[email protected] Suresh.B –9440163282 Manual Testing 1 Jai Sri Ram Jai Sai Ram Quality Quality means satisfaction of the customer. To define good quality of software, the company people will concentrate on two (2) factors such as 1) Technical factor and 2) Non-technical factor. 1) Technical factor a. Customer requirements in terms of functionalities. b. Customer expectations (Look and feel, Ease of use, right output, speed of processing, security) 2) Non-technical factor a. Low cost to purchase b. Time to market. S.Q.A (Software Quality Assurance) It means monitoring and measuring the strength of development process. REQUIREMENTS GATHERINGS Business Development People / Business Analyst Business Requirement Specification (BRS) / User Requirement Specification (URS) / Customer Requirement Specification (CRS) ANALYSIS Analyst Software Requirement Specification (S/W RS) FRS Functional Requirement Specification SRS System Requirement Specification DESIGN Designers Design Document LLD Low Level Design Document HLD High Level Design Document CODING Programmers TESTING Testers PROJECT MANAGEMENT Release and Maintenance

Transcript of Manual)

Page 1: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 1

 

Jai Sri Ram Jai Sai Ram Quality

Quality means satisfaction of the customer. To define good quality of software, the company people will concentrate

on two (2) factors such as 1) Technical factor and 2) Non-technical factor. 1) Technical factor

a. Customer requirements in terms of functionalities. b. Customer expectations (Look and feel, Ease of use, right output,

speed of processing, security) 2) Non-technical factor

a. Low cost to purchase b. Time to market.

S.Q.A (Software Quality Assurance) It means monitoring and measuring the strength of development process.

REQUIREMENTS GATHERINGS Business Development People / Business Analyst

Business Requirement Specification (BRS) / User Requirement Specification (URS) / Customer Requirement Specification (CRS)

ANALYSIS Analyst

Software Requirement Specification (S/W RS)

FRS Functional Requirement

SpecificationSRS

System Requirement Specification

DESIGN Designers

Design Document LLD Low Level Design Document 

HLD High Level Design Document 

CODING Programmers 

TESTING Testers 

PROJECT MANAGEMENT Release and Maintenance 

Page 2: Manual)

Suresh.B –9440163282 [email protected] 

2 Manual Testing

1) REQUIREMENT GATHERINGS: In general software development starts with requirement gathering. In

this stage Business Development People (BDP) / Business Analyst People (BA) are preparing Business Requirement Specification Document (BRS) / User Requirement Specification Document (URS) / Customer Requirement Specification Document (CRS), after gathering all required requirements from the user / customer.

Business Requirement Specification Document defines the requirement of the customer.

2) ANALYSIS: After completion of Business Requirement Specification Document,

Analyst People are preparing “Analysis Document”. This document is also called as “Software Requirement Specification Document” (S/w RS). The document consists of (2) Sub documents such as FRS & SRS

(i) FRS It means “Function Requirement Specification”. It defines

the required functionality to be used in the project. (ii) SRS

It means “System Requirement Specification”. It defines the required Hardware to develop that functionality.

3) DESIGN After completion of Analysis Document, Designers are preparing Design

Document. It consists of (2) sub documents, such as (i) HLD & (ii) LLD (i) HLD (High Level Design Document)

It is also called as External Design Document. It defines the hierarchy of over all application functionalities in terms of modules from root level to leaf level.

Ex:

Mail  Chat 

Login

Logout

Page 3: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 3

 

(ii) LLD (Low Level Design Document) It is also known as Internal Design Document. It defines the

internal logic of every functionality or module in terms of ER Diagrams, Data Flow Diagrams.

4) CODING: A Physical construction of Software is called as “Coding”.

Build: An executable form of all integrated module set is called “Build”.

5) TESTING In this stage, the testers are validating that developed Build with

respective Customer requirements and customer expectations. 6) RELEASE AND MAINTENANCE

After completion of software testing the Project Management will deliver that software to customer for usage.

During utilization of the software, if customer get any problem or if customer want to enhance the application, that can be handled by the company people.

System

M1 M2 M3

S2 S3 S1

SS1 SS2 SS3

P3 P2 P1

LOGIN User Name Password

V

V

OK CANCEL

DATA BASE

V

IV

IV

V

IV

IV

V - Valid

IV - Invalid

MESSAGE BOX

Please Try Again   OK

INBOX

Note: A Project will have one HLD and Multiple LLDs.

BUILD

Page 4: Manual)

Suresh.B –9440163282 [email protected] 

4 Manual Testing

What is the difference between Software Product and Software Application?

Software Application If the Software developed with respective particular client requirements

or single client requirements that can be called as Software Application. Ex: Bank Applications, Hospital Applications.

Software Product If the Software developed with respective multiple clients requirements,

that can be called as Software Product. Ex: MS Office, VB, Operating System etc.,

What is Error, Defect, Bug? Error:

Any mistake in a programme is called “Error”. Defect:

Any mistake found by the tester during Testing can be called as “Defect”. Bug:

The reported defect is accepted by developer to resolve can be called as “Bug”.

SQC (Software Quality Control)

It is a process of validating the Software.

Why Software has Bugs? (i) Poor requirements (ii) Futurities (Customers requirements are frequently changing) (iii) Miscellaneous Communication. (iv) Unrealistic schedule (v) Inadequate testing. Solutions (i) Solid requirements (ii) Good communication (iii) Realistic schedule (iv) Adequate testing (v) Gather / Stick to initial requirements as much as possible.

Page 5: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 5

 

TESTING MODELS FISH MODEL

Fish model defines the mapping between development stages and Testing stages.

Reviews in Analysis

In general Software Development process starts with requirements gathering and analysis. In this, Business Development People are preparing Business Requirement Specification Document and Analyst people are preparing Analysis Document with respective to Business Requirement Specification.

After completion of analysis document, the same category people conducting reviews in Analysis Document for completeness and correctness.

During the review they are concentrate on the below factors. i) Are they complete? ii) Are they right requirement? iii) Are they achievable? iv) Are they reasonable? v) Are they testable?

Reviews in Design Document

After completion of Analysis document and corresponding reviews, designers are preparing design document which includes Functional Requirement Specifications and System Requirement Specifications.

After completion of design document the same category people are conducting reviews in design document for completeness and correctness.

During the review they concentrate on below factors.

Requirements Gathering

BRS / CRS / URS

Reviews in Analysis

S/W RS (FRS & SRS) Analysis

Reviews in Design

Design (HLD & LLD) Coding

White Box Testing / Glass Box Testing /

Programe Phase Testing / Open Box

Testing

Black Box Testing /

Functional & System Testing

/ Close Box Testing

Release & Maintenance

Test Software Changes

Validation Verification

Page 6: Manual)

Suresh.B –9440163282 [email protected] 

6 Manual Testing

i) Are they complete/ ii) Are they met right requirements? iii) Are they understandable? iv) Does they handle Errors or not?

White Box Testing After completion of deign document and correspondence reviews,

programs with concentrate on coding to construct a Software Build. After completion of preparing all programs, Programmers are

interconnecting them to a system. In this interconnection of programs to verify the programs and interface between programs or modules, programmers are conducting “White Box Testing”

White Box Testing classified as Two Types such as (I) Unit Testing (II) Integration Testing.

(I) Unit Testing It is also called as Program Testing or Micro Testing. Unit testing

means “Single Program Testing or Component Testing. Unit testing consists of below factors.

a) Basic Path Testing. During this testing programmers are checking that whether

the program is running or not? To perform this test they will follow below approach. 1) Draw flow diagram of that program. 2) Calculate number of independent paths in that program

(Cyclometic Complexity) (The number of independent paths in the program)

3) Execute the program more that one time to cover all independent paths in that program.

b) Control Structure Testing In this testing the programmers will concentrate on

corresponding program output. In this programmers will concentrate on every statement

including, If conditions, For loops, Memory allocation etc., c) Program Technique Testing

In this testing the programmers are checking the execution speed of the program.

If the execution speed of the program is not good, then programmers are performing changes in the structure of the program without disturbing functionality.

d) Mutation Testing Mutation means changes in a program. In this testing

programmers are performing wanted changes in the program and executing the program repeatedly. In this Test repetition,

Page 7: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 7

 

Programmers are checking the completeness and correctness of the Test.

Passed Passed Failed (In-compete (Complete Testing) Testing)

(II) Integration Testing After completion of dependent program development and

corresponding Unit Testing, Programmers are interconnecting to form a system. To estimate the interface between programs or modules programmers are conducting Integration Testing. They are (4) Types of approaches. a) Top-Down Approach.

The verification of main module without coming to some of the Sub-Modules is called as Top-Down Approach.

“Conduct test on Main module without conducting test on some of the Sub-Modules is called Top-Down Approach.”

In the above approach “STUB” is a Temporary Program, it

works like as under constructive Sub Module, it is also called as Called Program.

b) Bottom-Up Approach. The verification of Sub-Modules without coming from Main

Module is called “Bottom-Up” Approach. “Conducting test on Sub-Modules without testing on Main

Module is called Bottom-up Approach.

