Masibambane Water Services Sector Coordinating Committee Meeting 22 February 2007 STRATEGIC OVERVIEW OF WATER SECTOR PROGRESS FOR THE 3 rd QUARTER 2006/2007 AND KEY ISSUES FOR THE 4 th QUARTER Kalinga Pelpola Masibambane Programme Manager

description

Masibambane Water Services Sector Coordinating Committee Meeting 22 February 2007. STRATEGIC OVERVIEW OF WATER SECTOR PROGRESS FOR THE 3 rd QUARTER 2006/2007 AND KEY ISSUES FOR THE 4 th QUARTER. Kalinga Pelpola Masibambane Programme Manager. INDEX. - PowerPoint PPT Presentation

Transcript of Masibambane Water Services Sector Coordinating Committee Meeting 22 February 2007

Page 1: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

Masibambane Water Services Sector Coordinating Committee Meeting

22 February 2007

STRATEGIC OVERVIEW OF WATER SECTOR PROGRESS FOR THE 3rd

QUARTER 2006/2007 AND KEY ISSUES FOR THE 4th QUARTER

Kalinga Pelpola

Masibambane Programme Manager

Page 2: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

• Sector Highlights

• President’s State of the Nation Address – 9 Feb 07

• National Budget Speech 2007/8 – 21 Feb 07

• Challenges for the Sector

• Key findings for the 3rd Quarter 2006/07

• Financial Summary – 3rd Quarter and YTD

• Key issues for 4th Quarter 2006/07

• Conclusion

INDEX

Page 3: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

Another award…The VUNA Award for Local Government Support was awarded to DWAF by the Minister DPLG. This achievement highlights the

successful collaboration between DWAF, DPLG and SALGA.

HIGHLIGHTS

15 December 2006

Page 4: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

• Cabinet Lekgotla – January 2007, and key issues affecting WS;

• Sector Collaboration with Business Partners for Development;

• SA and Netherlands signed “Partner for Water” Agreement on 5 December 2006;

• Swiss/SA annual consultation held on Sunday 18 Feb 07 in Cape town;

• Completion of Provincial Water Sector Plans; and

• Progress towards finalisation of National WS Programme III 2007/8- 2012/12 = National WS Strategy + National WS Work plan

HIGHLIGHTS

Page 5: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

• Address challenges of poverty, unemployment and marginalisation of communities;

• Accelerate economic growth and development (6% pa);

• Apply Batho Pele principles to improve effectiveness of social development programmes and institutional operational efficiency;

• Support local government sphere as per the Five Year Local Government Strategic Agenda;

• Speed up skills development and fill vacancies of senior management and professionals in municipalities;

• Align planning instruments across the spheres of government (i.e. National Spatial Development Perspective, Provincial Growth and Development Strategies and Integrated Development Plans);

PRESIDENT’S STATE OF THE NATION ADDRESS – 9 Feb 07

Page 6: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

PRESIDENT’S STATE OF THE NATION ADDRESS – 9 Feb 07

Expand access to services such as water, electricity and

sanitation and ensure the objectives of the MDG’s and

government’s service delivery targets are achieved: – Bucket eradication in formal settlements – Dec 2007;– Eradication of water supply backlog – 2008;– Eradication of sanitation backlog – 2010;– Eradication of clinic water and sanitation backlog – 2007;

Integrate youth development into the mainstream of

government work; Increase the roll-out of the low cost housing programme

(and by implication water and sanitation services); Strengthen monitoring and evaluation capacity across all

spheres; and Accelerate implementation of NEPAD Programmes.

Page 7: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

FINANCE Minister'sBudget Speech – 21 Feb 07

Human life has equal worth…

Motho Motho ke motho - ga ana bosehlana (a human being is a human

being, there is no lesser human being)

The idea, that human life has equal worth, and that this is the core value that

unites us, invites us to ask whether we have done enough to give practical

effect in SA today to our shared humanity. Have we acted in a manner that

shows that human life has equal worth?

