Manchester Proton Beam Therapy Centre - Home | Aurora · Concrete Design •CIRIA 660 Design •...
Transcript of Manchester Proton Beam Therapy Centre - Home | Aurora · Concrete Design •CIRIA 660 Design •...
Electrical Requirements
PBT Equipment Loads:
Cyclotron - xxxkVA
Each Gantry - xxxkVA
ESS and Beam Line Magnets – xxxkVA(Supplied from Power Supply Rooms)
Building HVAC systems – xxxkVA
Total Electical Load – xxxkVA
Load Characteristics
Power Factor Load Stability
Cooling Requirements
Main Process Cooling Loads:
Cyclotron - xxxkW
Energy Selection System – xxxkW
Each Gantry Section – xxxkW
Each Main Beam Line Section – xxkW
Operation of the furthest gantry – xxxkW
Cooling Requirements
Main Process Cooling Loads:
Operation of the furthest gantry – xxxkW
Control Cabinets – xxxkW
Total Process Cooling – xxxkW
Air Conditioning Loads:
Total Air Conditioning Load – xxxkW
TOTAL COOLING LOAD : 1400kW
4 Gantry PBT vs. 4 Bunker LINAC
Cooling Electrical Load
Energy Requirements
PBT LINAC
Footprint (m2)
Spatial Requirements
PBT LINAC
Volume (m3)
x10 x12 x4 x10
Design
Holistic and Sustainable Design:
Re-use of expelled heat from magnets
Turbo Core Chillers (Magnetic bearings)
Combined Heat and Power Unit (CHP)
MEP Service Routing - Challenges
Routing of services into radiation protected spaces:
- Planning restraints on building height – reduced maze
- 95% of services embedded within concrete - double bends and N+1 resilience to all
8kmembedded
manuf.
conduits
2kmembedded
MEP
conduits
1kmembedded
pipework
Structural Key Issues
• Vault Shielding Performance
• Concrete Design
• Pour Sequence
• Building Settlements
• Conduits & Co-ordination
Vault Shielding Performance
• Co-ordination with Monte Carlo Model• Geometry Alignment
• Embedded Ducts/Conduits
• Material Properties
• Key Material Issues• Minimum Dry Density
• Maximum crack widths
• Pour Joints
• Impact on Structural Design• 2,300 kg/m3 Minimum Dry Density
• 0.2mm maximum crack width
• Shield walls between 2m and 5m thick.
• Maze joints between pours
Concrete Design
• CIRIA 660 Design• Used for thick concrete sections
• Cracking-dominated reinforcement design
• Careful consideration of restraint conditions & construction sequence
• Getting the concrete mix right• Low water content
• Limestone aggregate
• High cement replacement
• Concrete mix options tested (Target Density)
• Full scale pre-construction pour test
• Tight specification on thermal conditions• Setting maximum concrete temperature
• Set maximum differential temperatures
• Provide ‘live’ logging of pour temperatures
Pour Sequence
• Detailed Review of Pour Sequence• Co-ordinated with Concrete Sub-Contractor
• Direct impact on design – internal restraint
• Informed programme, shutter designs and logistics
Building Settlements
• Tight differential settlement criteria• ~10x more onerous than ‘normal’ building
• Pre-contract pile test
• Pile stiffness data used in final design
• Rotary Bored Piles
Conduits & Co-ordination
• Approx 11km of conduits and services embedded in concrete –MEP plus specific treatment equipment cabling
• Over 500 individual conduits
• 2 to 4 bends and spacing rules apply
• All modelled and coordinated in a 3d BIM environment, including coordination with our reinforcement
• Detailed input to final MC model
Conduits & Co-ordination
• 3d Co-ordination of Reinforcement and Conduits/Services
• Individual pour by pour drawings issued showing all details, setting out and embedded items
• Full time Resident Engineer
• Key Vault Statistics• ~16,000 m3 concrete
• ~2,500 concrete wagons
• ~100 pours – up to 650m3 each
• ~2,000 tonnes reinforcement
• ~40,000 tonnes concrete