In the above approach “Driver” is temporary program, it

works like as under constructive Main Module. Driver is also known as Calling Program.

Perform change

A=10 B=20 I=A+B C=I msgbox I

A=10 B=20 C=A+B msgbox I

Main Module

Sub-Module-1 Sub-Module-2

STUB

Sub-Module-3

Main Module

Driver / Calling Program

Sub-Module-1 Sub-Module-2 Sub-Module-3

Temporary Program / Called Program

Page 8: Manual)

Suresh.B –9440163282 [email protected] 

8 Manual Testing

c) Hybrid Approach / Sand-witch Approach

The combination of Top-down Approach and Bottom-Up

Approach is called as Hybrid Approach / Sand-witch approach.

d) Bigbang Approach. The verification of all modules after completion of all

Modules development and corresponding unit testing is called as “Bigbang Approach”.

This approach is not suitable for large modules.

CASE STUDY

Case 1: Top-down approach is followable, when the customer’s

requirements are constituent of clear.

Case 2: Bottom-up approach is followable, when the customer’s

requirements are not clear or frequently changing.

Case 3: Hybrid Approach is followable, when the customer’s requirements

are clear and the architecture structure of the system is changing.

Case 4: Bigbang Approach is followable, when the application build

consists less number of modules or less number of

interconnections.

Main Module

Driver / Calling Program

Sub-Module-1 Sub-Module-2 Sub-Module-3

Sub-Sub-Module-1

STUB

Sub-Sub-Module-2 Sub-Sub-Module-3

Bottom-Up Approach

Top-Down Approach

Page 9: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 9

 

BLACK BOX TESTING After completion integration of all modules to form a system, developers

are sending that build to the separate Testing team. This separate testing team validates the Software build with respective customer’s requirements and expectations through “Black Box Testing” techniques.

It is also known as “Close Box Testing” / “Functional & System Testing” It is classified as (3) types such as

1) Usability Testing. a. User Interface Testing. b. Manual Support Testing.

2) Functional Testing. a. Functionality Testing. b. Sanitation Testing.

3) Non-Functional Testing. a. Recovery Testing. b. Compatibility Testing c. Configuration Testing. d. Intersystem Testing e. Comparative Testing f. Security Testing. g. Installation Testing. h. Load Testing. i. Stress Testing j. Data Volume Testing. k. Storage Testing.

1) Usability Testing After receiving build from the development people, testers are conducting

usability testing to check whether the application build is providing user friendly screens or not.

Usability Testing is classified into (2) Types such as (a) User Interface Testing (2) Manual Support Testing.

a. User Interface Testing During this testing testers are checking the Look and Feel, Ease of

use of application of build screen. Ex: The Microsoft (6) Rules for testing 1) Controls are initcaps. 2) Ok, Cancel existence. 3) System Menu existence. 4) Controls are not overlapped. 5) Controls should be visible. 6) Controls must be aligned.

Page 10: Manual)

Suresh.B –9440163282 [email protected] 

10 Manual Testing

b. Manual Support Testing It is also known as “Help document Testing”. During this testing

Testers are checking the context sensitiveness testing. Ex: Spelling Mistakes, Grammar mistakes, Word Missing, Line

Missing etc., Case 1: Receive build from the developers.

User interface testing. Functional & Non-Functional Testing Manual Support Testing.

2) Functional Testing After completion of User Interface testing, Testers are conducting

Functional Testing to validate customer requirements. Functional Testing classified into (2) Types (a) Functionality

Testing (b) Sanitation Testing. a) Functionality Testing

During this Testing Testers are validating customers requirement in terms of (6) coverage. 1) Behavioural Coverage. 2) Input Domain Coverage. 3) Error-Handling Coverage. 4) Calculation Coverage. 5) Back-end Coverage. 6) Service level Coverage.

1) Behavioural Coverage. In this testing Testers are checking whether the objects are properly

responding of not, with respective to Business Operation. 2) Input Domain Coverage

In this testing Testers are checking whether the input objects / Input fields are taking right type and range of value or not.

To perform this test we (Testers) are using (2) Types of Testing. (i) BVA (Boundary Value Analysis (ii) ECP (Equivalence Class Partitioning)

BVA (Range of Object)

ECP (Defines Type of Object)

Range Expected Actual Result Valid Invalid Min= Min-1= Min+1= Max= Max-1= Max+1=

Pass Fail Pass Pass Pass Fail

Pass fail

Usability Testing

Page 11: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 11

 

Ex: A Login process allows User Name and Password from a User. In this User Name object allows “Alphabets lower case” Range from 4 to 8 Characters long and Password object allows “Alphabets lower case” range from 6 to 10 Characters long.

Prepare BVA and ECP for the above expected.

BVA & ECP for User Name BVA ECP

Range Expected Actual Result Valid Invalid Min= 4 Char Min-1= 3 Char Min+1= 5 Char Max= 8 Char Max-1= 7 Char Max+1= 9 Char

Pass Fail Pass Pass Pass Fail

[a-z] [A-Z] [0-9] All

Special characters

BVA & ECP for Password

BVA ECP Range Expected Actual Result Valid Invalid

Min= 6 Char Min-1= 5 Char Min+1= 7 Char Max= 10 Char Max-1= 9 Char Max+1= 11 Char

Pass Fail Pass Pass Pass Fail

[a-z] [A-Z] [0-9] All

Special characters

Ex: Age object allows numeric range from 16 to 60.

Prepare BVA and ECP for the above expected.

BVA & ECP for Age BVA ECP

Range Expected Actual Result Valid Invalid Min= 16 Min-1= 15 Min+1= 17 Max= 60 Max-1= 59 Max+1= 61

Pass Fail Pass Pass Pass Fail

[0-9] [A-Z] [a-z] All

Special characters

Page 12: Manual)

Suresh.B –9440163282 [email protected] 

12 Manual Testing

Ex: Mobile No. object allows numeric 10

digits only. Prepare BVA and ECP for the above expected.

BVA & ECP for Mobile No. BVA ECP

Range Expected Actual Result Valid Invalid Max= 10 Max-1= 9 Max+1= 11

Pass Fail Fail

[0-9] [A-Z] [a-z]

All Special characters

3) Error-Handling Coverage. In this we are checking whether the objects are preventing

“Negative Operations” or not.

4) Calculation Coverage. In this we are checking whether the functionality output is right or wrong.

5) Back-End Coverage.

ODBC JDBC

In this testing we are checking whether the insert of front end operations on back end table context.

6) Service level coverage.

The order functionality.

Page 13: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 13

 

b) Sanitation Testing It is also known as “Garbage Testing”. During this testing,

testers are finding extra functionalities in the build with respect to customer requirements.

3) Non-Functional Testing After completion of Functional Testing, testers are concentrating

on Non-Functional Testing to validate extra characteristics of that build. They are divided into (11) Types.

a) Recovery Testing During this testing we are checking that whether the application

Build is changing from Abnormal State (Crash / Hang) to Normal State or not.

Abnormal State to Normal State Normal State

Abnormal State

b) Compatibility Testing They are (2) types of Compatibility Testing.

V.B Unix VC++ Win98 Ex: Unix does not support VB Win98 is supporting VC++ Techniques But Build is not working

Properly due to defects During this testing we are checking whether the application build is

able to run on different platforms or not. Platform means Operating System, Browsers, compilers and other

System software’s.

Build

O.S

Build

O.S

Page 14: Manual)

Suresh.B –9440163282 [email protected] 

14 Manual Testing

c) Configuration Testing It is also known as “Hardware Compatibility Testing”. During this

testing we are validating whether the application build is supporting different technologies input / Output devises or not.

d) Intersystem Testing. It is also known as “Inter operability Testing”. During this testing

we are checking whether the application build is coexistence with other existence to share common resource or not.

Ex.: E-Seva.

e) Comparative Testing. It is also known as “Competitive Testing”. During this testing we

are comparing the features of produce with some like previous produce (or) Existing produce in the market to estimate competitiveness.

f) Security Testing. It is also known as “Penetration Testing”. During this testing we

are validating (3) types of factors such as (i) Authorization. (ii) Access Control. (iii) Encrypt / Decrypt Data Testing.

(i) Authorization. In this testers are checking whether a valid user is accessible

or not, invalid user is preventable or not. (ii) Access Control

In this we are checking whether a valid user have permission to use specific features / Services or not.

Common Data Base

Server

Server Elec. Bill

Telephone Bill

Water Tax Bill

Income Tax Bill

Municipal Bill Server

Server

Server

Note: Comparative Testing is applicable for Software Produces only not for applications, because Software application is developed for a single client requirement, but product can be developed with respect to multiple clients requirements.

Page 15: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 15

 

(iii) Encrypt / Decrypt Data Testing. The code conversion in between client process and server

process to avoid third party accessing.

g) Installation Testing It is also known as “Deploying Testing”. During this testing we

are validating below factors.

h) Load Testing. Run the application under customer expected configuration under

customer load to estimate the speed of processing is called “Load Testing”.

i) Stress Testing. Run the application under customer expected configuration under

various loads from low to peak to estimate Stress capacity of the application build is called Stress Testing.

j) Storage Testing. The execution of application build under customer expected

configuration under huge amount of resources to estimate the storage capacity of the application database is called Storage Testing.

k) Data Volume Testing. During this testing Testers are calculating the number of records to

be stored into application database.

