Manus
-
Upload
aina-anchinges -
Category
Documents
-
view
215 -
download
2
description
Transcript of Manus
1
INCREASING OUTPUT THROUGH REDUCTION OF MACHINE UNPRODUCTIVE TIME AT THE BLACK SLIDE MACHINING PRODUCTION LINE OF T&S
LASER SOLUTIONS, INC. (TLS), STO.TOMAS BATANGAS
MARY ELAINE MANALO MARANAN 2005-48499
A PRACTICUM STUDY PRESENTED TO THE FACULTY OF THE DEPARTMENT OF INDUSTRIAL ENGINEERING COLLEGE OF ENGINEEERING AND AGRO-INDUSTRIAL
TECHNOLOGY UNIVERSITY OF THE PHILIPPINES LOS BAÑOS IN PARTIAL FULFILLMENT OF THE REQUIREMENTS
FOR THE DEGREE OF
BACHELOR OF SCIENCE IN INDUSTRIAL ENGINEERING
APRIL 2010
1
1. INTRODUCTION
2
1.1. Overview of the Company
T&S Laser Solutions, Inc. (TLS) is a manufacturing company that provides
laser cutting and machining services. It is a Filipino company that is backed by
Japanese expertise and technology in the laser and cutting field.
TLS has two operating sections within its manufacturing site: the laser
cutting section and the machining section.
The laser cutting section provides solution to companies that have metal
cutting as a part of their manufacturing process through the use of laser
technology. Its services include development cutting, laser marking, laser
sculpting, and laser engraving. The machining section on the other hand,
manufactures different type of gun slides as part of the product owned by the
Arms Corporation of the Philippines (Armscor), one of its main customers.
The laser cutting section operates on a single 10-hr-shift working schedule
during weekdays while the machining section works on a two 11-hr-shift rotation
structure from Mondays to Saturdays.
1.1.1. Company History
T&S Laser Solutions, Inc was established in the year 2006. It is a
member of T&S Global Solutions (TGS), to where the company, with the
other two members started. TGS began from a 12-man operation in 2004
until it grew steadily into a 60-man company of highly skilled engineers.
The two related companies are Philippine Tsugami T&S (PHITTS) and
Crossworld Buiness Solutios, Inc. PHITTS is an industrial machine
maintenance service provider which offers equipment calibration, equipment
repair and non-destructive testing and which provides the maintenance of
the equipment in the company. Crossworld Business Solutions is a
consulting firm providing services in assurance, investment planning,
corporate finance, accounting outsourcing, tax and technology consulting.
TLS is supported by its mother company – TandS, Inc. that is
located in Japan and has been in the industry for two decades. TLS started
3
as a provider of laser and cutting services only. It was only in August, 2008
when it started its machining operations.
1.1.2 Organizational Structure
Figure 1-1 shows the organizational structure of the company. The
company is made up of four major departments namely: Administration and
Accounting, Sales and Marketing, Laser Cutting Division, and Machining
Division. The laser cutting and machining divisions incorporate the
production section of the company with three workers and eight operators
respectively.
TLS employs 25 people in total. The laser cutting has three
operators while the machining division has eight workers including the
operators and the machinists.
The president oversees the overall operations of the company and
for each of the department a concerned head is assigned for supervision.
The vice presidents act also as the manager of the laser cutting and the
machining sections. The sales and marketing officer is the one in charged
with dealing with present and potential customers. The administration and
accounting department deals with the accounting system of the company
and serves also as the Human Resource Department.
4
Figure 1-1 Organizational chart of the company
5
1.1.3 Company Location
T&S Laser Solutions, Inc. is located at the First Philippine Industrial
Park in Sto. Tomas, Batangas. Figure 1-2 shows the location map of the
company.
Figure 1-2 Location map of the company
1.1.4 Customers Served
TLS offers its laser cutting services and machining services to
companies that require cutting and machining processes in their production.
Some of the industries it serves are advertising, architectural design,
aerospace/auto parts manufacturing, chemical engineering, construction,
electronics, machinery/equipment manufacturing, tooling, metal forming,
precision engineering, and semiconductor industries.
Some of its customers are Advantek, Philippine Yushin, Cebu
Yushin, Arms Corporation of the Philippines, and Babcock-Hitachi of the
Philippines, Inc.
BATANGAS
STO.TOMAS
TLS
6
1.1.5 Industrial Classification
TLS is considered a manufacturing company as it is involved in the
fabrication and machining of product parts that companies use in their own
manufacturing processes. Aside from manufacturing products and product
parts it is also a service provider of aesthetic and design services.
1.1.6 Lines of Products/Service
The company offers a wide range of products to other manufacturing
companies. Some of the products it produces are channels, ducts, casings,
base plates, washers, flanges, storage, spacers, signages, logos, keychains,
links, slides, machine parts, etc. It also provides aesthetic and design
services through laser marking, sculpturing and engraving. These are all
done in the laser cutting section. Through its machining operations, it
produces gun slides as part of products of the Arms Corporation of the
Philippines. Figure 1-3 shows some of the company’s (a) services and (b)
products.
Figure 1-3 Sample products and services
1.2. Background and Significance of the Study
One of the competitive advantages a company can gain over its
competitors is meeting customer demand. It is not only a means to achieve
higher sales but also to protect the reputation of the company and to build a
strong relationship with the customer. As much as manufacturers want complete
7
and readily available resources in producing their products, customers also do
not want insufficient delivery of their orders.
One way of meeting demand is increasing capacity. It may be through
adding more machines, hiring more workers or making sure that materials are
available at the start of production. But these are necessary if it is the maximum
capacity that cannot meet the demand. On the other hand, a company can meet
customer demand by making sure that the current capacity is utilized efficiently. It
means no unproductive time is present at the system or at the least, it is
minimized.
For TLS, who is new to the industry of machining metals, meeting its
customer’s demand is a good approach to create a good name in the industry.
One main source of income of the company is the machining production
line where the proponent of the study was assigned. The line is producing three
different types of slides namely: black slide, rough slide, and smooth slide. These
products were named as such for confidentiality purposes. Figure 1-4 shows the
distribution of product output in the machining production section.
Figure 1-4 Product output distribution of the machining production section
8
As shown, the major income of the machining production section comes
from black slides. But in its production period for five months it did not meet the
fixed monthly demand of 2800 units. Figure 1-5 shows the actual outputs of the
black slide production line for five months in the year 2009 and the monthly
demand.
Figure 1-5 Demand and actual output of the black slide machining line
Relative to the demand of the black slide production line, the actual outputs
are lower. The average monthly output of the line is 2471 units (see appendix A).
This causes lost sales to the production that is equal to 329 units per month or
equivalent to Php1, 101, 492 per year (refer to appendix B). Assessing the
capacity of the black slide production line, it was determined that the line is
capable of meeting the demand. The line capacity assessment was further
discussed in the results section. Table1-1 shows the line capacity assessment of
the black slide production line.
9
Table 1-1 Monthly capacity per process
Process Effective Capacity per
month(units)
Facing –off 5668
Drilling 3276
Milling Ref 3952
Milling Clearance 5668
Stop seat 3952
Stop slot 3250
Milling Barrel 3250
Pre drilling 3276
The stop slot process has the lowest capacity with 3250 units per month.
Since it is the bottleneck process, it will determine the maximum output or the
effective capacity of the whole line. Comparing it to the monthly demand of 2800
units, the capacity is higher, thus it can meet the demand. This means that there
are problems in the operation which contribute to low production output of the
line.
One area for improvement identified is the presence of unproductive time in
the production line of black slide. It was verified through continuous lapse time
method that the production line is having significant machine unproductive time.
Figure 1-6 shows the breakdown of production time in the black slide machining
line.
Figure1-6 Breakdown of production time
10
Unproductive time accounts for 22% of the available production time in the
morning shift. The data were obtained only from the nine hours in the morning
shift. The unproductive times recorded were the times when the machine is not
working either having downtime or idle time which in effect reduce the potential
output of each process. This was computed to be equivalent to production loss
of 22 units per day or 364 units per month. This was further discussed and
shown under line capacity assessment in the results section. Reducing the
unproductive time can therefore increase the output of the line by reducing the
production loss.
Also, the company gives additional 25% of the regular wage per hour for
overtime. In total, it pays regular overtime cost equivalent to Php148, 200 in a
year for all the four operators working in the black slide production line (see
appendix B). Thus, reducing the unproductive times cannot only increase the
company’s production output, it can also reduce or eliminate the need for
overtime schedules. Doing so would mean reduced costs for the company.
