MASTER^ - inis.iaea.org · Table 1. The CCW heat exchangers are one-pass, shell-and-tube heat...
Transcript of MASTER^ - inis.iaea.org · Table 1. The CCW heat exchangers are one-pass, shell-and-tube heat...
-
^ /
FLOW-INDUCED VIBRATION OF COMPONENT COOLING WATER
HEAT EXCHANGERS*
CONP-900617—1
^ DE90 003789
Y. S. Yeh and S. S. Chen**
Nuclear Engineering DepartmentTaiwan Power Company
Taiwan, Republic of China
**Materials and Components Technology DivisionArgonne National Laboratory
Argonne, Illinois USA
SUMMARY
This paper presents an evaluation of flow-induced vibration problems of
component cooling water heat exchangers in one of Taipower's nuclear power
stations. Specifically, it describes flow-induced vibration phenomena, tests to
identify the excitation mechanisms, measurement of response characteristics,
analyses to predict tube response and wear, various design alterations, and
modifications of the original design. Several unique features associated with the
heat exchangers are demonstrated, including energy-trapping modes, existence
of tube-support-plate (TSP)-inactive modes, and fluidelastic instability of TSP-
active and -inactive modes. On the basis of this evaluation, the difficulties and
future research needs for the evaluation of heat exchangers are identified.
* Paper to be submitted for presentation at the ASME Pressure Vessel and Piping
Conference, Nashville, Tennessee, June 17-21, 1990.
M A S T E R ^DISTRIBUTION OF THIS DOCUMENT IS UNLIMITED
The submitted manuscript has been authoredby a contractor of the U. S. Governmentunder contract No. W-31-109-ENG-38.Accordingly, the U. S. Government retains anonexclusive, royalty-free license to publishor reproduce the published form of thiscontribution, or allow others to do so, torU. S. Government purposes.
-
1. Introduction
The Maanshan Nuclear Power Station contains two trains of component
cooling-water (CCW) heat exchangers for each of two reactors. Trains A and B of
Unit 1 were placed in service in December 1982 and January 1983, respectively.
Tube leakage in both heat exchangers was discovered in March 1983, after only a
few months of operation. Damage was noticed at tube supports and midspan
regions. This was the beginning of a series of steps taken by Taiwan Power
Company (Taipower) to resolve the problem. A brief history is presented in
Table 1.
The CCW heat exchangers are one-pass, shell-and-tube heat exchangers
with sea water in the tube side and hot demineralized water in the shellside. A
schematic diagram of the heat exchanger is given in Fig. 1. Each exchanger
contains 3,488 tubes contained in a 66-in. (i.d.) circular cylindrical shell. The two
tube sheets are 1.75-in. aluminum-bronze plates, and two types of baffle plates are
0.625-in. carbon steel plates; four are segmental baffle plates with a single
horizontal cut, and ten are support plates with double horizontal cuts as shown in
Fig. 1.
A 36-in. (o.d.) circular impingement plate was installed at the inlet to
distribute the incoming flow to the first three passes. All heat exchanger tubes
are cupronickel with 0.75-in. o.d. and 0.049-in. wall thickness. The tubes are
arranged in a rotated triangular pattern with a pitch of 15/16-in.
-
2. Tube Damage
2.1 Initial Inspection
In March 1983, after a few months of operation, 14 tubes were found
damaged in Train A and 4 in Train B. All damaged tubes had flat spots
developing in the first and second baffle plates next to the inlet nozzle. These flat
spots are 6-24 inches long. A damaged tube in Train A developed a 4-in. long
crack along a 24-in. flat spot, and a damaged tube in Train B was severed at the
second support plate. All damaged tubes were located in the inlet area.
Apparently, the high flow velocity in the nozzle caused large tube motion that
resulted in tube damage. The flat spots were caused by tubes colliding with each
other.
In February 1984, the manufacturer of the CCW heat exchangers, Struthers-
Wells Corp. (SWC), completed initial modifications of both CCW heat exchangers
in Unit 1. The modifications included removing 420 tubes from each heat
exchanger. No damage inspection was performed when they were removed and
placed in groups in an open field.
In March 1984, the first five spans were inspected for flat spots between the
supports and ring-type markings at tube supports. If no damage was found in the
first five spans, the tube was considered undamaged. If damage was observed in
these five spans, inspection continued to the subsequent spans until no further
damage was found. Figure 2 shows the results of the damage inspection. Among
396 inspected tubes in Train A and 400 in Train B, 36 tubes in Train A and 28 in
-
Train B were damaged. Twenty tubes in Train A and 16 in Train B contained flat-
spot damage between the first two baffle plates.
2.2 Damage Inspection of Selected Tubes
In July 1984, 28 tubes from each heat exchanger in Unit 1 were selected for
evaluation of the extent and distribution of tube damage. Figure 3 shows the
location of the tubes selected from each heat exchanger. In contrast to the tubes
near the nozzle, most damage occurred at the supports and baffles. Only one tube
from Train A showed flat-spot damage. In general, most of the damage was in
the first three supports. However, several tubes showed damage only at the
middle supports, e.g., supports 5 through 9. This damage pattern shows that
tubes located in regions other than near the nozzle are also subjected to
unacceptable vibration.
From the damage inspection, several general conclusions can be made:
• Excessive flow-induced vibrations were noted in both Trains A and B.
• Tube-to-tube impacts appear between the first two baffles.
• Damage at supports occurs in various regions of the tube array and at
different axial locations.
It is apparent that the original design of the heat exchanger is inadequate
from the standpoint of flow-induced vibration. The mechanism causing such
large tube vibration is due to fluidelastic instability.
