Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate...

173
1 Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update Manitoba Hydro 2017/18 & 2018/19 General Rate Application PUB/MH I-60b-Attachment Available in accessible formats upon request

Transcript of Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate...

Page 1: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

1

Presentation to S & POctober 27, 2015

Manitoba HydroCorporate Update

Manitoba Hydro 2017/18 & 2018/19 General Rate Application PUB/MH I-60b-Attachment

Available in accessible formats upon request

Page 2: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

2

Agenda Corporate Profile

Financial Results

Capital Overview

Power Sale Contracts

Liquidity & Projected Financing

Financial Targets

Rates

Page 3: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

3

Corporate Profile

One of the largest integrated electricity and natural gas utilities in Canada.

562,000 electricity customers and275,000 natural gas customers.

$18 billion total assets. $2 billion annual revenues. 5,701 MW generating capability. Among the lowest electricity rates in North America. One of Canada’s “Top 100” Employers.

Page 4: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

4

Financial Results

Page 5: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

5

Financial ResultsFor the Fiscal Years Ended March 31st ($ are in millions)

Actual Actual Forecast Forecast2014 2015 2016 2017

Revenues(net of cost of gas) $2,060 $2,046 $2,121 $2,203Expenses (1,908) (1,943) (2,007) (2,144)Non‐Controlling Interest 22 11 12 8

Net Income  $174 $114 $126 $67

Total Assets $15,639 $17,594 $19,100 $22,030Retained Earnings $2,716 $2,830 $2,901 $2,968Financial Ratios:Debt/ Equity 76:24 79:21 81:19 83:17Interest Coverage 1.28 1.17 1.17 1.07

Page 6: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

6

Financial Results - IFRSFor the 3 Months Ended June 30th ($ are in millions)

3 Months 3 MonthsJune 2014 June 2015

Revenues $502 $502Expenses (505) (534)Regulatory Deferral Movement 7 0Non‐Controlling Interest 6 3

Net Income  $10 ($29)

Total Assets $15,779 $17,929Retained Earnings $2,653 $2,697

Page 7: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

7

Capital Overview

Page 8: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

8

Major Generation and Transmission Projects

Bipole III (2018/19) $4.65 billion

695 MW Keeyask G.S. (2019/20) $6.50 billion

Page 9: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

9

Capital Expenditures (CEF14)

Other Major

Pointe du Bois

Bipole III

Keeyask

$0

$500

$1,000

$1,500

$2,000

$2,500

$3,000

$3,500

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

2027

2028

2029

2030

2031

2032

2033

2034

Mill

ions

Fiscal Year Ending

Page 10: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

10

Long-Term Export Contracts

Page 11: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

11

Future Long-Term Export Contracts

Minnesota Power 250 MW System Participation Sale starting in 2020 (15 years) 133 MW Energy Sale starting in 2020 (20 years)

Northern States Power 125 MW System Power Sale starting in 2021 (4 years) 75 MW System Power Sale starting in 2016 (4 years)

SaskPower 25 MW System Power Sale starting in 2015 (7 years) 100 MW System Power Sale starting in 2020 (20 years)

Page 12: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

12

Future Long-Term Export Contracts

Wisconsin Public Service 108 MW System Power Sale starting in 2016 (5 years) 100 MW System Power Sale starting in 2021 (4 years) 100 MW Energy Sale starting in 2025 (4 years) 308 MW System Power Sale dependent on Conawapa 8 MW Energy Sale starting in 2023 (6 years)

NextEra Energy 100 MW Capacity Sale starting in 2016 (2 years)

American Electric Power Energy Partners 79/50 MW Capacity Sale starting in 2016 (4 years)

Page 13: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

13

Liquidity & Financing

Page 14: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

14

Cash Flow from Operations (IFF14)

-

100

200

300

400

500

600

700

800

900

2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

($ M

illio

ns)

Current Outlook Base Capital

Page 15: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

15

Forecasted New Debt Financing Requirements (IFF14)

0

200

400

600

800

1000

1200

1400

1600

1800

2000

2200

2400

2600

2800

3000

3200

2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

($ M

illio

ns)

Page 16: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

16

Financial Targets

Page 17: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Equity Ratio

17

0%

5%

10%

15%

20%

25%

30%

IFF14 Target

Page 18: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Capital Coverage Ratio

18

0.00

0.50

1.00

1.50

2.00

2.50

IFF14 Target

Page 19: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Interest Coverage Ratio

19

0.000.200.400.600.801.001.201.401.601.802.002.202.402.60

IFF14 Target

Page 20: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

20

Rates

Page 21: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Average Retail Price of ElectricityAverage Retail Price of ElectricityTop 10 Provinces/ States in North America

Source: US Dept of Energy (December 2014) & Edison Electric Survey (January 2015)(Exchange rate as of September 23, 2015: 1 US$ = 1.3278 Cdn)

21

6.306.61

8.849.05

9.39 9.55 9.57 9.60 9.60 9.61

5.0

6.0

7.0

8.0

9.0

10.0

Cents /

 kW.h (C

anad

ian)

Page 22: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Utility Rate Changes

22

Page 23: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

23

Domestic Rate Strategy Recent PUB Board Orders

On July 24, 2015 the PUB issued Orders 73/15 and 77/15 which approved a 3.95% across-the-board rate increase for all customer classes effective August 1, 2015

On January 16, 2015, Manitoba Hydro filed its 2015/16 & 2016/17 General Rate Application with the PUB, in which Manitoba Hydro requested approval, on an interim basis, of a 3.95% across-the-board rate increase effective April 1, 2015 and another effective April 1, 2016.