1.3. Statement of the Problem
High machine unproductive time was observed in the black slide machining
production line. It was identified as an area for improvement since the production
line cannot meet its monthly demand of 2800 units. The unproductive time was
verified to cause a significant loss in the production which limits the potential
maximum output to be achieved. The unproductive times include having
inefficient performances, poor workplace, non-standardized working procedures
and worker delays.
1.4. Objectives of the Study
The general objective of the study is to reduce machine unproductive time
in the machining production line of Black slides to increase its output.
Specifically, it aims to
• describe the current production system of black slide;
• identify the factors contributing to the machine unproductive time in
the line and its impact to the system;
• analyze these factors and establish solutions to it;
11
• evaluate the solutions formulated;
• develop the best solution to the problem;
• make further improvements to the system; and
• Apply Industrial Engineering tools and concepts as aid in analyzing
and solving the problem
1.5. Scope and Limitations
The study is limited to the Black Slide products. The operations under study
limit to the manufacturing process of Black Slides under the machining
production section. Due to morning work schedule, the time samples were
obtained for nine hours only from the morning shift. Late deliveries of raw
materials were not considered due to time constraints.
1.6. Date and Place of the Study
The study was conducted at the Black slide production line under the
machining production section of T&S Laser Solutions, Inc. at the First Philippine
Industrial Park, Sto. Tomas Batangas. The study covered the period May 2009 to
March, 2010.
1.7. Roadmap/Milestone
Figure 1-7 shows the Gantt chart schedule of activities done during the study.
Figure 1-7 Gantt chart schedules of activities.
12
2. METHODOLOGY
13
2.1. Procedures
The study started with the preliminary gathering of data. Actual observations
on the manufacturing processes, the operators and machine operations were first
done in order to familiarize with the production system. Initial gathering of data
was done through interviews with the operators, supervisors, and the production
engineer. Some pertinent and significant information in the form of brochure,
slides, and other printed materials were also secured from the company.
Through further gathering of data using continuous lapse time method,
unproductive times were present in the production. This became the initial
foundation of the problem. To verify if the unproductive times affect the
production, the machines were continuously observed and the unproductive time
at each process were recorded with their corresponding lapse time. Time study
was also done to determine processing times for the evaluation of the current
system including production capacity.
All the data gathered were used then for the analysis. The time samples
were used to determine the normal time for each process and to compute the
effective capacity of the line. The time records were used to determine the
percentage of machine unproductive time in the production. When the problem
was fully established, root-cause analysis and CNX analysis were used to
identify and group the factors that contribute to the problem.
Direct and alternative solutions were then generated to solve the problem.
The alternative solutions were evaluated based on selected criteria. Cost and
benefits of the best solutions and recommendation were discussed. All the
results of the study were then summarized and finally, recommendations were
presented along with the other areas for further study.
2.2. Definitions of Terms
The terms in Table 2-1 along with their definitions were used in the study.
14
Table2-1 List of defined terms used in the study
Term Definition
Actual Capacity Output of a line when unproductive
times are considered
Avoidable delay
Delay that can be controlled/avoided
(e.g. chatting, loitering)
Bottleneck process The process with the minimum capacity
Cycle time Total time spent by the material in a
workstation
Effective capacity The maximum possible output less set
up times and break times
Effective time The maximum available production time
Frequency (ƒ) The number of occurrence of an
element or process
Machine Idle time Time when the machine waits to be
attended
Machine Downtime Time when the machine is not working,
(e.g. when under repair)
Normal Time (NT) Observed time adjusted for worker
performance
Performance Rating (PR) Rating of the work performance of
operator
Relaxation Allowance (RA) Also rest allowance of workers
(including break times)
Standard Time Time required to perform a task
Unit normal time (UNT) Normal time of a process per unit, also
the processing time
Unproductive time (UT) Time when no output is produced (e.g.
downtime, idle time)
15
2.3 Description of Symbols
The following symbols in Table 2-2 were used in the study.
Table 2-2 Symbols used and their description
16
3. SYSTEMS DOCUMENTATION
17
3.1 Product Focus of the Study
The study considered the slide products that are produced in the machining
production section of the company.
There are three types of slides produced in the machining production
section. These include (a) Black slide, (b) Rough slide, and (c) Smooth slide. The
different types of slides are shown in Figure 3-1.
Figure 3-1 Slides Manufactured in the Machining Production Section
The study solely focuses on the Black Slides. All of the three slides belong
to product line of Arms Corporation of the Philippines but only Black slide has the
continuous production. The production output contribution of each product was
previously shown in the background and significance section.
3.2 Black Slide Manufacturing Process
In general, there are eight major operations in manufacturing of the Black
Slide products, namely: Facing-off; Drilling, Milling Ref, Milling clearance, Stop
seat, Stop slot, Milling Barrel, and Pre-drilling. Figure 3-2 shows the flow of
processes for Black Slide production.
(a).
(c).
(b).
18
Figure 3-2 Manufacturing Process of Black Slide
These major operations are the names of machine operations. As shown
in the figure, the processes are grouped per workstation. Four machines are
regularly used in the production of Black slide and in each machine, two
processes are performed. Because of limited number of machines, one of the
two processes in the same workstation is performed after the other process.
Work-in process units are allowed in each workstation.
Aside from machine operations, there are also independent manual
operations performed. These include filing before loading, filing after unloading,
and inspection. Figure 3-3 shows the process flow in each workstation.
19
The materials are filed first before they are loaded to the machine. This
process is done to prevent poor feeding of machine cutter. The materials are
then loaded and clamped tightly to the jig inside the machine. Once clamped, the
operator will start the machine to run. After the machine operation, the materials
are unclamped and unloaded to the table in front of the machine. They are then
filed again to smoothen sharp faces and to remove metal chips produced by the
machine operation. The materials are then inspected but only samples were
taken for the inspection process.
3.3. Facility Layout
The facility layout of the company is shown below in Figure 3-4.
Figure 3-3.Process flow chart at each workstation
20
MAIN SECTIONS :
Machining
Laser Cutting
Administration/Management
Figure 3-4 Facility layout of TLS
21
The darker green-colored area represents the administration and accounting
department of the company. The area with color light green represents the
machining production section. The dark blue-colored area represents the laser
cutting production section. Other colored parts of the layout represent areas such
as pantry (gray), pathway (light blue). The white-colored sections represent the
machines the company has. At the upper right section of the machining area is
where Black slide products are manufactured and the lower right area represents
the production section for other slide products of the machining section. The
surrounding area colored flesh shows the boundary of the building of the
company.
3.4 Production Operation Schedule
TLS, Inc. currently employs 3 workers in the laser cutting section and eight
workers in the machining section including the operators and the machinists, four
of who are assigned in the production of Black slides. The company is operating
on a two 8-hr-shift working schedule in the machining section with two operators
in each shift. The machining production works from Monday to Saturdays. For
the laser cutting section, the production works only during weekdays and on a
single 10-hr-shift. The company allows a one-hour lunch break and a 30-minute
break time for the laser cutting and the machining section. The company also
permits an overtime of 3hrs per shift for the operators in the machining section.
3.5 Manpower Complement
Currently, T&S Laser Cutting Solutions, Inc. is run by 25 people of which
three are workers on the laser cutting section, one operator, one production
assistant, and one quality analyst. The operator operates the machine, and the
quality analyst inspects if the finished goods conform to the design and
specifications of the product. The production assistant tasks include deburring or
filing, packaging and assistance in loading and unloading of the materials from
and to the machine.
In the machining section, four are operators who are assigned in the Black
slide product line and four are machinists assigned in other machining
operations.
22
3.6 Machines and Equipment
The laser cutting section uses the AMADA FO 3015 (3600 KW 5’ x 10’ bed)
machine in producing its goods and services. This machine maximizes utilization
with minimal set up between jobs. It supports its production with a crane used in
transporting of big raw materials from the material section to the machine bed.
They have manual calipers but use digital calipers in the inspection of the
finished product. They also uses height gage for inspection in processes such as
milling clearance, stop seat, stop slot, milling barrel, and pre drilling.
The machining production division has four CNC machines for
manufacturing of Black slide products and three machines for forge slides and
full slides. The company also has equipment for heat treatment of smooth slides.
Each of the machines performs two processes and each process has different
capacities. Table 3-1 shows the number of units that can be output per process
and the machine number where each process is performed.
Table 3-1Output per Process
Machine No. Process
Output per loading/unloading (units)
1 Face-off 4
2 drilling 4
3 milling ref 4
1 Mill clearance 1
3 Stop seat 2
4 Stop slot 4
4 milling barrel 4
2 Pre drilling 6
23
4. RESULTS AND DISCUSSION
24
4.1. Problem Identification
The black slide machining production line does not meet the monthly
demand of 2800 units which cause production lost sales amounting to 329 units
per month or is equivalent to Php1, 101, 492 in a year.