-
3. Vibration Tests of CCW Heat Exchangers by Bechtel Group, Inc.
3.1 Phase-1 Tests
Two modifications were made in accordance with the manufacturer's
recommendations after the initial report of tube damage: (1) removing 420 tubes
from each train. [One hundred fourteen removed tubes were not replaced and the
holes were left in the baffles; supports and tube sheets were plugged. The rest of
the tubes were replaced by BWG 12 tubes (0.75-in. o.d. and 0.109-in. wall
thickness.)]; and (2) replacing the original impingement plate at the inlet (a 36-in.
diameter, 3/8-in. thick stainless steel plate welded to tie bars and a support plate)
by a flow deflector. Bechtel Group, Inc. performed tests on the modified heat
exchanger [1].
Eighteen tubes were selected for measurement. Two accelerometers were
embedded in each pod and inserted inside the selected tubes to measure tube
accelerations in two perpendicular directions at midspans. Three additional
accelerometers were placed on the outside shell.
After properly checking all accelerometers, flow tests were performed at a
series of flow rates, varying from zero to the rated flow of 127,000 gpm. A 14-
channel FM-type recorder was used to store the accelerations.
Analysis of the data includes time-domain data, frequency spectra, and
vibration amplitude.
-
3.1.1 Time-Domain Data
The data on acceleration-time plots revealed that
• Low-level background vibration of about 0.25 g peak-to-peak existed at
zero flow due to other equipment.
• Tube accelerations increased with flow velocity, reaching a magnitude
of 10 g peak-to-peak (p-p) at 127,000 gpm.
• Impact signrls were noted for flow above 7,000 gpm.
• The impact signals, occurring right at the peak of the vibration
waveform, indicate a direct impact at the accelerometer pod location.
In addition, the accelerations were doubly integrated to obtain tube
displacements. Figure 4 shows the tube displacements (p-p) as a function of flow
rate for nine tubes.
3.1.2 Frequency Spactra
Typical frequency spectra are shown in Fig. 5. The following general
characteristics are noted:
• Tube responses at low flow rate are broadband, indicating that the
excitation is turbulent buffeting.
-
• As the flow velocity increases, the major frequencies are located in two
regions, i.e., at 21-24 and 26-32 Hz.
3.1.3 Monitoring of SheU Vibration
Three shell accelerometers were installed on the external surface of the heat
exchanger to supplement the internally mounted accelerometers. At 6,000 gpm,
faint impact sounds could be heard at the first baffle location. At 7,000 gpm,
clean, but still faint, impact sounds could be heard at the second support and first
baffle. At 8,000 gpm, sound intensities increased noticeably. At 12,000 gpm, the
impact sounds became more frequent and much stronger.
The heat exchanger was tested again with the flow deflector rotated 180
degrees. The objective was to obtain vibration response under a new shellside
inlet condition. The test was conducted in February 1984 with flow rates at 7,000,
10,000, and 12,000 gpm. Tube responses were comparable with those of the
original test. However, the flow deflector did change the details of tube response.
3.1.4 Conclusions and Recommendations
When the shellside flow rate exceeded 7,000 gpm, the modified CCW heat
exchanger experienced severe tube vibration. Some of the tubes are subjected to
fiuidelastic instability at the rated flow of 12,700 gpm. The modifications
recommended by the manufacturer are inadequate. Meanwhile, it is
recommended that the following steps be taken before a final resolution of the
problem is reached.
-
8
• Operate the heat exchangers at flow rates not to exceed 6,000 gpm
whenever possible.
• Implement a surveillance program to detect leakage and inspect tube
damage before final modification.
• Investigate measures to resolve the problem, (e.g., improve flow velocity
distribution by adding inlet and outlet nozzles, and increase tube natural
frequencies by adding tube supports, in particular, in the inlet and outlet
regions.
• Evaluate the feasibility of replacing the existing units with a better
design.
3.2 Phase-2 Tests
Additional modifications to the heat exchangers were made as a result of the
Phase-1 tests. The modifications included staking the bottom 14 tube rows in
Bays 1, 2, and 3, and installing perforated plates in Bays 2 and 3. Two large cuts
were made to implement these modifications in June 1984.
• The first bay was staked at midspan and the second and third bays were
staked at the 1/3 and 2/3 points of each span. Staking strips of carbon
steel with a width of 0.75-in. and a thickness of 60 mils were wedged
horizontally between adjacent tube rows.
-
• A plate, 43 x 45 x 3/8 inches, with 3/8-in. diameter holes on a 13/16-in.
staggered pitch, resulting in 19% open area, was installed in Bajr 2.
• Two perforated plates were installed in Bays 2 and 3; a top plate
contained 1/2-in. diameter holes on a 1-in. staggered pitch (22% open
area) and a bottom plate contained 7/16-in. diameter holes on a 1-in.
staggered pitch (17% open area). All plates were stainless steel sheets
3/8-in. thick.
The Phase-2 vibration tests were a continuation of the Phase-1 test. The test
procedure, instrumentation, and data analysis are the same as those in Phase 1.
Accelerometers used for Phase 1 were used, to the extent feasible, for Phase 2
tests. Twenty-eight additional acceleronieters were procured for Phase 2 [2].
To guide the selection of suitable locations for installing accelerometers, and
to assist the interpretation of test results, natural frequencies of selected tubes
were calculated.
The test results were summarized as follows:
• Tube impact signals are noted at high flow velocity.
• Response of the unstaked tubes in the frequency range of 20 to 55 Hz was
excited at flow rates of 6,100 gpm and above. The only tube that was
instrumented and staked detected prominent tube response at 129 Hz.
