Management Measures Chapter 9 | Biological Impacts and
Transcript of Management Measures Chapter 9 | Biological Impacts and
m
Chapter 9 | Biological Impacts and Management Measures
Chapter 9 | Physical Impacts and Management Measures
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-2
Chapter 9 | Physical Impact Assessment
9 PHYSICAL IMPACT ASSESSMENT ............................................................................. 9-1
9.1 Project Footprint ...................................................................................................................................................... 9-3
9.1.1 Issues and Findings ................................................................................................................................... 9-3
9.1.2 Avoidance, Mitigation and Management Measures ...................................................................... 9-5
9.1.3 Residual Impact Assessment ................................................................................................................. 9-7
9.2 Mine Pit and Waste Rock Disposal...................................................................................................................... 9-9
9.2.1 Issues and Findings ................................................................................................................................... 9-9
9.2.2 Avoidance, Mitigation and Management Measures .................................................................... 9-11
9.2.3 Residual Impact Assessment ............................................................................................................... 9-14
9.3 Tailings Disposal ..................................................................................................................................................... 9-15
9.3.1 Issues and Findings ................................................................................................................................. 9-15
9.3.2 Avoidance, Mitigation and Management Measures .................................................................... 9-16
9.3.3 Residual Impact Assessment ............................................................................................................... 9-18
9.4 Hydrology ................................................................................................................................................................. 9-19
9.4.1 Issues and Findings ................................................................................................................................. 9-19
9.4.2 Avoidance, Mitigation and Management Measures .................................................................... 9-27
9.4.3 Residual Impact Assessment ............................................................................................................... 9-28
9.5 Hydrogeology ......................................................................................................................................................... 9-30
9.5.1 Issues and Findings ................................................................................................................................. 9-30
9.5.2 Avoidance, Mitigation and Management Measures .................................................................... 9-32
9.5.3 Residual Impact Assessment ............................................................................................................... 9-32
9.6 Surface and Ground Water Quality .................................................................................................................. 9-33
9.6.1 Issues and Findings ................................................................................................................................. 9-33
9.6.2 Avoidance, Mitigation and Management Measures .................................................................... 9-39
9.6.3 Residual Impact Assessment ............................................................................................................... 9-43
9.7 Soils ........................................................................................................................................................................ 9-46
9.7.1 Issues and Findings ................................................................................................................................. 9-46
9.7.2 Avoidance, Mitigation and Management Measures .................................................................... 9-48
9.7.3 Residual Impact Assessment ............................................................................................................... 9-50
9.8 Air Quality ................................................................................................................................................................. 9-51
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-3
9.8.1 Issues and Findings ................................................................................................................................. 9-51
9.8.2 Avoidance, Mitigation and Management Measures .................................................................... 9-57
9.8.3 Residual Impact Assessment ............................................................................................................... 9-60
9.9 Noise ........................................................................................................................................................................ 9-62
9.9.1 Issues and Findings ................................................................................................................................. 9-62
9.9.2 Avoidance, Mitigation and Management Measures .................................................................... 9-68
9.9.3 Residual Impact Assessment ............................................................................................................... 9-69
9.10 Vibration and Airblast ........................................................................................................................................... 9-71
9.10.1 Issues and Findings ................................................................................................................................. 9-71
9.10.2 Avoidance, Mitigation and Management Measures .................................................................... 9-74
9.10.3 Residual Impact Assessment ............................................................................................................... 9-75
9.11 Flyrock ........................................................................................................................................................................ 9-76
9.11.1 Issues and Findings ................................................................................................................................. 9-76
9.11.2 Avoidance, Mitigation and Management Measures .................................................................... 9-76
9.11.3 Residual Impact Assessment ............................................................................................................... 9-77
9.12 General Waste and Hazardous Materials ....................................................................................................... 9-78
9.12.1 Issues and Findings ................................................................................................................................. 9-78
9.12.2 Avoidance, Mitigation and Management Measures .................................................................... 9-82
9.12.3 Residual Impact Assessment ............................................................................................................... 9-85
9.13 Accidental Events and Natural Hazards ......................................................................................................... 9-86
9.13.1 Issues and Findings ................................................................................................................................. 9-86
9.13.2 Avoidance, Mitigation and Management Measures .................................................................... 9-90
9.13.3 Residual Impact Assessment ............................................................................................................... 9-93
9.14 Climate and Greenhouse Gases ........................................................................................................................ 9-93
9.14.1 Issues and Findings ................................................................................................................................. 9-93
9.14.2 Avoidance, Mitigation and Management Measures .................................................................... 9-98
9.14.3 Residual Impact Assessment ............................................................................................................... 9-99
9.15 Visual Amenity ..................................................................................................................................................... 9-101
9.15.1 Issues and Findings .............................................................................................................................. 9-101
9.15.2 Avoidance, Mitigation and Management Measures ................................................................. 9-109
9.15.3 Residual Impact Assessment ............................................................................................................ 9-110
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-1
9 PHYSICAL IMPACTS AND MANAGEMENT MEASURES
The development of the Mako Gold Project will lead to physical environmental impacts during construction,
operation and Project decommissioning, with some residual physical impacts continuing post-closure.
Management, mitigation and monitoring measures will be implemented to avoid, minimise or mitigate
impacts to the extent practicable. Diligent application of best practices for managing potential impacts is
expected to significantly decrease the potential for residual impacts. Detailed management plans for
potential impacts are provided in:
Technical appendices to this ESIA (Volume A);
Management plans including the Environmental and Social Management and Monitoring Plan
(Volume C) and the Rehabilitation and Conceptual Mine Closure Plan (Volume E); and
Select chapters of the ESIA.
The following chapter summarises potential physical impacts from Project pre-construction / construction,
operation and decommissioning / closure and summarises management measures that are intended to
minimise residual impacts. Where significant differences in the potential impacts are expected to occur
between the various Project phases, these have been highlighted. Associated potential impacts to
environmental and social receptors are provided in Chapters 10 and 11, respectively.
Where feasible, the Project has been designed to reduce physical environmental impacts and their associated
biological and social impacts. The primary components of the Project that have the greatest potential to
physically impact the environment include the Petowal Mine Pit, Waste Rock Dump (WRD), Tailings
Management Facility (TMF), Process Plant and ROM Pad, Power Station and the Mine Services Area (refer to
Chapter 4). These facilities are located and designed to minimise environmental and social risk while
providing for an economically viable mining operation. Lesser physical impacts may be associated with the
Water Storage Dam (WSD), accommodation camps, quarries and access roads. Handover of some facilities
(pending the results of stakeholder consultation) to government or communities may derive beneficial
outcomes from physically impacted areas (e.g. road infrastructure and accommodation camps).
The following sections highlight potential physical impacts during construction, operation and post-closure
and provide management strategies established to avoid, minimise or mitigate potential impacts.
Impacts Categories
Project associated impacts are herein defined according to the following categories (refer to Figure 9-1):
Permanent impact: Project development permanently alters the physical landscape / feature to the
extent that it cannot be rehabilitated to provide self-sustaining native habitat;
Permanent impact – asset transfer: Project development permanently alters the physical landscape /
feature but the Project component will provide lasting benefit to the government or local communities
via asset transfer;
Temporary impact – rehabilitated to a natural ecosystem: Project development alters the physical
landscape / feature, however the impacted area will be rehabilitated and revegetated to provide self-
sustaining natural habitat; and
Temporary impact – access restriction: Project development does not physically impact the
landscape / feature, however community access to the area will be restricted or prohibited during
Project construction, operation and decommissioning (social impact) for safety considerations.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-2
Figure 9-1 Project Footprint and impact category
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-3
9.1 Project Footprint
9.1.1 Issues and Findings
This section considers potential impacts (and management / mitigation) to the physical landscape associated
with Project development. Associated impacts (e.g. to hydrology, water quality, and air quality etc. for each
Project component) are discussed in Sections 9.2 to 9.15.
The Project Footprint will comprise approximately 248.3 ha of land surface that will be subjected to
permanent or temporary physical impacts (refer to Figure 9-1). Approximately 74.3 ha will be permanently
impacted via development of the Project Footprint. Ownership of the facilities constructed on approximately
38.9 ha of this area will be transferred to government or local communities, providing a long-term benefit.
Approximately 174.0 ha of surface area will be temporarily impacted but will be rehabilitated and
revegetated to provide sustainable native ecosystems (refer to the Rehabilitation and Conceptual Mine Closure Plan, Volume E).
The PDA will be prescribed to prohibit or restrict access to buffer areas around Project facilities (refer to Figure
9-2) during the life of the mine to minimise potential health and safety risks. Enforcement of the PDAs will
increase the area of temporary impact via access restriction for residents of the region that currently utilise
this land. Temporary access restriction will not enhance the area of physical impacts, but may increase the
area of temporary socio-economic impacts and are therefore not evaluated in this chapter.
Development of the Project will impact 247.1 ha (surface area) of landform morphology and soil / subsoil
during construction and operation. Details for each Project facility are provided in the following section.
The Project has been designed to minimise the physical impacts to the natural landscape by minimising the
Project Footprint to the extent practicable. The WRD, TMF, Petowal Pit, Mine Services Area, ROM Pad and
Process Plant, and a significant portion of the road infrastructure will be almost exclusively located within one
relatively small catchment (Badalla Valley).
Pre-Construction / Construction
Site Preparation - The majority of physical impacts to landforms in the PDA will occur during Project
construction. The first phase of facilities’ construction will include vegetation clearing and grubbing;
preparatory earthworks; and topsoil removal (for specific facilities). Table 9-1 summarises the general impacts
of site preparation, which are discussed in detail in applicable Sections of this chapter.
Table 9-1 Summary of potential physical impacts related to site preparation during Construction
Impacts Assessment Reference Section
Erosion and
Sedimentation
Clearing and grubbing of vegetation, major earthworks, soil stockpiling, soil
compaction will increase the likelihood of soil erosion from water and wind with
subsequent sediment transport
Section 9.6
Section 9.8
Soil Compaction Heavy earthmoving equipment and pad / road preparation will compact surface
or subsoils (pending topsoil removal)
Section 9.7
Water Quality Diesel powered vehicles / equipment provide potential sources of
hydrocarbons to surface and groundwater and accommodation camps a
potential source of nutrients and pathogens
Section 9.6
Hydrology Surface water from seasonal drainages will be diverted around disturbance
areas, in some cases to sumps and / or permanent drainage channels
Section 9.5
Air Quality Particulate matter (dust) will be generated from clearing and grubbing, topsoil
stripping and stockpiling, vehicle transit on unsealed road networks, etc.
Exhaust emissions (e.g. CO, NOx, SO2, VOCs) will be generated from diesel
powered vehicles / equipment and Power Station
Section 9.8
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-4
Impacts Assessment Reference Section
Noise Vehicles / equipment will be a source of noise emissions during site
preparation. Blasting at quarries / road construction areas will be a short term
source of high intensity noise
Section 9.9
Vibration Blasting at the pit / quarries / road construction areas will provide airblast and
ground vibration and vehicle / equipment utilisation a source of vibration during
site preparation.
Section 9.10
Primary physical impacts to the Project Footprint during construction comprise the permanent or temporary
conversion of landforms from natural landscapes to Project components. Direct impacts, per Project
component include:
Petowal Mine Pit: the majority of pit development will occur during operation. However, site
preparation activities initiated early in the Construction Phase will include topsoil stripping and
transport to topsoil stockpiles (for subsequent revegetation efforts) and subsoil stripping (if of
adequate engineering grade) to provide material for various Project components (e.g. TMF and WSD
embankment material, road fill, etc.). The 35.4 ha Mine Pit surface will be stripped of topsoil to a depth
of approximately 0.5m (180,200 m3 topsoil). It is anticipated that subsoil will also be excavated and
transported for construction fill.