CLIENT User Name

Password

SERVER

Request Encrypt

Cipher Text

Cipher Text

Decrypt

Request

Encrypt Decrypt

Build & Supported

Software

Customer expected configure Computer

Setup Program. Easy Navigation. Occupied Disk Space. Check Un-installation.

Note: Storage Testing, Data volume Testing coverages same, but Storage Testing is representing in Number of bytes and Data Volume Testing is representing number of Records.

Page 16: Manual)

Suresh.B –9440163282 [email protected] 

16 Manual Testing

GRAY BOX TESTING Gray Box Testing is a combination of “White Box Testing” and

Black Box Testing. UAT (User Acceptance Test)

After completion of Software Testing, the Project Management / Project

Manager will invite customer to collect feedback on one developed software.

They are (2) types such as α – Test

(Alfa Test)

β – Test (Beta Test)

Software Application. By Real customer. At development site.

Software Product. By Model customer. At customer site.

Release Testing

It is also known as “Port Testing”. After completion of User Acceptance Test” and corresponding modifications, the Project Management will establish Release Team with few Developers, few Testers and One (or) two Hardware Engineers. This release team will go to customer’s site to install the software ion the customer’s environment.

During this they will concentrate on below factors. Compact Installation. Overall functionality. Input device handling. Output device handling. OS Error handling. Secondary storage handling. Coexistence with other existence software. After completion of above like factor observation the release team is

providing required training sessions to the customers to understand about the project.

Page 17: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 17

 

Maintenance During utilization of Software by customers, the company people are

receiving change request from them. To receive change request from the customers the Project Management

establish “CCB” (Change Control Board) with few Developers, few testers and Project Manager.

CASE STUDY

TESTING STAGES RESPONSIBLE PERSONS Review in Analysis Analyst Review in Design Designer Unit Testing Programmers Integration Testing Programmers Functional & System Testing Test Engineers / Testers User Acceptance Testing Users / Customers Release Testing / Port Testing CCB

TERMINOLOGY DEVELOPERS TESTERS

Input Test Data Output Test Log Program Test Script

Challenges in Testing Generally organizations are maintaining separate Testing for Functional

and System Testing. This separate Testing team is also involving in Release Team and CCB. Some time this separate Testing team is also not able to conduct planned Testing or good testing due to some risks.

CCB

Receive change

Enhancement Missed Defect

Impact Analysis

Perform changes

Test S/w changes

Impact Analysis

Perform changes

Test S/w changes

Increase Testing process Capability

Page 18: Manual)

Suresh.B –9440163282 [email protected] 

18 Manual Testing

The risks are Lack of knowledge on project domain. Lack of communication. Lack of resources. Lack of time. Lack of Test Data. To overcome above like risks, the people are following “Ad-hoc”

Testing.

Planned Testing A Tester conduct Test on application build with pre-planned procedure is

called Planned Testing. (or)

A Tester conduct Test on application build by following formal methods are called Planned Testing.

Ad-hoc Testing

A Tester conduct test on application build without Pre-planed is called Ad-hoc Testing.

(or) A Tester conduct test on application build by following “Informal

Methods” is called “Ad-hoc Testing”. They are classified as (4) Types.

(a) Monkey Testing. Due to lack of time, Testers are conducting test on major

functionalities of the application build. This style of testing is called “Monkey Testing”. It is also known as Cheapening Testing.

(b) Buddy Testing. Due lack of time, Testers are grouping with programmers to

conduct Test on application as early as possible. This style of Testing is called as Buddy Testing.

Buddy means a group of Programmers and Testers. (c) Pair Testing.

Due to lack of knowledge on domain Junior Testers grouped with Senior Testers to share their knowledge. This style of testing is called Pair Testing.

(d) Exploratory Testing. Due to lack of Test Data, Testers are conducting Test on

application depending on available documents, discussions with other and get the requirements from customers. This style of testing called Exploratory Testing.

Page 19: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 19

 

SOFTWARE DEVELOPMENT LIFE CYCLE (SDLC) 1) WATERFALL MODEL

In this Model next stage starts after completion of previous stage. There is no overlapping between two stages.

ADVANTAGES i) It is less expensive. ii) It works well for small applications. iii) It is flexible when the customer requirements are constant.

DISADVANTAGES

i) Testing is a single stage starts after coding. ii) If any defect is found during Testing, the rectification of that defect

would be difficult. iii) It is “not flexible” to have changes in the customer requirements during

developing the software.

2) INCREMENTAL WATERFALL MODEL To overcome some of the limitations of Waterfall we can use Incremental Waterfall model. Incremental Waterfall Model can be used Software Produce Development. In this Model a set of requirements they would be one working product.

Requirement Gathering

Analysis

Design

Coding

Testing

Release & Maintenance

R.G Analysis Design Coding Testing R & M

R.G Analysis Design Coding Testing R & M

R.G Analysis Design Coding Testing R & M

1.0

2.0

3.0

Page 20: Manual)

Suresh.B –9440163282 [email protected] 

20 Manual Testing

3) PROTOTYPE MODEL It is followable when the customer requirements are not clear. “Prototype means a sample Model of application without

functionality.

ADVANTAGES i) It is flexible when the customer requirements are not clear.

DISADVANTAGES i) It is expensive

4) Spiral Model

Spiral Model is followable when the customer requirements are enhanceble in terms of versions. In this Model we will start the process within complete requirements.

ADVANTAGES

It is flexible for high risk based projects. DISADVANTAGES

It is expensive.

Not Clear

Hardware Prototype Software Prototype

Demo to Client

Requirements refined Finalize Environment

BRS Base lined SRS Base lined

1.0 2.0 3.0 4.0 5.0

Planning Risk Analysis

Requirement Gathering

Engineers Evaluation

Coding and Testing

Customer Evaluation

Page 21: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 21

 

5) V-MODEL

Like as Fish Model “V-Model” is also defines the mapping

between Development stages and Testing stages.

In V-Model V stands for “Verification and Validation”.

Verification

To check whether the people are developing right product or not.

Validation

To check whether the developed product is right or not.

Software Testing

The “Verification and Validation” of a Software is called Software

Testing.

Requirement Gathering

Analysis

Design

BRS

Coding

User Acceptance Testing

System Testing

Integration Testing

Unit Testing

FRS

HLD

LLD White Box

Testing

Black Box Testing

Page 22: Manual)

Suresh.B –9440163282 [email protected] 

22 Manual Testing

6) Agile Model It is a latest model which is used in Software produce development. In this model we can get build from the developers in very short time (1 to 4 Weeks) In this model development process, testing process will be carried out parallelly. They are (2) methods such as (a) X-Tream Programming. (b) Scrum

ADVANTAGES i) Any defect identified early, so that he rectification of the defect cost

and time would be very less. ii) As the defect is identified early, the impact of the same defect is very

less on subsequent features. DISADVANTAGES

i) Documentation is very less. Sanity Testing

After receiving the build from the developers we people are conducting “Sanity Testing” to estimate stability of that build before start real testing.

During this testing we will be concentrate on below factors. a) Understandable. b) Operatable. c) Observable. d) Controllable. e) Consistency. f) Automatable. g) Maintainable h) Simplicity. From the above (8) factors, Sanity Testing is also known as Build

Verification Testing (BVT) or Tester Acceptance Testing (TAT) or Testability Testing or Oct-angle Testing.

Smoke Testing Like as Sanity Testing, Smoke Testing is also used to estimate the

stability of the Build.

Page 23: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 23

 

Re-Testing. Case 1: The repeating of same test for more than one time with multiple

data is called as “Re-Testing”. Case 2: The re-execution of failed tests on modified build to ensure bug

fixing work is called “Re-Testing” Regression Testing.

The Re-execution of selected test or modified build, to check is there any side effects occurred or not on dependent functionalities by modifying reported defects or by adding new requirements.

Types of Build They are (7) types of Build. They are (1) Initial Build

(2) Stable Build

(3) Defect effected Build

(4) Modified Build

(5) Complete Build

(6) Master Build

(7) Golden Build

Types of Projects

Mainly there are (3) Types of projects. They are (1) Traditional Project (2) Outsourcing Project (3) Maintenance Project Type of Project R/G Analysis Design Coding Testing R&M

Traditional Outsourcing Maintenance

DevelopmentInitial Build

Sanity Testing

Comprehensive Testing Bug

Fixing

Re-Testing Regression

Testing Test Closer(Test Lead)

U.A.T

Sign off

Stable Build

Defect Effected Build

Modified Build

Complete Build

Master Build

Golden Build

Page 24: Manual)

Suresh.B –9440163282 [email protected] 

24 Manual Testing

MANUAL TESTING

Testing Process

Test Initiation (Project Management /

Quality Analyst

T.R.M (Test Responsibility

Matrix) 3) Risk involved in that Project 2) Type of the Project 1) Scope of the Project

Test Plan Document (Test Lead)

4) Whom to Test?

