Managing Accelerator Quality

Matthew Conlon13 April 2015

Page 2: Managing Accelerator Quality Matthew Conlon 13 April 2015.

2

Vision and Strategy

Accelerator Systems Project Quality (ACCSYS Q)

Vision’to manage, assure and confirm the quality Accelerator’s systems and components’

StrategyAccelerator shall fulfil its Vision, and the expectations and directions of ESS and ESS Quality Division, by developing and performing a focused-for-Accelerator application of the ESS Management System (ESS MS). This will include Work Package (WP) audits, Quality assessment, technical reviews and other cooperative activity with WPs and partners (collaborators, In- Kind Contributors and suppliers) to assure quality (QA) and to confirm compliance to quality (QC)

Page 3: Managing Accelerator Quality Matthew Conlon 13 April 2015.

3

Definitions

Quality (Q)

‘The degree to which a set of inherent characteristics fulfils requirement’ISO 9000

Quality Management (QM)

Coordinated activities to direct and control an organization with regard to QualityESS Quality Div.

Quality Assurance (QA)

Activities that attempts to improve and stabilize production (and associated processes) to avoid, or at least minimize, issues which led to the defect(s) in the first placeESS Quality Div.

Quality Control (QC)

Activities that focus on fulfilling requirements such as testing of products to uncover non-conformitiesESS Quality Div.

Page 4: Managing Accelerator Quality Matthew Conlon 13 April 2015.

4

Start Point for Managing Quality

• Construction Phase since early 2013. Design is in detailed stage.

• ESS Q Div is a small organisation, so ESS projects must manage Quality largely with their own resources

• within Accelerator, a QA/QC representative was not initially in the staff plan. It is now limited to single resource which is part-time until mid-2015.

• differences in Accelerator WP procurement strategies, scope, budget and capability / resources

• varied capabilities of IKC and suppliers

Page 5: Managing Accelerator Quality Matthew Conlon 13 April 2015.

5

Conclusions and Way Forward

• Focussed approach rather than holistic:– more QA/QC on Accelerator systems and components, – less QA/QC on organisation and processes

• QA/QC assessment then a graded approach for:– ACCSYS WPs– IKC and suppliers

• ‘Matrix’ available resources from:– ESS Q Div and other ESS projects– ACCSYS WPs– external collaborators– IKC and suppliers

Page 6: Managing Accelerator Quality Matthew Conlon 13 April 2015.

6

ESS Quality Div milestones (including to meet SSM expectations)

• Implementation of ESS MS phase 1 2015 Q2

• Quality requirements for procurement and IKC, 2015 Q2

• Supplier/in-kind QA assessment established 2015 Q2

• Internal Audits (of ESS Projects) established 2015 Q3

• readiness review for installation and SSM Inspection 2015 Q4

Page 7: Managing Accelerator Quality Matthew Conlon 13 April 2015.

7

ACCSYS Q planning, 2015

• increase ACCSYS Q resources to 1 x FTE during Q2 2015

• Develop ACCSYS Quality plan by end of Q2 2015

• in parallel with the above, perform or participate in Accelerator’s and partner’s activities for assuring and controlling Quality

Page 8: Managing Accelerator Quality Matthew Conlon 13 April 2015.

8

Outline of activities for Quality (QA/QC)

activity ACCSYS Q representation

Work Packages (WP) audits participates in annual WP audits

assessment of capabilities and needs – WPs, IKCs, Suppliers

With ESS Q Div, WPs and partners, plans, coordinates and conducts assessment to determine graded approach

internal requirements review observes and/or receives copies of reports

procurement and IKC agreement participates in review of technical SoWs, specifications / requirements

design and verification reviews for Accelerator systems and components

• assist WP planning for technical reviews including readiness and acceptance reviews

• participates in technical reviews etc.• observe / witness verification activities

including testing• observe / witness regulatory compliance

activities