• The largest tube motion was about 15 mils.
-
10
Tube vibration amplitudes increase with increasing shell side flow velocity.
At the maximum flow rate of 12,700 gpm, the peak acceleration amplitude was
about 1.2 g, which was considerably lower than the 15 g in Phase-1 tests. The
maximum tube displacement was about 30 mils, peak to peak; tube collision at
midspan is unlikely. Impacts were noted for flow over 9,000 gpm. Tube wear is
still possible, and the long-term effect is uncertain. Under the described
conditions, it is recommended that flow rate be restricted to 9,000 gpm, a rigorous
surveillance and maintenance program be implemented, and sources be located
for replacement heat exchangers.
After the Phase-2 test, Taipower decided to replace two CCW heat exchangers
with a new design, and modify the other two trains. The new design has a 15-in.
tube span and it is not expected to have any flow-induced vibration problems. The
other two trains were modified as follows by Taiwan Machinery Manufacturing
Corp. (TMMC) on the basis of a recommendation of a French consulting firm:
• The inlet region was changed from the original three passes to seven
passes.
• The outer shell diameter was increased.
The modified heat exchanger is shown in Fig. 6 After completion of the
modification by TMMC, flow tests were conducted by Loutech Taiwan, Inc. [3].
-
11
4. Analysis and Vibration Tests of Modified Heat Exchangers
4.1 Tests by Loutech Taiwan, Inc.
To verify the severity of vibration and structural integrity, Loutech Taiwan,
Inc., performed a flow test in September 1988. Twenty-five tubes were
instrumented with two accelerometers each to measure the accelerations in two
perpendicular directions. The instrumented tubes and the fisial locations are
given in Fig. 7.
Four types of plots were obtained from the data from each accelerometer:
• Overall tube displacement versus time: the peak amplitudes at each of
147 time intervals within 110 seconds.
• Average spectra of tube displacements: average spectra for 0 to 147 Hz.
• Peakhold spectra: the peaks of all spectra from 0 to 147 Hz.
• Frequency spectra versus time: frequency spectra of different tubes as
function of time.
Figure 8 shows typical average frequency spectra for a series of flow rates
and Figs. 9 and 10 show the frequency spectra as a function of time.
One method to determine the response characteristics and the critical flow
velocity is to plot tube displacement as a function of flow rate. The most frequently
-
12
used tube response is the rms value of *abe response (acceleration, velocity, or
displacement). Loutech did not provide rms values of tube displacements.
Alternatively, the peak values are presented. Figures 11 to 13 show the peak tube
displacements as a function of flow rate in logarithmic scale for selected tubes,
where H and V are used to indicate horizontal and vertical components
respectively.
4.2 Natural Frequencies: ISP-active and-inactive Modes
The natural frequencies of the tubes are very important for the interpretation
of tube response data. A free-vibration analysis was performed for different cases.
CCW heat exchanger tubes, fixed to the tube sheets at the two ends, were
supported by 14 tube-support plates (TSP), see Fig. 14. To facilitate assembly and
relative motion caused by thermal expansion, holes in the TSP were made larger
than the tube diameters. It is not uncommon for tube holes to be drilled 0.4 to
0.8 mm larger than the outside diameter of the tubes. In this case, the magnitude
of the clearance was not known. Owing to the clearance, TSP? may not provide
support in some cases. Therefore, there are two types of modes: TSP-active and
TSP-inactive
Current design practices consider the heat exchanger tubes to be simply
supported, without clearances, at the TSPs. For small clearances, this
assumption is expected to be applicable; the tube will respond as a continuous
beam supported by all TSPs, and anti-nodes of all modes do not appear at the
TSPs. This type of mode is called "TSP-active." Studies show that this
assumption is indeed applicable if the clearance is small [4-7], although there are
-
13
some variations of resonant frequencies. With this assumption, the simple beam
theory can be used to predict tube natural frequencies, as well as tube responses to
different excitations.
When the clearance is relatively large, the tube will rattle inside some of the
TSP holes for small-amplitude oscillations. This type of mode, in which some
TSPs do not provide effective supports, is called "TSP-inactive.:i
For intermediate clearances, the tube response will depend strongly on the
excitation amplitude. For low excitations, the tube will vibrate within the
clearance gap (TSP-inactive modes). For large excitations, the tube will be in
contact with all TSPs most of the time (TSP-active modes). In reality, the tube
response will be composed of both TSP-active and TSP-inactive modes.
A typical CCW heat exchanger tube was analyzed for the TSP-active and
-inactive modes. Table 2 shows the natural frequencies of TSP-active and -inactive
modes for different cases. The characteristics of Tube BWG 12, presented in this
paper, are similar to those of Tube BWG 18 except that the natural frequencies of
Tube BWG 18 are a little lower. As an example, the natural frequencies of TSP-
active modes of two tubes are compared in Table 3. The difference in natural
frequencies of the two tubes for the TSP-active mode is small; this is also true for
TSP-inactive modes.
Two different situations are considered for TSP-inactive modes: a particular
TSP, such as TSP 2, being inactive, and two TSPs, such as TSPs 2 and 4, being,
inactive.
-
14
Figure 14 shows the tube and all TSPs. The TSP-active modes are given in
Fig. 15 for the first five modes. The results agree well with those obtained by
Bechtel [2]. Figure 16 shows the first five modes when TSP 2 is inactive, and Fig.
17 shows the first two modes when two TSPs are inactive.
