Manchester Metropolitan University
Design, Manufacture & Erection of Precast Concrete Frame
Mark Gilliland, Estimating Manager CCPL
Introduction
Creagh Concrete Products Ltd.
• Core BusinessDesign, Manufacture, Supply & Installation of Concrete, Concrete Products & Aggregates
• Standard Products• Hollowcore flooring• spanTherm flooring• Stairs & Landings• Agricultural products• Small precast • Bradstone• Aggregates, Blocks & Concrete
![Page 2: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/2.jpg)
15/06/2017
2
Introduction• Bespoke Products
• Wall panels (cross wall)• Sandwich panels• Architectural cladding• Retaining walls• Columns & Beams• Terrace units• Plate flooring• anything else made of concrete
• Recent & Current D&B Projects• Cowes School, Isle Of Wight• Greenwich Student Accommodation, London• Library Building, Univeristy of Roehampton• Apartment Development, Aberdeen• Blackpool MSCP, Blackpool• HMP The Mount, Hemel Hempstead
The process from tender to site
• Tender • 3D Modelling• Design & Detailing• Manufacturing• Logistics• Site Erection
![Page 3: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/3.jpg)
15/06/2017
3
Case Study – MMU
Project OverviewDesign & Erection• Columns & Beams• Plate flooring & Hollowcore slabs• Wall panels• Stairs & Landings• Terrace units
Creagh Team• Design & Detailing - 5 engineers, 11 detailers• Manufacturing - 60 personnel at 3 sites - Toome, Ardboe,
and Hoveringham• Site erection - 42 personnel
Concrete Statistics• 26,170 tonnes of precast concrete• Heaviest piece 28.7 tonnes• 5936 tonnes of insitu concrete
![Page 4: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/4.jpg)
15/06/2017
4
Project Overview
Precast package consisted of :-
– 327 columns– 546 beams– 325 wall panels– 55 stair flights– 64 ‘landing’ slabs– 36 terrace units– 753 plate flooring units– 134 hollowcore slabs– 16,333m2 of plate flooring & hollowcore slabs– 2240 pieces
Project Value £6.3M
Floor SlabsPlate Flooring and
Prestressed Hollowcore
![Page 5: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/5.jpg)
15/06/2017
5
![Page 6: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/6.jpg)
15/06/2017
6
Typical Design – Stage 1Worst case 11.45m effective span Live load during construction 1.5 kN/m2Slab self weight 5.44 kN/m2 (precast + void formers + insitu)Props at maximum 2.4m centresBackpropped a minimum of two levelsGirder designed for buckling to EC3180mm girder depthTop bar H10Bottom bars H6Diag. bars H7
Unpropped Design – Stage 1 5.2m effective span at 3rd floor, no lower floor levels under this areaTo avoid erecting an expensive and time consuming propping system from ground up to this level, an unproppedsolution was designed for these slabs.Girder depth increased to 220mmTop bar H16Bottom bars H6Diag. bars H8
![Page 7: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/7.jpg)
15/06/2017
7
![Page 8: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/8.jpg)
15/06/2017
8
![Page 9: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/9.jpg)
15/06/2017
9
Typical Design - Stage 2Loading – Live 3kN/m2
- Partitions 1 kN/m2- Finishes 0.44 kN/m2- Ceiling and Services 0.5 kN/m2- Slab self weight 5.44 kN/m2
Minimum Natural Frequency 4Hz
Exposure class XC150 year design life60 mins fire resistanceMovement after installation limited to span / 350 (Non-brittle floor finishes)Long term deflection limited to span / 250
Control of Temporary WorksProp release strategy – permit to load, access and unload
![Page 10: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/10.jpg)
15/06/2017
10
![Page 11: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/11.jpg)
15/06/2017
11
Stair & Lift Cores
Precast wall panels, stairs and landing slabs
![Page 12: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/12.jpg)
15/06/2017
12
![Page 13: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/13.jpg)
15/06/2017
13
![Page 14: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/14.jpg)
15/06/2017
14
![Page 15: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/15.jpg)
15/06/2017
15
![Page 16: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/16.jpg)
15/06/2017
16
The Structural Engineer - January 2014
Production
![Page 17: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/17.jpg)
15/06/2017
17
![Page 18: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/18.jpg)
15/06/2017
18
![Page 19: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/19.jpg)
15/06/2017
19
![Page 20: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/20.jpg)
15/06/2017
20
![Page 21: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/21.jpg)
15/06/2017
21
Site
![Page 22: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/22.jpg)
15/06/2017
22
![Page 23: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/23.jpg)
15/06/2017
23
![Page 24: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/24.jpg)
15/06/2017
24
![Page 25: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/25.jpg)
15/06/2017
25
17m Circular Column
![Page 26: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/26.jpg)
15/06/2017
26
![Page 27: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/27.jpg)
15/06/2017
27
Atrium Stair
![Page 28: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/28.jpg)
15/06/2017
28
![Page 29: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/29.jpg)
15/06/2017
29
![Page 30: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/30.jpg)
15/06/2017
30
Programme
Last piece being fitted 31st May 2013Creagh erecting for 20 weeks on site, to the hour. 2240 precast pieces, steel members in addition to this.
![Page 31: Mark Gilliland, Estimating Manager CCPL...Microsoft PowerPoint - MMU Birley Fields Powerpoint Presentation - Mark Gilliland.pptx Author Patienceg Created Date 6/20/2017 11:48:50 AM](https://reader036.fdocuments.in/reader036/viewer/2022070109/6045bcc9f59ecd5de07a3c13/html5/thumbnails/31.jpg)
15/06/2017
31
Summary
• Project ran according to programme
• Main contractor extremely satisfied
• Design and erection by Creagh worked out very efficiently
• High quality concrete elements
Thank you for your attention