Since high machine unproductive time was observed and verified in the
production, it was identified as an area for improvement in order to increase the
output of the black slide production line. Figure 4-1 shows the machine
unproductive time occurring at each process.
Figure 4-1 Machine unproductive time at each process
The stop slot process has the highest recorded machine unproductive time
with 111.62 minutes per day. Several causes were determined to contribute to
the machine unproductive time in the black slide production and these include
double filing, machine adjustment, late filing, transport delays and worker delays.
Figure 4.2 shows the top causes of machine unproductive time in the black slide
machining production line.
25
Machine unproductive time per day
Percent
Causes
Count
Percent 41.4 13.9 11.0 10.5 10.0 6.1 4.9 2.2
Cum %
259.1
41.4 55.3 66.3 76.8 86.8 92.9 97.8 100.0
87.2 68.6 65.7 62.7 38.0 30.8 13.9
Tool wear out
No mat'l
Other tasks
Machine adjustment
Transport
File before
Double file
Worker delay
700
600
500
400
300
200
100
0
100
80
60
40
20
0
Total Machine Unproductive Time per Cause
Figure 4-2Total machine unproductive time contribution of each cause
Worker delay has the largest contribution amounting to 259.1 minutes of
total unproductive time present in the whole operation in the production line (see
appendix C for average unproductive time at each process).
Five causes constitute the 86.8 percent of the total causes of machine
unproductive time. Using Pareto principle these causes will be the focus of the
analysis and recommendations of the study. These causes include worker
delay, double filing, filing before or late filing, transport delay and machine
adjustment.
To verify the effect of the recorded machine unproductive time on the
capacity of the production, the capacity of the line was determined and was
analyzed.
26
4.2. Analysis
4.2.1. Time Study Results
Time study was done to determine the effective capacity of the
black slide machining production line and to have values of processing
times since these are necessary in the analysis of the problem.
Twenty time samples of each process were initially taken (see
appendix D for the initial samples). The processes timed are initial filing or
filing before loading, loading, machine process, unloading, filing after
unloading, and inspection. Outliers or samples whose values are far from
the average time are removed and not considered. To get the required
number of samples, the following values were considered:
X – Average of the samples
PR – Performance rating of operators
NT – Normal time
ƒ– Frequency
UNT – Unit normal time
R - Range
N - number of samples required
To compute for the unit normal time, the equations below were used:
NT = X * (PR)
UNT = NT * ƒ
R = maximum time sample - minimum time sample
N = R/UNT
For each process, the average of the time samples was computed.
It was then multiplied to the performance rating derived using
Westinghouse Rating System (see appendix E) to get the normal time for
each process. The normal time was multiplied to the frequency of each
element or process to get the unit normal time. The range of time values at
each process was also obtained for the computation of the required number
of samples. The values were tabulated in appendix G.
27
The value of N was then computed using the formula given above
(Niebel, 2003) and then it was compared to the values appearing in the
table for N values (see appendix F for the table). In the initial result of N
values, the highest value equated to 0.36 (see appendix G). Interpolating
this value using the table, the required number of samples is 23.
To verify if this is the final required number of samples, three more
time samples for each process are added and then the same method is
applied again. The highest resulting value for N is still 0.36, thus 23
samples is the final required number of samples (see additional samples
and final N results in appendix H). Table 4-1 shows the resulting normal
time for each process or the processing time.
Table4-1 Unit normal time of each process
Process Name Unit Normal Time(min)
1. Facing –off 0.99
2. Drilling 5.4
3. Milling Ref 1.48
4. Milling Clearance 5.17
5. Stop seat 6.69
6. Stop slot 5.01
7. Milling Barrel 4.93
8. Pre drilling 4.39
For each process or element, the unit normal time was used as
the process time but only the unit normal time for loading, unloading, and
machine time were considered in determining the cycle time for each
process since filing before and after, and the inspection process are done
while the machine is running. This is because it is a standard procedure set
in the production. This is also because it is the effective capacity per
process that was computed.
28
4.2.2. Line Capacity Assessment
The black slide machining production line is operating 24 hours with
two shifts. The total available production time is 1440 in minutes per day.
The time allotted for breaks is 1.5 hrs per shift and the set up time is 5mins.
Given this operating schedule, the total effective time is 1250 minutes, with
the set up and break times already deducted. Since there are two
processes performed in each machine, the total production day is divided
into two processes.
In determining the effective capacity of each process, the equations
below were used.
For the two processes, facing-off and milling clearance which are both performed in machine 1, the values were computed as:
For facing off
= 16.07 % (of the total effective time)
For milling clearance
= 83.93 % (of the total effective time)
Getting the effective time and the effective capacity,
For facing off:
Effective time = 0.1607* 1250 minutes
= 200.893 minutes
Effective capacity = 121.48 min per day / 0.557 min
= 202.922 units per day
29
For milling clearance:
Effective time = 0.9027* 1250 minutes
= 1049.107 minutes
Effective capacity = 1049.107 min per day / 5.17min
= 202.922 units per day
Based on the results, the maximum output of each process is 202
units per day. The same method is applied to remaining processes and
table 4-2 shows the results.
Table 4-2 Summary of effective capacity per process
As shown, there are processes with the same output. These are the
processes that are performed in the same machine. It is expected since it is
the effective capacity or maximum finished output of a process that was
computed. Any difference in the output of the two processes would mean a
work in process unit and not a finished good because this unit underwent
one process but did not undergo the other process so to get the maximum
output, the output of the two processes should be the same. For instance, if
the output of facing-off process is greater than the output of milling
clearance then the milling clearance will dictate the maximum output
between the two processes. The same analysis was done with the
remaining processes.
Process Percentage
(%)
Effective time per day
(min)
Unit normal time (min)
Effective Capacity per
day(unit)
Face-off 16.07 200.893 0.99 202
Drilling 55.16 689.479 5.4 127
Mill ref 18.12 226.438 1.48 152 Mill clearance 83.93
1049.107 5.17 202
Stop seat 81.88 1023.562 6.69 152
Stop slot 50.4 630.03 5.01 125
milling barrel 49.6
619.97 4.93 125
pre drilling 44.84 560.521 4.39 127
30
Of all the processes, it is shown that Machine 4 dictates the
effective capacity of the line which is equal to 125 units per day or 3250
units per month.
Accounting for effect of machine unproductive time, for each
process the effective capacity would not be maximized due to such
unproductive time. To determine the actual capacity per process the
equation below was used:
For face-off:
Actual capacity = (200.893 min/day - 64.79 min/day) / 0.99 min/unit
= 137 units /day
Loss per day = Effective capacity - actual capacity
= 202 - 137
= 65 units / day
The same computation was applied to remaining processes and the results
are shown in table 4-3.
Table 4-3 Summary of actual capacity and loss per process
Process Per-
centage (%)
Eff time/ day (min)
Unit Normal time (min)
Eff Cpty / daY (unit)
Average machine UT/ day (min)
Actual Cpty / day (units
Loss / day (unit)
Face-off 16.07 200.9 0.99 202 64.79 137 65 Drilling 55.16 689.5 5.4 127 71.04 115 12 Mill ref 18.12 226.4 1.48 152 67.57 107 45 Mill
clearance 83.93 1049 5.17 202 76.98 188
14 Stop seat 81.88 1023. 6.69 152 59.8 144 8 Stop slot 50.4 630 5.01 125 111.62 103 22
milling barrel 49.6
619.9 4.93 125 99.86 105 20
pre drilling 44.84
560.5 4.39 127 74.26 111 16
*Eff -effective *Cpty - capacity
31
After the machine unproductive time is deducted from the effective
time for each process it resulted that the stop slot process has the lowest
actual capacity with 103 units per day. Since this is the bottleneck process,
it determines the capacity of the production line. From 125 units of effective
capacity, the actual capacity now is 103 units per day causing a loss of 22
units per day or 364 units per month. This loss represents the equivalent
value in units of machine unproductive time.
The discussion above focused on the capacities of each process
given the available effective time for each process. To evaluate manpower
capacity, and verify if it does not affect the capacity of the machine, the
formula for computing the number of machines an operator can handle was
used. The equation for number of machines is given below:
Where:
n = maximum number of machines that can be assigned to an
operator
a = concurrent activity time
b = independent operator activity time
t = independent machine activity time
Concurrent activities are those activities wherein both the operator
and the machine are involved. These include loading and unloading
process. Independent operator activities are solely the activities of the
operator and with no machine involved. In the production, these are the
filing process before loading and after loading, inspection, and traveling.