Waste Rock Dump: The majority of WRD development will occur during operation. However, site
preparation activities and topsoil reclamation will occur during construction. Following vegetation
clearing and grubbing, topsoil will be stripped from the 77.3 ha WRD footprint to a depth of 0.5m
(404,600 m3 topsoil), permanently impacting the landform and temporarily impacting the site’s ability
to support native vegetation.
Tailings Management Facility: The TMF dam wall will be constructed to height of 15 m during the
Construction Phase and will be incrementally increased to height of 26 m during mine operation.
Construction of the dam will impact 2.45 ha for the final TMF embankment and will require a
significant volume of suitable engineering material (clay rich material).
This material may be sourced from the Mine Pit overburden or WRD footprint, however it may require
excavation from local borrow areas which may expand the area of physical impact for TMF and WSD
construction (refer to below).
ROM Pad, Process Plant, and Power Station: Construction of these facilities will require clearing and
grubbing; stripping of topsoil for post-closure rehabilitation (if applicable); and import of foundation
material (e.g. sand and gravel), temporarily converting 15.9 ha (9.3 for the Process Plant and Power
Station and 6.6 ha for the ROM Pad) of vegetated area to a built environment.
Water Storage Dam (WSD): Construction of the WSD will permanently impact 14.9 ha of vegetated
area in the Wayako catchment, via construction of the dam, the permanent water holding facility, the
pump station adjacent to the Gambia River, and pipelines between the facilities.
WSD dam construction will require import of suitable engineering material (clay rich material, sand,
gravel and rip-rap) that will be sourced from local borrows (refer to below).
Main Access Road: The main access road will be constructed from highway RN7 to the Mine Services
Area in Badalla Valley. Secondary roads will be constructed that branch from this road to access the
WSD from the north, the Mine Pit, the WRD, and the TMF. Construction of this main access road
network will require clearing and grubbing, import of sub-base and base material and compaction of
the topsoil. Approximately 30.9 ha of vegetated area will be permanently converted to the road
facility.
Additional Construction Phase Road Infrastructure: The existing road running parallel to the
Gambia River between Mako and Linguekoto will be upgraded to support vehicle transport from
workforce accommodation in Mako and the Exploration camp and construction sites during early
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-5
Construction Phase works (prior to completion of the Main Access Road). Approximately 5.7 km of
existing road will be upgraded and widened. The area of impact to native vegetation depends on the
extent of proposed road-widening for the road facilities.
Mine Services and ancillary facilities: Construction of the Mine Services Area, Explosives Magazine,
and vehicle laydown facilities will temporary convert surface land to Project facilities. Construction
activities, including clearing and grubbing, levelling, compaction of surface soils, development of
drainage, etc. will temporarily impact approximately 2.5 ha of vegetated area, predominantly in the
Badalla catchment.
Workforce accommodation: Construction of the primary workforce accommodation areas will require
conversion of approximately 3.6 ha of vegetated area to a permanent facility.
Quarries: Earth-fill borrow material will be required for concrete batching (for facilities construction),
WSD embankment, TMF embankment, and road construction / upgrade activities. Much of the sand is
expected to be hauled to site from a quarry toward Dakar. Additional borrowing activities will likely
occur on-site, potentially impacting some land at quarry sites for material that cannot be sourced from
the Mine Pit overburden. However, existing quarries (refer to Figure 4-1) within the Project Concession
Area have been previously disturbed (and not rehabilitated), and are expected to be utilised for Project
borrow requirements, minimising the potential for any additional significant impacts. Impact area
determination for additional quarry areas requires further investigation.
Operation
Potential direct impacts include:
Petowal Mine Pit: Development of the Mine Pit will permanently impact 35.0 ha of surface land. A
portion of the ridge encompassing the boundary of the Badalla and Kelendourou catchments will
progressively be converted to a pit throughout operation. Approximately 73.6 Mt of material will be
excavated and transported to the ROM Pad / Process Plant, ore stockpile, or WRD during development
of the pit. The Petowal Mine Pit will be excavated to a final depth of approximately 100 metres above
sea level (masl), with the pit rim varying between approximately 260 - 355 masl.
Waste Rock Dump: Approximately 62.4 Mt of waste material will be moved from the Mine Pit to the
WRD, permanently altering the landform (77.3 ha footprint). The morphology of a significant portion of
the Badalla Valley will progressively be transformed to a higher elevation landform throughout Project
operation.
Ore stockpile: Excavated ore in excess of that which can be immediately processed will be stored at
the ROM Pad stockpile or Ore Stockpile (6.3 ha) during operation. Construction of the stockpiling areas
will require clearing and grubbing, stripping of topsoil, and construction of cut-off drains, temporarily
altering the landform.
Tailings Management Facility: Approximately 54.9 ha in the lower reach of the Badalla Creek Valley
will be temporarily impacted, with conversion of the vegetated area to a subaerial tailings holding
facility during operation.
Decommissioning / Closure
The area of physical impact will be reduced during decommissioning via rehabilitation of temporarily
impacted land surfaces to meet closure criteria (refer to below). No additional physical impacts to the Project
Footprint are anticipated during this phase of the Project.
9.1.2 Avoidance, Mitigation and Management Measures
Avoidance
The Project has been designed to avoid the physical impacts to the natural landscape by reducing the Project
Footprint to the extent practicable. Most notably, the WRD, TMF, Petowal Pit, Mine Services Area, ROM Pad and
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-6
Process Plant and a significant portion of the road infrastructure will be almost exclusively located within one
relatively small catchment (Badalla Valley).
Minimisation
Project facilities have been designed for geotechnical stability, with size and substrate considerations
including probable peak storm events and potential natural disasters, minimising the potential area affected
by and consequences of significant landslips or dam failure (refer to Section 9.11) and associated impacts to
water quality (refer to Section 9.6).
During construction, the majority of direct impacts will be associated with land clearing / topsoil removal
activities and conversion of native landforms to Project components.
Management and mitigation measures to minimise potential direct impacts to land areas during construction
include:
Minimising the size of the Project Footprint, where feasible; and
Surveying, delineating and demarcating the maximum extent (area) of earthworks for each Project
component and enforcing prohibition of vehicular / equipment access outside of the designated
Project Footprint.
Long-term physical impacts will be minimised through activities outlined in the Rehabilitation and Conceptual Mine Closure Plan (Volume E) that will progressively reduce the size of the Project footprint via
specific rehabilitation and revegetation activities (Refer to the section below).
Rehabilitation / Decommissioning / Closure
Landforms will be progressively rehabilitated throughout construction or immediately following
construction. This will apply to areas that are not required during operation, including buffer areas required
for construction equipment (e.g. road embankments, access for construction equipment for facilities
including the Mine Services Area, workforce accommodation areas, Process Plant and ROM Pad, etc.).
During Project the Operation Phase, the Mine Pit, WRD, and TMF will be progressively expanded, with
development converting additional area of natural landform to Project facilities throughout the life of the
mine. Some features of these components can be progressively rehabilitated and revegetated throughout
operation (refer to the Rehabilitation and Conceptual Mine Closure Plan, Volume E).
Progressive rehabilitation activities are expected to include:
The WRD, constructed in lifts from the bottom up, may be progressively rehabilitated (graded to
contour, geotextile and topsoil applied, and revegetated) following completion of each lift; and
Buffer areas adjacent Project components that were required for equipment access during
construction may be progressively rehabilitated throughout operation to reduce the size of the Project
Footprint.
Development of Project components during construction and operation will disturb landforms according to
impact definitions provided above (Permanent, Permanent – Asset Transfer, Temporary – Rehabilitated to a
Natural Ecosystem and Temporary – Access Restricted) (refer to Figure 9-1). Project decommissioning /
closure activities will progressively reduce the size of the Project Footprint for temporarily disturbed areas,
minimising long-term physical impacts via specific rehabilitation and revegetation activities. Detailed
strategies are provided in Volume E, Rehabilitation and Conceptual Mine Closure Plan. Table 9-2
summarises the anticipated actions that will be undertaken during decommissioning and closure to reduce
the post-closure Project Footprint. Additional measures to manage and mitigate for additional physical
impacts (e.g. air quality, water quality, noise, vibration) are detailed in subsequent sections.
Table 9-2 Summary of Decommissioning activities per Project component
Project
Component
Impact Category Decommissioning / Closure Strategies
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-7
Project
Component
Impact Category Decommissioning / Closure Strategies
Mine Pit Permanent Rehabilitation and revegetation of Pit margins and temporary equipment
access roads.
WRD Temporary –
Rehabilitated to
Natural Ecosystem
The WRD will be graded to contours that align with adjacent topography.
Erosion matting / geotextile and topsoil will be applied and the WRD surface
revegetated with native species of local provenance to create a Tree
savannah or Shrub savannah and grassland vegetative community.
Ore Stockpile Temporary –
Rehabilitated to
Natural Ecosystem
The footprint of the Ore Stockpile will be rehabilitated and revegetated with
native species of local provenance to create Tree savannah or Shrub
savannah and grassland vegetative community.
TMF Temporary –
Rehabilitated to
Natural Ecosystem
The majority of the TMF (other than rock-lined drainage channels) will be
rehabilitated and revegetated to create a Shrub savannah vegetative
community.
A base-layer (subsoil) will be placed on top of tailings and topsoil (to 150mm
depth) applied above the base-layer.
Rock-lined drainage channels will remain in place, with grasses /
herbaceous plant species expected to eventually establish some of the
channel area. Native trees will be planted along drainage channels /
Badalla Creek.
Process Plant
and ROM Pad Temporary –
Rehabilitated to
Natural Ecosystem
The Process Plant and ROM Pad will be dismantled. The surface soil will
be ripped to approximately 1 m and the area revegetated to re-create the
grassland vegetative community.
Power Station Temporary –
Rehabilitated to
Natural Ecosystem
The Power Station will be dismantled. The surface soil will be ripped to
approximately 1 m and the area revegetated to re-create the Tree savannah
or grassland vegetative community.
WSD Temporary –
Rehabilitated to
Natural Ecosystem
The embankment will be breached and removed, the morphology of the
ephemeral stream rehabilitated, and the area revegetated to re-create a
Tree savannah or Wooded savannah vegetative community.
Main Access
Road Permanent – Asset
Transfer It is anticipated that the Main Access Road, remaining Road Infrastructure,
and workforce accommodation facilities will be transferred to the local
government or communities (pending stakeholder consultation). Road
infrastructure in the PDA will be rehabilitated
Road
Infrastructure Permanent – Asset
Transfer
Workforce
Accommodation Permanent – Asset
Transfer
PDA (no
physical
impacts)
Temporary – Access
Restricted
The PDA will not be enforced following Project closure. Former agricultural
areas, livestock grazing areas, artisanal mining areas, etc. will be returned
to previous landholders / land users without Project restriction.
9.1.3 Residual Impact Assessment
The majority of the impacts associated with the disturbance of the Project Footprint, will occur during the
Pre-Construction / Construction Phase. In total, development of the Project will impact 248.3 ha (surface area)
of landform morphology and soil / subsoil during construction and operation.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-8
No additional land disturbance is expected outside the Project Footprint area during the Operation Phase.
Progressive rehabilitation and revegetation will restore some temporarily disturbed areas back to a natural
ecosystem during this phase.
While the majority of the Project Footprint will be rehabilitated and revegetated at closure, portions of the
Project Footprint will not be converted back to a natural ecosystem, including facilities / assets that will be
formally transferred to government or community ownership. Table 9-3 identifies the area of permanent
(residual) impact.
