Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

35
Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

description

Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005. Demographics. Kentfield Campus (KTD) - Kentfield Built – Original Buildings Date Back to 1926 Acreage – 87 Acres / 373,806 sf / 18 Buildings Parking – 1,774 Indian Valley Campus (IVC) – Novato - PowerPoint PPT Presentation

Transcript of Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Page 1: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Marin Community College DistrictCampus Organizations’ Briefing

Week of September 19-23, 2005

Page 2: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Demographics

Kentfield Campus (KTD) - Kentfield Built – Original Buildings Date Back to 1926 Acreage – 87 Acres / 373,806 sf / 18 Buildings Parking – 1,774

Indian Valley Campus (IVC) – Novato Built – 1975 Acreage – 333 Acres / 171,549 sf / 22 Buildings Parking - 900

Bolinas Marine Biology Center Partial Modernization – 1964 Acreage - .5 Acres / 4,178 sf / 3 Buildings & a Dock

District-wide 6,943 Students 4,049 Student FTES 340 Faculty and Staff

Page 3: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Kentfield CampusTentative Project List

Modernization of Learning Resource Center – 66,000 gsf Modernization of Harlan Center – 25,651 gsf Modernization of Fusselman Hall – 14,717 gsf Modernization of Science Center – 50,837 gsf Modernization of Fine Arts Center – 79,636 gsf Modernization of Student Center – 36,227 gsf Modernization of Diamond Physical Ed Center – 36,392 gsf Multi-purpose, Child Care & Support Facility – 75,000 gsf – New

Construction Liberal Arts Complex or Science Building - 75,000 gsf – New Construction Facilities Maintenance Center 30,000 gsf – New Construction Gateway Entrance Plaza – New Construction

Page 4: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Kentfield Campus (KTD)

Page 5: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005
Page 6: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005
Page 7: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Indian Valley CampusTentative Projects List

Modernization of Pomo Center - 47,494 gsf Modernization of Administrative & Children’s Center - 19,588 gsf Capital Renewal & Expansion of Central Plant - 2,000 gsf Capital Renewal of Library – 14,280 gsf Capital Renewal of Miwok Cluster – 28,410 gsf Capital Renewal of Ohlone Cluster – 20,543 gsf New Pedestrian & Bicycle Bridges (removal of (2) construction bridges) Stream Erosion Mitigation

Page 8: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Indian Valley Campus (IVC)

Page 9: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Bolinas Marine Biology Center

Modernization or New Construction – 3,333 gsf

Page 10: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

District-WideTentative Projects List

Telecommunications Infrastructure

Site Parking & Roadways Utilities (Sanitary, Storm, Electrical, Gas)

Fire Alarm Replacement Access Controls / Security ADA Accessibility Wayfinding

Page 11: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Preliminary Schedule (DRAFT)

Page 12: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Preliminary Schedule (DRAFT)

Page 13: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Preliminary Schedule (DRAFT)

Page 14: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Program Schedule

District-Wide Consultants Assessment Studies - September 2005 to December 2005 Systems Analysis - September 2005 to December 2005

Space Inventory (update to Chancellor’s Office by 10/1/05)

Educational Master Plan (EMP) Preliminary - November 2005 Final - April 2006

Page 15: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Program Schedule (cont.)

Master Planning/District Standards - October 2005 to April 2006 Environmental Review - January 2006 to November 2006 Program Definition Document - September 2005 to April 2006 Kentfield Campus Initial Project Programming

December 2005 to March 2006 Indian Valley Campus Initial Project Programming

December 2005 to March 2006

Page 16: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

District Architect

Campus Master Planning Design & Drafting Guidelines Interior & Exterior Finish Standards Furniture, Fixtures & Equipment Standards

Page 17: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

District Landscape Architect

Services Master Planning District Standards Design Guidelines

Page 18: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

District Civil Engineering

Update all Surveys (Topographic & Boundary) Locate, map, Identify, Inspect & Analyze all Utilities Identify all Easements & Encumbrances on District

Property Create Accurate Electronic “As-Built” / Record

Drawings that Record all Above Information Develop District Standards and Design Guidelines

Page 19: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

District Geotechnical Engineering

Collect and Synthesize all Existing Soils Testing and Analysis Information

Recommend and/or Perform Additional Soils Testing & Analysis

Perform Geologic Hazards Analysis Provide Design parameters for Building and

Infrastructure Design

Page 20: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Mechanical and Plumbing Engineering

Chilled Water Systems Heating Hot Water Systems Co-Generation / Central Plant Systems Water Distribution Systems Building and Site Mechanical Systems Savings by Design Building and Site Control Systems

Page 21: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Electrical Engineering

Substations Co-Generation Electrical Distribution Systems Lighting Savings by Design Control Systems MCC

Page 22: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

California Environmental Quality Act (CEQA)

Provides review, analysis & studies to assess the District’s development plan and its impact on the environment in accordance with the California Environmental Quality Act.