Independent machine activity refers to the activity of the machine alone.
Considering the first two processes, face-off and drilling, the average
loading time is 0.19 minutes, unloading time is 0.15 minutes, machine
operation is 2.86 minutes, filing time before loading is 0.105 minutes,
filing after is 0.14 minutes, inspection is 0.07 minutes, and the travel time
32
is 0.07 minutes. Face-off also has a cleaning process which takes 0.11
minutes.
a = 0.19+ 0.15 = 0.34 minutes
b = 0.105+ 0.14 + 0.11 + 0.07 + 0.07 = 0.495 minutes
t =2.86 minutes
To evaluate if the two machines can be handled by an operator, the
average times were used in the equation.
= 3.83 machines
This means that the operator can handle three machines and thus the two machines assigned to an operator will not have idle time because the operator can handle both machines.
For the rest of the processes, the same method was applied. Table 4-4 shows the average activity times and the number of machines the operator can attend to.
Table 4-4 Summary of number of machines an operator can handle
Concurrent Process a b t n
Facing -off and Drilling
0.34 0.495 2.86 3
Drilling and Milling Clearance
0.45 0.47 4.84 5
Facing-off and Pre-drilling
0.33 0.51 2.37 3
Milling Clearance and Pre-drilling
0.44 0.39 4.35 5
Stop slot and Stop Seat
0.49 0.485 5.37 6
Stop seat and Milling Barrel
0.49 0.595 5.32 5
Stop slot and Milling ref
0.41 0.57 2.84 3
Milling Barrel and Milling ref
0.42 0.59 2.79 3
33
Based on the number of machines computed, the operator can
handle more than two machines assigned to him on whatever two
processes are concurrently performed.
4.2.3. Root-cause analysis
To determine the possible root causes of the having high machine
unproductive times an Ishikawa diagram was used. The study considered
only three major sources including man, material, and method. Figure 4-3
shows the Ishikawa diagram of root-cause analysis.
34
Figure 4-3 Root-cause analysis of the problem
35
Figure 4-4 Root Cause - Man
Man
The operators cause unproductive time to the machine when the
machine has stopped working but it is not attended. Operators were
observed as frequently leaving the workplace either to go to the pantry to
drink water or to go to the comfort room. Since the pantry and the comfort
room are quite far from the workplace it takes the operators long time to get
back to the workplace. The possible cause of this is not enough rest
allowance for the operators which cause worker fatigue. Aside from leaving
the workstation, machines are not promptly attended because operators as
observed are chatting or workstation hopping during work and these cause
idle time of the machine. Operators are also having start-up delays which
36
cause late start of the production during resumption to work in the
afternoon.
Figure 4-5 Root cause - Material
Material
The insufficient number of filing tools and unloading tools causes
idle time to machines. The operators often spend time searching for the
tools before they can attend the machines. This problem is caused by lack
of tools in other workstations. One set of tools provided is used by an
operator for two workstations. Sometimes the tools are used and
misplaced by the other operator so the when the operator needs the tools,
he has to go to the other workstation to search the tools he needs causing
idle time of the machine. Searching of tools also give the operators
chances to do avoidable delays such as chatting.
37
Figure 4-6 Root cause - Method
Method
It was observed that the operators are doing improper working
practices which cause idle time of the machine. One of these is filing of the
material just when machine has stopped working. Based on the
computation of number of machines an operator can handle, the given the
elements or processes including filing before and after, loading, unloading,
and inspecting, the least number of machines he can handle is three. It was
previously discussed in chapter 4.2.2 in line capacity assessment. This
means that no machine idle times are expected because the operator can
attend the two machines assigned to him. This is also set by the manager
since the machines have long processing time. What often happens is that
the materials are filed just before loading the slides to the machine. This
practice adds up to the cycle time of the material and idle time of the
38
machine. The table used for filing in the stop slot and milling barrel
processes was also identified as another cause of machine unproductive
time. Because the height design of the table is not fit, the operator is having
difficulty in filing leading to late filing or filing just when the machine needs
the material. For other processes with table of fair height, the operators
were observed to not follow the procedures set and are having delays such
as chatting.
Another problem with the method is the inspection method. The
operators are having incorrect inspections. Due to this they have to stop
the machine and adjust its set up. This causes down time to the machine
being adjusted and idle time to the other machine that the operator
cannot attend to. The height design of the table used in inspection is the
factor identified which affects the performance of the operator.
The problem with double-filing of the slides also causes idle time to
the machine. Instead that the materials will already be loaded, the machine
waits for the material to be filed again. The operator just put the materials
that were already filed in the same table where the waste metal chips are.
In effect, the chips adhere to the slides so the operators have to file them
again before they load it to the machine.
4.2.4. CNX Analysis
The root causes were grouped into noise, controllable, and
experimental factors. Chatting of the operators was considered noise since
it is difficult to prevent and eliminate in the production system.
Controllable factors are factors that already have existing
procedures, rules or policies set by the management (Dalawampu, 2008).
These are also factors that can be instantly addressed (Bautista, 2008).
Table 4-5 shows the controllable factors that are identified with the
corresponding actions.
39
Table 4-5 Controllable factors and the corresponding action
Factors Actions
C1 Start-up delay Strict implementation of new policy on on-time start of production
C2 One set of tools for two workstations
Buy another set of tools
C3 Operator does not follow procedure
Strict supervision
Experimental factors as opposite to controllable factors, experimental
factors are factors that do not exist yet in the system or those that need to be
evaluated and improved (Dalawampu, 2008).
The factors identified as experimental are shown in table 4-6 with the
corresponding alternative solutions.
Table 4-6 Experimental factors and the recommended actions Factors Actions
E1 Leaving the workstation frequently
A. Schedule additional 30-min break time
B. Reschedule 15 min-break in the morning
C. Maintain current system
E2 Low height of the table for filing
D. Design table height for filing
E. Use the same table used in other workstations
F. Maintain current system
E3 Low height of the table for inspection
F. Design for average, the table height for inspection
H. Maintain current system
E4 Poor workplace I. Adapt 5S program
J. Maintain current system
40
4.2.5. Generation of Alternatives
To address the controllable factors direct solutions were
recommended. On the other hand, alternative solutions were generated for
the experimental factors.
Controllable Factor C1
To eliminate start-up delay, the Human Resource Department (HR)
should implement a new policy regarding starting the production on time.
The supervisor will be in charge of noting the operators who will violate the
policy.
This study proposes the department to conduct community works
such as tree planting or outreach programs. The HR department may
subject the operators who will violate the policy to joining to such activities.
The idea is just a proposal to the department and the policy as part of the
disciplinary actions is still under the decision of the HR department.
The implementation of a new policy would reduce machine
unproductive time caused by production start-up delay. Table 4-7 shows
the processes and the machine unproductive time due to start-up delays
that would be reduced at each process.
Table 4-7 Machine unproductive time caused by start-up delay Process Machine Unproductive Time
per day(min) Drilling 7.12
Mill clearance 6.76
Stop seat 6.27
Stop slot 6.04
Controllable Factor C2
Since the cause of transport delay is lack of tools at other
workstations, the production should provide a set of tools for each
41
workstation to prevent the operators from going to other workstations to get
and search the tools needed.
This action would solve the transport delays at each process. Table
4-8 shows the machine unproductive time caused by transport delay that
would be reduced at each process.
Table 4-8 Machine unproductive time caused by transport delay
Process Machine unproductive time per
day (min)
Face-off 9.86 Drilling 9.49 Mill ref 8.49 Mill clearance 6.54 Stop seat 4.44 Stop slot 10.42 Milling barrel 10.17 Pre drilling 6.25
This would incur an initial cost of Php630 per set of file hand tool
and Php120 per set of unloading tool with the total cost of Php750 (refer to
appendix K for estimated price).
Controllable Factor C3
Regarding procedure on filing at the right time, the supervisor
should strictly oversee the operators during work. Strictly overseeing means
he should direct the operators to perform and work properly whenever he
noticed that they are not following the right procedures. Use of posters may
be helpful to remind the operators of the correct working procedure but still
presence of the supervisor would force the operator to follow the
procedures.
This action would reduce machine unproductive time due to late
filing of materials. Table 4-9 shows the machine unproductive time due to
late filing.
