Managing Risks in the Project Pipeline Minimizing the Impacts of Highway Funding Uncertainties Larry...
-
Upload
veronica-black -
Category
Documents
-
view
213 -
download
0
Transcript of Managing Risks in the Project Pipeline Minimizing the Impacts of Highway Funding Uncertainties Larry...
Managing Risks in the Project Pipeline
Minimizing the Impacts of Highway Funding Uncertainties
Larry Redd, P.E.Tim McDowell, WYDOT, P.E.
Larry Redd LLC
Uncertainties Can Ruin Your Asset Management Plans
ProjectProgramming
ProjectDeliveries
STIP—”Project Pipeline”
201220162017 2015 2014 20132017+
Best Laid Plans• Optimized project selection• Intended performance benefits• Assumed revenue by year
Unplanned Outcomes• Actual Revenue?• Missed deliveries• Holding Costs• Obsolete projects• “Hurry-up” projects• Low performance
Pipeline Uncertainties• Scope growth and project cost• Labor and Materials price volatility• Environmental or ROW issues• Unplanned political priorities• Construction cost inflation• Uncertain or variable revenueLarry Redd LLC
Larry Redd, [email protected]
Costs of “Being Too Lean”-- -Loss of Stimulus Funds, Block Grants, Special Legislative Funds-”Hurry-up” design and devel. costs-Non-optimum advanced const.
Amount of Projects “On-the-Shelf” Ready to Go
Holding Costs –-“PE 10 yr Limit List”$Millions at risk, and $Billions in projects may not get done-Lost permit costs-ROW and EA costs-Development costs-Obsolete projects-Redesign costs
Costs
“Optimum”Range
Non-Optimum Project Pipeline Costs
Objectives
• Identify cost elements (holding and hurry-up costs) and uncertainty factors to reduce or trade off or mitigate.
• Identify controllable factors to optimize (examples) – – How to operate the pipeline (loading, project mix, draining, etc.)– Cost factors to reduce (holding, hurry up)– Reduce time delays in getting projects onto the shelf
• Bottom line – Determine how to deliver intended projects, with expected performance, on time; in the midst of uncertain and/or variable funding
• Not “Business as usual…” – Instead, using low impact solutions/methods to manage risks and uncertainties
Uncertainty Factors
• Scope growth• Political priorities• Material price volatility• Labor costs• Other construction cost escalation• Legal issues• Environmental or regulatory issues• Right-of-way issues• Funding issues
Simulation Cartoon
1R2R Project Loading Rate
1R2R Design Completion Rate
1R2R Paving Rate
1Rs and 2Rs in Design
1Rs and 2Rs “On-the-Shelf”
1R2Rs Paved
3R4R Project Loading Rate
3R4R Design Completion Rate
3R4R Paving Rate
3Rs and 4Rs in Design
3Rs and 4Rs “On-the-Shelf”
3R4Rs Paved
Higher Risk if delayed.
Lower Risk if delayed.
Available Funding – WYDOT Scenario
J an 01, 2012 J an 01, 2022150,000,000
200,000,000
250,000,000
300,000,000dollars/ yr
Available
Fundin
g
Sensitivity of Losses to Key Parameters
Parameter Initial Value Sensitivity Value Reduction in Losses
Design Time for 3R4Rs
5 yrs 3 yrs Up to 22% or more
Pipeline (Shelf) Draining Logic
Proportional based on intended Mix
“Keep the Critical Projects Moving”
Up to 16 % or more
Holding Cost factor (per year)
5% for 3R4Rs and 2% for 1R2Rs
2.5% for 3R4Rs and 1% for 1R2Rs
20 to 30%
Hurry Up Inefficiency
40% inefficiency 20% inefficiency 25% or more
Use of Projected Revenue
No Projections used
Projected two years out
Up to 30 % or much more
“Smoothness” of Funding
“Bumpy” or “Blocky” funding
Smoothed or flattened funding
Ideally this would eliminate losses
Observations and Conclusions
• Latest results verify that total Project Pipeline losses can be about 3% per year or more (off-nominal cost assumptions).– A 3 percent savings is representative based on the findings of the analysis. This would
amount to a total savings of $90 million,for example, for a budget of 3 billion dollars over a 10-year period.
• Multiple methods have been shown to be effective in cutting these losses:– Using (accurate) forward projections of available revenue, or reducing
design times in the pipeline (especially for 3R4R projects)– Reducing the values of the factors of Hurry Up and Holding Costs– The “Critical Project Method” of stabilizing the flow of major projects
has proven effective. Don’t delay the largest and more complex projects.
• Questions?????