Management of Mega Projects and Programs …HO20100329_101.PPT 2 Management of Mega Projects and...
Transcript of Management of Mega Projects and Programs …HO20100329_101.PPT 2 Management of Mega Projects and...
© 2009 Fluor Corporation
Management of Mega Projects and ProgramsCreating Value Through Lessons Learned
Instituto Mexicano del PetróleoXVI Foro de Avances de la Industria de Refinación
1 de Julio, 2010 José Carlos Herrero
HO20100329_101.PPT 2
Management of Mega Projects and ProgramsCreating Value Through Lessons Learned
Need to learn from the past
Reasons why owners invest
Adding value to owners investments
Root cause analysis on mega project failures
How to avoid mega project failures
Fluor University
HO20100329_101.PPT 3
Creating Value Through Lessons Learned
“Building the Lessons of the Past into the Projects of Today”
HO20100329_101.PPT 4
Recognize This Ship?
White Star’s The Olympic
HO20100329_101.PPT 5
The Olympic: Commissioned14th June 1911
The Titanic: Commissioned11th April 1912
HO20100329_101.PPT 6
Prelude to Disaster – The Olympic
21st Jun 1911– Upon commissioning crashed
into & almost sunk O.L. Halenbeck in Manhattan
20th Sep 1911– Crashed into the Naval Cruiser
the HMS Hawke in Southampton
24th Feb 1912 – Knocked-off one of its twenty-six
ton propellers on a well-known wreck in the Grand Banks
Captained by Edward J. Smith
Damage to the Olympic from the HMAS Hawkeimpact
Ref: ‘The Riddle of the Titanic’, Gardiner et. al. Orion, 1998
HO20100329_101.PPT 7
Captain Edward J. Smith
27th Jan 1889– Ran The Republic aground in New
York
1st Dec 1890– Ran The Coptic aground in Rio de
Janerio
4th Nov 1909– Ran The Adriatic aground outside New
York
History of running ships too fast through narrow passages and of not adequately training his officers
Captain Smith was commissioned to command the TitanicRef: ‘The Riddle of the Titanic’, Gardiner et. al. Orion, 1998
HO20100329_101.PPT 8
Tragic, Preventable Circumstances
Titanic - 14th April 1912– Sea dotted with hundreds of ice flows…no extra lookouts posted– Smith received up to 6 warnings of ice field from ships in area – No binoculars available in crow’s nest …early warning nearly impossible – Very hazy conditions…lookouts confused in what they saw ahead of them– Titanic sped toward ice field at 22.5 knots (10 knots recommended for conditions)
Ref: ‘The Riddle of the Titanic’, Gardiner et. al. Orion, 1998
Applying Tenets of Operation:1. Operate within design and environmental limits.2. Operate in a safe and controlled condition.3. Ensure safety devices are in place and functioning.4. Follow safe work practices and procedures.8. Address abnormal conditions.9. Follow written procedures for high-risk or unusual
situations.10. Involve the right people in decisions that affect
procedures and equipment.
HO20100329_101.PPT 9
Tragic, Preventable Circumstances
Motivations for speed– Desire to break transatlantic speed record – Encouraged by J. Bruce Ismay (White Star project sponsor),
on board for maiden voyage
Ref: ‘The Riddle of the Titanic’, Gardiner et. al. Orion, 1998
Applying Tenets of Operation:2. Operate in a safe and controlled condition.5. Meet or exceed customer’s expectations.
HO20100329_101.PPT 10
Tragic, Preventable Circumstances
Safety response capability– Lifeboat count reduced from 64 to 22 to enable more expansive promenades– Officers not trained in lifeboat use and were unsure of lifeboat capacity– No safety-response plan...‘Women and Children first’ was a reaction, not a
predetermined plan
Ref: ‘The Riddle of the Titanic’, Gardiner et. al. Orion, 1998
Applying Tenets of Operation:2. Operate in a safe and controlled condition.3. Ensure safety devices are in place and functioning.4. Follow safe work practices and procedures.7. Comply with applicable rules and regulations.9. Follow written procedures for high-risk or unusual
situations.10. Involve the right people in decisions that affect
procedures and equipment.