42
Table 4-9 Machine unproductive time caused by late filing
Process Machine Unproductive Time
(min/day)
Face-off 4.25
Drilling 4.21
Mill ref 4.37
Mill clearance 6.16
Stop seat 4.29
Stop slot 4.92
Milling barrel 4.92
Pre drilling 6.23
The total machine unproductive time in the stop slot and milling
barrel process due to late filing are 21.42 minutes and 17.63 minutes
respectively (see appendix C). Comparing these to other processes’, these
are relatively higher because two causes were determined as influencing
late filing in these processes: not following working procedures and low-
height table.
To determine the machine unproductive time in these two processes
caused by not following procedure, the average of the machine
unproductive time recorded in other processes will be used. The average of
the machine unproductive time in the six remaining processes is equal to
4.92 minutes.
This will be deducted from the recorded machine unproductive time
in the stop slot and milling barrel process and the remaining unproductive
time will be considered the machine unproductive time due to the other
cause which is low-height table for filing. This was assumed because only
the stop slot and milling barrel make use of the low-height table for filing.
43
Experimental Factor E1
From the principle of ergonomics (Niebel, 2003), the number of hours that an operator must have for break can be computed through the equation:
Where: R.A. = percent of rest that a worker must have per shift
W = Energy expenditure due to work
The difficulty of work in the production line was considered
moderate. From the table of Energy Expenditure (see appendix J),
moderate work had an energy expenditure ranging from 5- 7.5 (kcal/min).
Computing for the relaxation allowance,
R.A. = 0.1869 = 18.69% of the total working hours
The production starts from 6:00 AM to 6:00 PM. The break time
allotted for the operators is 1.5 hours, one hour for lunch break and 30
minutes for coffee break. Evaluating the relaxation allowance given to the
operators,
= 0.125 or 12.5% of the total working hours
Comparing the standard and the actual relaxation allowance, the
actual RA is relatively lower which causes fatigue to the operators. The
study then considers the action of adding break time for the operators.
Alternative Solutions to Experimental Factor E1
The first alternative solution (A) to operator delay of leaving the
workstation is to add 30 minutes to break time. To compute for the
44
recommended relaxation allowance, the RA that was previously
computed was used.
Total working hours per shift = 12 hours
RA required = 0.1869*12 hours/ per shift
= 2.24 hours
As computed, the number of hours that should be allotted for
break of the operators is approximately 2 hours per shift. The company
then can schedule a 30-minute break at 9:00 AM, 1-hour lunch break, and
another 30-minute break at 4:00 PM in the morning shift.
This recommendation will therefore reduce machine unproductive
time due operator delay of leaving the workstation to drink or go to the
comfort room. Along with this, the supervisor should be strict with the
operators. Such activities should be allowed during the break time added
in the morning. Table 4-10 shows the machine unproductive time that will
be reduced caused by operator delay of leaving the workstation.
Table 4-10 Machine unproductive time caused by leaving the workstation
Process Machine Unproductive Time per Day
(min)
Face-off 26.16
Drilling 18.38
Mill ref 27.74
Mill clearance 18.47
Stop seat 17.64
Stop slot 22
Milling barrel 26.78 Pre drilling 22
The drawback of adding 30 minutes to the break time of the
operators is that 30 minutes will be reduced from the total effective
production time and thus the capacity of each process will decrease.
Accounting this on the computation of machine unproductive time
that will be reduced in each process the computation is shown below.
45
effective time per day = 1250 minutes
Less = 30 minutes
New effective time/day = 1220 minutes
For face-off process:
Percentage = 16.07 %
Processing time = 0.99 minutes/ unit
Effective time for this process = 196 minutes
Effective capacity = 196 /0.99
= 198. 0519 units/day
Due to additional 30 minutes to the break time, the effective time
for face-off was reduced to 196 minutes per day. This was obtained by
multiplying the new effective time for face-off by the percentage of face-
off process after 30 minutes were reduced from the total effective
production time. Since the machine unproductive time due to leaving
workstation was eliminated, the capacity of the process is now 198.05
units per day which would equate to the effective capacity since the
unproductive time is already eliminated. To determine the number of units
that can be produced in face-off when the unproductive time is eliminated
and 30 minutes is deducted from the effective production time, the
capacity of face-off after improvement was computed as:
effective time = 1250 minutes
Effective time for face-off = 200.893 minutes
Average UT due to leaving workstation = 26.16 minutes per day
Capacity before improvement = (200.893 – 26.16)/0 .99
= 176.498 units per day
Getting the difference of the two capacities computed, the number
of units that can be output with the reduced unproductive time in the face-
off process is 21 units. This value is not yet the final or the representing
number of units that can be increased in the whole production line when
the machine idle time due to such cause is eliminated. To determine it,
the same method was applied to other processes. Table 4-11shows the
result of reducing operator delay through addition of 30-minute break.
46
Table 4-11. Effect on process output of adding 30-minute break
Process
Effective time (min)
Capacity (unit/day)
Effect on the
output per day (unit) Before After Before After
Face-off 174.733 196.071 176.49 198.05 21.55
Drilling 671.099 672.932 124.28 124.62 0.34
Mill ref 198.698 221 134.26 149.32 15.06 Mill clearance 1030.637 1023.929 199.35 198.05 -1.3
Stop seat 1005.922 998.996 150.36 149.33 -1.03
Stop slot 608.03 614.909 121.36 122.74 1.38
milling barrel 593.19 605.091 120.32 122.74 2.42
pre drilling 538.521 547.068 122.67 124.62 1.95
Average increased output = (1.38 + 3.42) / 2 = 1.9 units
After improvement, it was shown that eliminating the idle time due
to leaving the workstation and deducting 30 minutes from the effective
production time can increase an average output of 1.9 units. This will
determine the final increase in output of the whole production line since it
is the average output of the bottleneck processes stop slot and milling
barrel.
The second alternative (B) is to reschedule a 15-minute break in
the morning at 9:00 AM to 9:15 AM. The schedule of break time before
was 15- minutes in the morning and 15 minutes in the afternoon but now,
the schedule turned to 30 minutes in the afternoon. Strictly scheduling 15-
15-minutes break shall also be implemented with monitoring. In the
policy, the operators would not be allowed to go outside the workstation
during working hour since 15 minutes will be schedule for break in the
morning and afternoon. Operators who will violate the rule shall be
subjected to disciplinary actions. The supervisor should oversee the
operators during working hours to monitor the performance of the
operators. Since there is no established policy on leaving workstation, the
47
study proposes the Human Resource department to conduct community
works such as tree planting or outreach programs and involve the
operators who will violate the policy. The community work is just a
proposal which may prevent the operators from disobeying the rules. The
decision is still in the management to determine how they are going to
discipline violating operators.
The machine unproductive time caused by operator delay of
leaving the workstation that will be eliminated when this solution is
implemented is shown in Table 4-12.
Table 4-12 Effect on the process output of rescheduling 15-minute break
Process Machine Unproduc-tive Time
Effective time (min)
Unit Normal Time (min)
Effective Capacity per
day(unit)
Increase in output /day (unit)
Face-off 26.16 200.89 0.99 202 26.42
Drilling 18.38 689.48 5.4 127 3.4
Mill ref 27.74 226.44 1.48 152 18.74
Mill clearance
18.47 1049.1 5.17 202 3.57
Stop seat 17.64 1023.6 6.69 152 2.64
Stop slot 22 630.03 5.01 125 4.39
milling barrel
26.78 619.97 4.93 125 5.43
pre drilling 22 560.52 4.39 127 5.01
The effect of the solution is that all machine unproductive time due
to operator delay of leaving workstation would be reduced without having
reduction in the total effective time of the production, thus the capacity
after improvement will be equal to the effective capacity.
Since the capacity is dictated by the bottleneck processes stop
slot and milling barrel, the increase in output would be based from the
machine unproductive time that will be eliminated in these processes.
48
The equivalent output of the machine unproductive time due to operator
delay of leaving the workstation to drink or go to the comfort room is
computed as:
For stop slot: 22 minutes / 5.01 = 4.39 units per day
For milling barrel: 26.78 / 4.93 = 5.43 units per day
Getting the average of the two values, the average increase in
output is equal to 4.91 units per day.
The management can also choose to maintain the current system
as the third alternative (C). This alternative will not reduce the effective
time of the production but will not solve the machine unproductive time
caused by operator delay of leaving the workstation.
Alternative Solutions to Experimental Factor E2
The first alternative solution to late filing is to buy table of the
designed height for the operators to be comfortable in filing the materials.