Table 9-3 Residual physical impact areas Post-Closure
Project Component Residual Physical Impact Area Post-Closure
Mine Pit The 35.40 ha (surface area) Mine Pit void will be a permanent feature in the landscape
Main Access Road The 25.6 ha Main Access Road will be transferred to government ownership, providing lasting
benefit to the region
Road Infrastructure The majority of road infrastructure, including existing roads that were widened during
construction and those constructed for Project operation, will remain following Project closure,
providing lasting benefit to the region, albeit permanent physical impact. It is anticipated that
6.5 ha of the 32.04 ha road infrastructure network will be rehabilitated to provide a natural
ecosystem.
Workforce
Accommodation It is anticipated that the ownership of the 3.58 ha workforce accommodation camp and
3.24 ha exploration camp will transferred to government or local villages
The key expected residual impacts related to the Project Footprint under normal operating conditions, and
their overall significance for each Project phase, are summarised in Table 9-4. Monitoring will be required over
the mine life to confirm the residual impact predictions, and allow management measures to be adapted
accordingly.
Table 9-4 Summary of key expected pre-mitigation impacts, mitigation measures and residual impacts for the
Project Footprint for each Project phase
Receptor / Value
Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and Overall Impact Significance
Pre-Construction / Construction
Project Footprint
MODERATE
Minimising the size of the Project Footprint, where feasible
Surveying, delineating and demarcating the maximum extent (area) of earthworks for each Project component
Other management and monitoring measures for water quality, hydrology, dust, noise etc.
MODERATE
Land clearance, topsoil removal and earthworks within Project Footprint.
Total area of Project Footprint is 248.3 ha (surface area)
Operation
Project Footprint
MODERATE
As per Pre-Construction / Construction Phase
Restoration activities conducted in accordance with Rehabilitation and Conceptual Mine Closure Plan
Routine checks for compliance
MINOR
Some areas will continue to be cleared during operation within the PDA (e.g. within the WRD area)
Progressive rehabilitation and revegetation will restore some temporarily disturbed areas
Decommissioning / Closure
Project MODERATE Restoration activities conducted in MINOR
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-9
Receptor / Value
Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and Overall Impact Significance
Pre-Construction / Construction
Footprint accordance with Rehabilitation and Conceptual Mine Closure Plan
Routine checks for compliance
Portions of the Project Footprint will not be converted back to a natural ecosystem (e.g. pit)
9.2 Mine Pit and Waste Rock Disposal
9.2.1 Issues and Findings
Pre-Construction / Construction
The development of the Mine Pit and WRD will occur during the Operation Phase, therefore the majority of
potential impacts are associated with operation and decommissioning / post-closure. However, overburden
from the pit may be used for TMF and WSD embankment construction, if the material is found to have
suitable engineering quality. The pit and WRD will also be stripped of topsoil during construction to provide
material for Project rehabilitation during Project decommissioning (and progressively throughout operation).
Potential impacts from land clearing activities and topsoil stripping / transport to stockpiles may include:
Erosion and sedimentation (refer to Section 9.6);
Hydrocarbon spillage (refer to Section 9.6);
Soil compaction (refer to Section 9.7);
Particulate matter (dust) and exhaust emissions (refer to Section 9.8);
Noise (refer to Section 9.9);
Vibration (refer to Section 9.10); and
Hydrology (refer to Section 9.4): Surface water from seasonal streams will be diverted around the Mine
Pit and WRD footprints during site preparations. Impacts are not expected to be significant as surface
water will remain within the Badalla catchment, discharging to Badalla Creek (during construction)
prior to its confluence with the Gambia River.
Operation / Post-Closure
Development of the Mine Pit and WRD may lead to geotechnical and / or geochemical instability, potentially
affecting the landforms and receiving waters.
Geochemistry
Exposure of sulfidic materials to atmospheric oxygen can result in the generation and release of salinity,
dissolved metals and/or acid. Understanding the nature and distribution of reactive minerals within mine
materials is important for identifying potential water quality issues during operation and post closure.
Assessment and classification of mine materials on the basis of geochemical stability allows specific
management strategies to be developed for materials with different geochemical profiles in order to ensure
safe handling and storage in the long term.
MEC engaged Earth Systems and SRK to conduct a geochemical assessment of geological materials from the
Mako Gold Project. Geochemical classification was performed for samples collected from all geological
materials to be handled or disturbed by the mining operation (e.g. Mine Pit wallrock material, Waste Rock
Material, and Ore / Tailings material). Comprehensive results of the geochemical assessment undertaken and
the derivation of the geochemical classification scheme are provided in the Geochemical Assessment and
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-10
Management Strategies for the Mako Project, Senegal (Earth Systems, 2015). In summary, the geochemical risk
associated with waste rock, ore and pit wallrock was found to be low to very low (refer below).
Additional potential impacts to surface or groundwater quality associated with Mine Pit and WRD
development are discussed in Section 9.6 (Surface and Groundwater Quality).
WRD
Progressive disposal of waste rock on the WRD throughout operation will provide a source of material that
may be susceptible to geotechnical and / or geochemical instability. The potential issues include:
Erosion and sediment transport during high intensity rain events (refer to Section 9.6);
Landslips, providing a potential source of sediments to receiving waters (refer to Section 9.13); and
Saline and / or Metalliferous drainage in surface water runoff or seepage to groundwater.
Geochemical testwork of the waste rock samples determined that waste rock leachate pH is expected to be
near-neutral to slightly alkaline, with low levels of sulfate salinity and very low dissolved metal concentrations.
Other potential water quality issues associated with the waste rock material (e.g. nutrients) are discussed in
Section 9.6.
The siting of the WRD within the Badalla Valley, upstream of the TMF, will allow for the capture and retention
of leachate and sediments from the WRD during operation, with the water to be recycled on-site through the
Process Plant.
The stability of the proposed WRD has been assessed under static and seismic loading conditions using limit
equilibrium methods. ‘SLOPE/W’ has been used for the analysis using the Morgenstern-Price method of limit
equilibrium method of analysis by Knight Piesold (Knight Piesold, 2015g). The modelling results indicate that
the WRD will possess adequate stability for the modelled scenarios and conditions. However, the results
identify that WRD stability is sensitive to the level of the phreatic surface. Mitigation measures are therefore
required, as described in Section 9.2.2.
Mine Pit Wallrock
Geochemistry of the Mine Pit wallrock is expected to be similar to that of the waste rock, with a small
proportion of the Pit wallrock expected to be similar to the ore samples. Leachate from the Mine Pit wallrock
is expected to be near-neutral to slightly alkaline, with low levels of sulfate salinity and very low dissolved
metal concentrations. Other potential water quality issues associated with the Pit wallrock material (e.g.
nutrients) are discussed in Section 9.6.
Water from dewatering from the Mine Pit during operation will be pumped to the Process Plant to
supplement water Project water supply.
Ore Stockpile
As for the WRD, progressive stockpiling of ore throughout operation will provide a source of material that
may be susceptible to geotechnical and / or geochemical instability. The potential impacts include:
Erosion and sediment transport during high intensity rain events (refer to Section 9.6);
Landslips, providing a potential source of contaminants to receiving waters (refer to Section 9.13); and
Saline and / or Metalliferous drainage in surface water runoff or seepage to groundwater.
Testwork indicates that the AMD risk associated with the ore material is generally low. Approximately 87% of
the ore / tailings samples analysed were classified as non-acid forming (NAF).
All of the basalt lithology unit ore / tailings samples were classified as NAF; and
Two out of 16 samples were classified as potentially acid forming (PAF).
The PAF sample from the felsic lithology unit was classified as having a moderate-high potential for acid
generation and represents approximately 13% of the Felsic ore / tailings samples analysed. The other sample
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-11
was a composite sample of weathered ore material and was classified as having a low potential for acid
generation. The sulfide oxidation rate for the stockpiled ore material is expected to be similar to the waste
rock material, given the expected similar particle size distribution of the materials in the WRD and ore
stockpile. This sulfide oxidation rate is expected to translate to very low sulfate salinity generation rates. Ore
stockpile leachate pH is expected to be near-neutral to slightly alkaline, with low levels of sulfate salinity and
very low dissolved metal concentrations.
The siting of the ore stockpile within the Badalla Valley, upstream of the TMF, will allow for the capture and
retention of leachate and sediments from the ore stockpile during operation, with the water to be recycled
on-site through the Process Plant.
9.2.2 Avoidance, Mitigation and Management Measures
Avoidance
MEC will implement specific measures to reduce potential impacts associated with land clearance / site
preparation and topsoil removal activities (e.g. erosion and sedimentation, hydrocarbons spillage, soil
compaction, air quality impacts and altered hydrology) during construction.
Management and mitigation measures to avoid potential impacts are provided in Section 9.4 (Hydrology),
Section 9.6 (Surface and Groundwater Quality), Section 9.7 (Soils) and Section 9.8 (Air Quality).
Geochemistry
On-going monitoring of waste rock and ore geochemistry will allow for placement of identified reactive
materials within sufficient neutralising or containment materials to avoid development of AMD/NMD issues.
Water Quality
Strategic water quality management issues generated by the ore stockpile and WRD will be avoided by the
‘zero operational discharge’ mine design. The Mine Pit dewatering stream will also be diverted for use as
mine process water. Some minor volumes of mine water may not be collected as seepage from the TMF, this
will be monitored and avoided or minimised through treatment if required.
Ore Stockpile
All ore from the Ore Stockpile (and ROM ore stockpile) will be processed prior to Project decommissioning.
Minimisation
Geotechnical stability of Mine Pit
The engineered pit design incorporates design elements to minimise the risk of block, wedge or planar
sliding within the Mine Pit. Geotechnical analyses by Cube (2014) and SRK (2014c), including: assessment of
geotechnical characteristics of the Petowal deposit (rock mass, structures, and hydrogeology); and stability
assessment (limit equilibrium analysis and kinematic analysis) were used to generate slope design
recommendations.
Inter-ramp angles in fresh rock units will be 56º (20 m bench height, 8 m berm width, 75º bench face
angle);
Overall slope angles will vary between 53º and 55º on the hanging wall depending on the number and
width of ramp off-sets on each slope;
Overall slope angles will vary between 44º and 48º on the footwall slopes depending on the number
and width of ramp off-sets on each slope; and
Overall slope angles include flatter oxide zone slopes for weathered material (~10 m bench height, 10
m berm width, 75º bench face angle).
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-12
Water Quality in Mine Pit
Rainwater and groundwater will be diverted to a pit sump. Pit sump water will be regularly monitored for
water quality.
Mine Pit sump water will be pumped to the Process Plant to supplement process water requirements. Pit
water will not be discharged to the environment during operation.
Waste Rock Disposal
The geochemical risk associate with the waste rock material is very low. The primary mitigation strategy for
potential impacts from the WRD is locating it in the Badalla Valley, upstream of the TMF. The TMF will be
utilised during operation as a sediment retention dam to capture drainage from the WRD and allow for the
retention and re-use of this water on-site during operation. Surface water will not be discharged to receiving
waters during operation.
Additional WRD design and / or management strategies that are likely to be effective in further reducing the
potential low level water quality impacts related to the geotechnical / geochemical stability of the waste rock
include:
Routine monitoring of surface water and groundwater quality downstream of the WRD during the
Operation Phase to identify any potential water quality impacts associated with the WRD; and
If the geochemical risk of the waste rock material is found to increase during operation, a Geochemistry
Management Plan should be developed for the WRD.
Surface water drainage from the Badalla catchment will be diverted around the WRD to minimise erosion of
the facility, where possible.
