26.jpg)
Airport Traffic Control Tower (ATCT) Facility
![Page 27: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/27.jpg)
27Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Overview
Site 3a was chosen as a preferred site for the future air traffic control facility at BFM based on our preliminary evaluation of visual performance criteria with FAA ATCTVAT tool, and line of sight and shadow study using a 3D model.
Studied sites
Preferred site
![Page 28: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/28.jpg)
28Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Site 3a – Shadow Study
▪ No obstruction
― Runway 14-32
― Runway 18-36
― Taxiway A
― Taxiway K
▪ In viewshed
― Taxiway H (partially in shadow)
― Taxiway LSite 3a
Rw
y 1
8-3
6
Twy L
N
Viewshed
Possible improvements
![Page 29: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/29.jpg)
29Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Eye height: 116.8’ Eye height: 166.8’ (+50’)
Site 3a – Viewshed
Taxiway H is visible approximately 150’ from the intersection of Taxiway A and H
Taxiway H is visible approximately 200’ from the intersection of Taxiway A and H
Twy HTwy H
![Page 30: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/30.jpg)
30Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Summary
▪ Issue: Taxiway H is only visible approximately 150’ from the intersection of Taxiway A and H
― If controller eye level is raised to 166.8’ (+50’), Taxiway H is visible approximately 200’ from the intersection of Taxiway A and H
― If higher tower is not feasible, accept 150’ visibility on Taxiway H and make the rest non-movement area
▪ Issue: No landside access
― Relocate Taxiway K to south
![Page 31: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/31.jpg)
Aircraft Rescue and Firefighting (ARFF) Facility
![Page 32: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/32.jpg)
32Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Overview
▪ Studied 4 potential sites
▪ Facility requirements:
― 3-bay space with overhead doors on both sides
― offices, training, berthing, and fitness rooms
― approximately 9,000 sf
![Page 33: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/33.jpg)
33Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Methodology
▪ Computer based analysis based on travel time and total response time
▪ Turn-out time (activation time) is not included
― Provided by operations
▪ Within 3 minutes from the time of the alarm, at least one required ARFF vehicle must reach the midpoint of the farthest runway serving air carrier aircraft or reach any other specified point of comparable distance on the movement area that is available to air carriers, and begin application of extinguishing agent.
![Page 34: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/34.jpg)
34Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Recommendation
▪ Site 1 is recommended
― Offers good access
― On airport property
― Does not require land acquisition
― Does not require crossing an active taxiway (after Taxiway K relocation)
― Is centrally located
![Page 35: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/35.jpg)
Multi-Use Aviation Area
![Page 36: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/36.jpg)
36Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Potential Sites
▪ Site 1
― Near Runway 14 Threshold
― Approximately 32 acres
▪ Site 2
― Along Runway 18/36
― Approximately 30 acres
Site 1
Site 2
Site includes airfield access
![Page 37: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/37.jpg)
37Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Recommendation
▪ Site 1 is recommended
― On-airport property
― Good airside and landside access
― Limited environmental impacts (area already developed)
▪ Potential challenges
― Allowable height of building and hangars limited by airspace and transitional surface impacts
Multi-use aviation area
Taxiway access to open area for development
![Page 38: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/38.jpg)
On-Airport Land Use Opportunities
![Page 39: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/39.jpg)
39Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Aviation Development Opportunities - Future
Hangars 3, 4, 5, 6
Group IV Taxilane
Red outline is leasehold being returned to MAA
Broad St
Mic
hig
an A
ve
![Page 40: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/40.jpg)
40Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Aviation Development Opportunities - Ultimate
Hangars 3, 4, 5 and 6
Group IV Taxilane
Red outline is leasehold being returned to MAA
Broad St
Mic
hig
an A
ve
![Page 41: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/41.jpg)
Airfield
![Page 42: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/42.jpg)
42Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Future Airfield Development
Construct future parallel taxiway
Relocate Taxiway K
Upgrade Runway 32
to CAT II/III
Instrument Landing
System (ILS)
Relocated ARFF
Relocated ATCT
Add shoulders on Taxiway A
south of Runway 36
Construct
access taxiway
Extend Airbus Way
![Page 43: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/43.jpg)
On-Airport Development Plan
![Page 44: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/44.jpg)
44Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
On-Airport Development Plan – Existing
![Page 45: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/45.jpg)
45Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
On-Airport Development Plan – PAL 1
![Page 46: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/46.jpg)
46Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
On-Airport Development Plan – PAL 2
![Page 47: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/47.jpg)
47Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
On-Airport Development Plan – PAL 3
![Page 48: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/48.jpg)
48Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
On-Airport Development Plan – PAL 4
![Page 49: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/49.jpg)
Environmental Overview
![Page 50: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/50.jpg)
50Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Environmental Overview
▪ “Proposed actions” that have potential to impact the environment, alter airport operations or obstruct airport navigation are required to be evaluated under the National Environmental Policy Act (NEPA) and its implementing regulations issued by the Council on Environmental Quality (CEQ) [codified in 40 CFR Parts 1500-1508].
▪ The FAA can only “unconditionally” approve change to an ALP if an environmental analysis has been prepared in accordance with NEPA and CEQ regulations.
▪ FAA Order 1050.1B and 5050.4B establishes FAA policies and procedures to help airport comply with NEPA environmental review.
![Page 51: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/51.jpg)
51Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Environmental Overview
Environmental Categories Resources Evaluated
Air Quality Greenhouse gas emissions, construction emissions
Water Resources Wetlands, creeks, floodplain, surface waters, stormwater management
Biological Resources Protected plant, fish and wildlife species
Section 4(f) Sources Parks, Wildlife Refuge, Public Lands
Noise-compatible land use Local jurisdictions, community development plans, existing land use
Hazardous Materials Solid Waste, Pollution Prevention Plans
![Page 52: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/52.jpg)
52Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Environmental Overview
▪ Proposed action alternatives are evaluated from an environmental perspective for impact.
▪ Proposed actions that require environmental effects evaluation:
― New terminal construction
― Roadway improvements
― New taxilane(s)
― Building demolition
― Tenant relocations
▪ The overview presents environmental conditions and constraints for consideration during planning.
Legend:Airport Boundary
Environmental Study Boundary
Area surrounding future alternative terminal location
![Page 53: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/53.jpg)
53Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Baseline 2018 Noise Contours
![Page 54: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/54.jpg)
54Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Future 2040 Noise Contours
![Page 55: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/55.jpg)
Crepe Myrtle Trail Assessment
![Page 56: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/56.jpg)
56Mobile Downtown Airport
Master Plan Public Webinar 8/4/2020
Crepe Myrtle Trail Assessment
▪ Included on Airport Layout Plan for FAA and TSA evaluation
Crepe Myrtle Trail (proposed)
![Page 57: Master Plan Public Webinar - mobileairportauthority.com · Master Plan Public Webinar 8/4/2020 Overview Site 3a was chosen as a preferred site for the future air traffic control facility](https://reader033.fdocuments.in/reader033/viewer/2022042811/5fa5d549acbb655b2a1e8ee0/html5/thumbnails/57.jpg)
Thank you