Page 24: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

24

Domestic Rate Strategy Future Plans

MH will continue to request domestic rate increases in support of the Finance goal in the Corporate Strategic Plan to “maintain a strong financial structure.”

Page 25: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

25

Questions?

Page 26: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

1

Presentation to Moody’sJune 17, 2015

Manitoba HydroCorporate Update

Page 27: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

2

Agenda Corporate Profile

Financial Results

Capital Overview

Power Sale Contracts

Liquidity & Projected Financing

Financial Targets

Rates

Page 28: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

3

Corporate Profile

One of the largest integrated electricity and natural gas utilities in Canada.

556,000 electricity customers and272,000 natural gas customers.

$16 billion total assets. $2 billion annual revenues. 5,725 MW generating capability. Among the lowest electricity rates in North America. One of Canada’s “Top 100” Employers.

Page 29: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

4

Financial Results

Page 30: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

5

Financial ResultsFor the Fiscal Years Ended March 31st ($ are in millions)

Actual Preliminary Forecast Forecast2014 2015 2016 2017

Revenues(net of cost of gas) $2,035 $2,031 $2,121 $2,203Expenses (1,883) (1,928) (2,007) (2,144)Non‐Controlling Interest 22 11 12 8

Net Income  $174 $114 $126 $67

Total Assets $15,639 $17,585 $19,100 $22,030Retained Earnings $2,716 $2,830 $2,901 $2,968Financial Ratios:Debt/ Equity 76:24 79:21 81:19 83:17Interest Coverage 1.28 1.17 1.17 1.07

Page 31: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

6

Capital Overview

Page 32: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

7

Major Generation and Transmission Projects

Bipole III (2018/19) $4.65 billion

695 MW Keeyask G.S. (2019/20) $6.50 billion

Page 33: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

8

Capital Expenditures (CEF14)

Other Major

Pointe du Bois

Bipole III

Keeyask

$0

$500

$1,000

$1,500

$2,000

$2,500

$3,000

$3,500

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

2027

2028

2029

2030

2031

2032

2033

2034

Mill

ions

Fiscal Year Ending

Page 34: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

9

Long-Term Export Contracts

Page 35: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

10

Future Long-Term Export Contracts

Minnesota Power 250 MW System Participation Sale starting in 2020 (15 years) 133 MW Energy Sale starting in 2020 (20 years)

Northern States Power 125 MW System Power Sale starting in 2021 (4 years) 75 MW System Power Sale starting in 2016 (4 years)

SaskPower 25 MW System Power Sale starting in 2015 (7 years)

Page 36: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

11

Future Long-Term Export Contracts

Wisconsin Public Service 108 MW System Power Sale starting in 2016 (5 years) 100 MW System Power Sale starting in 2021 (4 years) 308 MW System Power Sale starting in 2027 (9 years) 8 MW Energy Sale starting in 2023 (6 years)

Page 37: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

12

Liquidity & Financing

Page 38: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

13

Cash Flow from Operations (IFF14)

-

100

200

300

400

500

600

700

800

900

2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

($ M

illio

ns)

Current Outlook Base Capital

Page 39: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

14

Forecasted New Debt Financing Requirements (IFF14)

0

200

400

600

800

1000

1200

1400

1600

1800

2000

2200

2400

2600

2800

3000

3200

2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

($ M

illio

ns)

Page 40: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

15

Financial Targets

Page 41: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Equity Ratio

16

0%

5%

10%

15%

20%

25%

30%

IFF14 Target

Page 42: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Capital Coverage Ratio

17

0.00

0.50

1.00

1.50

2.00

2.50

IFF14 Target

Page 43: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Interest Coverage Ratio

18

0.000.200.400.600.801.001.201.401.601.802.002.202.402.60

IFF14 Target

Page 44: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

19

Rates

Page 45: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Average Retail Price of ElectricityAverage Retail Price of ElectricityTop 10 Provinces/ States in North America

Source: US Dept of Energy (December 2014) & Edison Electric Survey (January 2015)(Exchange rate as of March 31,2015: 1 US$ = 1.2683 Cdn)

20

6.306.61

8.849.05

9.39 9.55 9.57 9.60 9.60 9.61

5.0

6.0

7.0

8.0

9.0

10.0

Cents /

 kW.h (C

anad

ian)

Page 46: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Utility Rate Changes

21

Page 47: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

22

Domestic Rate Strategy Recent PUB Board Orders

On May 7, 2014, the PUB issued Order 51/14 with respect to Manitoba Hydro's Application for Interim Rates Effective May 1, 2014 approving on an interim basis a 2.75% across-the-board rate increase for all customer classes.

On January 16, 2015, Manitoba Hydro filed its 2015/16 & 2016/17 General Rate Application with the PUB, in which Manitoba Hydro is requesting approval, on an interim basis, of a 3.95% across-the-board rate increase effective April 1, 2015 and another effective April 1, 2016.

Page 48: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

23

Domestic Rate Strategy Future Plans

MH will continue to request domestic rate increases in support of the Finance goal in the Corporate Strategic Plan to “maintain a strong financial structure.”

Page 49: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

24

Questions?

Page 50: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

1

Presentation to Moody’s July 13, 2016

Manitoba Hydro Corporate Update

Page 51: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

2

Agenda

Corporate Profile Financial Results Capital Overview Power Sale Contracts Liquidity & Projected Financing Financial Targets Rates

Page 52: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

3

Corporate Profile

One of the largest integrated electricity and natural gas utilities in Canada.