To reduce WRD instability risks, drainage measures will be provided to direct surface water away from the
WRD, to reduce water infiltration and to reduce the level of the phreatic surface that develops. The WRD be
constructed from the bottom up so that the toe support is provided to the sections of WRD located on
steeper and higher ground. An additional recommendation is that, during the initial mining phase a further
stability and deformation investigation analysis is undertaken to refine the WRD stability analysis (Knight
Piesold, 2015j).
Ore Stockpile
During operation, excavated ore in excess of that which will be processed in the short-term will be
temporarily stockpiled (refer to Figure 9-1).
The ore stockpile will be located adjacent the WRD, within the Badalla Valley. As per the WRD, surface
water draining the Badalla catchment will be diverted around the stockpile, where possible. Drainage
from the ore stockpile will report to the TMF for re-use of this water on-site during operation. Surface
water will not be discharged to receiving waters during operation; and
Erosion and sediment control facilities will be constructed to minimise losses of stockpiled ore and
potential transport to receiving waters. Surface water will be diverted to the TMF for storage, with a
portion of the water pumped to the Process Plant for use as process water.
The geochemistry of the ore and the chemistry of drainage from the stockpile will be monitored throughout
operation to confirm whether the potential risk associated with the material remains low.
Mine Pit
The closure water balance for the pit indicates the formation of a pit lake that overflows seasonally for two
months approximately 20 years after cessation of dewatering in 2045. In the first year the pit lake will be
elevated in some water quality parameters, but this will quickly be diluted with additional rainfall and
groundwater inflow. By the point of discharge occurring pH is predicted to be neutral, salinity (TDS) will likely
be approaching 500 mg/L, most metals (including Cu, Zn, Mn Sb) will be under ambient guideline levels, while
As and Pb may be slightly elevated. Management and monitoring measures to include:
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-13
If required, establish a passive anaerobic wetland system to lower sulfate salinity and dissolved metal
concentrations in the pit lake via sulfate reducing bacteria.
Design the pit lake to include management strategies that will minimise hydrogen sulfide (H2S) gas
formation.
Routine monitoring of:
» Static geochemistry of pit wallrock samples from active mining benches during operation to
confirm that the potential geochemical risk associated with the pit wallrock material remains low. If
a change in the geochemical risk classification of the wallrock is observed, a geochemistry
management plan should be prepared; and
» Water quality in the Mine Pit sumps. Monitoring of water quality during operation will inform the
potential requirement and method for water treatment, if required.
Monitoring of pit inflow water quality during operation will inform whether water treatment will be
required post-closure.
Rehabilitation / Decommissioning / Closure
Mine Pit –Pit Lake Development
When mining is complete, Mine Pit dewatering will be ceased and pit inflow will contribute to the formation
of a Mine Pit lake, which may overflow within 20 years of the end of mining. Modelling shows the potential
for slightly elevated salinity which will be treated with TMF seepage if required, and if pit lake overflow occurs.
Waste Rock Disposal
To further reduce the potential low level water quality impacts related to the geotechnical / geochemical
stability, progressive rehabilitation and revegetation of the WRD batters during operation to assist with the
stabilisation of the WRD surface sediments.
Waste Rock Dump
The WRD will be a stable long term structure that will be progressively rehabilitated throughout operation
and finally rehabilitated to a self-sustaining natural ecosystem at the conclusion of mining (whilst processing
continues). The detailed rehabilitation objectives and rehabilitation plan is provided in the Rehabilitation and Conceptual Mine Closure Plan (Volume E). WRD design and construction will allow the outer batter
face to be rehabilitated during its construction. Upon decommissioning, the batters and top surface of the
WRD will be graded to provide a uniform slope, with contours diverting water to controlled drainage
structures and ultimately Badalla Creek. Geotextile / erosion control blankets (e.g. jute netting) and topsoil
will be applied and the WRD planted with native vegetation to minimise erosion.
The geochemical risk associated with the waste rock material is very low. Drainage from the WRD will report
to the TMF prior to discharge from site. The management of the water quality draining the WRD post-closure
will include, depending on the solute loads generated, an engineered passive anaerobic wetland system
which may be effective in lowering sulfate salinity and metal concentrations in the WRD leachate post-
closure, if required.
Ore Stockpile
To minimise potential for erosion and sedimentation during decommissioning and closure, the topsoil will be
ripped to a depth of approximately 1 m, graded to match the contours and drainage pattern of adjacent
topography, and planted with native vegetation.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-14
9.2.3 Residual Impact Assessment
The Mine Pit will be a permanent feature in the landscape. The Company has committed to monitor the
water quality in the Mine Pit, Badalla Creek and the Gambia River to ensure that potential discharge from the
pit lake, post-closure, meets Project discharge requirements and ambient water quality requirements.
Implementation of the prescribed management and mitigation measures for the WRD will effectively avoid
potential water quality impacts during operation (i.e. sediment transport beyond the Project PDA, AMD, NMD,
etc.). Rehabilitation of the WRD at decommissioning and processing all ore from stockpiles (and
rehabilitating / revegetating stockpile areas) is expected to minimise the potential for residual impacts.
Monitoring of surface and groundwater post-closure will be implemented to determine whether additional
measures are required to avoid post-closure impacts to water quality.
To avoid potential safety risks at the Mine Pit, an earthen bund will be constructed around the perimeter,
access blocked, and warning signage erected at key access points to warn people of the potential safety risk
of entering the facility.
The key expected residual impacts related to Mine Pit and waste rock disposal under normal operating
conditions, and their overall significance for each Project phase, are summarised in Table 9-5. Monitoring will
be required over the mine life to confirm the residual impact predictions, and allow management measures
to be adapted accordingly.
Table 9-5 Summary of expected Mine Pit and waste rock disposal pre-mitigation and residual impacts
Receptor / Value Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and Overall Impact
Significance
Pre-Construction / Construction
Waste Rock Geochemistry
MINOR
WRD in controlled catchment
Stormwater and sediment treatment
Monitoring
NEGLIGIBLE
Salinity generation from WRD
Mine Pit water quality MODERATE
Dewatering and runoff water collected in sediment basin to settle solids
Dewatering sent to process water and TMF
NEGLIGIBLE
Elevated solids and salinity
Operation
Waste Rock Geochemistry
MINOR
WRD in controlled catchment
Stormwater and sediment treatment
Runoff and seepage collected in TMF
Monitoring
NEGLIGIBLE
Salinity generation from WRD
Mine Pit water quality MODERATE
Dewatering and runoff water collected in sediment basin to settle solids
Dewatering sent to process water and TMF
NEGLIGIBLE
Elevated solids and salinity
Ore Stockpile erosion and water quality
MINOR
Sediment control structures
Runoff contained in TMF catchment
NEGLIGIBLE
Salinity generation from Ore
Decommissioning / Closure
Waste Rock Geochemistry
MINOR
WRD in controlled catchment
Stormwater and sediment treatment
Seepage treatment below TMF if
NEGLIGIBLE
Potential salinity generation from WRD
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-15
Receptor / Value Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and Overall Impact
Significance
required
Monitoring
Revegetation of WRD
Mine Pit water quality MODERATE
Operation of pit lake
Bunding to prevent access
Pit lake may develop overflow
Monitoring/modelling of inflow quantity/quality
Possible wetland treatment of overflow
Management to minimise H2S
Monitoring
MINOR
Potential elevated salinity
Ore Stockpile erosion and water quality
MINOR
Site rehabilitation and revegetation
Sediment control structures
Drainage lines re-established and revegetated
NEGLIGIBLE
Suspended sediment generation until grass revegetation closes
9.3 Tailings Disposal
9.3.1 Issues and Findings
Pre-Construction / Construction
Tailings disposal / impacts will not occur during Project construction.
Operation
Approximately 225 tonnes per hour of solids process tailings and 225 tonnes per hour of process water will
be generated from the Process Plant. Tailings will be disposed of in the TMF. Approximately 50% of the
process water will be entrained in saturated tailings in the TMF, while the remaining will be recovered and
returned to the Process Plant for re-use.
TMF surface water may have elevated concentrations of cyanide from ore processing, elevated salinity,
dissolved metals, and elevated nutrients (breakdown products of cyanide). Further, the tailings are a potential
(though unlikely) source of Acid and Metalliferous Drainage (AMD) or Neutral Metalliferous Drainage (NMD),
as the geochemical risk associated with the tailings material is low. Cyanide destruction, via the INCO (SO2 +
air) process, will be implemented to ensure weak acid dissociable (WAD) cyanide concentrations are below 50
mg/L in the TMF. Tailings piped to the TMF may have elevated concentrations of cyanide, elevated salinity,
heavy metals, and nutrients that are an additional potential source for surface or groundwater contamination
if the piping network is ruptured.
The potential AMD risk associated with the tailings material is low. Approximately 87% of the tailings samples
analysed were non-acid forming and all of the basalt tailings samples analysed were non-acid forming. As a
result of the geochemical / sulfide oxidation processes (i.e. not accounting for process water chemistry),
tailings pore water / supernatant and seepage is expected to be near neutral to slightly alkaline, with low
levels of sulfate salinity and very low dissolved metal (e.g. arsenic, chromium ± manganese, as a result of the
dissolution of carbonate minerals) concentrations.
A small proportion of the ore / tailings samples (~13%) were classified as potentially acid forming (PAF).
However, it is likely that the ore / tailings material is mostly NAF. Routine monitoring and analysis of tailings
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-16
static geochemistry on samples collected from the tailings thickener underflow during operation will be
conducted to confirm that the geochemical risk associated with the tailings material remains low.
The TMF has been designed with a composite basin liner system, with an engineered soil liner over the entire
basin, constructed primarily with re-worked in-situ material. A HDPE geomembrane liner will be installed over
the southern TMF area to cover the extent of the average TMF supernatant pond to limit seepage and
percolation from the TMF.
All drainage pipes will be directed to an HDPE lined seepage collection pond located downstream of the TMF
embankment. At the inlet to the pond, the flow from the drainage pipes will go over a v-notch weir or similar
to enable measurement of individual flows and samples to be taken. The seepage collection pond will be
provided with a pump and pipeline to allow water to be pumped back into the TMF.
The TMF facility has been designed to avoid discharge to receiving waters during Project operation.
The TMF is designed to contain a 1 in 100 year 72 hour storm event and a 1 in 100 year 12 month wet rainfall
sequence (Knight Piesold, 2015d). Stormwater diversion channels will divert water from the catchment
around the facility to limit TMF input to that from processing and direct precipitation.
Decommissioning / Closure
Upon Project decommissioning / closure, the TMF will be rehabilitated and surface water from the facility (as
well as inputs from the WRD and Mine Pit overflow (if applicable) will discharge from a constructed TMF
spillway into Badalla Creek downstream of the facility, a small tributary of the Gambia River. Seepage
monitoring during operation will be used to determine if TMF seepage post closure will require treatment.
9.3.2 Avoidance, Mitigation and Management Measures
Avoidance
The TMF facility has been designed to avoid discharge to receiving waters during Project operation.
The TMF is designed to contain a 1 in 100 year 72 hour storm event and a 1 in 100 year 12 month wet rainfall
sequence, with an additional 1 m contingency freeboard (Knight Piesold, 2015d). Shallow and deep
groundwater monitoring bores will be installed downgradient of the TMF to detect seepage water quality
and quantity.
Geochemistry / water quality
The TMF has been designed with a composite basin liner system, with an engineered soil liner over the entire
basin, constructed primarily from re-worked in-situ material. A HDPE geomembrane liner will be installed
over the southern TMF area to cover the extent of the average TMF supernatant pond and limit seepage of
water from the TMF. The TMF facility has been designed to avoid discharge to receiving waters during Project
operation.