Among the TSP-inactive modes, some of the modes are dominant in specific
spans; these modes are called energy-trapping modes [8]. For example, Fig. 18
shows the lowest TSP-inactive modes for different cases. These modes are the
most important ones when one TSP is inactive.
43 Tube Response Characteristics
Among the information that is most important for the interpretation of the
daca is the natural frequency of the tubes. Based on the results presented in Table
2 and Figs. 15-18, we can construct frequency bands for tube BWG 12, as shown in
Fig. 19. These frequency bands are plotted on the assumption that only one
support is inactive. Experimental data show that those modes associated with
more than two inactive supports are not significant. Two types of frequency
bands, passing and stopping, can be constructed. Within a passing band, waves
can propagate freely through each tube support; however, within a stopping band,
waves will be attenuated as they travel from one support to the next. All natural
frequencies are in the passing bands only. In a stopping band, since no natural
frequencies exist within that frequency range, tube response will be very small.
Figure 19 shows the approximate boundaries of the first two stopping and passing
bands:
First Stopping Band 0 - 9.5 Hz
-
15
First Passing Band 9.5 - 73 Hz
Second Stopping Band 73 - 95 Hz
Second Passing Band 95 - 176 Hz
The first passing band is approximately between 9.5 and 73 Hz; therefore, the
dominant tube response is expected to be in this frequency range. In addition, the
first TSP-active mode is at 23.9 Hz; any frequencies below this are the energy-
trapping modes associated with TSP-inactive modes. The first two stopping bands
are approximately between 0 and 9.5 Hz and 73 and 95 Hz; in these two frequency
bands, we expect that the tube response will be very small.
Based on the experimental data and analytical results, some general
observations can be made.
TSP-inactive modes contribute significantly to tube response. It can be seen
from the frequency spectra that TSP-inactive modes, whose frequencies are lower
than that of the first TSP-active mode of approximately 23 Hz, contribute
significantly to the response.
Some of the tubes are subjected to fiuidelastic instability of TSP-inactive
modes. For example, let us consider Tube 11C. The frequency spectra for Tube
11C are given in Fig. 8 for various flow rates. When the flow rate is increased
from 10,000 gpm to 145,000 gpm, the contribution of TSP-inactive modes increases;
at 14,000 and 14,500 gpm, TSP-inactive modes are dominant. Furthermore, Fig.
13 shows that the slope of the response curve is much larger than 2, an indication
that the tube is subjected to fiuidelastic instability associated with TSP-inactive
modes.
-
16
The response of various tubes is different and the response of each tube
changes with flow rate. The key parameter in this case is the clearance between
the tube and TSP holes. As flow rate changes, the tube configurations also
change, i.e., the contact points of the tubes with TSPs changes with flow rate due
to the change in drag and lift forces.
The motion of Tube 5B is the largest of all instrumented tubes associated with
TSP-active and -inactive modes; however, the TSP-inactive modes are not the
dominant mode of the response. The large amplitudes are believed to be
attributable to the high local flow velocity. The tube is not subjected to fluidelastic
instability.
Based on the frequency band presented in Fig. 19, the dominant mode of each
tube at different flow rates can easily be identified from the spectra.
The response of all tubes is contained in the first passing band; this is in
agreement with the frequency band consideration. The modes include TSP-active
and -inactive modes. In some cases, the frequencies of the active and inactive
modes can be seen clearly in the spectra. As an example, the frequency spectra of
Tubes 1A-H and 2A-H are given in Fig. 9, the lower frequency peaks are TSP-
inactive modes and the higher peaks are TSP-active modes. In some other cases,
only TSP-inactive or TSP-active modes dominate; see Fig. 10 for typical examples.
Among the instrumented tubes, the displacements of the tubes in the first
row in the inlet region are the largest. This can easily be seen by comparing the
displacements of tubes in different locations.
-
17
The tube displacements in the inlet regions are larger than those in the outlet
region. In addition, the spans close to the inlet nozzle (accelerometer groups B
and C) have larger displacements than spans further av/ay from the inlet nozzle.
The main characteristics of the tube responses are
• TSP-inactive modes are important since some of them are subjected to
fluidelastic instability.
• Fluidelastic instability of TSP-active modes does not occur.
• Tube characteristics (support conditions) change with flow rate.
• The tubes located in the front row in the inlet region have larger
displacements.
• Tube wear may be important owing to the impact/sliding associated with
fluidelastic instability of TSP-inactive modes and turbulence excitation of
TSP-active and -inactive modes.
4.4 Fluidelastic Instability and Wear
From the experimental data, it is noted that fluidelastic instability may
occur, depending on the modes. The critical flow velocities for different cases
were calculated. The flow velocity distribution is not known. Assuming a
uniform flow velocity distribution, the flow velocity is 1.16 ft/sec at 12,700 gpm.
-
18
The mass-damping parameter is 0.24, assuming a damping ratio of 1%.
Therefore, the reduced flow velocity is 0.84 and 1.84 for TSP-active and TSP-
inactive modes, respectively. On the basis of the existing correlations [9,10], the
critical reduced flow velocity ranges from 1.1 to 2.2, On the basis of the existing
correlations, we expect the tubes are not subjected to fluidelastic instability of TSP-
active modes, but may be subjected to fluidelastic instability of TSP-inactive
modes. This is in agreement with the experimental data.
In the original design, the incoming fluid passes across three passes only;
the reduced flow velocity at 12,700 gpm is 1.96 and 4.29 for TSP-active and TSP-
inactive modes, respectively. Therefore, the tubes are subjected to fluidelastic
instability of TSP-inactive modes and some of the tubes are subjected to fluidelastic
instability of TSP-active modes. The instability of the TSP-active modes had
caused tube damage in the original design.