568,000 electricity customers and 277,000 natural gas customers.

$20 billion total assets. $2 billion annual revenues. 5,680 MW generating capability. Among the lowest electricity rates in North America. One of Canada’s “Top 100” Employers.

Page 53: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

4

Financial Results

Page 54: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

5

Financial Results - IFRS For the Fiscal Years Ended March 31st ($ are in millions)

Preliminary Preliminary Forecast Forecast2015 2016 2017 2018

Revenues $2,316 $2,258 $2,436 $2,511Expenses (2,229) (2,266) (2,403) (2,441)Net Movement in Regulatory Balances 38 47 0 0Non-Controlling Interest 11 10 9 4

Net Income $136 $49 $42 $74

Total Assets and Regulatory Deferral Balance $17,567 $19,780 $23,360 $26,286Retained Earnings $2,779 $2,828 $2,793 $2,867Financial Ratios:Debt/ Equity 82:18 83:17 86:14 85:15EBITDA Interest Coverage 1.73 1.55 1.55 1.55

Page 55: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

6

Capital Overview

Page 56: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

7

Major Generation and Transmission Projects

Bipole III (2018/19) $4.65 billion 695 MW Keeyask G.S. (2019/20) $6.50 billion

Page 57: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

8

Capital Expenditures (CEF15)

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

Mill

ions

of D

olla

rs

Fiscal Year Ending

Electric Gas Other MNG&T Wuskwatim Keeyask Conawapa Bipole III DSM Pointe Du Bois Pointe Du Bois

Page 58: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

9

Long-Term Export Contracts

Page 59: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

10

Future Long-Term Export Contracts Minnesota Municipal Power Agency

60 MW Energy Sale starting in 2017 (5 years)

Minnesota Power

250 MW System Participation Sale starting in 2020 (15 years) 133 MW Energy Sale starting in 2020 (20 years) 50 MW Capacity Sale starting in 2018 (2 years)

Northern States Power 125 MW System Power Sale starting in 2021 (4 years)

Page 60: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

11

Future Long-Term Export Contracts

SaskPower 100 MW System Power Sale starting in 2020 (20 years)

Wisconsin Public Service 100 MW System Power Sale starting in 2021 (4 years)

(with an option to extend to 2027) 100 MW Energy Sale starting in 2025 (4 years) 308 MW System Power Sale TBD (Ending in 2036) 8 MW Energy Sale starting in 2023 (6 years)

Basin Electric Power 50 MW Capacity Sale starting in 2018 (2 years)

Page 61: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

12

Liquidity & Financing

Page 62: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

13

Cash Flow from Operations (IFF15)

-

100

200

300

400

500

600

700

800

900

1,000

1,100

2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026

($ M

illio

ns)

Current Outlook Base Capital

Page 63: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

14

Forecasted New Debt Financing Requirements (IFF15)

-

200

400

600

800

1,000

1,200

1,400

1,600

1,800

2,000

2,200

2,400

2,600

2,800

3,000

3,200

2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026

($ M

illio

ns)

Page 64: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

15

Financial Targets

Page 65: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Equity Ratio

16

0%

5%

10%

15%

20%

25%

30%

35%

40%

IFF15 Target

Page 66: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Capital Coverage Ratio

17

0.00

0.50

1.00

1.50

2.00

2.50

3.00

IFF15 Target

Page 67: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Interest Coverage Ratio

18

0.00 0.25 0.50 0.75 1.00 1.25 1.50 1.75 2.00 2.25 2.50 2.75 3.00 3.25

IFF15 Target

Page 68: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

19

Rates

Page 69: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Average Retail Price of Electricity Average Retail Price of Electricity

Top 10 Provinces/ States in North America

Source: US Dept of Energy (December 2015) & Edison Electric Survey (January 2016) (Exchange rate as of May 4,2016: 1 US$ = 1.2870 Cdn)

20

6.456.81

8.26

9.02 9.03

9.83 9.84 10.03 10.03

10.81

5.0

6.0

7.0

8.0

9.0

10.0

11.0

12.0

Cent

s / k

W.h

(Can

adia

n)

Page 70: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Utility Rate Changes

21

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Cumulative

Current Rate

Index*

Manitoba Hydro 2.25% 5.00% 2.90% 2.80% 2.00% 4.40% 3.50% 2.75% 3.95% 3.36% 38.2% 100

Hydro Quebec 1.90% 2.90% 1.20% 0.35% -0.40% -0.50% 2.41% 4.30% 2.90% 0.70% 16.8% 106

BC Hydro 2.10% 0.83% 9.28% 7.29% 7.77% 7.07% 1.44% 9.00% 6.00% 4.00% 69.8% 129

SaskPower 4.20% 0.00% 8.50% 4.50% 0.00% 0.00% 4.90% 5.50% 5.00% 5.00% (proposed)

44.2% 152

New Brunswick Power

5.90% 3.00% 3.00% 3.00% 0.00% 0.00% 2.00% 2.00% 1.60% 2.00% (proposed)

24.8% 159

Nova Scotia Power

3.80% 0.00% 9.30% 0.00% 6.05% 8.70% 3.00% 3.00% 0.00% -1.00% 37.4% 207

* This index is based on the Edison Electric Institute Survey and compares the average price per kWh for the various utilities. Manitoba Hydro's average price is $0.0645/kWh in Canadian dollars. The Survey is based on 12 months data ending December 2015. SaskPower average price/kWh is based on their 2015 annual report.