1) What to Test?

3) Who to Test?

Test Scenarios & Test Cases with

Step by step procedure

(Test Engineer / Tester)

Test Case execution as Batches

Test Closer (Test Lead) Bug fixing

2) How to Test?

Re-testing & Regression Testing

UAT 

Sign Off 

Defect Report Final Summary Report

Page 25: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 25

 

PETT Process (Process Expert Tolls and Techniques)

Requirement Gathering

Analysis

Test initiation Design

Coding Test Plan Document

Test Scenarios & Test Case with Step by step process

Level ‘0’ Testing / Sanity Testing

Level ‘1’ Testing / Comprehensive Testing / Batch Testing 

Level ‘3’ Testing / Test Closure / Postmortem Testing / Pre-acceptance Testing 

(1) Initial Build

(2) Stable Build

(5) Complete Build

(3) Defect Effected Build Bug

Fixing

Level ‘2’ Testing Re-Testing / Regression

Testing 

Defect Report (4) Modified Build

User Acceptance Testing

Sign Off

(6) Master Build

(7) Golden Build

Page 26: Manual)

Suresh.B –9440163282 [email protected] 

26 Manual Testing

Testing Initiation:

In general testing process start with “Test initiation”. In this, Project

Manager / Quality Analyst develop Test starting Document. This document

defines the required testing approach to be followed by the testing team.

During this document preparation they will concentrate on below (12)

components.

1) Scope & Objective. 7) Test Automation 2) Budget Control. 8) Defect Tracing & Reporting 3) Test approach. 9) Measurements & Matrix. 4) Roles & Responsibilities 10) Change & Configuration Management 5) Communication & Status Reporting 11) Risks & Mitigations 6) Test deliverables 12) Training Plan.

1) Scope & Objective: The need of testing in the project.

2) Budget Control. Time & Cost allocation to the project.

Ex: As per U.S. Norms

3) Test approach

In this they will specify a list of selected quality factors to be

applied by the Tester.

T.R.M (Test Responsibility Matrix) can be finalized by Project

Manager / Quality Analyst based on scope of the project, type of the

project and Risks involved in that project.

TRM : It defines the mapping between Test factors and Development

Stages.

100%

64% Development Department

36% Testing Department

# ## 

Page 27: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 27

 

Quality Factors / Test Factors

RG & Analysis Design Coding

Function & System Testing

R & M

1) Authorization 2) Access Control 3) Ease of use 4) Ease of operation 5) Correctness 6) Continuity &

Processing

7) Coupling 8) Data integrity 9) Recovery 10) Portable 11) Service Level 12) Performance 13) Maintainable 14) Methodology 15) Audit trail. 1) Authorization: Whether a valid user is accessible or not and Invalid

User is preventable or not. 2) Access control: Whether a valid user have permission to user specific

service of not 3) Ease of Use: Whether the application build is providing user

friendly screens or not. 4) Ease of operate: Easy to installation, downloading, uploading,

dumping, un-installing. 5) Correctness: Whether the functionality output is right or wrong. 6) Continuity & processing: The integration of modules. 7) Coupling: Co-existence with other Software. 8) Data Integrity: Whether the input objects are taking right type and

range of values or not. 9) Recovery: Whether the application build is changing from

abnormal state to normal state or not. 10) Portable: Whether the application build is able to run on

different platforms or not. 11) Service Level: The order of functionality. 12) Performance: The speed of processing. 13) Maintainable: Whether the application build is longtime serviceable

in customers site or not.

Page 28: Manual)

Suresh.B –9440163282 [email protected] 

28 Manual Testing

14) Methodology: Whether the people (Tester) are following right process of not. If not he will be punishable.

15) Audit Trail: Whether the system is maintains data for the user operation (Ex. Bank Application, Withdrawal time, ATM Centre Code etc.,)

1) Authorization Security Testing 2) Access Control Security Testing 3) Ease of use User interface Testing 4) Ease of operation Installation Testing 5) Correctness Functionality Testing 6) Continuity & Processing Integration Testing 7) Coupling Intersystem Testing 8) Data integrity Input domain Testing 9) Recovery Recovery Testing 10) Portable Compatibility Testing 11) Service Level Functionality Testing 12) Performance Load, Stress, Storage, Data volume Testing 13) Maintainable Stress Testing 14) Methodology Compliance Testing 15) Audit trail. Functionality Testing

4) Roles and Responsibilities

Name of the jobs and his / her responsibilities.

5) Communication n& Status reporting The required communication between two consecutive jobs.

Ex:

When do report? Weekly Once, twice, daily etc.,

6) Test deliverables The required documents to be prepared by the testing team. The

following documents were prepared by the Test lead and Test engineers. Test Plan, Test Scenario, Test Cases, Test Data, Test log, Defect report, Final Summery Report etc.,

7) Test automation The purpose of Automation testing in the project and available

tools in the organization.

Project Management Test Lead Test Engineer

Page 29: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 29

 

8) Defect tracing & Reporting. The required communication between Programmers and Testers

when Test Engineer / Tester got a mismatch. Large Scale Small Scale

Transmittal Report

9) Measurement & Matrix: The required measurement to estimate the status of the project. In

measurements there are (3) types such as (1) Quality Assessment Measurement (2) Test Management Measurement (3) Process Capability Measurement.

10) Change & Configuration Management

How to handle change request from the customer and how to store the documents for future reference.

11) Risk & Mitigations: The possible risks and solutions to overcome them.

12) Training Plan: The required training secession to the Testing team to understand

about the project.

Project Management

Project Lead

Team Lead

Programmer

Test Lead

Test Engineer

Project Management

Team Lead

Programmer

Test Lead

Test Engineer

Page 30: Manual)

Suresh.B –9440163282 [email protected] 

30 Manual Testing

TEST PLAN

After completion of Test Strategy Document, the strategy of the Project

implemented by Test Lead in the Project through Test Plan.

During Test Plan Document preparation, Test Lead category people

follows below approach.

a) Team Formation:

In general Test Plan Document preparation starts with Team

formation. In this Test Lead category people form the Testing Team

depending on below factors.

i. Project size. ii. Project duration.

iii. Availability of domain testers. iv. Resources (Automation Tools)

b) Identify Risks

After completion of Team Formation the Test Lead identifies risks

with respect to that formed testing team in Testing.

i. Lack of time. ii. Lack of resources. iii. Lack of communication. iv. Lack of knowledge on project domain. v. Lack of test data. vi. Lack of development process rigor. vii. Delays in delivery.

BRS

TRM

Development Plan

a) Team formation

b) Identify risks

c) Prepare Test Plan

d) Review Test Plan

System Test Plan Module Test Plan (if project is big then only Module Test Plan is to be prepared)

Page 31: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 31

 

c) Prepare Test Plan After completion of Team formation and Risk Analysis, Team

Lead will prepare Test Plan Document in IEEE (Institute of Electrical & Electronic Engineer) Format (829)

1) Test Plan ID 9) Exit Criteria 2) Introduction 10) Test deliverables 3) Test items 11) Test environment 4) Features to be tested 12) Staff & Training needs 5) Features not to be tested 13) Responsibilities 6) Test approach 14) Schedule 7) Entry criteria 15) Risks & Mitigations 8) Suspension Criteria 16) Approved by 1) Test Plan ID:

Unique number for feature reference.

2) Introduction Introduction about the project or module.

3) Test items The name of the requirements or features.

4) Features to be tested

The name of the requirements or features to be test.

5) Features not to be tested The name of the requirements or features not to be test

6) Test approach The list of selected quality factors to be applied by the Tester.

7) Entry criteria When to start Testing

Take complete and correct Test cases. Create Test Environment. Receive Stable Build from the developers.

8) Suspension criteria

When to suspend testing temporarily When we have network problem. If pending defects are more

(Pending defects = No. of reported defects – No. of resolved defects)

Page 32: Manual)

Suresh.B –9440163282 [email protected] 

32 Manual Testing

9) Exit criteria When to stop testing

After completion of all module testing. After completion of all Major bugs resolved.

10) Test deliverables

The required documents to be prepared by the Testers. Ex.: Test Scenarios, Test Cases, Test Scripts, Test Data, Test log, Defect

Report, FSR ………… etc., 11) Test environment

The required Software and Hardware to conduct Testing.

12) Staff and Training needs The names of selected testers and their training needs.

13) Responsibilities Work allocation to the testers. Ex. Modules Vs. Testers.

14) Schedule Time duration to the testers.

15) Risks and Mitigations

The required solutions for the previously analyzed risks.

16) Approved by Who approved the document, the signature of the Project Manager.

Name of the Test Lead.

d) Review Test Plan: Completion of Test Plan Document preparation, Test Lead is conducting

Review Meeting to estimate completeness and correctness of that document. During this review they will concentrate on below coverages.

(i) Requirements Based Coverage (What to Test?) (ii) Risk Based Coverage (Who to Test & When to Test?) (iii) TRM Based Coverage (How to test?)

