Transcript of MAR2012 Introduction 2011 Block Breakdown
![Page 1: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/1.jpg)
Paul Stott
Hossein Enshaei
February 2011
MAR2012 Engineering applications
![Page 2: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/2.jpg)
Agenda
• Statement of the coursework
• Product breakdown and shipyard layout: Paul Stott
• Process analysis: Hossein Enshaei
• Questions
![Page 3: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/3.jpg)
Block breakdown
Modern shipbuilding divides the ship into blocks.
![Page 4: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/4.jpg)
Block breakdown
• This is a typical block, leaving fabrication ready for erection on the building
berth.
![Page 5: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/5.jpg)
Ship construction processes
Don’t forget that some means is necessary to get the block
to the erection site
![Page 6: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/6.jpg)
Ship construction process
• This is what the erection of blocks in a building dock looks like when it is
very well done.
![Page 7: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/7.jpg)
Block breakdown
How is the block breakdown decided on?
Shipyards strive for the largest practical block at
the erection stage.
Why?........
![Page 8: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/8.jpg)
Block breakdown
0
2
4
6
8
10
12
12
4
8
12
Relative cost of work (manhours) by stage of construction
![Page 9: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/9.jpg)
Block breakdown
Fewer manhours are needed at earlier stages of
production because:
• Supply routes are short
• Access is open and easy
• Crane accessibility is good
• Work can be done “down-hand”
• Staging is unlikely to be required
• Conflict with other work will be minimum
![Page 10: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/10.jpg)
Block definition in shipbuilding
How is the block breakdown for a ship determined?
Constraints and considerations:
• Blocks should as far as possible be self-supporting
• Where possible temporary bracing should be avoided
• Unit breaks should be away from major elements of structure
• Blocks should take account of functional zones
• Maximise the final lift (maximum weight – including outfit)
• Capacity of transport from steel shop to blocking area
• Door dimensions from steel shop
• Workstation dimensions within steel shop
• Blocking area workstation dimensions
• Crane heights
• Other constraints?
![Page 11: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/11.jpg)
Block definition in shipbuilding
How is the block breakdown for a ship determined?
Further considerations:
• Blocks will have a leading edge and a trailing edge
• The leading edge should be relatively rigid – for example close to
a bulkhead: this will ensure maximum stability (i.e. Maintaining
the shape) of the steel until the next block is added
• The trailing edge should be relatively flexible to allow for fairing
• If “green” material is used it should be on the trailing edge
![Page 12: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/12.jpg)
Block definition in shipbuilding
![Page 13: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/13.jpg)
Block definition in shipbuilding
![Page 14: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/14.jpg)
Block definition in shipbuilding
![Page 15: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/15.jpg)
15 20 25 30 35 40
Considering the equipment functional
arrangements define the block breakdown for
both steel and outfit.
Lower zone configuration
Outfit Block Breakdown
As far as possible keep block
breaks clear of equipment
![Page 16: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/16.jpg)
15 20 25 30 35 40
Lower zone configuration
Outfit Block Breakdown
Define the outfit units
installed on steel blocks
prior to erection
As far as possible keep block
breaks clear of outfit unit boundaries
![Page 17: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/17.jpg)
15 20 25 30 35 40
Define the outfit units to
be installed “blue sky”
after block erection
Lower zone configuration
Outfit Block Breakdown
Ensure that the erection sequence
enables straight-lift unit installation
![Page 18: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/18.jpg)
15 20 25 30 35 40
Lower zone configuration
Outfit Block Breakdown
Define accessway and services
route assemblies installed on
steelwork blocks
Ensure that services routes are contained
within steel block boundaries
![Page 19: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/19.jpg)
Steel production
Blocks are the ultimate product of the steel shops.
How are the blocks built up?
![Page 20: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/20.jpg)
Steel manufacture processes• Assembly: the hierarchy of stages
The following diagrams are by kind permission of Malcolm
Bell Associates (Malta)
![Page 21: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/21.jpg)
3D solid model
2 Blocks (P&S)
![Page 22: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/22.jpg)
CAD model exploded at second level
Block assembly analysis
1 Blocks = 4 units + 4 sub assemblies
![Page 23: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/23.jpg)
CAD model Block Breakdown
Unit definition
![Page 24: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/24.jpg)
1 Unit = 5 sub assemblies
![Page 25: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/25.jpg)
![Page 26: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/26.jpg)
Steelwork processes
OU
TF
T IN
STA
LL
AT
ION
• Treatment (shotblasting & priming)
• Cutting / marking
• Forming / shaping
• Welding
• Painting
• Storage, transport and marshalling
![Page 27: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/27.jpg)
Outfit installation
It is essential to productivity and competitiveness that
outfit work and steelwork are integrated as far as
possible and that outfit items are fitted at the earliest
possible stage
Piece parts
Minor assembly
Sub assembly
Unit assembly
Block assembly
Ship
OU
TF
IT IN
STA
LL
AT
ION
![Page 28: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/28.jpg)
Outfit installation
Outfit installation stages by increasing cost
On sub-assembly
On Unit
On Block: open sky
On Block: closed
On Berth: open sky
On Berth: closed
Post-launch
Cost increases
because of more
difficult access and
more difficult working
conditions
![Page 29: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/29.jpg)
Outfit installationIt is essential to productivity and competitiveness that
outfit items are installed in units or assemblies
wherever possible, rather than piece by piece.
Optimum ease of access and least cost in a workshop
environment
![Page 30: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/30.jpg)
Outfit manufacture workshops
• Pipe shop
• Machine shop
• Sheet metal shop
• Electrical shop
• Stores
![Page 31: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/31.jpg)
Don’t forget painting
![Page 32: MAR2012 Introduction 2011 Block Breakdown](https://reader034.fdocuments.in/reader034/viewer/2022051820/552b12eb55034688478b458d/html5/thumbnails/32.jpg)
Shipyard layouts
A layout is on Blackboard for you to look at –
• Yanbu al Bahr (note – this is a large yard and
includes repair as well as newbuild)