According to Niebel, the height of the table should be based on
elbow height because if the work surface is too high, the upper arms will
experience shoulder fatigue, and if low, the back is flexed to lean forward
leading to back fatigue. The effect of it on the performance of the
operators is the tendency of filing the materials just when the machine
needs the materials and have incorrect results on inspections. To design
the new height of the table, designing for the average method was
applied. This study considered the Filipino anthropometric measures as
reference to height design of the tables (see appendix J). The average
height of the operators considered is 5’6 ft or 167.64 cm. The following
values were considered in the design:
Standing Height (cm)
@5th percentile: 157
@95th percentile: 178
49
Through interpolation, the percentile where 167.64 lies, is
determined to be in the 50.6th percentile.
Elbow Height (cm)
@5th percentile: 96.5
@95th percentile: 112.8
Assuming 50th percentile, the elbow height is computed through
interpolation and this is equal to 104.65 cm. Thus, this height will be the
recommended designed height of the table. Figure 4-7shows the sample
height-designed table.
Figure 4-7. Height-designed table for filing
This action would incur the production an initial cost of Php5000
(see appendix K for estimated price). The machine unproductive time that
will be eliminated would be equal to the machine unproductive time at the
stop slot and milling barrel process less the average machine
unproductive time in other processes since these are the two processes
affected by late filing due to low-height of the table. For stop slot process,
the machine unproductive time that would be eliminated is 16.5 minutes
and 12.71 minutes for milling barrel. These values were obtained by
104.65 cm
91.44 cm
50
subtracting the average of the machine unproductive time (4.92 min) in
processes other than stop slot and milling barrel from the total machine
unproductive time at the two latter processes. This was briefly explained
in the discussion of Controllable Factor 3.
To get the effective capacity of the process after improvement, the
machine unproductive time that was eliminated would be reduced from
the average machine unproductive time in that process. In this case,
since all the recorded machine unproductive time were eliminated, there
would be no more machine unproductive time caused by late filing thus
the effective time would not be reduced.
For stop slot:
Effective time = 630.03 minutes per day
Eliminated machine UT = 16.5 minutes
New effective time = 630.03 - 0*
Capacity after improvement = 630.03 / 5.01 min
= 125.75 units per day
The same method was applied to milling barrel process. The
number of units that would be increased is equal to the average of the
increase of the stop slot and milling barrel. This is because after
improvement the capacities of the two processes are the same. Table 4-
13 shows the effect of designing table height on output of the two
processes.
Table 4-13 Effect on process output of using height-designed table for filing
Process Machine UT
(min/day)
Effective time per day (min)
Unit Normal Time (min)
Capacity per day (unit)
Increase in output per day (unit) after before
Stop slot
16.5 630.03 5.01 125.75 122.46 3.29
Milling barrel
12.71 619.97 4.93 125.75 123.18 2.58
51
Average increase = (3.29 + 2.58) / 2
= 2.94 units per day
Alternative E is to use the same table as in the other workstations.
The cost of the table was estimated to be of the same cost as the existing
table considering the same type of wood material. Using the same table
will also reduce the same amount of machine unproductive time since the
height is fair to the operators’ height. This considers that machine
unproductive time in workstations 1 to 3 due to late filing is caused by not
following the procedures set in the production.
Alternative solution F is to maintain the current system or use the
same table used in the workstation. The production would not have cost
on it but the machine unproductive time due to low-height table will be
remained in the system.
Alternative Solutions to Experimental Factor E3
Alternative solution G is to buy table of the same designed height
for inspection. Since the inspection makes use of height gage the height
of the table would still be suitable for the operator doing the inspection.
The initial cost for buying the table is also Php5000. The unproductive
times that will be reduced will be on the five last processes since these
are the processes where incorrect inspections occur due to back-fatigue.
Using the table would not surely eliminate all the unproductive time
caused by it, so the efficiency of the production would be used as the
percentage that could possibly be reduced. The current efficiency of the
production is 76% (see appendix B)
The increase in units per process was computed by deducting the
remaining machine unproductive time from the effective time of the
process and dividing the answer by the processing time.
52
For mill clearance:
Ave. machine UT = 12.82
Reduced UT = 0.76 * 12.82
= 9.74 minutes/day
Remaining UT = 12.82 - 9.74
= 3.08 minutes /day
Capacity after improvement
= (effective time - remaining UT) / processing time
= (1049.107 min - 3.08) / 5.17
= 202. 326 units / day
Increase in output = capacity after improvement - capacity before
improvement
= 212.326- 200.94 units
= 1.88 units / day
Applying the same method to other processes, the results are
shown in table 4-13 shows the reduced machine unproductive time in
these processes.
Table 4-13 Effect on process output of designing table height for inspection
Process
Ave Machine UT /day (min)
Remaining Machine UT / day (min)
Reduced machine UT / day (min)
Capacity (unit/day) Increase
in output /day (units) after before
Mill clearance 12.82 3.08 9.74 202.33 200.94 1.88
Stop seat 8.58 2.06 6.52 152.7 151.97 0.97
Stop slot 19.55 4.69 14.86 124.82 122.63 2.97
Milling barrel 11.56 2.77 8.79 125.13 123.88 1.78 Pre drilling 10.14 2.43 7.71 127.13 125.83 1.76
The bottleneck processes is the stop slot process therefore this
would dictate the increase in output of the whole line. The increase in
output would be equal to 2.97 units per day.
53
On the other hand, the management can choose alternative H
which is to maintain the current system. This would not incur cost to the
production but would not reduce the machine unproductive time caused
by low-table height for inspection.
Alternative Solutions to Experimental Factor E4
Alternative solution I is to adapt 5S program in the production.
A Five S (5S) program is usually a part of, and the key component
of establishing a Visual Workplace. It focuses on having visual order,
organization, cleanliness and standardization. It can also reduced set-up
times and cycle times, Increased floor space and working space, lower
safety incident or accident rate, better equipment reliability, and less
wasted labor.
The study recommends the company to implement the 5S
program in the production to maintain orderliness, organization, and
standards in the production line. Since the operators do not already have a
background on 5S, the management can organize a half-day orientation
about the program. Since the only 10 workers from the production will be
involved, a half-day-orientation would be enough. Table 4-14 lists the
proposed introductory discussion about each ‘S’ in the 5S.
54
Table 4-14 Proposed discussion for the orientation on 5S program
5S English Translation
Concept
Seiri
Sort
Clearing the work area: Difining all the materials that will be necessary in the production and those that are not should be kept in storage. Thework area should only have the items needed to perform the work
Seiton
Set In Order
Designating locations: Everything in the work area should be placed and designated properly. The use of signs and labels to identify "what is to be stored where" helps employees use storage locations as they were intended to be used.
Seiso
Shine
Cleanliness & workplace appearance: The work area should be clear and clean. It involves housekeeping efforts, improving the appearance of the work area, and preventive work area from getting dirty. Using preventive measures to keep the workplace clean:
• Once the work area, tools, and equipment are clean, they need to be kept that way.
• Continued housekeeping
• Preventive measures from getting dirty in the first place.
• Root cause analysis, mistake-proofing
Shit-suke
Standar-dize
Everyone doing things the same way:
Everyone in the work area and in the organization must be involved in the 5S effort, creating best practices and then getting everyone to "copy" those best practices the same way, everywhere, and every time.
Sei-ketsu
Sustain
Sustain: Ingraining the 5S's into the cultureIt involves a culture change and to achieve a culture change, it has to be established in the organization - by everyone at all levels in the organization.
Adapting 5S in the production system will minimize unproductive
times on the machining line. It can address the system’s problem on
55
machine waiting time due to double filing, not following procedures such as
prioritizing other tasks than attending the machine, material unavailability at
the workstations and other incorrect practices in the production.
Since the concept is not practiced and applied in the company,
there should be an orientation of the 5S concept to the operators in the
black slide line as well as to other operators in the whole machining
production line. Listed in table 4-15 are the proposed applications for each
‘S’ in the 5S.
Table 4-15 List of applications for each ‘S’ 5S Application
Seiri
• Define the materials frequently needed (file hand tool, unloading/loading tool, raw materials, inspection tools, and calculator, dolleys).
• Define the materials rarely used (water containers, tool changing materials, wrench, tool cutters, cleaning materials etc.)
Seiton
• Use separate boxes as containers of filed materials and materials that are to be filed.
• Label the boxes as “filed “and “to be filed”.
• Put the tools in their proper places. The file hand tool as frequently used should be placed at the right side of the table and the unloading tool at the hanging platform in front of the machine body. Only the file hand tool and the boxes should be placed in the table for ease of getting materials and filing.
• Only measuring tools(height gage, calculator, caliper) should be found in the inspection table
• Calipers used for in section in the work table should be placed in the platform of the machine.