Once the tubes are subjected to fluidelastic instability of TSP-active modes,
they are not acceptable from the standpoint of flow-induced vibration and it is not
necessary to calculate wear rate because tube leaks will occur within a very short
time of operation. On the contrary, when the tubes are subjected to fluidelastic
instability of TSP-inactive modes, the wear rate is much smaller and its
significance depends on many other parameters. In general, it is difficult to
predict tube wear under such conditions. In CCW heat exchangers, several
important parameters, such as clearance, flow velocity distribution, and wear
rate, are not known. It is impossible to predict tube wear with confidence.
However, as an exercise, tube wear was calculated by means of the approach
taken by Connors [11]. If a wear coefficient of 600 and clearance of 25 mils are
used in the calculations, it is concluded that it will take about 16 years for a tube to
-
19
wear through. This wear calculation is not accurate and only gives an estimate of
order of magnitude.
5. CONCLUSIONS
On the basis of this evaluation, we have concluded the following:
In the original design, the flow velocity was larger than the critical flow
velocity; therefore, the tubes were subjected to the fiuidelastic instability of TSP-
active modes. The original design was not acceptable and the observed damage
was due to fluidelastic instability.
In the extensively modified version, the tubes are not subjected to the
fluidelastic instability associated with TSP-active modes. Therefore, occurrence of
tube leaks caused by flow-induced vibration is not expected to occur during short-
term operation. Based on the tube response characteristics, it is believed that the
clearance between the tubes and support plate holes is relatively large. Because of
the clearance, wear will result from the sliding and impacting of the surfaces due
to the oscillations associated with turbulence excitation and instability of TSP-
inactive modes. When the unit is put in service, a surveillance program and
follow-up work should be conducted to ensure the safety and predict the useful life
of a unit.
From the experience with CCW heat exchangers, it appears that the state of
the art is such that more work remains to be done. Specifically, the following
items should be emphasized:
-
20
• Flow Velocity Distribution. An efficient computer code to compute the
flow velocity distribution for general heat exchangers would be very
useful. Currently, few codes can be used for CCW heat exchangers.
Unfortunately, more time and cost will be required to use these codes.
• Wear Prediction. The state of the art is inadequate to predict tube wear.
Very little information is available for wear associated with TSP-inactive
modes and data for TSP-active modes are very limited. The detailed
dynamics of tube/support interaction are still not well understood.
• Tube Response and Prediction of Stability. Methods are available to
predict the critical flow velocity of fluidelastic instability and tube
response to various excitations. However, the methods require further
improvement.
ACKNOWLEDGMENTS
Tests of CCW Heat Exchangers were performed by Bechtel Group, Inc., and
Loutech Taiwan, Inc.
Many engineers in the Nuclear Engineering Department of Taiwan Power
Company have contributed to various aspects of the program; among them are Y.
H. Cheng, S. C. Cheng, T. K. Lee, P. C. Kao, F. Y. Lai, H. H. Lee, and P. F. Wang.
This work was performed for Taiwan Power Company under an agreement
with the U.S. Department of Energy under contract agreement 31-109-ENG-38-
85847.
-
21
This work was performed for Taiwan Power Company under an agreement
with the U.S. Department of Energy under contract agreement 31-109-ENG-38-
85847.
1. "Test Report: Vibration of Tubes in Component Cooling Water Heat
Exchangers, Phase 1 Tests," Bechtel Group, Inc., San Francisco, CA,
(September 1984).
2. "Test Report: Vibration of Tubes in Component Cooling Water Heat
Exchangers, Phase 2 Tests," Bechtel Group, Inc., San Francisco, CA,
(October 1984).
3. "Final Report on CCW Heat Exchanger Tube Vibration Test, Third Nuclear
Power Station, Taiwan Power Company," by Loutech Taiwan, Inc.,
(December 1988).
4. Sebald, J. F., and Nobles, W. D., "Control of Tube Vibration in Steam
Surface Condensers," Proc. Am. Power Conf., Vol. XXIV, 630-643 (1962).
5. Moretti, P. M., and Lowery, R. L., "Heat Exchanger Tube Vibration
Characteristics in a 'No Flow1 Condition," Final Report: Tubular
Exchanger Manufacturers Association Experimental Program, Oklahoma
State University (1973).
-
22
6. Shin, Y. S., Jendrzejczyk, J. A., and Wambsganss, M. W., "Effect of
Tube/Support Interaction on the Tube Vibration of a Tube on Multiple
Supports," Argonne National Laboratory, Technical Memorandum ANL-
CT-77-5 (1977).
7. Rogers, R. J., and Pick, R. J., "On the Dynamic Spatial Response of a Heat
Exchanger Tube with Intermittent Baffle Contacts," Nucl. Eng. Des. 36, 81-
90(1976).
8. Chen, S. S., "Vibration of Continuous Pipes Conveying Fluid/' in Flow-
Induced Structural Vibrations, ed. by E. Naudascher, IUTAM-IAHR
Symposium, Karlsruhe, Germany, 1972, pp. 663-675.
9. Pettigrew, M. J., Sylvestre, Y., and Campagna, A. O., "Vibration Analysis
of Heat Exchanger and Steam Generator Designs," Nucl. Eng. Des. 48, 97-
115(1978).
10. Chen, S. S., Flow Induced Vibration of Circular Cylindrical Structures.
Hemisphere Publishing Corp., 1987.
11. Connors, H. J., "Flow-Induced Vibration and Wear of Steam Generator
Tubes," Nucl. Technol., 33, 311-331 (1981).