Prepares & Produces Required Documentation Negative Declaration Mitigated Negative Declaration Environmental Impact Report(s)

Page 23: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

District Design Team

FIRM NAME DISCIPLINE ADDRESS CONTACT Steinberg Architects

District Architect 60 Pierce Ave San Jose, CA 95110

Rob Barthelman Tom Lawrence

CSW/Stuber-Stroeh District Civil Engineer 790 De Long Ave Novato, CA 94945

James Grossi, Jr. Al Cornwell

Alfa Tech District MEP 120 Montgomery St, Ste 715 San Francisco, CA 94104

Mike Lucas

Fugro West, Inc. District Geotechnical 1000 Broadway, # 200 Oakland, CA 94607

Corey Dare Mark Caruso

Ninyo & Moore District Industrial Hygienist

1956 Webster St, # 400 Oakland, CA 94612

Joel Kushins Bill Larkin

Royston, Hanamoto, Alley & Abey

District Landscape Architect

225 Miller Ave Mill Valley, CA 94941

Aditya Advani Nathan Lozier Cordy Hill

Degenkolb Engineers

District Structural Engineer

300 Frank H. Ogawa Plaza # 450 Oakland, CA 94612

Holly Razzano Rob Tovani

Amy Skewes-Cox District CEQA Consultant

PO Box 422, 45 Laurel Ave Ross, CA 94947

Amy Skewes-Cox

MBT Architecture Bolinas Marine Lab Architect

185 Berry St, Lobby One, # 5100 San Francisco, CA 94107

Stevens Williams Susan Seastone

(TBD) Information Technologies (IT)

Page 24: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Next Steps

Board of Trustee Retreats September 20th – Facilities Master Planning October 11th – Program Controls

Facilities Workshop on Sustainability & Environmental Stewardship September 30, 2005 – 9 A. M. to 3 P. M. (Initial Sustainability Summit Held September 9th)

Page 25: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Next Steps

Campus Forums Indian Valley Campus, October 25, 2005

2 PM to 3 PM, Pomo 188 Kentfield Campus, October 27, 2005

2:30 PM to 3:30 PM, Olney Hall Community Forums

Indian Valley Campus, November 1, 2005 7 PM to 8 PM, Pomo 188

Kentfield Campus, November 3, 2005 7 PM to 8 PM, Olney Hall

Page 26: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Next Steps

Educational Master Plan – Road map to future District Consultants

Design Guidelines Building Standards FF & E Standards

District Assessments and Surveys Program Definition

Scope / Schedule / Budget

Page 27: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Next Steps

Projects in Design Kentfield

Roof Repairs – Harlan Center and LRC (Oct to Nov 2005) Partial Roof Replacement – Physical Education Building

(Apr to Jun 2006) Tree Trimming and Removal (Dec 2005 to Feb 2006) Demolition of Larkspur Annex (Dec 2005 to Mar 2006)

Indian Valley Wildfire Mitigation (Oct 2005 to Feb 2006) Partial Gas Main Replacement (Nov to Dec 2005) Tree Trimming and Removal (Jan to Mar 2006) Stream Erosion Mitigation (May to Sep 2006)

Page 28: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Other Issues

Kentfield Title 9 Compliance (PE Complex)

Indian Valley Bridge Load Testing

Bolinas Geologic Hazards Study

Page 29: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Subcommittees

Page 30: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Subcommittees

Page 31: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Subcommittees

Page 32: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Subcommittees

Page 33: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Subcommittees

Page 34: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Subcommittee Meeting Schedule

Page 35: Marin Community College District Campus Organizations’ Briefing Week of September 19-23, 2005

Questions & Answers

Dave KirnProgram Manager(415) [email protected]

José D. NuñezDirector of Modernization(650) [email protected]

Elizabeth TuckerSenior Project Field Administrator(415) [email protected]