56
Seiso
• Clean table after filing the materials. The operator assigned to the workstation should be the one responsible in cleaning his workstation. Not only the worktable should be cleaned, the but also the materials and the machine. Conduct routine cleaning maintenance. Collect wastes.
Seiketsu
• Define tasks of operators, regulations, and standard working procedures within the production. Tasks include moving the material to the next when already processed, following standard operating procedures. Machines should be attended first before other tasks. Rules include avoiding frequent leaving from work, chatting or hopping stations for no valid reason or non-work related matters.
• Use posters to remind the right procedures that will serve as a guide for the operators..
Shitsuke
• Recognize jobs that were done well d
• Bulid a concept of teamwork with the operators to motivate them
• Continuously stress and remind roles and responsibilities
This program mainly addresses the problem on double filing of the
materials. Seiton or to “set in orde” as highlighted in the table above is the
‘S’ that answers the problem on double filing which is one of the causes
that the study solves. The study recommends through the concept of
“Seiton” to use separate boxes for filed materials and materials that are yet
to be filed to prevent adhesion of waste metal chips to the slides. Figure 4-8
shows the proposed arrangement of materials used in work surface of the
table used by the operators.
57
Figure 4-8 Work table surface layout
To implement the program, the management should be able to
communicate the significance of the program to the company and to the
operators as well. They should keep reinforcing and emphasizing the
program to the operators. The proposed flow chart of implementing 5S is
shown in figure 4-9.
Figure 4-9. Flow chart of 5S program implementation
The implementation must start with the top management to build the
leadership team. They will be the ones to develop and plan the programs
that are to be taught to the operators and other employees of the company.
The next process will be communicating the planned program to the
production line operators. Included in this step is the use of communication
media such as having regular meetings involving all employees of the
company. Posters containing the important details of the program will be
helpful in reminding the operators as well as other employees of the
contents and major points of the program.
TO BE FILED
F
I
L
E
Build the Leader- ship
Communi-cate to the Body
Training and
Practice
Recognize changes
Continuous Evaluation
58
After the program has been communicated, training of the operators
and leaving them to practice will follow. Supervisors must assist and guide
the operators while practicing the details of the program to motivate them
more. The operators may be also be trained problem-solving techniques,
what to do in a certain situation, when to do a task, and how to do it. As part
of initial evaluation, the operators should be involved in recognizing
changes. The management should get inputs or ideas from the operators to
improve the program. From initial evaluation, new and improved plans can
be developed including the right sequence of processes, working
procedures and performance measures.
The cost that will be incurred in implementing 5Sprogram would
estimate to Php1500 for miscellaneous and for posters and leaflets.
The main effect on the problem of adapting 5S program is on the
elimination of machine unproductive time due to double filing of the
materials. Table 4-16 shows the machine unproductive time that would be
reduce at each process due to double filing.
Table 4-16 Machine unproductive time due to double filing
Process Machine Unproductive Time per
day (min)
Face-off 7.55
Drilling 16.76
Mill ref 7.85
Mill clearance 8.86
Stop seat 6.54
Stop slot 13.99
milling barrel 10.38
pre drilling 15.27
Table 4-17 shows the effect on the output of each process when 5S program is adapted in the production.
59
Table 4-17 Effect on process output of adapting 5S process
T
h
e
f
i
n
a
l
Before improvement, the capacity is lower due to unproductive
time, but after unproductive time reduction, the capacity was increased.
The increase in output of the whole line depends on the stop slot and
milling barrel processes since these processes are the bottleneck
processes. The increase in output would be equal to the average of the
increase in units in the two processes because the capacity results after
improvement of both processes are the same. The average output would
be equal to 2.44 units per day when the machine unproductive time due
to double filing was eliminated.
4.2.6. Evaluation of Alternative Solutions
The alternative solutions for each factor were evaluated based on
different criteria and ranking system.
For experimental factor E1, the criteria with the corresponding
percentages and the ranking system are shown in table 4-18.
Process Machine UT
(min/day)
Effective time/day (min)
Unit Normal Time (min)
Capacity Increase in units per day before after
Facing -off
7.55 200.89 0.99 195.3 202.92 7.63
Drilling 16.76 689.48 5.4 124.58 127.68 3.1
Milling Ref
7.85 226.44 1.48 147.7 153 5.3
Milling Clearance
8.86 1049.11 5.17 201.21 202.92 1.71
Stop seat 6.54 1023.56 6.69 152.02 153 0.98
Stop slot 13.99 630.03 5.01 122.96 125.75 2.79
Milling Barrel
10.38 619.97 4.93 123.65 125.76 2.11
Pre drilling
15.27 560.521 4.39 124.20 127.68 3.48
60
Table 4-18 Criteria and scoring system for factor E1
Score
Effectiveness
(50%)
(addition in units)
Fatigue-
reducing (40%)
Ease of
implementation
(10%)
3 >3- 4.5 More reducing easy
2 >1.5- 3 Slightly reducing average
1 0-1.5 Not reducing difficult
Three criteria were considered in the evaluation: effectiveness,
fatigue-reduction, and ease of implementation. Effectiveness refers to the
number of units the alternative can increase or add to the output. Fatigue-
reduction refers to the level of reduction of fatigue the alternative can
cause to the operator and ease of implementation is how easy it is for the
management to apply the solution. The summary of scores for each
alternative in each criterion is presented in table 4-19.
Table 4-19. Scores under each criterion for factor E1.
Alternatives
Effectiveness
(50%) Fatigue-
reducing
(40%)
Ease of
Implementa-
tion (10%) Units
added score
1. Add 30 minutes to
break 1.9 2 3 1
2. Reschedule 15-min
break 4.91 3 2 1
3. Maintain current
system 0 1 1 3
The summary of total final scores of each alternative is presented
in table 4-20.
61
Table 4-20. Summary of total score for factor E1
Alternatives
Effectiveness
(50%)
(addition in
units)
Fatigue-
reducing
(40%)
Ease of
implementa-
tion (10%)
Total
1. Add 30 minutes to
break 1 1.2 0.1 2.3
2. Reschedule 15-15-
min break 1.5 0.8 0.1 2.4
3. Maintain current
system 0.5 .4 0.3 1.2
Based on the total scores, the best alternative solution is to re
reschedule 15-minuute break in the morning and in the afternoon with a
total score of 2.4. Though it is less fatigue-reducing than adding 30-
minute break time, it was given the highest score because it is the most
effective solution among the three. It can render an increase in output of
4.91 units per day compared to adding 30 minutes which can only render
an increase of 1.9 units per day (computation shown in the discussion of
alternative solutions). Maintaining current system was given the lowest
score since it would not eliminate or reduce machine unproductive time
due to operator delay nor would it reduce worker-fatigue.
For experimental factors E2 and E3, same criteria and scoring
system were used. Table 4-21 shows the scoring system and the criteria
used in rating the alternatives.
Table 4-21 Criteria and scoring system for Factor E2 and E3 Score Effectiveness (40%)
(addition in units)
Cost (20%) Fatigue-reducing
(40)
3 >2-3 0- 1000 More reducing
2 >1 - 2 >1000 - 2000 Slightly reducing
1 0-1 >2000 - 3000 Not reducing
62
The summary of scores for each alternative for factor E2 under
each criterion is shown in table 4-22.
Table 4-22 Scores under each criterion for factor E2
h The total score for each alternative solution for factor E2 is
presented in table 4-23.
Table 4-23 Summary of total score for factor E2 Alternatives Effective-
ness (40%)
Cost (20%)
Fatigue-reducing (40%)
Total
1. Buy height-designed
table
1.2 0.2 1.2 2.6
2. Use table used in other
workstations
1.2 0.2 0.8 2.2
3. Maintain current system 0.4 0.6 0.4 1.4
Based on the final scores, buying height-designed table is the best
solution to reduce machine unproductive time caused by late filing with a
total score of 2.6. It is as effective as the second alternative solution
because both can render an increase of 2.94 units per day. Buying either
table would also incur the same cost. But the first alternative is more
fatigue-reducing since the height of the table is designed based on the
height of the operator that is why it is given the highest score. Though
Alternatives
Effectiveness (40%)
Cost (20%) Fatigue-reducing (40%) Units
added score
Cost (Php)
score
1. Buy height-designed
table 2.94 3 3000 1 3
2. Use table used in other
workstations 2.94 3 3000 1 2
3. Maintain current system 0 1 0 3 1
63
maintaining the current system would not incur any cost, it was given the
lowest score because it is the not fatigue-reducing and it is ineffective.
For evaluation of Experimental Factor E3, the same criteria and
scoring system as in factor E3 were used. Table 4-24 shows the score for
each alternative under each criterion.