During operation, monitoring and analysis of tailings static geochemistry on samples collected from the
tailings thickener underflow will be conducted to confirm that the geochemical risk associated with the
tailings material remains low. TMF liquor and supernatant pond quality and groundwater quality in
monitoring piezometers downstream of the TMF will also be monitored routinely during operation.
Salinity and metals
Supernatant water will be contained within the TMF (or the seepage collection pond) for recycling as Process
water. TMF water will not discharge to the receiving environment under normal operating conditions.
Based on the Knight Piesold (2015) water balance model, arsenic levels in the TMF supernatant pond are likely
to be above the IFC Effluent discharge standard of 0.1 mg/l at all times and above 1 mg/l at the end of the dry
season (25~73% of the time) due to evaporative concentration when supernatant pond levels are at their
lowest.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-17
Water quality in the supernatant pond will be of better quality during the wet season. At the end of the dry
season, water quality within the TMF will be poor with high salinity and high arsenic and copper levels, lead
and zinc levels.
Access to the TMF facility will be restricted by the use of fencing, to prevent poor quality TMF supernatant
water from being consumed by local wildlife during the operation of the TMF (see Figure 9-1). In any case,
elevated salinity levels are expected to make the supernatant water unpalatable for local species.
Minimisation
Cyanide
Weak acid dissociable (WAD) cyanide concentrations in the TMF will be below 50 ppm to comply with the
International Cyanide Management Code (ICMC) Guidelines. Destruction of residual cyanide from the CIL
circuit in the Process Plant down to < 50ppm will occur via air / SO2 process utilising reagents (sodium
metabisulfite, sodium hydroxide and copper sulphate). Recycling of process water from the TMF will recover a
portion of the residual cyanide from spent leach, reducing cyanide input.
Rehabilitation / Decommissioning / Closure
The TMF surface will be rehabilitated via placement of 300 mm thick sub-base material and 150 mm thick
topsoil on all but the rock-line drainage channels (approximately 25% of the TMF surface area). The TMF will
be revegetated with native species (Shrub savannah vegetative community). The riparian corridor of Badalla
Creek / TMF discharge channel will be planted with native shrub and tree species to stabilise the landform.
Upon Project closure, runoff from the surrounding catchment and rehabilitated WRD surface, and pit overflow
will be directed through rock-line channels to the rehabilitated TMF. The TMF spillway constructed across the
low ridge on the west abutment of the TMF embankment (refer to Project Description, Chapter 4) will
discharge surface water from the WRD, TMF, and Pit Lake (when applicable). TMF supernatant water (and WRD
/ Pit wallrock geochemistry) will be monitored throughout operation, immediately prior to Project
decommissioning, and post-closure. Surface water / TMF supernatant water will be treated (as required) to
ensure compliance with discharge guidelines (GRS, 2002; IFC, 2007) and ambient water quality guidelines
(USEPA, 2009 and EU, 2006), prior to commencement of discharge to the spillway.
Initial modelling of TMF seepage during closure predicts that seepage will most likely be variable depending
on the season and will be low in volume relative to surface water flows in the Badalla Creek. Surface water
quality modelling indicates that seepage water of poor quality may influence the water quality in Badalla
Creek during low flow periods, and when the creek ceases to flow and creek pools are concentrating during
the dry season. Treatment of TMF seepage water, if required, could include measures such as:
Metal removal with the addition of an iron based compound to allow metal adsorption;
Wetland treatment of metalliferous seepage;
Shallow groundwater interception of groundwater prior to entering Badalla Creek and return for
treatment; and
Capture in designed storage pond or subsurface drain (e.g. drainage cells) to meet dilution
requirements with no discharge until sufficient flow develops in the Badalla Creek.
Ongoing post-closure water quality monitoring will be conducted at the Badalla Creek and Gambia River
compliance sites, to ensure water flowing from the rehabilitated TMF (and WRD) and any treatment system if
required, is compliant with applicable guidelines. Shallow and deep groundwater monitoring bores will be
installed below the TMF embankment and downstream of the TMF to monitor groundwater quality during
TMF operation. Analysis and modelling of surface water quality can then be used to determine if the seepage
requires additional treatment, based on the findings of the operational surface and groundwater monitoring
programs.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-18
9.3.3 Residual Impact Assessment
Implementation of the prescribed management and mitigation measures for the TMF will effectively avoid
potential water quality impacts during operation (i.e. sediment transport beyond the Project PDA, AMD, NMD,
etc.) via avoidance of discharge from the PDA.
Rehabilitation of the TMF at decommissioning, including treatment of the TMF supernatant pond at
decommissioning, is expected to minimise the potential for residual impacts. Monitoring of surface and
groundwater during operation and post-closure will be implemented to determine whether additional
measures are required to avoid post-closure impacts to water quality.
Treatment of TMF seepage, if required, will enable the Badalla Creek to meet ambient water quality standards
(USEPA, 2009 and EU, 2006) during the post closure period.
The key expected residual impacts related to tailings disposal under normal operating conditions, and their
overall significance for each Project phase, are summarised in Table 9-6. Monitoring will be required over the
mine life to confirm the residual impact predictions, and allow management measures to be adapted
accordingly.
Table 9-6 Summary of expected tailings disposal pre-mitigation and residual Impacts
Receptor / Value Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and Overall Impact Significance
Pre-Construction / Construction
TMF water quality MINOR
TMF in controlled catchment
Stormwater and sediment treatment
Monitoring
NEGLIGIBLE
Suspended solids from construction disturbance
Operation
TMF geochemistry and water quality
MODERATE
TMF liner and seepage collection
Monitoring of tails static geochemistry
Treatment for CN, possibly As reduction
Exclusion zone and site fencing to prevent access
MINOR
Infrequent bird life contact with poor
quality water
TMF seepage -groundwater quality
MODERATE
TMF liner and seepage collection system
Down gradient groundwater monitoring bores
Treatment
NEGLIGIBLE
Salinity generation from seepage
TMF emergency discharge/Overflow
MAJOR
Freeboard design of TMF to incorporate 1:100 ARI events through the life of the mine
Overflow channel designed for peak flow during 1:100 ARI event
MINOR
Overflow unlikely during mine operation
Dilution of overflow expected in surrounding storm/flood waters
Decommissioning / Closure
TMF geochemistry and water quality
MODERATE
Treatment of final TMF supernatant
Rehabilitation and revegetation of TMF
Seepage rate limited by catch and release cover
MINOR
Treatment may be required if salinity and metals elevated during low flow/cease to flow events in Badalla Creek
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-19
Receptor / Value Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and Overall Impact Significance
TMF seepage -groundwater quality
MODERATE
Down gradient groundwater monitoring bore
Seepage collection and treatment (if required)
Possible dilution with pit lake overflow water
MINOR
Treatment may be required if salinity and metals elevated during low flow/cease to flow events in Badalla Creek
9.4 Hydrology
9.4.1 Issues and Findings
The PDA and Access Corridor are located in the upper Badalla Valley and western Wayako Valley catchments.
All of the sub-catchments form small tributaries to the Gambia River which is approximately 5 km to the
south of the proposed Mine Pit. The Petowal ridgeline is 400 m in elevation and forms the western most
catchment boundary for Badalla Valley, and the northwest catchment boundary for Wayako Valley. To the
west of the ridgeline, three small unnamed streams that are tributaries of the Kelendourou Creek, flow into
the PNNK which is approximately 1-2 km to the west of the PDA. These tributaries have very small areas of
catchment in the PDA, all of which is confined to the proposed Mine Pit.
The primary Project affected watercourses requiring assessment include (Figure 9-2):
Badalla Creek, an ephemeral first order tributary of the Gambia River, where the majority of the
proposed Project infrastructure would be constructed (in its catchment);
Kobokou Creek, an ephemeral first order tributary of the Gambia River, the upper catchment of which
will be impounded by the WSD;
Kelendourou Creek, a second order tributary of the Gambia River which captures water from
ephemeral tributaries with small catchments in the PDA (flows to the PNNK); and
Gambia River (the major watercourse in the region, also flowing through the PNNK).
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-20
Figure 9-2 Mako Gold Project Development Area Hydrology
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-21
The PDA is primarily located in the upper Badalla Valley, with minor overlap into the western Wayako Valley
and Kelendourou catchments. Catchment slopes in the PDA vary from steep (10 to 20%) at ridgelines, 3-5% in
the mid catchment areas and flattening to less than 3% towards lower catchment areas as streams discharge
to the Gambia River or Kelendourou Creek. The stream slope of the Gambia River itself is slight at
approximately 0.1% within the reaches in the vicinity of the PDA.
Stream gauging stations (refer to Figure 9-3) were installed on Badalla Creek draining the Petowal deposit
(SW3); Bowoyoto Creek (SW2), which drains the Wayako valley; and the Kobokou Creek (WSD1) draining the
proposed WSD, to monitor flow in these ephemeral creeks during the wet season of 2014. Gambia River stage
height has been measured twice daily by the Direction des Parcs Nationaux at the Gambia River Mako Station
(SW8) to determine the flow (m3/s) of the Gambia River. A height - discharge rating curve for the Gambia
River at Mako has been established using data collected between 1976 and 1987 by Institut Français de
Recherche Scientifique pour le Developpement en Cooperation (ORSTOM) and Organisation pour la Mise en
Valeur du Fleuve Gambie (OMVG) (Lamagat et al., 1990). Recent data were added to the rating curve between
1998 and 2000 by the Water Brigade of Tambacounda to validate the original stage - discharge rating curve.
The current rating curve is gauged to maximum flow of approximately 700 m3/s.
Operation
The assessment of potential impacts on the hydrology of local streams was undertaken using modelling to
support the limited stream flow data available for the Project area. Hydrologic modelling was undertaken
using the US EPA SWMM modelling system (USEPA 2008), using an initial and continuing loss model, based on
observations of the flow records collected in the area, and local climate patterns. The predicted surface water
hydrological impacts in the Operation Phase are shown in Figure 9-4.
Badalla Creek
Pre-mining peak flow for Badalla Creek (median year) is estimated (modelled) to be approximately 5.2 m3/s.
As discharge from Project facilities into Badalla Creek will be prohibited during operation (to avoid potential
water quality impacts), Badalla Creek peak flow for the Project operational phase will decrease (predicted to
be approximately 2.9 m3/s). The change in annual flow in the Badalla Creek catchment from pre-mining to
the operational phase is a reduction in flow of approximately 48%, while peak flows are similarly reduced by
approximately 45% (refer to Table 9-7).
The modelling point (refer to Figure 9-3) for this assessment is located 600 m to the north of the confluence
of the Badalla Creek and Gambia River.
Table 9-7 Hydrograph analysis for Badalla Creek, Pre-mining and Operation Phase
Hydrograph Analysis Pre-Mining Operation Change (%)
Annual flow (ML) 1564 809 -48
Peak Flow (m3/s) 5.2 2.9 -45
95% flow (m3/s) 0.6 0.3 -48
Kobokou Creek
The WSD embankment will impound the upper reach of Kobokou Creek, though a horizontal blanket drain in
the spine of the valley will maintain drained conditions downstream of the WSD embankment area during
operation and water from the catchment downstream of the WSD will continue to flow to the natural
channel.