DISCLAIMER
This report was prepared as an account of work sponsored by an agency of the United StatesGovernment. Neither the United States Government nor any agency thereof, nor any of theiremployees makes any warranty, express or implied, or assumes any legal liability or responsi-bility for the accuracy, completeness, or usefulness of . . , . information, apparatus, product, orprocess disclosed, or represents that its use would not infringe privately owned rights. Refer-ence herein to any specific commercial product, process, or service by trade name, trademarkmanufacturer, or otherwise does not necessarily constitute or imply its endorsement recom-mendation, or favoring by the United States Government or any agency thereof. The viewsand opinions of authors expressed herein do not necessarily state or reflect those of theUnited States Government or any agency thereof.
-
Table 1. History of CCW Heat Exchangers
1. Trains A and B of Unit 1 were placed in service in December 1982, andJanuary 1983, respectively.
2. Tube leakage was discovered in March 1983. Damage was found at supportsand midspans.
3. The manufacturer's action taken after tube leakage:
* Damage was considered to be attributable to inappropriate design of theinlet flow distributor.
• Modifications, as follows, were recommended to alleviate the problem:
a. Replacing the original flow impingement plate by a flow deflector.b. Replacing 306 tubes from each heat exchanger with heavier tubes (8WG
12vs.BWG18).c. Eliminating 114 tubes from each heat exchanger and plugging the holes
in the tubesheets and baffles.
4. The CCW Heat Exchangers of Units 1 and 2 were placed in service in Januaryand February of 1984, respectively, after modifications were made in responseto manufacturer's recommendations.
5. Bechtel Group, Inc. performed Phase-1 test.
Test of Train A after modifications in February 1984. Six tubes at the inletregion and three tubes at the outlet region were instrumented.
Train A was tested again with the flow deflector rotated 90 degrees.
6. Additional modifications were recommended on the basis on the results of thePhase-1 test.
Staking the bottom 14 tube rows in bays 1, 2 and 3.
Installing perforated plates in bays 2 and 3.
-
7. Modifications of Unit 2 were completed in June 1984, and those in Unit 1 werecompleted later.
8. Bechtel Group, Inc. performed Phase-2 test in July 1984.
Train B of Unit 2 and Train A of Unit 1 were tested.
Train B of Unit 2 was retested.
9. Taipower decided to order two new CCW heat exchangers and to modify two ofthe original CCW heat exchangers
10. The modification of the original CCW heat exchanger was completed byTaiwan Machinery Manufacturing Corp. in 1988.
11. Loutech Taiwan, Inc., performed tests on the modified Train B of Unit 1 inSeptember 1988.
12. Taipower and Argonne National Laboratory performed an evaluation of CCWheat exchangers.
-
Table 2. Natural Frequencies in Hz of CCW Tubes
All TSPsActive
2.38B48E+012.47746E+012.61928E+012.80613E+013.02973E+013.28225E+013.55647E+013.84557E+014.14246E+014.43886E+014.72400E+014.98308E+015.19570E+015.33561E+015.416e8E+019.55004E+019.74398E+011.0O413E+02i,04170E+021.08504E+021.13254E+021.18294E+021.23513E+021.28796E+021.34005E+021.38959E+021.43402E+021.46972E+021.49222E+021.52036E+022.24451E+022.27477E+022.32095E+022.37882E+022.44457E+022.51509E+022.58773E+022.66008E+022.72974E+022.79427E+02
TSP 2Inactive
1.13053E+012.39328E+012.49449E+012.65018E+012.84452E+013.062Q9E+013.29786E+013.55885E+013.84635E+014.15166E+014.46243E+014.76359E+015.03460E+015.24556E+015.41605E+016.81634E+019.55977E+019.77727E+011.00993E+021.04873E+021.09095E+021.13550E+021.18346E+021.23522E+021.28941E+021.34393E+021.39611E+021.44234E+021.47717E+021.52035E+021.76043E+022.24604E+022.27996E+022.32972E+022.38855E+022.45133E+022.51733E+022.58778E+022.66092E+022.73303E+02
TSP 3InactJve
9.68389E+002.39275E+012.48674E+012.62322EI012.80663E+013.043B6E+013.32520E+013.63698E+013.96541E+014.28958E+014.54128E+014.72946E+014.99427E+015.22849E+015.41581E+016.49951E+019.55868E+019.76213E+011.00489E+021.04179E+021.08759E+021.14026E+021.19731E+021.25641E+021.31414E+021.35919E+021.39086E+021.43571E+021.47461E+021.52035E+021.70462E+022.24585E+022.27741E+022.32180E+022.37920E+022.44969E+022.52867E+022.61100E+022.69198E+022.76585E+02
TSP 4Inactive
9.53309E+002.39177E+012.47919E+012.62222E+012.B3474E+013.09982E+013.36640E+013.57155E+013.85633E+014.20758E+014.56757E+014.89305E+015.02601E+015.20820E+015.41540E+016.43080E+019.55670E+019.74738E+011.00469E+021.04707E+021.09784E+021.14751E+021.18557E+021.23706E+021.29952E+021.36271E+021.41933E+021.44225E+021.47154E+021.52034E+021.69312E+022.24553E+022.27520E+02 .?.32211E+022.38809E+022.4652BE+022.53571E+022.58937E+022.66472E+022.74758E-I-02
9222233334445,5,5,6,9.9.1.1.1.1.1.1.1.1.1.1.1.1.1,2.2.2.2.2.2.2.2.2.