Reconfirmation of service delivery targets & availability of additional

funding;

Funding mechanisms;

Sound management of public finance

Structural unemployment (mismatch of skills);

Capacity and skills development

Page 8: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

DWAF CHALLENGES FROM PRESIDENT’S ADDRESS

• Challenges: - Lack of skills and public service capacity;

- Meeting the water and sanitation targets;

- Effective implementation of Local Government Support Programmes;

- Monitoring and information management;

- Poverty eradication through economic opportunities in the WS;

- Supporting delivery of MDGs in Africa/Nepad with special focus on emerging democracies e.g.; DRC,Liberia

• Issues to be addressed:- Promote effective sector collaboration;

- Improve leadership within DWAF management;

- Decentralisation and empowerment of DWAF Regional Offices;

- Engage Institutions of Higher Learning to fast track talent building

Page 9: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

• Overall Water Sector Budget 2006/7 = R12,87bn - Expenditure to date (excl. Equitable Share, LGFM Grants, Drought relief)

=40,2%

• Good progress DWAF expenditure (Quadrant 1)- DWAF WS expenditure (capital + recurrent) = 64,3%

Expenditure assessment, budget re-allocation and revision of FD;

• Low expenditure on MIG Funding (Quadrant 2)- MIG Capital expenditure = 36,9%

Working with dplg on re-allocation of MIG budget to munics;

- Equitable Share unconditional grant, no report on expenditure from WSA’s Will call a high level meeting between DWAF and DDG: PC dplg to discuss strategy and

way fwd;

• Capacity Building Grants (Quadrant 4)- MSIG Grant = 30,7%- LGFM Grant = updated expenditure figures not available from DPLG- KFA 12 = 48%

The trend on under expenditure continues – this is a serious issue and was brought to the notice of DDG:PC at dplg and will be dealt with at the high level meeting;

Issue addressed partly in the PSSIP

MIGLP

(32,2%); MP

(18,5%);

KEY FINDINGS - QUARTER 3(See Volume I, pages 12-18 of 206)

Page 10: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

*unverified MIG sanitation data (not yet confirmed by dplg) is provided by DWAF Sanitation unit

SERVICE DELIVERY PROGRESS - QUARTER 2

Water Sector Progress - Financial Year 2006/2007

Quarter 3 (October to December 2006) Activity Annual Sector

Target

YTD Sector1

DWAF DPLG3 DOE Health Housing

Access to Services

Household

Water

1,500,000

people

1,414,189 people 0 n/a - - n/a

Household

Sanitation

350,000

households

291,013

households

0 150,637 - - n/a

School Water 597 schools 324 schools - - n/a - -

School

Sanitation

2,211 schools 621 schools - - n/a - -

Clinic Water4 79 clinics 8 clinics - - - n/a -

Clinic

Sanitation4

155 clinics 11 clinics - - - n/a -

Bucket

Eradication

80,000

households

50,565

households

8,427 - - -

Health &

Hygiene

n/a n/a - - - -

FBW

provision

75% people 74,65% (of total population) served with FBW;

165 out of 170 WSA’s providing FBW

Chinese

development

aid (PTD2)

3,066km of uPVC pipes installed;

163,727 water meters installed

*

Page 11: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

The total number of job days created by the MIG programme to end September 2006 amounts to 20,287,959 job days, of which 34,52%

(7,004,387) are woman job days and 35,52% (7,206,943) youth job days. This is however not specific to the water sector.

SERVICE DELIVERY PROGRESS - QUARTER 2

Water Sector Progress - Financial Year 2006/2007

Quarter 3 (October to December 2006) Activity Annual Sector

Target

YTD Sector1

DWAF DPLG3 DOE Health Housing

Institutional Development & Performance

Policy and

Strategy

WS

Amendment

Bill by Mar’05

Guideline document on Small Scale & Productive uses of water at

household level is being finalised;

Guideline Document on Private Land is being piloted in 3 DM’s;

draft 2: National Water Services Bill produced.

IGR and

sector

collaboration

WS functioning Gauteng Sector Forum launched;

Provincial sector meetings held in EC, KZN, EC, FS, and NC.

Provincial WS Plans reviewed.

LG Support DWAF 5-Year Local Government Water Sector Support Plan

Support provided to municipalities through Project Consolidate.

WSDP 155 WSDPs

received by

Mar’05

Support currently provided to 155 municipalities

2006/07 = WSDP’s in various stages of development.

Drinking

Water Quality

Number of health related DWQ failures – EC(14), LP(4), NW(148 borehole

samples), FS(10), WC(6), MP(2)

WSA’s

Checklist

154 WSA’s checklist interviews completed

122 checklist results signed off and adopted by some sort of Committee,

Council or Executive Manager.

Transfer of

Schemes

58 transfer

agreements &

318 schemes

transferred by

March 2006

52 transfer agreements concluded (1 in circulation awaiting Minister’s

approval

304 of the original 318 water schemes identified in the Funational

Assessment transferred;

Total 1,628 schemes transferred in accordance with TA’s.