The WSD is predicted to capture approximately 92 ML of Kobokou Creek streamflow per annum. The
predicted peak flow velocity in Kobokou Creek is approximately 1.2 m3/s pre-mining and 0.75 m3/s after the
WSD is constructed, a decrease of 66% and 64% annual and peak flow, respectively. Model outputs are based
on a point approximately 300 m to the north of the Gambia / Kobokou confluence. Surface flow will be
significantly decreased during the rainy season (south of the WSD) during mine operation. Table 9-8 shows
the hydrograph analysis for Kobokou Creek.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-22
Table 9-8 Hydrograph analysis for Kobokou Creek, Pre-mining and Operation Phase
Hydrograph Analysis Pre-Mining Operation Change (%)
Annual flow (ML) 140 48 -66
Peak Flow (m3/s) 0.7 0.3 -64
95% flow (m3/s) 0.0 0.0 0
Kelendourou Creek
Three small Kelendourou Creek tributaries will be affected by small catchment area losses to the Mine Pit
during operation (and post-closure). Modelling of hydrological impacts on these tributaries is presented to
assess potential changes to hydrological regimes entering the Niokolo-Koba National Park. The small
difference in flow is observable only at the tip of the flow hydrograph peak flows (~1.7%), due to the relatively
small catchment areas being diverted to the Mine Pit.
Statistical analysis of the Kelendourou tributaries hydrographs before mining and in the operational phase is
provided in Table 9-9. The results predict that catchment flow reduction in the Kelendourou tributaries is very
low, at approximately 1.7% of annual flow volumes and with no measurable reductions in peak flow or flow
duration. There is negligible change in the natural flow hydrograph predicted due to Mine operation.
Table 9-9 Hydrograph analysis for Kelendourou Creek, Pre-mining and Operation Phase
Hydrograph Analysis Pre-Mining Operation Change (%)
Annual flow (ML) 3862 3797 -1.7
Peak Flow (m3/s) 3.5 3.5 0.0
95% flow (m3/s) 1.6 1.6 0.0
Figure 9-3 Predicted Pre-mining and Operation / Post Closure flow in Kelendourou Tributaries
The flows of the three Kelendourou Creek tributaries whose catchments are slightly intercepted by the Mako
Gold Project represent a very small proportion of flow entering the Kelendourou system. As a result,
graphical analysis of change in Kelendourou Creek flow for pre-mining to operational phases is not
detectable on a visual hydrograph.
0
0.5
1
1.5
2
2.5
3
3.5
4
21
-Ap
r-0
1
28
-Ap
r-0
1
05
-May
-01
12
-May
-01
19
-May
-01
26
-May
-01
02
-Ju
n-0
1
09
-Ju
n-0
1
16
-Ju
n-0
1
23
-Ju
n-0
1
30
-Ju
n-0
1
07
-Ju
l-0
1
14
-Ju
l-0
1
21
-Ju
l-0
1
28
-Ju
l-0
1
04
-Au
g-0
1
11
-Au
g-0
1
18
-Au
g-0
1
25
-Au
g-0
1
01
-Se
p-0
1
08
-Se
p-0
1
15
-Se
p-0
1
22
-Se
p-0
1
29
-Se
p-0
1
06
-Oct
-01
13
-Oct
-01
20
-Oct
-01
27
-Oct
-01
03
-No
v-0
1
Flo
w (
m3
/s)
Premining Operations
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-23
Gambia River
The Mako Gold Project will abstract approximately 770 ML of water per year from the Gambia River during
the rainy season months for storage in the Water Supply Dam (and utilisation as Process water, dust
suppression, and camp supply) (Toro Gold, 2015c).
During a relatively dry year, total flow in the Gambia is approximately 1,760,000 ML and approximately
2,888,000 ML during the median year. The total annual supply of mine water proposed during a dry year
represents 0.04% of the Gambia River annual flow and 0.03% of the annual Gambia River flow during the
median year.
Analysis of the impact of water supply pumping on the Gambia River daily hydrograph during dry years show
that during peak flows the rate of abstraction is approximately 0.015% of instantaneous river flow. This is
unlikely to cause any impacts to the aquatic ecosystem or downstream users, but as each dry season may
display different characteristics, it is recommended that daily pumping data be compared with daily flow in
the Gambia River to prevent over-abstraction in the early dry season flow. Project water abstraction will
represent a higher percentage of the instantaneous river flow at the beginning and the end of the wet
season, when river discharge is low.
Peak flow from Kelendourou Creek, Badalla Creek and Kobokou Creek represent a very small fraction of
Gambia River flow (i.e. Kelendourou Creek contributes approximately 1.5% to the Gambia in the median year).
The very small reduction in flow from prohibiting discharge from much of the Badalla and Kobokou
catchments and a negligible flow reduction in Kelendourou Creek was not detectable during the conduct of
surface water modelling for this Project. The flow reduction statistics from water supply pumping and mine
operation is shown in Table 9-10.
Table 9-10 Hydrograph analysis for the Gambia River, Pre-mining and Operation Phase
Hydrograph Analysis Pre-Mining Operation Change (%)
Annual flow (ML) 2,888,234 2,886,602 -0.06
Peak Flow (m3/s) 728.81 728.76 -0.01
95% flow (m3/s) 445.63 445.54 -0.02
80% flow (m3/s) 153.08 153.03 -0.03
Median flow (m3/s) 15.20 15.15 -0.33
25% flow (m3/s) 1.70 1.70 0.00
Minimum flow (m3/s) 0.00 0.00 0.00
Most change in flow conditions from pre-mining to operation is in the range of less than 0.1% of total flow in
the Gambia River. The only percentile not meeting this level of impact was the median flow, which showed a
slightly higher 0.33% flow reduction. This is considered to be a very Minor to Negligible reduction in overall
flow in the Gambia River and the impact to downstream users and aquatic ecosystems is also considered to
be Negligible.
Decommissioning / Closure
The hydrology for the Project affected streams will gradually return to baseline status, including flow volume,
post-closure. Discharge for Badalla Creek and Kobokou Creek will resume near natural character. The
catchments for Badalla Creek and Kelendourou Creeks (to a lesser extent) will be slightly reduced, given the
Mine Pit void will remain following closure. This potential water loss may be offset by the development of the
mining pit lake which is predicted to deliver additional flow to Badalla Creek post closure (after 2046) for
three months with a peak flow of approximately 0.04 m3/s. Peak flow in the Badalla Creek is predicted to be
1.2 m3/s, during this period so pit lake overflow, if occurring will be a small component, approximately 3%, of
total flow. While this is a negligible peak flow increase, and represents very low risk to the ecosystem or local
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-24
communities, it is likely that the creek may flow continuously during this period rather than ceasing to flow
between rainfall events.
The resulting impacts to surface water hydrology may include:
Approximately 1.7% less flow in the three Project affected Kelendourou tributaries during peak flow;
and
Potentially slower flow due to ponding of Badalla Creek on the flat TMF surface.
A post-closure water balance will be required in order to quantify potential hydrology impacts post-closure.
Stream flow gauging stations developed during the project can be used to measure actual flow regime
change post closure to determine if any further corrective action is required.
Predicted post-closure impact levels on surface water hydrology are shown in Figure 9-5.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-25
Figure 9-4 Operation Phase surface water hydrology impacts
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-26
Figure 9-5 Post-Closure surface water hydrology impacts
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-27
9.4.2 Avoidance, Mitigation and Management Measures
Avoidance
Protection of Project receiving waters, which ultimately flow to the Niokolo-Koba National Park has been
considered a very important objective throughout Mako Gold Project design, with several major design
changes resulting to avoid potential environmental impacts from the Project. These are described in Chapter
5.
The principal management measure for avoiding impacts to hydrology is the siting of the majority of Project
infrastructure in Badalla Valley (one small catchment), to limit the extent of potentially significant impacts to
one ephemeral stream. Additional avoidance techniques include:
Minimised catchment footprint for Mine Pit and operation; and
Diversion of clean stormwater around mine structures to the natural catchment.
Minimisation
Badalla Creek
Surface water flowing from upstream of Project facilities will be diverted around the Project Footprint for
discharge into the TMF. The small drainage area around the Mine Pit will be allowed to drain in a controlled
manner into the pit, with no engineered surface water channels required around the pit itself due to the
topographical layout. Peripheral surface water drainage channels will be constructed at the perimeter of the
WRD, with open channels designed to collect surface water runoff originating from the waste rock material.
These channels will redirect the intercepted water into the TMF. Surface water hydrology for Badalla Creek will
be significantly reduced during operation due to the Project’s ‘zero discharge’ design for this catchment (to
protect water quality), which will alter stream flow during the rainy season for this ephemeral stream. The
zero discharge measure prevents impacts to water quality but also limits additional management measures
to offset flow reduction for this stream; the PDA water balance indicates the Project is in deficit, which means
no additional water sources are available to supplement environmental flows. Badalla Creek does not contain
any identified sensitive aquatic ecosystem components such as springs or groundwater dependent
ecosystems, and so therefore reduced streamflow is acceptable during the period of mining.
Badalla Creek flow will resume to a near natural response post-closure as the TMF spillway will be configured
to convey surface water from the Project Footprint back to the natural channel.
Kobokou Creek
A horizontal blanket drain in the spine of the valley will maintain drained conditions downstream of the WSD
embankment area during operation. Water from the catchment downstream of the WSD will continue to flow
to the natural channel. Kobokou Creek does not contain any identified sensitive aquatic ecosystem
components such as springs or groundwater dependent ecosystems, and so therefore reduced streamflow is
acceptable during the period of mining.
Kelendourou Creek
Three small Kelendourou Creek tributaries will be affected by small catchment area losses to the Mine Pit
during the operational mining phase. The orientation of the Mine Pit has been designed to minimise impacts
to stream hydrology for the Kelendourou Creek and the Niokolo-Koba National Park.
As hydrologic impacts to this stream are Negligible, management measures are implemented to protect its
water quality only (i.e. surface water from the disturbed portion of the Kelendourou catchment will be
diverted to the Badalla Creek catchment to prevent sediment input to Kelendourou Creek).
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-28
Gambia River
Abstraction from the Gambia will occur during high flow months from July – December, pending the onset of
rains. Abstraction will not commence until the Gambia River flows reach adequate volume to minimise
impacts to the river and the associated aquatic habitat.
It is proposed to establish a minimum environmental flow requirement of 5 m3/s in the Gambia River before
abstraction can commence. In addition to the minimum environmental flow requirement, a maximum take of
3% of instantaneous Gambia River flow is proposed, to further reduce any potential impacts on downstream
users or the aquatic ecosystem to as low as reasonably practical.
Most years the Gambia River ceases flow in the dry season for several months. Flow commences in the small
tributaries (such as Badalla Creek) of the Gambia River prior to wet season flow developing, in the Gambia
River. Surface water quality modelling indicated that management of stormwater water quality during these
first flush periods is therefore of importance as there will be little or no potential for dilution in the Gambia
River, even though the Badalla Creek may be at nearly peak flow during rainfall periods.
Rehabilitation / Decommissioning / Closure
Badalla Creek
Badalla Creek flow will resume to a near natural response post-closure as the TMF spillway will be configured
to convey surface water from the Project Footprint back to the natural channel.
Kobokou Creek
Post-closure, the WSD embankment will be removed and the channel morphology rehabilitated to allow the
pre-project flow regime to continue.
Kelendourou Creek
As hydrologic impacts to this stream are Negligible, no rehabilitation measures are required.
Gambia River
Water will not be abstracted from the Gambia River following Project decommissioning. No rehabilitation
measures are required.
Enhancement
If Mine Pit lake overflows do occur post closure (~August 2045), there is the possibility to provide some
additional water to maintain dilution and suitable water quality in Badalla Creek during the post closure
period if required. This could be particularly useful during low flows or at the beginning or end of the dry
season.
9.4.3 Residual Impact Assessment
Impacts to surface water hydrology during pre-construction / construction and operation will be Negligible
to Moderate, depending on the watercourse.