Page 33: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 33

 

TEST SCENARIOS & TEST CASE DESIGN After completion of Test Plan Document and corresponding Reviews

Test Lad allocate the work to the Testers. Testers are preparing corresponding Test Scenarios and Test Caes based

on Requirement Specifications. USE CASE

Use Case is a required document which maintenance the detail information about one low level requirement.

If you want to design Test Cases based on Use Cases, we can study the Use Case below approach. USE CASE FORMAT: Title Requirement Description Actors / Users Pre-operation Action Positive Flows Exceptions / Negative flows Alternative flows / Alternative Positive flows

1) Collect all Use Cases. 2) Take one Use Case and Study.

2.1) Identity Entry Point. 2.2) Identity Input Requirement 2.3) Identity Outputs 2.4) Identity Alternative flows and exceptions. 2.5) Identity exit point.

3) Prepare scenarios. 4) Review scenarios. 5) Prepare Test Cass with step by step procedure. 6) Continue from step (2) to (6) until completion of all Use Cases.

TEST SCENARIOS Test Scenarios means Test situations.

Test Scenario Template These templates are created in MS Excel.

Project Name: Reviewed by Module Name: Created by: Reviewed by Created on:

Sl. No. Requirement Name Test Scenario Test Cases

Page 34: Manual)

Suresh.B –9440163282 [email protected] 

34 Manual Testing

TEST CASES A set of Test steps documented along with required inputs and expected

results in order to test one low level requirement.

Thinks to remember while designing the Test Cases. 1) Test Case should be simple and clear. 2) Test Case should be complete. 3) No duplicate Test Case should b written.

TEST CASE TYPE

1) User Interface Test Cases. 2) Usability Test Cases. 3) Validation Test Cases. 4) Functional Test Cases.

1) User Interface Test Cases

To verify the look and Feel of application build screens. Ex: Font Size, Text alignment, Images etc.,

2) Usability Test Cases To verify ease of use of application build screens.

Ex: a) Default cursor should be present at the first field. b) Tab keys should be implemented for all input objects from left to right

in downward direction. c) Shortcut keys should be implemented for all menu operation. d) Tool tips (Whenever we place the cursor on particular object, it should

return meaningful message)

3) Validation Test Cases: Test Cases that are required to validate business rules or field

validation.

4) Functional Test Cases: Test Cases that are required to validate the functionality.

TEST DESIGN TECHNIQUES

They are mainly (5) types of design techniques. (1) Boundary Value Analysis (BVA) (2) ECP (Equal Class Partition) (3) Error Guessing (4) Decision Tables (5) State transition.

Page 35: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 35

 

(1) BVA: It is used to validate the range of input objects.

(2) ECP: Splitting the inputs into equal parts and randomly checking them. To verify the type of input objects.

(3) Error Guessing

It is a technique which can be used by the people, who have prior knowledge on that application (Ex. This can be used by experts)

(4) Decision Tables

A Black Box Test Design testing in which test cases are designed to execute the combination of inputs.

(5) State Transition

A Black Box Test design techniques, in which test cases are designed to execute valid, invalid state transition.

Valid Invalid Valid Invalid

Valid Valid Invalid Valid

Insert card

Wait for PIN Entry

1st Entry

2nd Entry

3rd Entry

Block Card

Access Account

PIN Wrong PIN Wrong

PIN Wrong

PIN Ok

PIN Ok

PIN Ok

Page 36: Manual)

Suresh.B –9440163282 [email protected] 

36 Manual Testing

TEST CASE TEMPLATE Test Case Name / ID

Test Case Description Priority Step

Name Step

DescriptionTest Data

1 2 3 4 5 6

Expected Results

Actual Results Status Created

By Created

on Comments

7 8 9 10 11 12

QC Path Reviewed By

Reviewed On

Reviewer’s Comments

13 14 15 16

1) Test Case Name / ID: Unique Number for future reference Ex: TC001_Project Name_Module Name_Functionality Name

2) Test Case Description: The description about that Test case.

Pre-requisites Documents referred.

3) Priority

Importance of the Test Case. They are classified into (3) Types such as

(1) High Priority (Basic functionality Test Cases) (2) Medium Priority (General functionality Test Cases – Recovery, Compatibility Testing etc.,) (3) Low Priority (Cosmetic Test Cases – User Interface Testing)

4) Step Name Every Test Case divided into multiple steps, every step in the test

case will have unique number. Ex: Step–1; Step–2; Step–3 etc.,

5) Step Description The required action to be performed by the user.

6) Test Data Set of inputs that are required to execute steps.

Page 37: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 37

 

7) Expected Results The required expected output from the system for the

corresponding user action.

8) Actual Results The actual output of the system after performing user action.

9) Status The current position of the Test Case. They are classified into (4)

types, such as (a) No Run: Test Case not executed atleast for once. (b) Not complied: A partially executed test case. (c) Passed: Test Case executed and the expected value and

Actual value is same, “Test is passed”. (d) Failed: Test Case any step(s) expected values

mismatched with actual value, “Test is failed”. 10) Created By

The name of the Test Engineer, who created the Test Cases.

11) Created on Date and Time of the created Test Case.

12) Comments

A set of comments given by Tester for the Step or Test Cases.

13) QC Path The path of Quality Control.

14) Reviewed By Name of the Reviewer.

15) Reviewed on When (Date & Time) the document was reviewed by reviewer.

16) Reviewer’s Comments A set of comments given by reviewer.

Page 38: Manual)

Suresh.B –9440163282 [email protected] 

38 Manual Testing

CASE STUDY

Page 39: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 39

 

User Name User Name object allows alphabets lower case range from 4 to 8

characters.

Password Password object allows alphabets lower case range from 6 to 10

characters.

Customer Name Customer Name object allows alphabets. Range from 4 to 12 characters. First letter should be Upper Case. Mandatory.

Customer Address

Customer Address object allows alpha-numeric and some special Characters (“–“ “/” “#” “,” “.”)

Maximum of 20 Characters. Mandatory.

Customer DOB

Customer DOB object allows Numeric Only. The format is MM/DD/YYYY. Date should be less than current system date. Mandatory.

Customer Ph.No.

Customer Ph.No. object allows Numeric Only. Allows 10 digits only. Phone number is unique. Mandatory.

E–Mail

E-Mail object allows alpha-numeric and special Characters. Format is [email protected]. It is not mandatory.

Page 40: Manual)

Suresh.B –9440163282 [email protected] 

40 Manual Testing

TEST SCENARIO DOCUMENT Project Name: Customer Info Reviewed by Module Name: Admin Created by: Suresh Reviewed by Created on: 18/10/2008

Sl. No. Requirement Name

Test Scenario Test Cases

1 Login Ok

Cancel

1) Verify Ok with valid data. 2) Verify Ok with invalid data. 3) Verify Cancel

2 Add

Insert

Cancel

1) Verify Insert with valid data. 2) Verify Insert with invalid

data. 3) Verify Insert with duplicate

data. 4) Verify Insert with missing

mandatory fields. 5) Verify Cancel

3 Search

Search

Cancel

1) Verify Search with valid data.

2) Verify Search with invalid data.

3) Verify Cancel

4 Edit

Update

Cancel Home

1) Verify Update with valid data.

2) Verify Update with invalid data.

3) Verify Update with duplicate data.

4) Verify Update with missing mandatory fields.

5) Verify Cancel 6) Verify Home

5 Delete Delete Verify Delete 6 Cancel Cancel Verify Cancel 7 Home Home Verify Home 8 Logout Logout Verify Logout

Note: RCN (Requirement Clarification Note)

Any doubt in FRS / BRS Document, we people design RCN Document and the same will be sent to BDP for clarification.

Page 41: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 41

 

TEST CASE DOCUMENT Test Case

name Test Case

description Step

NameStep

Description Test Data Expected Result

TC01_ Customer Info_Admin_ Verify Ok with Valid data

This Test case validates ‘Ok’ functionality with valid data

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

TC02_ Customer Info_Admin_ Verify Ok with invalid data

This Test case validates ‘Ok’ functionality with invalid data

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter invalid User Name and Password click on Ok

User Name & Pass word

It should display meaningful error message.

TC03_ Customer Info_Admin_ Verify Cancel

This Test case validates Cancel functionality

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter User Name and Password click on Cancel

User Name & Pass word

It should clear all fields and cursor should be present in the first field.

TC04_ Customer Info_Admin_ Verify Insert with Valid data

This Test case validates ‘Insert’ functionality with valid data

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Step-3 Click on Add - - It should display Add Customer page with C.Name, C.Addr., C.DOB, C.Ph.No., E-mail objects and Insert, Reset, Cancel functionalities.

Page 42: Manual)

Suresh.B –9440163282 [email protected] 

42 Manual Testing

Test Case name

Test Case description

Step Name

Step Description

Test Data Expected Result

Step-4 Enter data in corresponding fields and click on Reset

C.NameC.Addr. C.DOB C.PhNo E-mail

It should clear all fields and cursor should be present in the first field.