Page 71: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

22

Domestic Rate Strategy Recent PUB Board Orders

On July 24, 2015, the PUB issued Orders 73/15 and 77/15 with respect to Manitoba Hydro's 2015/16 & 2016/17 General Rate Application approving a 3.95% across-the-board rate increase for all customer classes effective August 1, 2015.

On April 28, 2016, the PUB issued Order 59/16 with respect to Manitoba Hydro’s Supplemental Filing for Interim Electric Rates effective April 1, 2016 approving a 3.36% interim increase; Manitoba Hydro had requested a 3.95% across-the-board rate increase.

Page 72: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

23

Domestic Rate Strategy Future Plans

MH will continue to request domestic rate increases in support of the Finance goal in the Corporate Strategic Plan to “maintain a strong financial structure.”

Page 73: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

24

Questions?

Page 74: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

1

Presentation to Moody’sJuly 20, 2017

Manitoba HydroCorporate Update

Page 75: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

2

Agenda Corporate Profile

Financial Results

Capital Overview

Power Sale Contracts

Liquidity & Projected Financing

Financial Targets

Rates

Page 76: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

3

Corporate Profile

One of the largest integrated electricity and natural gas utilities in Canada.

573,000 electricity customers and279,000 natural gas customers.

$22 billion total assets. $2 billion annual revenues. 5,680 MW generating capability. Among the lowest electricity rates in North America. One of Canada’s “Top 100” Employers.

Page 77: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

4

Financial Results

Page 78: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

5

Financial Results - IFRSFor the Fiscal Years Ended March 31st ($ are in millions)

 Preliminary Forecast Forecast

2016 2017 2018 2019

Revenues $2,258 $2,327 $2,512 $2,780Expenses (2,266) (2,323) (2,425) (2,578)Net Movement in Regulatory Balances 47 55 93 109Non‐Controlling Interest 10 12 8 1

Net Income  $49 $71 $188 $312

Total Assets and Regulatory Deferral Balance $19,779 $22,338 $25,533 $28,366Retained Earnings $2,828 $2,899 $3,087 $3,399Financial Ratios:Debt/ Equity 83:17 84:16 85:15 85:15EBITDA Interest Coverage 1.57 1.54 1.66 1.83

Page 79: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

6

Capital Overview

Page 80: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

7

Major Generation and Transmission Projects

Bipole III (2018/19) $5.04 billion

695 MW Keeyask G.S. (2021/22) $8.70 billion

Page 81: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

8

Capital Expenditures (CEF16)

0

500

1,000

1,500

2,000

2,500

3,000

3,500

Mill

ions

of D

olla

rs

Fiscal Year Ending

Electric Gas Other MNG&T Wuskwatim Keeyask Conawapa Bipole III Pointe Du Bois Electric DSM Gas DSM

Page 82: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

9

Long-Term Export Contracts

Page 83: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

10

Future Long-Term Export Contracts Minnesota Power

250 MW System Participation Sale starting in 2020 (15 years) 133 MW Energy Sale starting in 2020 (20 years)

Northern States Power 125 MW System Power Sale starting in 2021 (4 years)

Page 84: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

11

Future Long-Term Export Contracts

SaskPower 100 MW System Power Sale starting in 2020 (20 years)

Wisconsin Public Service 100 MW System Power Sale starting in 2021 (4 years) 100 MW Energy Sale starting in 2025 (4 years) 308 MW System Power Sale TBD (Ending in 2036) 8 MW Energy Sale starting in 2023 or 2021 (6 years)

Basin Electric Power 50 MW Capacity Sale starting in 2018 (2 years) 50 MW Capacity Sale starting in 2020 (1 year)

Page 85: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

12

Liquidity & Financing

Page 86: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

13

Cash Flow from Operations (IFF16 Update)

-

100

200

300

400

500

600

700

800

900

1,000

1,100

1,200

1,300

1,400

1,500

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

($ M

illio

ns)

Current Outlook Base Capital

Page 87: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

14

Forecasted New Debt Financing Requirements (IFF16 Update)

-

200

400

600

800

1,000

1,200

1,400

1,600

1,800

2,000

2,200

2,400

2,600

2,800

3,000

3,200

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

($ M

illio

ns)

Page 88: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

15

Financial Targets

Page 89: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Equity Ratio

16

0%

5%

10%

15%

20%

25%

30%

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

IFF16 Update Target

Page 90: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Capital Coverage Ratio

17

0.00

0.50

1.00

1.50

2.00

2.50

3.00

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

IFF16 Update Target

Page 91: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

EBITDA Interest Coverage Ratio

18

0.00

0.25

0.50

0.75

1.00

1.25

1.50

1.75

2.00

2.25

2.50

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

IFF16 Update Target

Page 92: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

19

Rates

Page 93: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Average Retail Price of ElectricityAverage Retail Price of ElectricityTop 10 Provinces/ States in North America

Source: US Dept of Energy (December 2016) & Edison Electric Survey (January 2017)(Exchange rate as of April 26 ,2017: 1 US$ = 1.3592 Cdn)

20

6.456.84

8.56

10.09 10.1410.45 10.48 10.51 10.64 10.68

5.0

6.0

7.0

8.0

9.0

10.0

11.0

12.0

Cents /

 kW.h (C

anadian)

Page 94: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Utility Rate Changes

21

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Cumulative

Current Rate

Index*

Manitoba Hydro 2.25% 5.00% 2.90% 2.80% 2.00% 4.40% 3.50% 2.75% 3.95% 3.36% 7.90% 49.1% 100