Page 12: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

FINANCIAL SUMMARY

Quadrant 1 DWAF

WSS specific

Quadrant 3Not WSS

specific

Quadrant 2Non DWAF

WSS specific

Quadrant 4Non DWAF

Non WSS specific

Capital – R479mRecurrent R 1,104bn

Capital – R nilRecurrent – R 66mNot WSS specific

Capital MIG – R 2,282bnCapital DFID – R 14m

Recurrent – R 2,679bn

1

3 4

2Quadrant 1

DWAF

WSS specific

Quadrant 3

DWAFNot WSS specific

Quadrant 2

Non DWAF

WSS specific

Quadrant 4

Non DWAF

Non WSS specific

Capital – R358mRecurrent R 1,126bn

Capital – R nilRecurrent – R 39mDrought Relief: R793m

Capital – R4,817bn

Recurrent – R6,320bn

2006/2007 WS Grand total budget = R12,869bn

1

3 4

2

Page 13: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

EXPENDITURE ANALYSISQUADRANT 1: DWAF WATER SERVICES

Quadrant 1: DWAF - Water Services Specific

Budget Expend.

R'000 R' 000

Capital

- DWAF Funding

> Indirect Grant to Capital Projects - - -

> Management Support Overheads 71,470 31,514 44%

- Donor Funding (EU, DCI, Flemish, Swiss 286,820 137,301 47.9%

> EU 231,736 112,666 48.6%

> DCI 46,556 17,871 38.4%

> Flemish 5,528 3,764 68.1%

> Swiss 3,000 3,000 100.0%

358,290 168,815 47.1%

Recurrent

- Department Baseline 273,602 150,594 55.0%

- Indirect Grant Water Services Operating Subsidy 990,500 375,309 37.9%

1,264,102 525,903 41.6%

Total 1,749,071 1,123,783 64.3%

2006/2007

% Expenditure

Page 14: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

QUADRANT 1: DWAF EXPENDITURE PER PROVINCE

Province

Q1 June 06 - Cumulative

Expenditure YTD

Q2 - Sept 06 Cumulative

Expenditure YTD

Q3 - Dec 06 Cumulative

Expenditure YTD2006/2007 RFD

Sept 06%

ExpenditureCC 377,327 1,342,145 4,457,567 4,420,000 100.8%EC 3,375,484 10,155,729 12,977,181 30,870,000 42.0%FS 820,369 2,691,813 7,579,410 17,225,000 44.0%GT 899,060 6,665,781 12,401,131 19,550,000 63.4%HO 14,712,989 39,193,609 62,167,371 129,377,000 48.1%KN 371,101 670,001 2,928,420 10,348,344 28.3%LP 9,799,807 15,334,942 24,530,114 57,388,612 42.7%MP 4,492,715 9,187,163 14,107,479 34,222,000 41.2%NC 547,459 1,290,506 5,617,910 13,648,000 41.2%NW 3,803,452 3,815,074 8,014,160 23,346,050 34.3%WC 548,655 5,028,396 14,034,265 17,895,000 78.4%

Grand Total 39,748,418 95,375,158 168,815,008 358,290,006 47.1%Note: 2006/2007 RFD Sept 06 = DWAF Budget 2006/2007 FY

As at 5 February 2007, total BAS expenditure = R168,815,008 (47,1%)

0

20,000,000

40,000,000

60,000,000

80,000,000

100,000,000

120,000,000

140,000,000

Am

ou

nt

CC EC FS GT HO KN LP MP NC NW WC

Province

Quadrant 1: DWAF Capital Expenditure per Region

Q1 June 06 - Cumulative Expenditure YTD Q2 - Sept 06 Cumulative Expenditure YTD

Q3 - Dec 06 Cumulative Expenditure YTD 2006/2007 RFD Sept 06

GP (63,4%);

WC (78,4%);

KZN (28,3%);

NW (34,3%)

Page 15: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

QUADRANT 1: EXPENDITURE PER KFA

OVERALL WATER SERVICE PROGRAMME

2006/2007

Expenditure Dec 06

MTEF Budget of

Prog 3

Donor Budget

Total Budget

Exp vs.