Step-5 Enter valid data in corresponding fields and click on Insert

C.NameC.Addr. C.DOB C.PhNo E-mail

It should display a meaningful Message such as “Customer Data created with Customer ID”

TC05_ Customer Info_Admin_ Verify Insert with invalid data

This Test case validates ‘Insert’ functionality with invalid data

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Step-3 Click on Add - - It should display Add Customer page with C.Name, C.Addr., C.DOB, C.Ph.No., E-mail objects and Insert, Reset, Cancel functionalities.

Step-4 Enter invalid data in corresponding fields and click on Insert

C.NameC.Addr. C.DOB C.PhNo E-mail

It should display a meaningful Error Message.

TC06_ Customer Info_Admin_ Verify Insert with duplicate data

This Test case validates ‘Insert’ functionality with duplicate data

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Step-3 Click on Add - - It should display Add Customer page with C.Name, C.Addr.,

Page 43: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 43

 

Test Case name

Test Case description

Step Name

Step Description

Test Data Expected Result

C.DOB, C.Ph.No., E-mail objects and Insert, Reset, Cancel functionalities.

Step-4 Enter duplicate data in corresponding fields and click on Insert

C.NameC.Addr. C.DOB C.PhNo E-mail

It should display a meaningful Error Message.

TC07_ Customer Info_Admin_ Verify Insert with missing mandatory fields

This Test case validates ‘Insert’ functionality with missing mandatory fields

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Step-3 Click on Add - - It should display Add Customer page with C.Name, C.Addr., C.DOB, C.Ph.No., E-mail objects and Insert, Reset, Cancel functionalities.

Step-4 Enter data in corresponding fields by missing some mandatory fields and click on Insert

C.NameC.Addr. C.DOB C.PhNo E-mail

It should display a meaningful Error Message.

TC08_ Customer Info_Admin_ Verify Cancel

This Test case validates ‘Cancel’ functionality

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Page 44: Manual)

Suresh.B –9440163282 [email protected] 

44 Manual Testing

Test Case name

Test Case description

Step Name

Step Description

Test Data Expected Result

Step-3 Click on Add - - It should display Add Customer page with C.Name, C.Addr., C.DOB, C.Ph.No., E-mail objects and Insert, Reset, Cancel functionalities.

Step-4 Enter data in corresponding fields and click on Cancel

C.NameC.Addr. C.DOB C.PhNo E-mail

It should close current page and display previous page.

TC09_ Customer Info_Admin_ Verify Search with valid data

This Test case validates ‘Search’ functionality with valid data

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Step-3 Click on Search

- - It should display Search Page with C.ID, C.Name, C.DOB, C.Ph.No., objects and Search, Reset, Cancel functionalities.

Step-4 Enter data in corresponding fields click on Reset

C.ID C.NameC.DOB C.PhNo

It should clear all fields and cursor should be present in the first field.

Step-5 Enter valid data in corresponding fields and click on Search

C.ID C.NameC.DOB C.PhNo

It should display Search Results Page with Customers Information and Edit, Delete, Cancel, Home functionalities.

TC10_ Customer Info_Admin_ Verify Search with invalid data

This Test case validates ‘Search’ functionality with invalid

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name

User Name

It should display Customer Information

Page 45: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 45

 

Test Case name

Test Case description

Step Name

Step Description

Test Data Expected Result

data and Password click on Ok

& Pass word

page with Add, Search, Logout functionalities.

Step-3 Click on Search

- - It should display Search Page with C.ID, C.Name, C.DOB, C.Ph.No., objects and Search, Reset, Cancel functionalities.

Step-4 Enter invalid data in corresponding fields and click on Search

C.ID C.NameC.DOB C.PhNo

It should display meaningful error message.

TC11_ Customer Info_Admin_ Verify Cancel

This Test case validates ‘Cancel’ functionality

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Step-3 Click on Search

- - It should display Search Page with C.ID, C.Name, C.DOB, C.Ph.No., objects and Search, Reset, Cancel functionalities.

Step-4 Enter data in corresponding fields and click on Cancel

C.ID C.NameC.DOB C.PhNo

It should close current page and display previous page.

TC12_ Customer Info_Admin_ Verify Update with valid data

This Test case validates ‘Update’ functionality

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Page 46: Manual)

Suresh.B –9440163282 [email protected] 

46 Manual Testing

Test Case name

Test Case description

Step Name

Step Description

Test Data Expected Result

Step-3 Click on Search

- - It should display Search Page with C.ID, C.Name, C.DOB, C.Ph.No., objects and Search, Reset, Cancel functionalities.

Step-4 Enter valid data in corresponding fields and click on Search

C.ID C.NameC.DOB C.PhNo

It should display Search Results Page with Customers Information and Edit, Delete, Cancel, Home functionalities.

Step-5 Select a Customer data click on Edit

- It should display Edit Page with C.ID, C.Name, C.Addr., C.DOB, C.Ph.No., E-mail objects and Update, Reset, Cancel, Home functionalities.

Step-6 Enter data in corresponding fields click on Reset

C.ID C.NameC.DOB C.Addr. C.PhNo E-mail

It should clear all fields and cursor should be present in the first field.

Step-7 Enter valid data in corresponding fields click on update

C.ID C.NameC.DOB C.Addr. C.PhNo E-mail

It should display “Update done” message.

TC13_ Customer Info_Admin_ Verify Update with invalid data

This Test case validates ‘Update’ functionality with invalid data

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Step-3 Click on Search

- - It should display Search Page with C.ID, C.Name, C.DOB, C.Ph.No., objects and Search,

Page 47: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 47

 

Test Case name

Test Case description

Step Name

Step Description

Test Data Expected Result

Reset, Cancel functionalities.

Step-4 Enter valid data in corresponding fields and click on Search

C.ID C.NameC.DOB C.PhNo

It should display Search Results Page with Customers Information and Edit, Delete, Cancel, Home functionalities.

Step-5 Select a Customer data click on Edit

- It should display Edit Page with C.ID, C.Name, C.Addr., C.DOB, C.Ph.No., E-mail objects and Update, Reset, Cancel, Home functionalities.

Step-6 Enter invalid data in corresponding fields click on update

C.ID C.NameC.DOB C.Addr. C.PhNo E-mail

It should display meaningful error message.

TC14_ Customer Info_Admin_ Verify Update with duplicate data

This Test case validates ‘Update’ functionality with duplicate data

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Step-3 Click on Search

- - It should display Search Page with C.ID, C.Name, C.DOB, C.Ph.No., objects and Search, Reset, Cancel functionalities.

Step-4 Enter valid data in corresponding fields and click on Search

C.ID C.NameC.DOB C.PhNo

It should display Search Results Page with Customers Information and Edit, Delete, Cancel, Home functionalities.

Page 48: Manual)

Suresh.B –9440163282 [email protected] 

48 Manual Testing

Test Case name

Test Case description

Step Name

Step Description

Test Data Expected Result

Step-5 Select a Customer data click on Edit

- It should display Edit Page with C.ID, C.Name, C.Addr., C.DOB, C.Ph.No., E-mail objects and Update, Reset, Cancel, Home functionalities.

Step-6 Enter duplicate data in corresponding fields click on update

C.ID C.NameC.DOB C.Addr. C.PhNo E-mail

It should display meaningful error message.

TC15_ Customer Info_Admin_ Verify Update with missing mandatory fields

This Test case validates ‘Update’ functionality with missing mandatory fields

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Step-3 Click on Search

- - It should display Search Page with C.ID, C.Name, C.DOB, C.Ph.No., objects and Search, Reset, Cancel functionalities.

Step-4 Enter valid data in corresponding fields and click on Search

C.ID C.NameC.DOB C.PhNo

It should display Search Results Page with Customers Information and Edit, Delete, Cancel, Home functionalities.

Step-5 Select a Customer data click on Edit

- It should display Edit Page with C.ID, C.Name, C.Addr., C.DOB, C.Ph.No., E-mail objects and Update, Reset, Cancel, Home functionalities.

Page 49: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 49

 

Test Case name

Test Case description

Step Name

Step Description

Test Data Expected Result

Step-6 Enter data in corresponding fields by missing some mandatory fields and click on update

C.ID C.NameC.DOB C.Addr. C.PhNo E-mail

It should display meaningful error message.

TC16_ Customer Info_Admin_ Verify Cancel

This Test case validates Cancel functionality

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Step-3 Click on Search

- - It should display Search Page with C.ID, C.Name, C.DOB, C.Ph.No., objects and Search, Reset, Cancel functionalities.

Step-4 Enter valid data in corresponding fields and click on Search

C.ID C.NameC.DOB C.PhNo

It should display Search Results Page with Customers Information and Edit, Delete, Cancel, Home functionalities.

Step-5 Select a Customer data click on Edit

- It should display Edit Page with C.ID, C.Name, C.Addr., C.DOB, C.Ph.No., E-mail objects and Update, Reset, Cancel, Home functionalities.

Step-6 Enter data in corresponding fields and click on Cancel

C.ID C.NameC.DOB C.Addr. C.PhNo E-mail

It should close current page and display Previous Page.

Page 50: Manual)

Suresh.B –9440163282 [email protected] 

50 Manual Testing

Test Case name

Test Case description

Step Name

Step Description

Test Data Expected Result

TC17_ Customer Info_Admin_ Verify Home

This Test case validates Cancel functionality

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Step-3 Click on Search

- - It should display Search Page with C.ID, C.Name, C.DOB, C.Ph.No., objects and Search, Reset, Cancel functionalities.