Hydro Quebec1.90% 2.90% 1.20% 0.35% ‐0.40% ‐0.50% 2.41% 4.30% 2.90% 0.70% 0.70% 17.6% 106

BC Hydro 2.10% 0.83% 9.28% 7.29% 7.77% 7.07% 1.44% 9.00% 6.00% 4.00% 3.50% 75.7% 132

SaskPower4.20% 0.00% 8.50% 4.50% 0.00% 0.00% 4.90% 5.50% 5.00% 5.00% 3.50% 49.2% 156

New Brunswick Power 5.90% 3.00% 3.00% 3.00% 0.00% 0.00% 2.00% 2.00% 1.60% 1.66% 1.77% 26.6% 162Nova Scotia Power 3.80% 0.00% 9.30% 0.00% 6.05% 8.70% 3.00% 3.00% 0.00% ‐1.00% 1.50% 39.4% 205

* This index is based on the Edison Electric Institute Survey and compares the average price per kWh for the various utilities. Manitoba Hydro's average price is $0.0648/kWh in Canadian dollars based on 12 months data ending December 2016.

Page 95: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Residential Monthly Bill ComparisonAverage Retail Price of ElectricityIn 2018/19 – Residential Consumption 1,000 kWh/ month

22

$181$169

$167

$164

$163$132

$116

$114$108

$101

$72

$0 $20 $40 $60 $80 $100 $120 $140 $160 $180 $200

Toronto

Ottawa

Charlottetown

Halifax

Regina

Moncton

St. John's

Vancouver

Calgary

Winnipeg

Montreal

Monthly Bill Comparison in 2 years (2018/19)Residential Consumption: 1,000 kWh / month

Page 96: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

23

Domestic Rate Strategy Recent PUB Board Orders

On May 5, 2017, Manitoba Hydro filed its 2017/18 & 2018/19 General Rate Application with the PUB. In this filing, Manitoba Hydro is requesting approval of a 7.9% rate increase effective August 1, 2017 and a further 7.9% rate increase effective April 1, 2018.

On July 11, 2017, Manitoba Hydro filed an update to its financial forecast for electric operations as part of the 2017/18 & 2018/19 General Rate Application with the PUB.

Page 97: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

24

Domestic Rate Strategy Recent PUB Board Orders

On May 17, 2016, the PUB issued Order 68/16 approving a 3.36% electricity rate increase for all customer classes effective August 1, 2016; Manitoba Hydro had requested a 3.95% across-the-board rate increase.

Page 98: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

25

Domestic Rate Strategy Future Plans

MH will continue to request domestic rate increases in support of the Finance goal in the Corporate Strategic Plan to “maintain a strong financial structure.”

Page 99: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

26

Questions?

Page 100: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

1

Presentation to DBRSNovember 16, 2015

Manitoba HydroCorporate Update

Page 101: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

2

Agenda Corporate Profile

Financial Results

Capital Overview

Power Sale Contracts

Liquidity & Projected Financing

Financial Targets

Rates

Page 102: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

3

Corporate Profile

One of the largest integrated electricity and natural gas utilities in Canada.

562,000 electricity customers and275,000 natural gas customers.

$18 billion total assets. $2 billion annual revenues. 5,701 MW generating capability. Among the lowest electricity rates in North America. One of Canada’s “Top 100” Employers.

Page 103: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

4

Financial Results

Page 104: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

5

Financial ResultsFor the Fiscal Years Ended March 31st ($ are in millions)

Actual Actual Forecast Forecast2014 2015 2016 2017

Revenues(net of cost of gas) $2,060 $2,046 $2,121 $2,203Expenses (1,908) (1,943) (2,007) (2,144)Non‐Controlling Interest 22 11 12 8

Net Income  $174 $114 $126 $67

Total Assets $15,639 $17,594 $19,100 $22,030Retained Earnings $2,716 $2,830 $2,901 $2,968Financial Ratios:Debt/ Equity 76:24 79:21 81:19 83:17Interest Coverage 1.28 1.17 1.17 1.07

Page 105: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

6

Financial Results - IFRSFor the 3 Months Ended June 30th ($ are in millions)

3 Months 3 MonthsJune 2014 June 2015

Revenues $502 $502Expenses (505) (534)Regulatory Deferral Movement 7 0Non‐Controlling Interest 6 3

Net Income  $10 ($29)

Total Assets $15,779 $17,929Retained Earnings $2,653 $2,697

Page 106: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

7

Capital Overview

Page 107: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

8

Major Generation and Transmission Projects

Bipole III (2018/19) $4.65 billion

695 MW Keeyask G.S. (2019/20) $6.50 billion

Page 108: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

9

Capital Expenditures (CEF14)

Other Major

Pointe du Bois

Bipole III

Keeyask

$0

$500

$1,000

$1,500

$2,000

$2,500

$3,000

$3,500

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

2027

2028

2029

2030

2031

2032

2033

2034

Mill

ions

Fiscal Year Ending

Page 109: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

10

Long-Term Export Contracts

Page 110: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

11

Future Long-Term Export Contracts

Minnesota Power 250 MW System Participation Sale starting in 2020 (15 years) 133 MW Energy Sale starting in 2020 (20 years)

Northern States Power 125 MW System Power Sale starting in 2021 (4 years) 75 MW System Power Sale starting in 2016 (4 years)

SaskPower 25 MW System Power Sale starting in 2015 (7 years) 100 MW System Power Sale starting in 2020 (20 years)