The hydrology of Badalla and Kobokou Creek will be significantly impacted during the rainy season, with flow
restricted to that stemming from the catchments downslope of the Project Footprint. Impacts will be
restricted to the lower reaches of Badalla and Kobokou Creeks. The morphology of the Badalla Creek will be
altered and all water flow from the upper reaches of the creek will be impounded in the TMF, while The flow
of Kobokou Creek will be impounded in the WSD when the dam embankment .
Impacts to regional hydrology (e.g. the Gambia River) will be Negligible. Water will be abstracted from the
Gambia River during the wet season and stored in the WSD as make-up water for operation of the Process
Plant. Water abstraction from the Gambia River during the rainy season will not impact the river. The total
volume of water abstracted for the Project is less than 0.04% of the total Gambia River flow during a dry year
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-29
and less than 0.03% during the median flow year. Impacts to the hydrology of Kelendourou Creek will be
Negligible during operations.
Post-closure impacts to surface water in the Project Area are expected to be Negligible.
The key expected residual impacts on hydrology under normal operating conditions, and their overall
significance for each Project phase, are summarised in Table 9-11.
Monitoring will be required over the mine life to confirm the predictions, and allow management measures to
be adapted accordingly. The Company has established a number of hydrology monitoring stations around
the Mako Project area which are monitored on an ongoing basis. Stream gauges will be used to measure
surface flow and stream height. Data will be collected routinely (e.g. daily or monthly) depending on the
location. Implementation and management will be the responsibility of the Company’s Environment
Department. Further details regarding hydrology monitoring are provided in the ESMMP (refer to Volume C).
Table 9-11 Summary of key expected pre-mitigation impacts, mitigation measures and residual impacts on
hydrology for each Project phase
Receptor / Value Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures Key Expected Residual Impacts and Overall Impact Significance
Pre-Construction / Construction
Impact to hydrology of Badalla Creek
MODERATE
Surface water flowing from upstream of
Project facilities will be discharged into the
TMF.
MODERATE
Stream flow will be reduced.
Impact to hydrology of Kobokou Creek
MODERATE
A horizontal blanket drain in the spine of the
valley will maintain drained conditions
downstream of the WSD embankment area.
MODERATE
Stream flow will be reduced.
Impact to hydrology of Kelendourou
NEGLIGIBLE
None required NEGLIGIBLE
No detectable impact to flow
Impact to hydrology of Gambia River
NEGLIGIBLE
None required NEGLIGIBLE
No detectable impact to flow
Operation
Impact to hydrology of Badalla Creek
MODERATE
Surface water flowing from upstream of
Project facilities will be discharged into the
TMF
MODERATE
Stream flow will be reduced.
Impact to hydrology of Kobokou Creek
MODERATE
A horizontal blanket drain in the spine of the
valley will maintain drained conditions
downstream of the WSD embankment area
during operation.
MODERATE
Stream flow will be reduced.
Impact to hydrology of Kelendourou
NEGLIGIBLE
None required NEGLIGIBLE
No detectable impact to flow
Impact to hydrology of Gambia River
NEGLIGIBLE
Minimum environmental flow requirement of
5 m3/s in the Gambia River before abstraction
can commence.
Maximum take of 3% of Gambia River flow
NEGLIGIBLE
No detectable impact to flow
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-30
Receptor / Value Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures Key Expected Residual Impacts and Overall Impact Significance
Decommissioning / Closure
Impact to hydrology of Badalla Creek
MODERATE
Configure TMF spillway to convey surface
water from the Project Footprint back to the
natural channel at closure.
MINOR
Badalla Creek may flow continuously if the pit lake overflow develops
Impact to hydrology of Kobokou Creek
MODERATE
Remove WSD embankment and rehabilitate the channel morphology post-closure
MINOR
Stream discharge may reduce due to vegetation regrowth
Impact to hydrology of Kelendourou
NEGLIGIBLE
None required NEGLIGIBLE
No detectable impact to flow
Impact to hydrology of Gambia River
NEGLIGIBLE
None required NEGLIGIBLE
No detectable impact to flow
9.5 Hydrogeology
9.5.1 Issues and Findings
Groundwater flow in the Project region appears to be through fractured zones in low permeability bedrock.
Groundwater in the overlying weathered zone and bedrock is likely a single aquifer, with groundwater
flowing towards topographic depressions and mirroring topography. Locally, the geology of the deposit
broadly consists of a felsic volcanic unit that is bounded by basaltic volcanics. The felsic unit is discontinuous,
decreasing in thickness and eventually disappearing to the northeast. The weathering profile generally
comprises laterite / saprolites and saprock (transitional) materials from host rock (SRK, 2015). The weathering
profile at the Petowal deposit is expected to be largely unsaturated during the wet and dry seasons. The fresh
basement represents the only substantially saturated aquifer unit and is only permeable where fractured. The
groundwater elevations and flow directions provide evidence for a groundwater system that drains either
into local tributaries of the Gambia River or directly to the river itself. Groundwater transport in the fresh
basement is primarily dipping to the northwest to southwest via fractures. Inflow zones (to the pit) may be
present across the entire depth of mining either by single, discrete fractures or by fracture zones. The bulk
hydraulic conductivity of the rock mass ranges between 7.62 E-2 and 7.40 E-5 m/d, with a geometric mean of
1.66 E-3 m/d. The estimated recharge (between 30 to 126 mm/yr based on two analysis methods provides an
estimated recharge equivalent to approximately 3 – 10% of total annual rainfall (SRK, 2015).
Based upon hydrogeological modelling conducted for the Project (SRK, 2015), groundwater inflow into the
Mine Pit is effectively zero for the first eight months of mining until the Pit reaches the water table. Inflows
rise to a maximum of 259 m3/d (3L/s) by the end of mining.
Structural modelling (SRK, 2015) indicates the predominance of small-scale discontinuous faults in the Mine
Pit area which are typically characterised by limited storage of groundwater and are therefore not likely to be
significant in terms of long-term (base-case) groundwater inflows. However, short-term inflows associated
with such structures may occur where a fault of significant fracture is intersected following blasting.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-31
Figure 9-6 Base-case and Maximum Short-term Groundwater Inflow to the Mine Pit from Numerical Modelling
(Source: SRK, 2015)
Surface water inflow as a result of direct rainfall within the Mine Pit footprint / small catchment ranges from
0.02 km2 (year 1) to 0.27 km2 (year 9) (SRK, 2015). It is estimated that approximately 30% of the direct rainfall
will be lost due to a combination of evaporation and storage. Figure 9-7 estimates the total inflow of water
(groundwater + surface water) that will be abstracted from the Mine Pit during operation.
Figure 9-7 Total (groundwater and direct precipitation) Minimum and Maximum inflows for the Life of Mine
(Source: SRK 2015).
Mine Pit
Development of the Mine Pit will generate a cone of depression whereby some of the southeast moving
groundwater that recharges the aquifer at lower elevations (e.g. Badalla Creek and Gambia River Valleys) will
move into the pit void, where it will be pumped to the Process Plant or WSD. The cone of depression has been
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-32
estimated to extend to a maximum of 900 m from the pit edge, which would not impact known water supply
boreholes used by local communities (SRK, 2015).
Initial modelling of the development of the mining pit lake predicts the delivery of additional flow to Badalla
Creek post closure (after 2046) for three months each wet season with a peak flow of approximately 0.04 m3/s,
while peak flow in the Badalla Creek is predicted to be 1.2 m3/s, approximately 3% of total flow. While this is a
negligible peak flow increase, and represents very low risk to the ecosystem or local communities, it is likely
that the creek may flow continuously during this period rather than ceasing to flow between rainfall events.
Salinity contained in local groundwater is predicted to concentrate slowly in the pit lake until the estimated
lake overflow 20 years after the cessation of pit dewatering. Pit lake overflows may require treatment during
the post closure period.
Initial modelling of the Mine Pit lake allows for the estimation of groundwater loss. Pit lake losses of the post
mining pit lake (when full) are estimated to be in the order of 270,000 m3/year due to evaporation and
250,000 m3/year due to the pit lake overflow. Annual recharge of the groundwater upgradient of the Mine Pit
(~65 ha) is estimated to be in the order of 90,000 to 200,000 m3/year. Annual rainfall into the pit lake is in the
order of 450,000m3. Annual losses of groundwater in the Badalla Creek aquifers due to the pit lake are
extremely low, estimated to in the order of 20,000 m3/year or approximately 1 x 10-5 %.
Modelling of pit lake development upon cessation of dewatering will be required using the regional
groundwater model in order to determine the potential for discharge of water from the Mine Pit post-closure.
This modelling will be undertaken during the Operation Phase using the groundwater inflow and quality data
from the pit dewatering systems.
9.5.2 Avoidance, Mitigation and Management Measures
Minimisation
The cone of depression cannot be mitigated during operation. Water from the dewatering of the Mine Pit
during operation will be maintained on-site for re-use in the Process Plant, with any excess water to be
pumped to the WSD. Post-closure, surface water in excess of the Mine Pit lake storage capacity will be
directed via rock-line channel to Badalla Creek, a first order tributary of the Gambia River.
Enhancement
The following actions are recommended to enhance understanding of hydrogeology in the Mine Pit area
during operation:
Expand the Petowal groundwater monitoring network by converting core holes into sealed monitoring
piezometers. Core-holes that reside outside of the planned pit perimeter should be selected. These
piezometers would be used for water quality monitoring in addition to hydrogeology monitoring;
Continue groundwater level monitoring on a monthly basis and consider increasing the frequency
during the wet-season; and
Use the Mine Pit water balance and dewatering pumping records to determine the total groundwater
inflow over time.
9.5.3 Residual Impact Assessment
Impacts to regional hydrogeology are expected to be Negligible. The cone of depression will not impact local
groundwater abstraction during operation. The cone of depression will decrease incrementally post-closure,
as the Mine Pit void fills with groundwater / surface water.
The development of the pit lake is not expected to substantially alter the hydrogeology of the aquifers of the
surrounding area.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-33
The key expected residual impacts on hydrogeology under normal operating conditions, and their overall
significance for each Project phase, are summarised in Table 9-12. Monitoring will be required over the mine
life to confirm the predictions, and allow management measures to be adapted accordingly.
Table 9-12 Summary of key expected pre-mitigation impacts, mitigation measures and residual impacts on
hydrogeology for each Project phase
Receptor / Value Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and Overall Impact
Significance
Pre-Construction / Construction
Construction water use
MINOR
Transfer to site water supply. NEGLIGIBLE
Minor use of groundwater during construction
Operation
Impact to hydrogeology of pit dewatering
NEGLIGIBLE
Expand the Petowal groundwater
monitoring network by converting core
holes into sealed monitoring
piezometers.
Continue groundwater level monitoring
on a monthly basis and consider
increasing the frequency during the wet
season.
NEGLIGIBLE
Pit dewatering drawdown impact area could cause tree mortality in deeper drawdown zones
TMF - Poor groundwater quality
MODERATE
Seepage recovery and recirculation in
TMF
NEGLIGIBLE
Small amount of seepage not recovered from TMF escapes to groundwater
Decommissioning / Closure
TMF - Poor groundwater quality
MODERATE
Monitoring of seepage groundwater
Seepage treatment if required
NEGLIGIBLE
Seepage may influence low flow
water quality in Badalla Creek
9.6 Surface and Ground Water Quality
9.6.1 Issues and Findings
Surface water quantity and quality modelling with SWMM (USEPA 2008) has confirmed that creeks and rivers
in the PDA are ephemeral and are therefore susceptible to evaporative concentration effects during cease to
flow events and in the early dry season as pools evaporate. Additionally in the early wet season, the Badalla
Creek is likely to flow into the Gambia River for several weeks before wet season flow is established in the
Gambia River. Predicted surface water quality impacts are shown in Figures 9-8 to 9-10.