Step-4 Enter valid data in corresponding fields and click on Search

C.ID C.NameC.DOB C.PhNo

It should display Search Results Page with Customers Information and Edit, Delete, Cancel, Home functionalities.

Step-5 Select a Customer data click on Edit

- It should display Edit Page with C.ID, C.Name, C.Addr., C.DOB, C.Ph.No., E-mail objects and Update, Reset, Cancel, Home functionalities.

Step-6 Enter data in corresponding fields and click on Home

C.ID C.NameC.DOB C.Addr. C.PhNo E-mail

It should close current page and display Customer Info Page.

TC18_ Customer Info_Admin_ Verify Delete

This Test case validates Delete functionality

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Page 51: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 51

 

Test Case name

Test Case description

Step Name

Step Description

Test Data Expected Result

Step-3 Click on Search

- - It should display Search Page with C.ID, C.Name, C.DOB, C.Ph.No., objects and Search, Reset, Cancel functionalities.

Step-4 Enter valid data in corresponding fields and click on Search

C.ID C.NameC.DOB C.PhNo

It should display Search Results Page with Customers Information and Edit, Delete, Cancel, Home functionalities.

Step-5 Select a Customer data click on Delete

- It should remove customer’s information with “Customers Information was successfully deleted”.

TC19_ Customer Info_Admin_ Verify Cancel

This Test case validates Cancel functionality

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Step-3 Click on Search

- - It should display Search Page with C.ID, C.Name, C.DOB, C.Ph.No., objects and Search, Reset, Cancel functionalities.

Step-4 Enter valid data in corresponding fields and click on Search

C.ID C.NameC.DOB C.PhNo

It should display Search Results Page with Customers Information and Edit, Delete, Cancel, Home functionalities.

Step-5 Select a Customer data click on Cancel

- It should close current page and display previous page.

Page 52: Manual)

Suresh.B –9440163282 [email protected] 

52 Manual Testing

Test Case name

Test Case description

Step Name

Step Description

Test Data Expected Result

TC20_ Customer Info_Admin_ Verify Home

This Test case validates Home functionality

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Step-3 Click on Search

- - It should display Search Page with C.ID, C.Name, C.DOB, C.Ph.No., objects and Search, Reset, Cancel functionalities.

Step-4 Enter valid data in corresponding fields and click on Search

C.ID C.NameC.DOB C.PhNo

It should display Search Results Page with Customers Information and Edit, Delete, Cancel, Home functionalities.

Step-5 Select a Customer data click on Home

- It should close current page and display Customer Info Page.

TC21_ Customer Info_Admin_ Verify Logout

This Test case validates Logout functionality

Step-1 Open Brower, enter Url. Address, click on Go

Url It should display Login Page with User Name, Password objects and Ok, Cancel functionalities.

Step-2 Enter valid User Name and Password click on Ok

User Name & Pass word

It should display Customer Information page with Add, Search, Logout functionalities.

Step-3 Click on Logout

- It should close current page and display Login Page

Page 53: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 53

 

User Name User Name object allows alphabets lower case range from 4 to 8

characters.

BVA & ECP for User Name BVA ECP

Range Expected Actual Result Valid Invalid Min= 4 Char Min-1= 3 Char Min+1= 5 Char Max= 8 Char Max-1= 7 Char Max+1= 9 Char

Pass Fail Pass Pass Pass Fail

[a-z] [A-Z] [0-9] All

Special characters

Password

Password object allows alphabets lower case range from 6 to 10 characters.

BVA & ECP for Password BVA ECP

Range Expected Actual Result Valid Invalid Min= 6 Char Min-1= 5 Char Min+1= 7 Char Max= 10 Char Max-1= 9 Char Max+1= 11 Char

Pass Fail Pass Pass Pass Fail

[a-z] [A-Z] [0-9] All

Special characters

Customer Name

Customer Name object allows alphabets. Range from 4 to 12 characters. First letter should be Upper Case. Mandatory.

BVA & ECP for Customer Name BVA ECP

Range Expected Actual Result Valid Invalid Min= 4 Char Min-1= 3 Char Min+1= 5 Char Max= 12 Char Max-1= 11 Char Max+1= 13 Char

Pass Fail Pass Pass Pass Fail

[a-z] [A-Z]

[0-9] All

Special characters

Page 54: Manual)

Suresh.B –9440163282 [email protected] 

54 Manual Testing

Customer Address

Customer Address object allows alpha-numeric and some special Characters (“–“ “/” “#” “,” “.”)

Maximum of 20 Characters. Mandatory.

BVA & ECP for Customer Address BVA ECP

Range Expected Actual Result Valid Invalid Max= 20 Char Max-1= 19 Char Max+1= 21 Char

Pass Pass Fail

[a-z] [A-Z] [0-9]

Some Spl. Characters

– / # , .

All Special

characters Except

mentioned

Customer DOB

Customer DOB object allows Numeric Only. The format is MM/DD/YYYY. Date should be less than current system date. Mandatory.

BVA & ECP for Customer DOB BVA ECP

Range Expected Actual Result Valid Invalid Max= 20 Char Max-1= 19 Char Max+1= 21 Char

Pass Fail Pass

[a-z] [A-Z] [0-9]

Some Spl. Characters

– / # , .

All Special

characters Except

mentioned

Customer Ph.No. Customer Ph.No. object allows Numeric Only. Allows 10 digits only. Phone number is unique. Mandatory.

BVA & ECP for Customer Ph.No. BVA ECP

Range Expected Actual Result Valid Invalid Max= 10 Digits Max-1= 19 Digits Max+1= 21 Digits

Pass Fail Pass

[0-9] [a-z] [A-Z]

All Spl. Characters

Page 55: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 55

 

TEST DATA DOCUMENT Project Name Reviewed by Module Name Created By Reviewed on Created on  

Sl. No.

Test Case Name

Step Name

Data required Data generated Comments

1

TC01_ Customer Info_Admin_ Verify Ok with Valid data

Step-1 Url http://192.168.1.0

/Customer Info 1.0

Step-2

User Name

1) rama 2) rames 3) gahesha 4) reliance

Password

1) suresh 2) sureshb 3) sureshbug 4) sureshbuga

2

TC02_ Customer Info_Admin_ Verify Ok with invalid data

Step-1 Url http://192.168.1.0

/Customer Info 1.0

Step-2

User Name

1) ram 2) sureshbug 3) ga*1 4) ram@123

Password

1) sures 2) sureshbugat 3) SURESH 4) sarvani@bu

3

TC03_ Customer Info_Admin_ Verify Cancel

Step-1 Url http://192.168.1.0

/Customer Info 1.0

Step-2

U.Name pava Password ganesh

4

TC04_ Customer Info_Admin_ Verify Insert with Valid data

Step-1 Url http://192.168.1.0

/Customer Info 1.0

Step-2

U.Name pava Password ganesh

Step-5

C.Name

Ramu Sita Ramakrishna Koteswararao

C.Addr. Koti,D.No.-5/G Brundavancolony7/G-3

Page 56: Manual)

Suresh.B –9440163282 [email protected] 

56 Manual Testing

Sl. No.

Test Case Name

Step Name

Data required Data generated Comments

C.DOB 05/25/1976 C.Ph.No. 9440163282

E-mail suresh_240878@ yahoo.com

5

TC05_ Customer Info_Admin_ Verify Insert with invalid data

Step-1 Url http://192.168.1.0

/Customer Info 1.0

Step-2

U.Name pava Password ganesh

Step-4

C.Name Sai Saisarvanibug

C.Addr. Brundavancolony7/G*3 Brundavanacolony 7/G-3

C.DOB 25/10/1976 C.Ph.No. +91-9440163282

E-mail suresh_240878# yahoo.com

6

TC06_ Customer Info_Admin_ Verify Insert with duplicate data

Step-1 Url http://192.168.1.0

/Customer Info 1.0

Step-2

U.Name pava Password ganesh

Step-4

C.Name Koteswararao C.Addr. Brundavancolony7/G-3 C.DOB 05/25/1976 C.Ph.No. 9440163282

E-mail suresh_240878@ yahoo.com

7

TC07_ Customer Info_Admin_ Verify Insert with missing mandatory fields

Step-1 Url http://192.168.1.0

/Customer Info 1.0

Step-2

U.Name pava Password ganesh

Step-4

C.Name Koteswararao C.Addr. Brundavancolony7/G-3 C.DOB 05/25/1976 C.Ph.No. 9440163282

E-mail suresh_240878@ yahoo.com

8 TC08_ Customer Info_Admin_

Step-1 Url http://192.168.1.0

/Customer Info 1.0

Page 57: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 57

 

Sl. No.