Page 111: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

12

Future Long-Term Export Contracts

Wisconsin Public Service 108 MW System Power Sale starting in 2016 (5 years) 100 MW System Power Sale starting in 2021 (4 years) 100 MW Energy Sale starting in 2025 (4 years) 308 MW System Power Sale dependent on Conawapa 8 MW Energy Sale starting in 2023 (6 years)

NextEra Energy 100 MW Capacity Sale starting in 2016 (2 years)

American Electric Power Energy Partners 79/50 MW Capacity Sale starting in 2016 (4 years)

Page 112: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

13

Liquidity & Financing

Page 113: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

14

Cash Flow from Operations (IFF14)

-

100

200

300

400

500

600

700

800

900

2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

($ M

illio

ns)

Current Outlook Base Capital

Page 114: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

15

Forecasted New Debt Financing Requirements (IFF14)

0

200

400

600

800

1000

1200

1400

1600

1800

2000

2200

2400

2600

2800

3000

3200

2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

($ M

illio

ns)

Page 115: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

16

Financial Targets

Page 116: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Equity Ratio

17

0%

5%

10%

15%

20%

25%

30%

IFF14 Target

Page 117: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Capital Coverage Ratio

18

0.00

0.50

1.00

1.50

2.00

2.50

IFF14 Target

Page 118: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Interest Coverage Ratio

19

0.000.200.400.600.801.001.201.401.601.802.002.202.402.60

IFF14 Target

Page 119: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

20

Rates

Page 120: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Average Retail Price of ElectricityAverage Retail Price of ElectricityTop 10 Provinces/ States in North America

Source: US Dept of Energy (December 2014) & Edison Electric Survey (January 2015)(Exchange rate as of September 23, 2015: 1 US$ = 1.3278 Cdn)

21

6.306.61

8.849.05

9.39 9.55 9.57 9.60 9.60 9.61

5.0

6.0

7.0

8.0

9.0

10.0

Cents /

 kW.h (C

anad

ian)

Page 121: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Utility Rate Changes

22

Page 122: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

23

Domestic Rate Strategy Recent PUB Board Orders

On July 24, 2015 the PUB issued Orders 73/15 and 77/15 which approved a 3.95% across-the-board rate increase for all customer classes effective August 1, 2015

On January 16, 2015, Manitoba Hydro filed its 2015/16 & 2016/17 General Rate Application with the PUB, in which Manitoba Hydro requested approval, on an interim basis, of a 3.95% across-the-board rate increase effective April 1, 2015 and another effective April 1, 2016.

Page 123: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

24

Domestic Rate Strategy Future Plans

MH will continue to request domestic rate increases in support of the Finance goal in the Corporate Strategic Plan to “maintain a strong financial structure.”

Page 124: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

25

Questions?

Page 125: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

1

Presentation to DBRS

August 22,2016

Manitoba Hydro Corporate Update

Page 126: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

2

Agenda

Corporate Profile Financial Results Capital Overview Power Sale Contracts Liquidity & Projected Financing Financial Targets Rates

Page 127: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

3

Corporate Profile

One of the largest integrated electricity and

natural gas utilities in Canada.

568,000 electricity customers and 277,000 natural gas customers.

$20 billion total assets.

$2 billion annual revenues.

5,680 MW generating capability.

Among the lowest electricity rates in North America.

One of Canada’s “Top 100” Employers.

Page 128: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

4

Financial Results

Page 129: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

5

Financial Results - IFRS For the Fiscal Years Ended March 31st ($ are in millions)

Actual Actual Forecast Forecast

2015 2016 2017 2018

Revenues $2,316 $2,258 $2,436 $2,511

Expenses (2,229) (2,266) (2,403) (2,441)

Net Movement in Regulatory Balances 38 47 0 0

Non-Controlling Interest 11 10 9 4

Net Income $136 $49 $42 $74

Total Assets and Regulatory Deferral Balance $17,567 $19,780 $23,360 $26,286

Retained Earnings $2,779 $2,828 $2,793 $2,867

Financial Ratios:

Debt/ Equity 82:18 83:17 86:14 85:15

EBITDA Interest Coverage 1.73 1.55 1.55 1.55

Page 130: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

6

Capital Overview

Page 131: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

7

Major Generation and Transmission Projects

Bipole III (2018/19) $4.65 billion 695 MW Keeyask G.S. (2019/20) $6.50 billion

Page 132: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

8

Capital Expenditures (CEF15)

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

Mill

ions o

f D

olla

rs

Fiscal Year Ending

Electric Gas Other MNG&T Wuskwatim Keeyask Conawapa Bipole III DSM Pointe Du Bois Pointe Du Bois

Page 133: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

9

Long-Term Export Contracts

Page 134: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

10

Future Long-Term Export Contracts

Minnesota Municipal Power Agency

60 MW Energy Sale starting in 2017 (5 years)

Minnesota Power

250 MW System Participation Sale starting in 2020 (15 years)

133 MW Energy Sale starting in 2020 (20 years)

50 MW Capacity Sale starting in 2018 (2 years)

Northern States Power

125 MW System Power Sale starting in 2021 (4 years)

Page 135: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

11

Future Long-Term Export Contracts

SaskPower

100 MW System Power Sale starting in 2020 (20 years)

Wisconsin Public Service

100 MW System Power Sale starting in 2021 (4 years)

(with an option to extend to 2027)

100 MW Energy Sale starting in 2025 (4 years)

308 MW System Power Sale TBD (Ending in 2036)

8 MW Energy Sale starting in 2023 (6 years)

Basin Electric Power

50 MW Capacity Sale starting in 2018 (2 years)

Page 136: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

12

Liquidity & Financing

Page 137: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

13

Cash Flow from Operations (IFF15)