Total Budget

R' 000 R' 000 R' 000 R' 000 %

KFA 10 – Water & Sanitation Services 70,635

21,131 78,147 99,278 71%

KFA 11 – Water Sector Support 142,279 119,911 99,806 219,717 65%

KFA 12 – Institutional Support 70,968 57,109 91,617 148,726 48%

KFA 13 - Transfers 1,110 15,480 5,500 20,980 5%

KFA 14 – African Participation 0 400 2,500 2,900 0%

KFA 18 – Water Services Admin 81,466 116,096 0 116,096 70%

KFA 21 – Operation of Water Services 753,331 1,132,124 0 1,132,124 67%

KFA 6 – Water Resource Interface 3,994 0 9,250 9,250 43%

1,123,783 1,462,251

286,820 1,749,071 64%

Page 16: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

EXPENDITURE ANALYSISQUADRANT 2:

NON-DWAF WATER SERVICES

Quadrant 2: Non-DWAF - Water Services Specific

Budget Expen WS Budget WS Expend.

R'000 R'000 R' 000 R' 000

Capital

- Municipal Infrastructure Grant - MIG (61,49%) 5,865,300 3,606,573

- Eradication of Bucket Sanitation - (100%) 400,000 400,000

- Dept. of Education

Provincial Infrastructure Grant (2.5%) 4,118,000 - 102,950 - 0%

- Dept. of Health

Hospital Revitalisation Grant (5%) 1,440,000 1,114,100 72,000 55,705 77%

- Dept. of Housing

Integrated Housing and Human Settlement Dev Grant (10%) 6,350,000 4,171,909 635,000 417,191 66%

- Cities Network 139,000 - 0%

18,312,300 7,596,231 4,816,523 1,893,451 39.3%

Recurrent

- Equitable Share 18,057,940 6,320,279 0%

18,057,940 0 6,320,279 0 0.0%

Total 36,370,240 7,596,231 11,136,802 1,893,451 17.0%

2006/2007

% WS Expenditure

2,310,222 1,420,556 36.9%

Page 17: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

QUADRANT 2: MIG EXPENDITURE PER PROVINCE

Province

MIG BUDGET 2006/07 as per

DoRA

Estimated MIG WS Budget 2006/2007 (61.49% of DoRA

allocation)

Q1 - MIG WS Cumulative

Expenditure (Apr - June 2006)

Q2 - MIG WS Cumulative

Expenditure (Apr - Sept 2006)

Nov 06 - MIG WS Cumulative

Expenditure (YTD)

% MIG WS Expenditure

2006/07EC 1,288,257,481 792,149,525 90,666,180 215,876,761 313,033,859 39.5%FS 563,895,790 346,739,521 26,003,245 73,975,931 120,773,178 34.8%GT 898,553,840 552,520,756 30,456,614 109,831,040 183,334,321 33.2%KZ 1,262,412,326 776,257,339 80,068,598 191,187,747 284,567,544 36.7%LP 821,263,702 504,995,051 29,597,305 92,183,743 162,644,031 32.2%MP 470,283,899 289,177,569 10,112,381 28,668,533 53,587,422 18.5%NW 525,573,629 323,175,225 14,589,333 93,701,591 160,200,755 49.6%NC 130,922,167 80,504,040 7,116,034 12,219,255 26,404,230 32.8%WC 304,136,901 187,013,780 25,671,965 86,327,909 116,009,996 62.0%

Grand Total 6,265,299,735 3,852,532,807 314,281,656 903,972,510 1,420,555,335 36.9%

0

100,000,000

200,000,000

300,000,000

400,000,000

500,000,000

600,000,000

700,000,000

800,000,000

Am

ou

nt

EC FS GT KZ LP MP NW NC WC

Province

MIG Water Services Expenditure per Province

Estimated MIG WS Budget 2006/2007 (61.49% of DoRA allocation) Q1 - MIG WS Cumulative Expenditure (Apr - June 2006)

Q2 - MIG WS Cumulative Expenditure (Apr - Sept 2006) Nov 06 - MIG WS Cumulative Expenditure (YTD)

MIGNW (49,6%);WC (62,0%

%)

MIGMP

(18,5%); LP

(32,2%);

Page 18: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

ProvinceEquitable Share Sector

Budget 2006/07WS - Equitable Share (35%) Budget 2006/07

Equitable Share Expenditure June 2006

EC 2,308,185,000 807,864,750FS 1,222,029,000 427,710,150GT 5,107,755,000 1,787,714,250KZ 3,091,031,000 1,081,860,850LP 1,565,837,000 548,042,950MP 1,284,092,000 449,432,200NC 424,513,000 148,579,550NW 1,202,687,000 420,940,450WC 1,851,811,000 648,133,850