TSP 5Inactive
.51959E+00
.39064E+01
.47765E+0I
. 63923E-I01
.86230E101
.05253E+01
.29078E+01
.6315SE+01
.97486E+01
.16079E+01
. 4727IE+01
.84508E+01
.34234E+O1
.19770E+01
.41472E+01
.41603E+01
.55442E+0174437E+0100799E+02,05206E+0208902E+0213414E+0219654E+0225808E+0229097E+0234623E+0241092E+0246170E+0247017E+0252031E+0269085E+0224517E+0227486E+0232747E+0239495E+0244902E+0251894E+02 '61017E+0269207E40273149E+02
TSP BInactive
9.51825E+002.38852E+012.49456E+012.62225E+C12.85222E+013.04704E+013.34421E+013.60336E+013.90738E+014.23021E+014.48968E+014.84973E+015.01855E+015.30070E+015.40789E+016.41220E+019.55012E+019.77780E+011.OO463E+O21.05040E+021.08789E+021.14413E+021.19067E+021.24690E+021.30252E+021.35013E+021.41028E+021.44153E+021.4B675E+021.51990E+021.69032E+022.24452E+022.28015E+022.32154E+022.39318E+022.44784E+022.53491E+022.59662E+022.68039E+022.74624E+02
TSPs 2 & l\Inactive
B.29776E+001.25001E+012.39854E+012.50390E+012.65102E+012.85479E+01.3.11S83E+O13.38327E+013.57531E+013.85679E+014.21025E+014.57386E+014.91663E+015.19907E+015.41526E+016.05711E+017.06316E+019.57002E+019.79375E+011.01002E+021.05086E+021.10094E+021.15084E+021.1B641E+021.23711E+021.29995EH021.36372E+021.42288E+021.47022E+021.52033E+02I.63128E+021.80180E+022.24763E+022.28230E+022.32974E+022.39309E+022.468B9E+022.53823E+022.58943E+022.66510E+02
TSPs 3 & AInactive
4.66164E+001.32502E+012.39716E+012.49075E+012.62533E+012.83516E+013.11056E+013.42886E+013.76846E+014.C8698E+014.31113E+014.58220E+014.89624E+015.16138E+015.31758E+015.41642E+017.29944E+019.56835E+019.77076E+011.00526E+021.04718E+021.10005E+021.15936E+021.22136E+021.27918E+021.31901E+021.36535E+021.41980E+0?1.46557E+021.49476E+021.52036E+021.84664E+022.24733E+022.27853E+022.32271E+022.38848E+022.46978E+022.55829E+022.64736E+022.72761E+02
-
Table 3. Natural Frequencies ot the TSP-active Modes of Tubes BWG 12 and 18
Modes
123456789
1011121314151617180920
Tube BWG 12Hz
23.924.826.228.130.332.835.638.541.444.447.249.851.953.454.295.597.4
100.4104.2108.5
Tube BWG 18Hz
21.522.323.625.327.329.632.134.737.440.042.644.946.848.048.886.187.990.593.997.8
-
oFig. 1. Arrangement of Baffles and Support Plates
-
I ' ' I ' ' I ' 'I M i l
I I I f f' ' I '
! • • 1+-»
• ' m 11 ' i • • i ' •
i i i i
15 13 11 9 7
TRAIN A
TUBE FRETTING DAMAGEATSUPPORT
FLATTENED TUBE SURFACE
2/3/4 FLATTENED SURFACESFOUND ON ONE SPAN
flff i
Fig. 2. Damage Inspection of Removed Tubes
-
CCW HXs, Unit 1(Both Train A and B)
Daaage Appeared at Supports as Follows:
EX A EL-3-1£1-26-2E5-1-2/3/4/5/8£5-4-1/2/3/4/6/9E5-51-3/4/6/9£5-54-1/2/3/4/6/8E29-26-6£53-1-1
HX B EL-3-2/4El-26-2/3E5-1-2/4/5/6/7E3-4-2/3/4/5/6/7/9/10/12/13/14E5-51-1/2/3/4/5/6/7E53-4-8/9E53-51-5E53-38-6
El-3-2/4Row 1 (from bottom), tube 3 (fron left) at support plates 2 and 4
Fig. 3. Location of 28 Tubes Selected from Each Heat Exchanger
-
Fiq. 4. Peak-to-Peak Displacements as Function of Flow Rate
5000 1.000e+04 1.500e+04FLOW RATE, gpm
-
1 0 0 200 300 400
Frequency500 100 200 300 400 500
Fig. 5. Frequency Spectra of Tube 1H, a Typical Tube
-
Fig. 6. CCW Heat Exchanger Modified by TMMC
-
13
/ > A / W V A / \ / V A A A A A A y A . V ^ . A y y A^ A A/NyV̂ y V \A/W*V/**/ VVVW yVW VW\A Ay^ A ^ V A A / V W V V V W