Test Case Name

Step Name

Data required Data generated Comments

Verify Cancel

Step-2

U.Name pava Password ganesh

Step-4

C.Name Koteswararao C.Addr. Brundavancolony7/G-3 C.DOB 05/25/1976 C.Ph.No. 9440163282

E-mail suresh_240878@ yahoo.com

9

TC09_ Customer Info_Admin_ Verify Search with valid data

Step-1 Url http://192.168.1.0

/Customer Info 1.0

Step-2

U.Name pava Password ganesh

Step-5

C.Name Koteswararao C.DOB 05/25/1976 C.Ph.No. 9440163282

Page 58: Manual)

Suresh.B –9440163282 [email protected] 

58 Manual Testing

Review on Test Cases After completion of Test Case preparation, Test Engineer is conducting

Peer Review and Test Lead is conducting Lead Review to estimate “Completeness and Correctness” of that document

Peer Review

After completion of review on Test Cases, Test lead is mapping Test

Cases with Requirement Traceability Matrix Document. (RTM) RTM defines the mapping between requirements and Test Cases.

Traceability Matrix Template Project Name Project Manager Prepared By Reviewed By

Prepared on Reviewed on Last Updated on

Sl. No. Requirement Description

Use Case Reference Test Scenario Test Case

Reference

TEST CASE EXECUTION

After completion of Test Cases preparation and corresponding reviews, Testers are receiving initial build from the development people.

During Test Case execution Testers are receiving modified build from the

developers. To receive any type of build from the developers, Testers required a valid negotiation / communications with developers like as below.

PM PL

TE-1 TE-2

Page 59: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 59

 

EXECUTION LEVELS:

COMMON REPOSITORY / SOFT BASE

VSS (Visual Source Safe) The versions have been maintained by these VSS

1.0 2.0 3.0

FTP (File Transfer Protocol)

Deploy / Install Build Sanity Testing

Testers

Developers

Client

Initial Build

Level ‘0’ Sanity Testing

Level ‘1’ Comprehensive

Testing

Bug Fixing

Level ‘2’ Re-Testing

Regression TestingLevel ‘3’

Test Closer (Test Lead)

U.A.T

Sign off

Stable Build

Defect Effected Build

Modified Build

Complete Build

Master Build

Golden Build

Page 60: Manual)

Suresh.B –9440163282 [email protected] 

60 Manual Testing

TEST HARNESS: Test Harness means ready to start testing. Test Harness = Test Environment + List of Test Cases.

LEVEL ‘0’ TESTING

After receiving initial build from the development people, Testers are conducting Level ‘0’ Testing to estimate stability of that build before start real testing.

In this testing, Testers are concentrates on Core (Basic) functionalities. During this Testing they will concentrates on below factors.

1) Under standable. 2) Operatable 3) Observable 4) Controllable. 5) Consistency. 6) Automatable. 7) Maintainable. 8) Simplicity. From the above factors Level ‘0’ Testing is also known as “Oct-Angle

Testing” or Sanity Testing or Build Verification Testing or Tester Acceptance Testing or Testability Testing. LEVEL ‘1’ TESTING

It is also known as “Comprehensive Testing”. During this testing Testers are executing all P0, P1, P2, Test Cases (P0–High Priority, P1–Medium Priority, P2–Low Priority) to validate functionality. In this every Test Case has to be executed by Tester either in Manual or in Automation.

Build

Test Engineer

Test Cases

Build

Automation Testing

Test Cases

Test Engineer Manual Testing

Automation Testing

Page 61: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 61

 

Execution Process

Defect Report During test execution, Testers are reporting mis-matches to development

Teas as “Defect” in Defect Report Document. Defect Report Format 1) Defect ID

Unique for future reference.

2) Summary Brief description of the defect.

3) Features

The name of the feature / functionality in which defect.

4) Test Case Name Name of the Test Case (in which Test Case execution the defect is

raised)

5) Reproducible The defect is repeatable in every time execution.

a. If Yes: It is reproducible, attach test procedure. b. If No: It is not reproducible, attach test procedure along with snap

shots. 6) Status

Status of the defect. They are (2) types (i) New–Reporting for first time. (ii) Re-open–For re-reporting defects.

Take all the Test Cases

Test Case Execution

Blocked Test Cases

Close

Partial Pass or Fail

Skip

Fail

Pass

Page 62: Manual)

Suresh.B –9440163282 [email protected] 

62 Manual Testing

7) Severity (Seriousness with respect to Testers) It means seriousness of the defect with respect to Tester or

seriousness of the functionality. They are classified into (3) Types such as (i) High severity – Urgent to solve (ii) Medium severity – Mandatory to solve (iii) Low severity – Compulsory to solve

8) Priority

Importance of the defect with respect to customer or importance of the functionality. It is classified into (3) types such as

(i) High Priority (ii) Medium Priority (iii) Low Priority

9) Assigned to

Name of the Developer

10) Detected By Name of the Tester (Who detected the defect)

11) Reported on Date and Time

12) Build Version ID In which version of the build the defect is raised.

13) Suggested to fix Suggestions to developer to fix the defects

By Developers Fixed By: Name of the Programmer who fixed the defect. Resolved on

Date and Time Resolution Type:

Acknowledgment from the developers for the reported defect.

Approved by

Signature of the Team Lead / Project Lead.

Page 63: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 63

 

Types of defects 1) User interface defects (Low Severity)

Spelling mistakes (High Priority) Improper alignment (Low Priority)

2) Input domain defect (Medium Severity) Input type is not taking valid type ((High Priority) Input type is taking invalid type also (Low Priority)

3) Error handling defect (Medium Severity) No error message for wrong operation (High Priority) Complex message in error message (Low Priority)

4) Calculation defect (High Severity) Wrong outputs (High Priority)

5) Load conditional defect (High Severity) Build is not supporting more than one user (High Priority) Build is not supporting customer expected load (Low/Medium Priority)

6) Hardware defect (High Severity) Build is not supporting any hardware devices (High Priority) Build is supporting hardware and wrong output coming from hardware (Low Priority)

7) Role conditional defect (High Severity) System crash, Showstoppers, Dead lock etc.,

8) Version control system (High Severity) Mistake in version control

9) Source defects (Medium Severity) Mistake in Help Document (High Priority)

What is defect Age? The time gap between defect reported on and defect resolved on.

What is Build Internal period?

The time gap between two consequent builds is called as Build Internal period.

Page 64: Manual)

Suresh.B –9440163282 [email protected] 

64 Manual Testing

BUG LIFE CYCLE / DEFECT LIFE CYCLE

Hold: The defect is not accepted, not rejected due to developer need more

information about that defect. Duplicate: The defect is rejected due to defect is previously accepted defect. Deferred: The defect is postponed to next version / release. LEVEL ‘2’ TESTING

After receiving the modified build from the developers, Testers are performing Re-testing / Regression Testing to ensure whether the reported defects are properly rectified by the developers or not and to check whether there is any side effects occurred or not on dependent functionalities by solving the reported defects or by adding new requirements. Case Study

New

Open

Fixed

Close

Defect

Rejected Hold Duplicate Deferred

If defect is not fixed

Reopen

Review the defect

Modified Build

High SeverityAll P0, P1, P2 Test Cases

Medium SeverityAll P0, some P1, & Selected P2 Test

Cases

Low SeveritySome P0 &

Selected P1, P2 Test Cases

EnhancementAll P0, P1, P2 Test Cases

Page 65: Manual)

[email protected] Suresh.B –9440163282

Manual Testing 65

 

Case 1: If the development team resolved bug severity is high, then Testers are re-executing all P0, P1, P2 Test Cases on that modified build.

Case 2: If the development team resolved bug severity is medium then, Testers are re-executing all P0, some P1 and selected P2 Tests cases on that modified Build.

Case 3: If the development team resolved bug severity is low, then Testers are re-executing some P0 and selected P1 and P2 Test cases on that modified build.

Case 4: If the development team released modified build due to some change request then the Testers are re-executing all P0, P1, P2 Test Cases on that modified build.

LEVEL ‘3’ TESTING

After completion of all test cases execution and corresponding bugs resolving, Testers are sending complete build to the Test lead along with FSR (Final Summary Report)

After receiving Final Summary Report from the Testers, Test lead is conducting “Test Closure” to estimate that whether the Test Engineer meets exit criteria or not.

In this Test lead category people will concentrate on below coverages. 1) Requirements Coverage:

All the requirements with respect to functionality.

2) Bug density No. of defects in Module . No of defects in the Project

3) Analysis of deferred bugs: Whether the deferred bugs are reasonable or not to postpone.

After completion of above like coverages Test lead is conducting Test Closure in below approach.

Take High Bug density Module

Effort Estimation

Plan Regression

Do Regression

Do Regression

Do Regression

X 100

Page 66: Manual)

Suresh.B –9440163282 [email protected] 

66 Manual Testing

User Acceptance Testing After completion of “Test Closure” the Project Manager collects

feedback from the customers on developed software through “User Acceptance Testing”. They are two types such as

α – Test (Alfa Test)

β – Test (Beta Test)

Software Application. By Real customer. At development site.

Software Product. By Model customer. At customer site.

Signoff

After completion of User Acceptance Testing and corresponding modifications, the Project Management deliver that software / build to the client along with Software Delivery Note (S/w DN). It consists of (2) issues such as

(i) User Manual. (ii) Known issues