Grand Total 18,057,940,000 6,320,279,000

0200,000,000400,000,000600,000,000800,000,000

1,000,000,0001,200,000,0001,400,000,0001,600,000,0001,800,000,000

Am

ou

nt

EC FS GT KZ LP MP NC NW WC

Province

Quadrant 2: WS Portion of Equitable Share per Region

WS - Equitable Share (35%) Budget 2006/07 Equitable Share Expenditure June 2006

QUADRANT 2: EQUITABLE SHARE

Note: Equitable share is an unconditional grant – no reports submitted by WSA’s

Page 19: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

QUADRANT 3: DWAF NON-WATER SERVICES

(DROUGHT RELIEF FUNDING PER PROVINCE)

ProvinceDR Exp Dec 06 (approved for

payment)Total Gazetted D/Relief

allocation % DR ExpenditureEastern Cape 106,404,429 138,726,000 76.7%Free State 11,850,066 18,528,000 64.0%Gauteng 25,443,309 27,524,000 92.4%KwaZulu Natal 187,201,543 198,529,000 94.3%Limpopo 102,067,389 151,218,000 67.5%Mpumalanga 40,721,891 45,856,000 88.8%North West 57,487,932 97,768,000 58.8%Northern Cape 70,284,699 77,640,000 90.5%Western Cape 19,845,960 36,251,000 54.7%

Grand Total 621,307,218 792,040,000 78.4%

Quadrant 3: Drought Relief Funding as at December 2006

0

50,000

100,000

150,000

200,000

250,000

Province

Am

ou

nt

(R '0

00

)

DR Exp Dec 06 (approved for payment) Total Gazetted D/Relief allocation

Page 20: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

Notes:

• Q3 LGFM grant information not available from DPLG at the time of preparing this report.

• Local Government Restructuring Grant will not be used for capacity building and support in the water sector

EXPENDITURE ANALYSISQUADRANT 4: NON-DWAF, NON WATER SERVICES

(CAPACITY BUILDING GRANTS)

Quadrant 4: Non-DWAF - Non-Water Services Specific

Budget Expen WS Budget WS Expend.

R' 000 R'000 R' 000 R' 000

Capital

- None - - 0

Recurrent

- Local Government Financial Management Grant 198,700 - 19,870 0.0%

- Local Government Restructuring Grant 350,000 - - -

- Municipal Systems Improvement Grant 200,000 61,404 20,000 6,140 30.7%

748,700 61,404 39,870 6,140 15.4%

Total 748,700 61,404 39,870 6,140 15.4%

2006/2007

% WS Expenditure

Page 21: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

• Finalisation of NWSP 2007-12 and work plan & financial delegation 2007/8

• Towards a communication & change management plan to better understand WfGD

• High level meeting between DWAF & dplg and SALGA;

• Bi-lateral engagement between DWAF & DoHealth;

• Extension of the WS M&E reporting into WR + Forestry and impact assessment of WS programmes;

• WS/WR interface and alignment;

• Support dplg/munics towards meeting target;

• Support for acceleration of the sanitation delivery and bucket eradication;

• Support municipalities through Project Consolidate;

• Finalisation of DWAF LG Water Sector Support Plan;

• Towards establishment of Siyense Manje ‘water sector’ unit in collaboration with DBSA/dplg/SALGA & DWAF

KEY ISSUES FOR THE 4TH QUARTER 2006/07

Page 22: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

• Implementation of partnership agreement between the

Private Sector and knowledge sharing agencies in

Netherlands & SA: – Support the water sector in SA through Partnership with Private

Sector and sharing & transferring expertise and experience available in the Dutch WS and SA.

• Support SADC and NEPAD through DWAF and WSP-AF

Strategic Cooperation Alliance : – Assist with poverty reduction programmes throughout Southern

Africa and in other NEPAD countries;

– Partnerships in the accelerated delivery of WS MDG’s in Africa;

– Sharing knowledge and best practice through WIN

KEY ISSUES FOR THE 4TH QUARTER 2006/07 (cont…)

Page 23: Masibambane Water Services Sector  Coordinating Committee Meeting 22 February 2007

• In view of consultations held with provincial and national

stakeholders, progress reports for the 3rd quarter

2006/2007 were compiled into:– Volume I: Consolidated Water Sector Report

– Volume II: Regional Reports

– Volume III: Sector Partner Reports

• It is recommended that the above reports are formally

accepted by the WSSCC, subject to incorporation of the

comments made today at the meeting.

THE END

CONCLUSION