-

100

200

300

400

500

600

700

800

900

1,000

1,100

2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026

($ M

illions)

Current Outlook Base Capital

Page 138: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

14

Forecasted New Debt Financing Requirements (IFF15)

-

200

400

600

800

1,000

1,200

1,400

1,600

1,800

2,000

2,200

2,400

2,600

2,800

3,000

3,200

2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026

($ M

illions)

Page 139: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

15

Financial Targets

Page 140: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Equity Ratio

16

0%

5%

10%

15%

20%

25%

30%

35%

40%

IFF15 Target

Page 141: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Capital Coverage Ratio

17

0.00

0.50

1.00

1.50

2.00

2.50

3.00

IFF15 Target

Page 142: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Interest Coverage Ratio

18

0.00

0.25

0.50

0.75

1.00

1.25

1.50

1.75

2.00

2.25

2.50

2.75

3.00

3.25

IFF15 Target

Page 143: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

19

Rates

Page 144: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Average Retail Price of Electricity Average Retail Price of Electricity

Top 10 Provinces/ States in North America

Source: US Dept of Energy (December 2015) & Edison Electric Survey (January 2016)

(Exchange rate as of May 4,2016: 1 US$ = 1.2870 Cdn)

20

6.456.81

8.26

9.02 9.03

9.83 9.8410.03 10.03

10.81

5.0

6.0

7.0

8.0

9.0

10.0

11.0

12.0

Ce

nts

/ k

W.h

(C

anad

ian

)

Page 145: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Utility Rate Changes

21

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Cumulative

Current

Rate

Index*

Manitoba Hydro 2.25% 5.00% 2.90% 2.80% 2.00% 4.40% 3.50% 2.75% 3.95% 3.36% 38.2% 100

Hydro Quebec 1.90% 2.90% 1.20% 0.35% -0.40% -0.50% 2.41% 4.30% 2.90% 0.70% 16.8% 106

BC Hydro 2.10% 0.83% 9.28% 7.29% 7.77% 7.07% 1.44% 9.00% 6.00% 4.00% 69.8% 129

SaskPower 4.20% 0.00% 8.50% 4.50% 0.00% 0.00% 4.90% 5.50% 5.00% 5.00%

(proposed) 44.2% 152

New Brunswick

Power 5.90% 3.00% 3.00% 3.00% 0.00% 0.00% 2.00% 2.00% 1.60%

2.00% (proposed)

24.8% 159

Nova Scotia

Power 3.80% 0.00% 9.30% 0.00% 6.05% 8.70% 3.00% 3.00% 0.00% -1.00% 37.4% 207

* This index is based on the Edison Electric Institute Survey and compares the average price per kWh for the various utilities.

Manitoba Hydro's average price is $0.0645/kWh in Canadian dollars. The Survey is based on 12 months data ending December 2015.

SaskPower average price/kWh is based on their 2015 annual report.

Page 146: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

22

Domestic Rate Strategy Recent PUB Board Orders

On July 24, 2015, the PUB issued Orders 73/15 and 77/15 with respect to Manitoba Hydro's 2015/16 & 2016/17 General Rate Application approving a 3.95% across-the-board rate increase for all customer classes effective August 1, 2015.

On April 28, 2016, the PUB issued Order 59/16 with respect to Manitoba Hydro’s Supplemental Filing for Interim Electric Rates effective April 1, 2016 approving a 3.36% interim increase; Manitoba Hydro had requested a 3.95% across-the-board rate increase.

Page 147: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

23

Domestic Rate Strategy Future Plans

MH will continue to request domestic rate increases in support of the Finance goal in the Corporate Strategic Plan to “maintain a strong financial structure.”

Page 148: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

24

Questions?

Page 149: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

1

Presentation to DBRSJune 8, 2017

Manitoba HydroCorporate Update

Page 150: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

2

Agenda Corporate Profile

Financial Results

Capital Overview

Power Sale Contracts

Liquidity & Projected Financing

Financial Targets

Rates

Page 151: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

3

Corporate Profile

One of the largest integrated electricity and natural gas utilities in Canada.

573,000 electricity customers and279,000 natural gas customers.

$22 billion total assets. $2 billion annual revenues. 5,680 MW generating capability. Among the lowest electricity rates in North America. One of Canada’s “Top 100” Employers.

Page 152: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

4

Financial Results

Page 153: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

5

Financial Results - IFRSFor the Fiscal Years Ended March 31st ($ are in millions)

Preliminary Forecast Forecast2016 2017 2018 2019

Revenues $2,258 $2,330 $2,442 $2,736Expenses (2,266) (2,323) (2,417) (2,585)Net Movement in Regulatory Balances 47 55 88 100Non‐Controlling Interest 10 12 9 1

Net Income  $49 $74 $122 $252

Total Assets and Regulatory Deferral Balance $19,780 $22,341 $25,424 $28,390Retained Earnings $2,828 $2,902 $2,993 $3,245Financial Ratios:Debt/ Equity 83:17 84:16 85:15 85:15EBITDA Interest Coverage 1.55 1.51 1.60 1.79

Page 154: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

6

Capital Overview

Page 155: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

7

Major Generation and Transmission Projects

Bipole III (2018/19) $5.04 billion

695 MW Keeyask G.S. (2021/22) $8.70 billion

Page 156: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

8

Capital Expenditures (CEF16)