HO20100329_101.PPT 11
MIT Findings / Conclusions
0 5 10 15 20 25 30 35 40
Meet or exceed customer requirements
Comply with all rules and regulations
Maintain integrity of dedicated systems
Operate within design and environmental limits
Follow written procedures for high risk or unusual situations
Involve the right people in decisions
Ensure safety devices are in place and functioning
Address abnormal situations
Operate in a safe and controlled condition
Follow SWP and procedures
Number of Incidents
Tenets Not Followed
20% of the incidents involved “snap decisions” by individuals (i.e. a quick decision that violated tenets or was made without understanding or assessing the risk)
Tenets were not used as an active part of decision making by individuals or teams
HO20100329_101.PPT 12
0
5
10
15
20
25
30
35
40
45
50
Low Sense ofVulnerability
Risk Review LessThan Adequate
Normalization of Deviation
Demonstrate VisibleLeadership &
Commitment LessThan Adequate
Insufficient Auditing
OpenCommunication
Less Than Adequate
IndependentValidation/Diversity
of Opinion LessThan Adequate
Nu
mb
er
of
Inci
de
nts
Organizational Culture
Low Sense of Vulnerability:
Underlies many of the identified RCs Deemphasizes risk assessments &
auditing Allows for “snap decisions” Can result from ineffective processes for
learning from past incidents Results in high normalization of deviation
(i.e. complacency)
HO20100329_101.PPT 13
References
Sources:
• “Titanic Lessons for IT Projects”, MultiMedia Publications, Authored by Mark Kozak-Holland, HP Services, September 21, 2006, Presentation for PMI Mass Bay
• “Could disaster have been prevented?” Case study– Second set of lessons from Titanic, New publication authored by Mark Kozak-Holland, HP Services, May 31st, 2006, Presentation for PMI CTT
• Safety Presentation authored by J P Kenny
HO20100329_101.PPT 14
Management of Mega Projects and ProgramsCreating Value Through Lessons Learned
Need to learn from the past
Reasons why owners invest
Adding value to owners investments
Root cause analysis on mega project failures
How to avoid mega project failures
Fluor University
HO20100329_101.PPT 15
Reasons Why Owners Invest
Most of the time is to improve the Return on the Capital Employed (ROCE)
ROCE = Revenues - Opex / Capex
How a contractor can help an owner to add value to the equation
HO20100329_101.PPT 16
Management of Mega Projects and ProgramsCreating Value Through Lessons Learned
Need to learn from the past
Reasons why owners invest
Adding value to owner’s investments
Root cause analysis on mega project failures
How to avoid mega project failures
Fluor University
HO20100329_101.PPT 17
Project Management and Value Creation
Good Project, Good Definition
Poor Project Definition
Poor Project Execution
Good Project Execution
Phase 1Opportunity
Identified andAssessment
Phase 2Generate &
SelectAlternatives
(FEL 1)
Phase 3Develop
PreferredAlternative
(FEL 2 and 3)
Phase 4Execute
EPC
Phase 5Operate &Evaluate
Opportunity for value creation maximized in Phases 1, 2 and 3
AFE
HO20100329_101.PPT 18
Random SuccessGood Projects
Average Execution
Consistent SuccessGood ProjectsGood Execution
Success UnlikelyPoor ProjectsPoor Execution
Dec
isio
n Q
ualit
y
Execution Quality
Low HighMedium
Hig
hM
ediu
m
Random SuccessPoor ProjectsGood Execution
Corporate Vision For Program Management
HO20100329_101.PPT 19
Adding Value to Owners Investments
Optimal process plant configuration during the FEL 1
Excellence in Execution/ Baseline Centric (FEL 2,3 and EPC)
Applying Value Improving Practices (FEL1, 2, 3, EPC)– Standard 11 IPA VIP’s– Fluor 12 specific VIP’s
Reliable AFE (Cost and Schedule) (FEL 2, 3, EPC)
Applying Change Management (FEL 2 and 3 and EPC)
Right first time (Flawless) Start-up (planning from the beginning)
HO20100329_101.PPT 20
Management of Mega Projects and ProgramsCreating Value Through Lessons Learned
Need to learn from the past
Reasons why owners invest
Adding value to owners investments
Root cause analysis on mega project failures
How to avoid mega project failures
Fluor University
HO20100329_101.PPT 21
Root Cause Analysis on Mega Project Failures
Few Mega Projects meet Cost and Schedule Targets
3 independent sources of information– Megaprojects and Risk: An Anatomy of Ambition. Bent Flyberg, Nils Bruzelius
and Werner Rothengatter (2002). Cambridge University Press : “Cost over runs of 50% to 100% in real terms are common, and over runs above 100% are not uncommon”.
– Alborg University, Denmark study: “Cost underestimation and overruns have not decreased over the last 70 years. No learning seems to take place”.
– Two recent presentations by IPA:• 2006 38th ECC Conference: “56% of international mega projects experienced cost
and/or schedule overruns of more than 25%”.• 2009 Alberta experience: “Between 1998 and 2008 massive cost blowouts. The largest
projects took the biggest hits (48% of projects over $500 MM)
Cost underestimation and overruns can’t be explained only by estimating errors.
HO20100329_101.PPT 22
10 Top Reasons of Mega Project Failures
Inefficient project organization/decisions structure * Inadequate risk management *Unrealistic cost estimates and schedules* Poor Scope Definition Inadequate Execution PlanShortage of ResourcesDelays in Engineering, Procurement and ConstructionAbsence of a “No Change” culturePoorly developed goals & expectationsMisalignment between stakeholders
What to do?