\ y V . y v y y ^ y \ A y V / \ y y y v
VVVV^AyY^y^;Ay^Av^r,/^/^AAAA^AA7^y^y^y^yvX/V^/AAAXXA/A/. A/v^Ay^A/Vv^yV^yV^y•vVV^y^AAy^y^Ay^vVAAy^Ay^yvv^y^XAy\X\A,VVVV>AAyVV^AA/kyvV\Ay\AAAyNA/\/V\AAy\A/^yV^AA/VA/Vyv^A-AAy^Ay^A/\y^vv^y^y^/^V•\AyV^Ay\.AA^^y^yVV^AyV^y^ A X X A / /\.-••%Ayv\Ay^/VV
NAyV^yV^y^y^Ay^AAy^AyVV^y^y^Ay^AAA/v^/V^AAX
VV^AAXXAy^Ay•VVVV^AyXAyVN''
A.AyNy^cVAAy^yVVAyVAAy^AXy^AAAAAAAAj^ «- A ~ - - ' - AAAy%* 9
^y\Ay\yV
\A A * /s A X A A A \ X \ ' V V V ' - VV VV VVV V VVVN W V V W V VV ' vf v v V V V-' VV V W v V W \AyOC^XYAYAi/VY^^^ 1 ,̂ AAv^Ay^Av^A.̂ A.VVVV^AAAv^A'
NAAA^y^AAy^y^AAAAXy^AOOOOvAA A ^ y ^ ^ ' ^ ' ^ \AAyVV^y\AA^%A/vV\AAAA^VAyV\A/Ay^WNyA^"A,A.AAA/WA-VWW\.XyVV\AAAA'WW/OO^^YXVVYV , ' w ̂ '"^Wvv^A-V\/VVVV\Ay^AyvVAA-• AAAAyV^A,rtv^y\AyVV\A.XAA/Jr ŷv̂ Aŷ A.-• •AyV^-^AAAAAAAAAAAy\AA.-.-AAA.\/V\A'5 AAAy\A_Ay\AA/\AA "AAA/
\A/VVVV\AvT^/\Ay\yv\AA AAyAA/\AAAA/\Ay\AAAAAA/\AAAy
\ A - - H p V ^ y
INLET INSTRUMENTATION DEPTH
A 25.5 !N. (TUBE 1-4 & 20, GROUP A)
• 65 IN. (TUBE 5-9 &19, GROUP B)
• 107 IN. (TUBE 10-15, GROUP C)
• 149 IN. (TUBE 16-18, GROUP D)
OUTLET INSTRUMENTATION DEPTH
• 25 IN. (TUBE 11 & 2', GROUP E)
X 64.25 IN. (TUBE 3'-5\ GROUP F)
• 106 IN. (TUBES 61 & T, GROUP G)
Fiq. 7. Instrumented Tubes
-
11C-H
4\; • • • ? * ! •
TV. 1 . . : . ,
Ullllu
J •:
fBjnriT
; i H 5 4 i
Liiiiiillllyi'iiiiiiiiiii,
' . • • • • ! •
gpm
145,000
11C-V
140,000
130,000
120,000
110,000
qj...j..4...j....j 100,000
90,000
76,000
•*3i:
J : : :
=..; (I
iuiOl
i! H
yil
T e l•••••!• •{••ii-
!G jn?
U : :"
..J....
.!*...:
iiiiliiibui....
60,000
140 0 140
Frequency, Hz Frequency, Hz
Fiq. 8. Frequency SDectra of Tube 11C
-
TSP-InactiveModes
mtnu
TSP-ActiveModes
Tube 1A-H10,000 gpm
140.
TSP-InactiveModes
ml nut
TSP-ActiveModes
Tube 2A-H145,000 gpm
P-Q.
140.
Fig. 9. TSP-Inactive and TSP-Active Modes
-
TSP-Inactive Modes
mlnuTube 5F-H1200 GPM
TSP-Active Modes
Tube 5B-V7000 GPM
Hz. 140.
Fig. io. Either TSP-Inactive or TSP-Active Modes Are Dominant
-
TUBE 1A-V
0.1
EBUJQ
0.011000 10000
FLOW RflTE, gpm
100000
0.1
£
LUQ=3H
0.011000
TUBE 1A-H
10000
FLO ID RflTE, gpm
100000
Fig. 11. Displacement of Tube 1A
-
TUBE 5B-V
£UiQ
t o.i-Ja.z
0.011000 10000
FLOW RflTE, gpm100000
TUBE 5B-H
ESuuQ
to.i
z
0.011000 10000
FLOW RflTE, gpm100000
Fig. 12. Displacement of Tube 5B
-
0.1TUBE11C-Y
E£
o3
0.011000 10000
FLOW RflTE, gpm100000
0.1 TUBE 11C-H
10000FLOW RflTE, gpm
100000
Fig. 13. Displacement of Tube 11C
-
CM
CM
CO
-
1ST MODE, 23.9 HZ
3RD MODE, 26.2 HZ
4TH MODE, 28.1 HZ
5TH MODE, 30.3 HZ
TSP-flCTlUE MODES
Fiq. 15. The First Five Modes of TSP-Active Modes
-
1ST MODE, 11.3 HZ
2ND MODE, 23.9 HZ
3RD MODE, 24.9 HZ
4TH MODE, 26.5 HZ
5TH MODE, 28.4 HZ
TSP 2 SNflCTlUE
Fig. 16. The First Five Modes of TSP-Inactive Modeswhen TSP 2 is Inactive
-
8.30 HZ
12.5 HZ
TSP2 RNDTSP 4 INRCTIUE
4.66 HZ
13.25 HZ
TSP 3 HND TSP 4 INflCTlUE
Fiq. 17. The Fi rs t Two Modes for TSPs 2 and 4 Inactive andTSPs 3 and 4 Inactive
-
TSP 2 INflCTlUE 11.31 HZ
TSP 3 INflCTlUE 9.68 HZ
TSP 4 INflCTlUE 9.53 HZ
TSP 5 INflCTlUE 9.52 HZ
TSP 8 INflCTlUE 9.52 HZ
Fig. 18. The First TSP-Inactive Mode for One TSP Inactive
-
FIRST
STOPPING
BANDFIRST
PASSINGBAND
SECONDSTOPPING
BAND
SECONDPASSING
BAND
'7/777.
OHZ 50 HZ 100 HZ 150 HZ
Fig. 19. Frequency Bands for Tube BWG12