Table 4-24 Score under each criterion for factor E3
T
The summary of total scores for each alternative solution for
factor E3 is presented in table 4-25.
Table 4-25 Summary of total score for factor E3.
Based on the total scores, the best solution to reducing machine
unproductive time due to machine adjustment is buying height- designed
table with a total score of 2.6. It was given the highest score because it is
Alternatives
Effectiveness (40%)
Cost (20%) Fatigue-reducing (40 %)
Units
added
score Cost
(Php)
score
1. Buy height-designed
table for inspection
2.97
3 3000 1 3
2. Maintain current
system
0
1 0 3 1
Alternatives Effectiveness
(40%) Cost (20%)
Fatigue-reducing (40%)
Total
1. Buy height-
designed table for
inspection
1.2 0.2 1.2 2.6
2. Maintain current
system 0.4 0.6 0.4 1.4
64
more effective than maintaining the current system though it would incur
cost to the production. It can render an increase of 2.97 units per day.
Also, it is fatigue-reducing since the height of the table is designed based
on the height of the operator.
For evaluation of factor E4, the criteria that were considered
include cost of implementation, ease of implementation and effectiveness.
Table 4-26 presents the scoring system for each alternative.
Table 4-26 Criteria and Scoring system for factor E4
The total scores for each alternative for factor E4 are presented in
Table 4-27
Table 4-27 Scores under each criterion for factor E4 Alternative Effectiveness
(50%)
Cost (30%)
Ease of
implementation
(20%) Added
units
score Cost
(Php)
score
1. Adapt 5S
Program 2.44 3 1500 2 2
2. Maintain
current system 0 1 0 3 3
Table 4-28 summarizes the total score of each alternative for
factor E4.
Score Effectiveness (50%) (addition in units)
Cost (30%) (Php)
Ease of implementation
(20%) 3 >2-3 0- 1000 easy
2 >1 - 2 >1000 - 2000 average
1 0-1 >2000 - 3000 difficult
65
Table 4-28 Summary of total score for factor E4
Adapting 5S program is the solution to reducing machine
unproductive time due to double filing of the materials. Although it would
incur cost to the company and the company has to plan for its
implementation it is better than maintaining the current system since it
can render an increase of 2.44 units per day compared to maintaining the
current system which is ineffective because it would not reduce or
eliminate the machine unproductive time caused by double filing.
The summary of reduced machine unproductive time is at each
cause is presented in Table 4-29 along with the overall increase per day
at each process. Capacities of each process per day before and after
improvement are also presented to see the increase per day from
reducing machine unproductive time at each process.
Alternatives
Effectiveness (50%)
(addition in units)
Cost (30%)
Ease of implementation
(20%)
Total
1. Adapt 5S
Program 1.5 0.6 0.4 2.5
2. Maintain
current system 0.5 0.9 0.6 2
66
Table 4-29. Summary of increased output per day at each process
67
As shown in the table above, implementing the best solutions would
reduce a total of 68.83 minutes of machine unproductive time. It is also shown
that these, in effect would increase the output of the black slide machining
production line by 14 units per day or 364 units per month. This is equivalent
to Php1, 218, 672 per year but to meet the monthly demand of 2800 units per
month, only 329 units are considered lost sales thus this number of units will be
added to the sales of the production. This is equivalent to Php1, 101, 492 per
year. The summary of costs for the initial year of implementing each solution is
presented in Table 4-30.
Table 4-30. Summary of costs of implementing the solutions
The savings for the initial year would be equal to the difference of the
total benefits and the total cost incurred in the first year.
Savings for the initial year = Php1, 101, 492 – Php12, 250
= Php1, 089, 242
For the succeeding years, no more costs will be incurred since the
recommendations require one-time investments. The savings for the
succeeding then would then be equal to the annual benefit of Php1, 101, 492.
Recommendation Costs for the Initial Year
(Php)
Buy height-designed table for filing
and inspection 5000 *2
Adapt 5S 1500
Buy tools 750
Total 12, 250
68
5. Summary and Conclusions
69
The Black slide machining production line does not meet its monthly
demand of 2800 units. Because of this, the production line loses sales of 329
units each month amounting to Php1, 101, 492 per year. Using time study, it was
found out that the capacity if the line can meet the demand. One possible area
identified for increasing output was the reduction of machine unproductive time to
increase the monthly output of the production line. It was verified that the 22% of
the total effective production time is accounted by machine unproductive time.
Using Ishikawa diagram, the root causes were identified. These include
low height design of table for filing and inspection, insufficient number of tools,
lack of strict supervision, poor workplace, and worker delay which include
chatting of operators, start-up delay and frequent leaving of the workstation. CNX
Analysis was used to group the factors and to determine where to focus the
solutions and recommendations. Chatting of operators was identified as noise.
Start-up delay, insufficient number of tools, and lack of strict supervision were
grouped under controllable factors. Frequent delay of leaving the workstation,
low height design of tables, and poor workplace were categorized under
experimental factors. Direct solutions were addressed to controllable factors and
alternative solutions were generated for the experimental factors.
For frequent delay of leaving the workstation the alternative solutions
generated were adding 30-minute break time, rescheduling 15-min break time in
the morning and maintaining the current system. For low height design of table
for filing, the alternative solutions include buying new height-designed table,
providing the same table used in other workstations, and keeping the current
system. For low-height table used in inspection, the alternatives generated were
buying the height-designed table and maintaining the current system. For poor
workplace, the alternatives include adapting 5S program and maintaining the
current system. Using different criteria for each factor and through factor rating
method, the alternatives were evaluated. Some of the criteria used are
effectiveness, cost of implementation and fatigue reduction.
From the ratings, the best alternative solutions determined include
rescheduling break time, adaptation of 5S program, and the use of height-
designed tables for inspection and for filing.
70
Based on the results, it was concluded that a monthly increase of 364
units on the bottleneck process can be improved and from these the production
can now meet its monthly demand of 2800 units per month. The costs of each
solution chosen were also considered and it was determined that if the
recommendations would be implemented, the company would have a total
savings of Php1, 089, 242 in the first year and Php1, 101, 492 for the succeeding
years.
71
6. Recommendations
72
The study has come up with four major recommendations. First is
rescheduling 15-minute break of operators in the morning and 15 minutes in the
afternoon. Since worker delay is the main cause of machine unproductive time in
the production this would reduce such unproductive time.
Second is the use of height-designed tables to prevent worker back
fatigue. This would reduce delays due to fatigue and so the unproductive time of
the machines due to machine adjustments. Along with these two
recommendations is having strict supervision in the production. The operators
should always be supervised to monitor if they are performing the assigned tasks
to them. This is to address avoidable worker delays such as chatting with other
operators in the machining section and station hopping.
Third, there should be tools designated for each workstation to avoid
transport delays of operators. It should also be taught to the operators to keep
their own tools to avoid misplacement and tool searching.
Fourth, the study recommends adapting and implementing 5S program in
the production. As one main cause of idle time is the practice of double filing of
the materials due to dirty workplace, adapting 5S will lessen such problem. The
program would also address problems on materials unavailability and problems
on regarding procedures. In line with the program is building standards and
correct working procedures for the operators to follow. The management should
train the operators on proper working procedures such as cleaning the
workplace, keeping of tools, following standard operating procedures, and doing
their own responsibilities.
The management should also be able to build and impart a concept of
discipline to the operators so that the procedures set would not be violated and
avoidable delays would be prevented in the production. The management should
also continuously monitor and evaluate the performance of the operators.
73
7. Areas for Further Study
74
The study considered only the reduction of the machine unproductive
time as an area for improvement and a means to meeting demand by increasing
the output of the Black slide machining production line.
Studies can also be conducted on other possible area which causes low
production output. The material supply or delivery, and the performance of the
operators working in the night shift can also have effect on the output of the black
slide production line. The gathering of data was done in the morning shift only.
Twenty two percent was verified as the percentage of machine unproductive time
contributed by the morning shift which reduces the potential output of the
production line. This only reflects the unproductive time present in the morning
shift and so the night shift can also be studied to get the percentage of
unproductive time it contributes to the total unproductive time per day in the
production line.
Four machines only which are regularly used were considered in the
study. The other machine that is not regularly used can also be studied in order
to evaluate its effect in the capacity of the production. Utilizing this machine may
increase the effective capacity of the black slide production line and so the output
of the line can also be increased.
A study can also be done on increasing the cycle time of the machines to
speed up processing but this will involve a trade-off between increasing
production rate and increasing possible machine delays because the number of
operators might not be enough to handle the machines.