HO20100329_101.PPT 23
Management of Mega Projects and ProgramsCreating Value Through Lessons Learned
Need to learn from the past
Reasons why owners invest
Adding value to owners investments
Root cause analysis on mega project failures
How to avoid mega project failures
Fluor University
HO20100329_101.PPT 24
How To Avoid Mega Project FailuresWhat Owners Can Do?
Use a Toll Gate Process and for World-class Capital stewardship: – Value Improving Practices– Best Practices
Appropriate Contracting Strategies– Use of Program Management Contractor (PMC) – Effective interface management– Analysis of contracting alternatives– Early Contractor pre-qualification, evaluation, selection and
continuity Critical Issues / Risks Identification
– Implement and enforce a rigorous Risk Management system– Early identification & management– On going risk assessment and mitigation plans– Ownership of action plans
Personnel development and training– Processes and Procedures
HO20100329_101.PPT 25
PMC Focus - Total Program View
EPC ContractorPMC/Owner
MaintenanceTraining
Contractors
Constructor
Engineer
Process/Planner
Phase 5Operate &Evaluate
Phase 4Execute
EPC
Phase 3Define Project(FEL 2 and 3)
Phase 2Generate and
Select Alternatives(FEL 1)
Phase 1Identify & Assess
Opportunity
Operational Support
Maintenance
Training
Start-Up
Construction
Procurement
Design / Engineering
Feasibility Studies
Concept Development
Basic Design
Business Planning
HO20100329_101.PPT 26
Program Manager’s Focus
PMC/Owner
Project 1
Project 2
Project 3
Project 4
PMC ’s Focus Must Extend Across Dependent Projects within the
Program
HO20100329_101.PPT 27
What is Program Management
The process of providing execution certainty to meet the strategic business objectives of an owner.
Requires a broader, more strategic focus than project management and a tighter integration across all elements of the execution process
It is not just the sum of all project management activities but also includes management of the risks, opportunities, and activities that occur “in the white space” between projects.
Opportunities of leverage across projects, benefits of standardization and management of systemic risks
HO20100329_101.PPT 28
Management of the White Spaces
HO20100329_101.PPT 29HO20100329_101.PPT 29
Program Manager’s Focus
IntegratedRefinery
program Strategy
EconomicDevelopment
Strategy
SocialDevelopment
Strategy
EnvironmentalSustainability
Strategy
IntegratedRefinery Program
BusinessDevelopment
Program
Social Development
Program
EnvironmentalSustainability
Program
Crude/VacuumDistillates
CokerU&O
Cogeneration
Capacity buildingIndustry creation
Infrastructure development
Staff trainingKnowledge
capture Craft training
Energy optimization
Waste minimization
Water Minimization
Common temp. facilitiesSite prep. contract
Standardization agreements
Infrastructure contracts
Independent Revenue Analysis
Safety training Knowledge database
Craft training contract
Construction materials recycling
Program Management
Level 0Strategy
Level 1Program
Level 2Project
Level 3Work Package
/ContractProgram Phases
(time)
HO20100329_101.PPT 30
How To Avoid Mega Project FailuresWhat Contractors Can Do?
Program Organization with clear Roles & Responsibilities focused on ROCE and meeting strategic objectives
Develop reliable Cost / Schedules– Work process and Systems– Historical data– Base Line Centric Execution
Professional Business Risk Management
Invest in Personal Development and Training
HO20100329_101.PPT 31
Management of Mega Projects and ProgramsCreating Value Through Lessons Learned
Need to learn from the past
Reasons why owners invest
Adding value to owners investments
Root cause analysis on mega project failures
How to avoid mega project failures
Fluor University
HO20100329_101.PPT 32
Fluor University
Permanent Project Execution Services organization serving Fluor’s 5 Business Groups:
– Energy & Chemicals– Power– Global Services (Operations & Maintenance)– Industrial & Infrastructure– Government
Global Excellence (Functional) Leaders are the Deans of the Virtual Fluor University:
– On line and Instructor based courses– Practices and Work Processes
Knowledge on Line – Knowledge communities, Forums and Knowledge objects
Training to owners
HO20100329_101.PPT 33
Questions
HO20100329_101.PPT 34
Lessons Learned
Focus on safety at all levels of the organization
Actively communicate safety expectations to employees
Strive for safe behavior, not catchy slogans– Act consistently with safety message– Do not sacrifice safety for other concerns
Train personnel in safe work practices and procedures for their specific positions
Learn from the past– Report incidents and near misses– Identify unsafe conditions and at-risk behaviors – Determine root causes and take corrective action
Coach employees displaying pattern of at-risk behavior