Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

18
Maplewood Middle School Addition Board of Education Meeting May 7, 2012

Transcript of Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

Page 1: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

Maplewood Middle School

Addition

Board of Education Meeting

May 7, 2012

Page 2: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

Approval Process

• Identify Program Requirements and Budget• Develop Design Documents • NJDOE Approval (educational capacity)• Planning Board Courtesy Review• NJDCA Approval (specification codes)• Bid• Construct

Page 3: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

Identify Program RequirementsSchool Year Middle School Enrollments Increase Over Previous Year

2002-2003 1,547

2003-2004 1,504 (40)

2004-2005 1,468 (36)

2005-2006 1,414 (54)

2006-2007 1,371 (43)

2007-2008 1,332 (39)

2008-2009 1,356 14

2009-2010 1,394 38

2010-2011 1,404 10

2011-2012 1,416 57

2012-2013 projected 1,440 24

2013-2014 projected 1,544 104

2014-2015 projected 1,584 40

Page 4: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

Develop Design Documents

• 2010-2011 Confirmed Need to Address Increasing Enrollment

• 2010-2011 Identified Need to Renovate Science Labs

• Reviewed 2001-2003 Original Addition Plans • Updated Plans for current needs, efficiencies,

and cost analysis• 2011-2012 Funding for Project Identified

Page 5: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

Plan Development and Approvals

• NJDOE Approved Project and Educational Capacity

• Maplewood Planning Board Raised question regarding brick façade facing Maple Avenue and Impact on Existing Foliage

• Interior Details Being Finalized for Submittal to NJDCA

Page 6: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

Future Timeline

• June 2012 Submittal to DCA• Summer 2012 Bid for Project

• (dependent on DCA review)

• September 2012 Begin Construction• (dependent on DCA review)

• September 2013 Opening of New Addition

Page 7: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

Site Plan for

Maplewood Middle School

Addition

Page 8: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

Existing BuildingFront FaçadeFacing Burnet Street

Page 9: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

Addition Facing the Front of the School

Page 10: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

View from Rear of Addition

Page 11: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

Existing Building Side View Facing Maple Avenue

Page 12: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

Side of Addition Facing Maple Ave

Page 13: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

Revised Side View for Discussion

Page 14: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

Existing Tree in Front of Maplewood Middle School Near the Site of the Addition

Page 15: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.
Page 16: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

First and Second Floor Science Labs

Page 17: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

Basement Level Classrooms

Page 18: Maplewood Middle School Addition Board of Education Meeting May 7, 2012.

What’s Next?• Finalization of Plans and Internal Space• June 2012 Submittal to DCA• Summer 2012 Bid for Project • September 2012 Begin Construction• September 2013 Opening of New Addition

Communication to Neighbors:– Sign up for Notification this evening– Send contact information to:

[email protected]