0

500

1,000

1,500

2,000

2,500

3,000

3,500

Mill

ions

of D

olla

rs

Fiscal Year Ending

Electric Gas Other MNG&T Wuskwatim Keeyask Conawapa Bipole III Pointe Du Bois Electric DSM Gas DSM

Page 157: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

9

Long-Term Export Contracts

Page 158: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

10

Future Long-Term Export Contracts Minnesota Power

250 MW System Participation Sale starting in 2020 (15 years) 133 MW Energy Sale starting in 2020 (20 years)

Northern States Power 125 MW System Power Sale starting in 2021 (4 years)

Page 159: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

11

Future Long-Term Export Contracts

SaskPower 100 MW System Power Sale starting in 2020 (20 years)

Wisconsin Public Service 100 MW System Power Sale starting in 2021 (4 years) 100 MW Energy Sale starting in 2025 (4 years) 308 MW System Power Sale TBD (Ending in 2036) 8 MW Energy Sale starting in 2023 or 2021 (6 years)

Basin Electric Power 50 MW Capacity Sale starting in 2018 (2 years) 50 MW Capacity Sale starting in 2020 (1 year)

Page 160: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

12

Liquidity & Financing

Page 161: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

13

Cash Flow from Operations (IFF16)

-

100

200

300

400

500

600

700

800

900

1,000

1,100

1,200

1,300

1,400

1,500

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

($ M

illio

ns)

Current Outlook Base Capital

Page 162: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

14

Forecasted New Debt Financing Requirements (IFF16)

-

200

400

600

800

1,000

1,200

1,400

1,600

1,800

2,000

2,200

2,400

2,600

2,800

3,000

3,200

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

($ M

illio

ns)

Page 163: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

15

Financial Targets

Page 164: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Equity Ratio

16

0%

5%

10%

15%

20%

25%

30%

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

IFF16 Target

Page 165: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Capital Coverage Ratio

17

0.00

0.50

1.00

1.50

2.00

2.50

3.00

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

IFF16 Target

Page 166: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

EBITDA Interest Coverage Ratio

18

0.00

0.25

0.50

0.75

1.00

1.25

1.50

1.75

2.00

2.25

2.50

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

IFF16 Target

Page 167: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

19

Rates

Page 168: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Average Retail Price of ElectricityAverage Retail Price of ElectricityTop 10 Provinces/ States in North America

Source: US Dept of Energy (December 2016) & Edison Electric Survey (January 2017)(Exchange rate as of April 26 ,2017: 1 US$ = 1.3592 Cdn)

20

6.456.84

8.56

10.09 10.1410.45 10.48 10.51 10.64 10.68

5.0

6.0

7.0

8.0

9.0

10.0

11.0

12.0

Cents /

 kW.h (C

anadian)

Page 169: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Utility Rate Changes

21

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Cumulative

Current Rate

Index*

Manitoba Hydro 2.25% 5.00% 2.90% 2.80% 2.00% 4.40% 3.50% 2.75% 3.95% 3.36% 7.90% 49.1% 100

Hydro Quebec1.90% 2.90% 1.20% 0.35% ‐0.40% ‐0.50% 2.41% 4.30% 2.90% 0.70% 0.70% 17.6% 106

BC Hydro 2.10% 0.83% 9.28% 7.29% 7.77% 7.07% 1.44% 9.00% 6.00% 4.00% 3.50% 75.7% 132

SaskPower4.20% 0.00% 8.50% 4.50% 0.00% 0.00% 4.90% 5.50% 5.00% 5.00% 3.50% 49.2% 156

New Brunswick Power 5.90% 3.00% 3.00% 3.00% 0.00% 0.00% 2.00% 2.00% 1.60% 1.66% 1.77% 26.6% 162Nova Scotia Power 3.80% 0.00% 9.30% 0.00% 6.05% 8.70% 3.00% 3.00% 0.00% ‐1.00% 1.50% 39.4% 205

* This index is based on the Edison Electric Institute Survey and compares the average price per kWh for the various utilities. Manitoba Hydro's average price is $0.0648/kWh in Canadian dollars based on 12 months data ending December 2016.

Page 170: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

Residential Monthly Bill ComparisonAverage Retail Price of ElectricityIn 2018/19 – Residential Consumption 1,000 kWh/ month

22

$181$169

$167

$164

$163$132

$116

$114$108

$101

$72

$0 $20 $40 $60 $80 $100 $120 $140 $160 $180 $200

Toronto

Ottawa

Charlottetown

Halifax

Regina

Moncton

St. John's

Vancouver

Calgary

Winnipeg

Montreal

Monthly Bill Comparison in 2 years (2018/19)Residential Consumption: 1,000 kWh / month

Page 171: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

23

Domestic Rate Strategy Recent PUB Board Orders

On May 5, 2017, Manitoba Hydro filed its 2017/18 & 2018/19 General Rate Application with the PUB. In this filing, Manitoba Hydro is requesting approval of a 7.9% rate increase effective August 1, 2017 and a further 7.9% rate increase effective April 1, 2018.

On May 17, 2016, the PUB issued Order 68/16 approving a 3.36% electricity rate increase for all customer classes effective August 1, 2016; Manitoba Hydro had requested a 3.95% across-the-board rate increase.

Page 172: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

24

Domestic Rate Strategy Future Plans

MH will continue to request domestic rate increases in support of the Finance goal in the Corporate Strategic Plan to “maintain a strong financial structure.”

Page 173: Manitoba Hydro Corporate Update · Presentation to S & P October 27, 2015 Manitoba Hydro Corporate Update ... another effective April 1, 2016. 24 Domestic Rate Strategy Future Plans

25

Questions?