Pre-Construction / Construction
Suspended sediment: The primary impact to surface water quality during construction will likely be
suspended sediments generated from land clearing / earthworks, sand / gravel extraction from quarries /
borrow areas, and road construction / unsealed road surfaces. The majority of input will result from water
erosion of disturbed areas during the wet season, while wind erosion will provide some additional input
during drier months, particularly given the Harmattan winds associated with the region (refer to Section 9.13).
The design and construction of access road / road infrastructure will be particularly important in controlling
sediment-laden runoff from the Project site. Roads intercept, concentrate and direct water from potentially
large catchments on compacted surfaces to receiving waters.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-34
Land clearance and/or topsoil removal associated with site preparation will provide significant areas of
disturbance that will be susceptible to erosion, specifically:
Mine Pit: 36.04 ha;
Access road / road infrastructure: 15.0 ha;
Waste Rock Dump: 80.9 ha;
Tailings Management Facility: 25.5 ha;
Process Plant and ROM Pad: 13.4 ha;
Mine Services Area: 2.7 ha;
Accommodation camps: 8.8 ha; and
Power Station Facility: 8.0 ha.
Hydrocarbons: Diesel fuel for vehicles and equipment will be transported and stored / handled on-site
providing potential for spillage and subsequent impacts to surface and groundwater.
A truck wash will generate <50 m3/day of potentially hydrocarbon contaminated wash water and
<10 m3/week of potentially contaminated sludge in the truck wash sump (refer to Section 9.12).
Non-hazardous waste: Non-hazardous waste will be generated during construction of major Project
facilities (e.g. alkalinity from concrete batching); calcium carbonate, activated carbon, and flocculent will be
stored at the Process Plant, and general refuse generated in workforce accommodation areas, the Mine
Services Area, etc. If improperly stored, non-hazardous waste may pollute surface water during storm events
(refer to Section 9.12).
Nutrients and Pathogens: The workforce required to construct the Project is expected to peak at 886
employees, 396 of which will be accommodated within the Project Footprint. Waste water from the
accommodation / construction facilities will comprise a potential source of nutrients and pathogens that may
be released into receiving waters via grey-water or septic systems. Solid waste landfills may provide an
additional source of pathogens to surface or groundwater if they are not effectively isolated (refer to Section
9.12).
Operation
TMF Supernatant water: Potential pathways of solute discharge related to acidity and/or alkalinity, from the
TMF during operation may include:
Uncontrolled discharge of TMF supernatant water;
Discharge of tailings slurry or return water to the downstream environment from tailings or return
water pipeline failure;
Seepage of tailings pore water through the TMF embankment;
Percolation of tailings pore water through the foundations of the TMF to the down hydraulic gradient
groundwater; and
Failure of the TMF embankment, resulting in a release of tailings and supernatant pond water to the
downstream environment.
Cyanide and reagents: An assessment of potential impacts of tailings disposal in the TMF and potential
impacts to surface and groundwater quality is provided in Section 9.3. In summary, the tailings liquor is
expected to contain elevated concentrations of process reagents (sodium metabisulfite, sodium hydroxide
and copper sulfate), alkalinity, salinity (elevated Na, Ca, Mg, and SO4), nutrients, and dissolved metals. Cyanide
destruction, via the INCO process, will be implemented to maintain WAD cyanide concentrations in the TMF
supernatant pond below 50 mg/L at all times.
As the Project has been designed to eliminate discharge from the TMF during operation, the primary impact
will be to the TMF reservoir surface water. However, percolation of water from the TMF may impact down-
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-35
gradient groundwater and downstream surface water from the TMF. Surface water impacts from seepage
may be direct (via seepage directly through the dam wall to the downhill soil surface) or through down
gradient emergence of impacted groundwater.
Uncontrolled or controlled discharge of surface water from the TMF during an extreme storm event, failure of
the TMF dam wall, or surface water overtopping the TMF dam wall would significantly impact receiving
waters pending the concentration of cyanide and nutrients, salinity of the water, and dissolved metals.
Hazardous waste: The following potentially hazardous reagents will be stored at the Process Plant and / or
the Mine Services Area: cyanide, sodium hydroxide, hydrochloric acid, copper sulphate, sodium
metabisulphite, and leach aid (refer to Section 9.12). If discharged beyond containment, each of these
materials pose a potential threat to downstream or down-gradient surface or groundwater, respectively.
Hydrocarbons: Diesel fuel for vehicles and equipment and for the Power Station will be transported to site;
stored at the Mine Services Area and Power Station, respectively; and handled during operation providing
potential for spillage and subsequent impacts to surface and groundwater.
The truck wash at the Mine Services Area will generated truck wash water (<50 m3/week) that may be
contaminated with hydrocarbons.
Nutrients and Pathogens: The workforce accommodation facility will accommodate approximately 130
people during Project operation. As per the Construction Phase, waste water from the accommodation and
administration facilities will comprise a potential source of nutrients and pathogens that may be released into
receiving waters via grey-water or septic systems discharge. Solid waste landfills may provide an additional
source of pathogens to surface or groundwater if they are not effectively isolated. Elevated nitrate
concentrations may be present in the leachate from the waste rock and Mine Pit wallrock, associated with
ammonium nitrate fuel oil (ANFO) blast residues.
Suspended sediment: The PDA is moderately steep and is comprised of soils prone to erosion. During
operation it is expected that erosion and sediment transport will be less extensive then during construction.
However, the unsealed road network, progressive dumping of waste rock and low grade ore, progressive TMF
embankment construction, and soil stockpiles will provide substrate for erosion and potential transport to
receiving waters.
Decommissioning / Closure
A spillway will be constructed from the TMF during Project decommissioning (refer to Section 9.3) and
discharge of Badalla catchment surface water into Badalla Creek (and subsequently the Gambia River) will
resume. If improperly managed, TMF supernatant water and runoff from the WRD and Mine Pit may pose a
significant potential threat to downstream surface water quality.
Monitoring data from the operation phase in the pit lake, TMF and WRD seepage, and groundwater
monitoring bores, will be analysed to determine any potential water treatment requirements.
As above, deconstruction / decommissioning activities will require vehicle / equipment operation and
workforce accommodation, with associated potential impacts from hydrocarbon spillage and nutrients /
pathogens, respectively.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-36
Figure 9-8 Surface water quality, potential impacted streams during Construction
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-37
Figure 9-9 Surface water quality, potential impacted streams during Operation
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-38
Figure 9-10 Surface water quality, potential impacted streams Post Closure
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-39
9.6.2 Avoidance, Mitigation and Management Measures
Avoidance
The Project design will reduce potential impacts to surface and groundwater during the Construction Phase
via placement of the majority of the footprint (i.e. Mine Pit, WRD, TMF, Process Plant and ROM Pad, Mine
Services Area) in the Badalla catchment (and diverting surface water to the Badalla catchment for those
facilities that straddle the Badalla and neighbouring catchments). Sediment laden water, hydrocarbons and
other potential contaminants will be managed and mitigated by avoiding significant inputs of potential
pollutants to Badalla Creek and additional tributaries of the Gambia River (refer to below).
Erosion and suspended sediment:
Interception channels will be positioned to capture ‘clean’ runoff and divert it around disturbed areas. Runoff
from the disturbed areas will be routed to sedimentation ponds or the TMF, pending location. Sediment
ponds, ‘clean’ water diversion channels, and contact channels (diversion from Project construction areas) are
designed to capture and accommodate peak flows (100 year 24 hr average rainfall events) modelled for their
respective catchments.
As the timing for earthworks will likely extend into the wet season, sediment control dams, drainage
structures, and additional sediment control facilities will be completed prior to the onset of the 2016 wet
season. An event pond will be constructed below the Process Plant and ROM Pad footprints and a sediment
control pond will be constructed downstream from the TMF.
Each water diversion channel has been designed for continuous flow (i.e. aligned to initiate at a high point
and finish at a low point), terminating at settlement ponds to allow for the settling of entrained sediments
prior to discharge to the environment.
Channels will be designed as follows:
Cut slopes at channel sides at 3H:1V;
Channel depths varying depending on the elevation of the invert;
A 3 m wide access surface will be provided using suitable material to allow maintenance; and
Bed stabilisation and energy dissipation structures will be implemented where channels discharge into
sedimentation ponds / TMF or where channels are steep.
Channels have been designed for the final life of mine footprints and will require maintenance activities to
minimise build-up of material and replacement of bed scour protection.
In addition, the following erosion control and sediment management measures will be implemented during
the Construction Phase to mitigate potential impacts associated with site preparation:
Vegetation clearing will be restricted to the minimum area possible and vegetation will be preserved in
areas where construction will occur and a later date. Areas scheduled for vegetation clearance will be
clearly demarcated and personnel will be informed of the maximum extent of clearance and the
requirement to prohibit heavy equipment from straying beyond demarcated zones;
Where feasible, major earthworks and grading operation will be scheduled for early in the dry season;
Surface water management infrastructure (e.g. cut-off / diversion drains, velocity dissipation devices,
culverts) will be installed in appropriate locations to minimise and control surface water flow over
disturbed areas;
Vegetation on steep slopes and riparian corridors will be preserved where possible; and
Disturbed land areas will be progressively rehabilitated when feasible, with priority rehabilitation and
revegetation undertaken in high risk areas such as steep slopes and sites close to rivers and creeks.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-40
Minimisation
Erosion and suspended sediment:
The following management and mitigation measures (adapted from the Minesite Water Management
Handbook (MCA, 1997) should be implemented to minimise erosion and suspended sediment input to
receiving waters from Access road and road infrastructure facilities:
Roads will be constructed during the dry season to the extent possible. Erosion and sediment control
facilities for unsealed roads will be completed before the onset of the wet season;
The road design will include a drainage system to channel water from the road surfaces to outlets with
erosion and sediment control facilities, including rip-rap at inlets and outlets of culverts and channels
and sediment control basins constructed for larger catchment areas;
Roads will be constructed with cross-fall slopes of (maximum 3%) to promote rapid drainage from
unsealed road surfaces to avoid scouring. Where cross-fall is insufficient, waterbars will be constructed
to direct water to road discharge channels that will be outfitted with velocity dissipaters and sediment
control (e.g. rip-rap, sumps and/or silt fencing);
Drainage from upslope of road surfaces will be diverted via roadside drainage channels to culverts
with velocity dissipaters and sediment control at outlets;
Culverts will be installed at drainage crossings, perpendicular to the road alignment and implemented
with appropriate slopes to facilitate water and sediment movement with deposition and consequent
culvert blockages;
Permanent structures should be designed using an average peak storm recurrence interval of 50 years,
and temporary structures should be designed using an average recurrence interval of two years (24
hour storm events);
Batter slope angles will be minimised to the extent feasible;
Soil will not be side-cast (pushed) over the crest of the low side of the road. Excess soil will be
transported to the topsoil stockpile or temporary stockpiles, with stockpile locations identified prior to
the onset of construction; and
Where feasible, vegetation will be left intact on road verges and roadside batters to reduce surface flow
velocity and erosive potential.
Hydrocarbons
The following management and mitigation measures will be implemented to minimise impacts from
accidental spills associated with transport of hydrocarbons, use of heavy machinery during site preparation,
and storage and handling of hydrocarbons to avoid or minimise potential impacts to surface or groundwater:
All hydrocarbons (e.g. fuels and lubricants) will be stored in fully bunded areas in the Mine Services
Area and / or applicable vehicle laydown / maintenance areas. Bunded areas will be covered to
prohibit rain infiltration. Bunds will have sufficient capacity to contain at least 110% of the tanks’
maximum capacity;
Vehicle maintenance bays, equipment laydown areas, and re-fuelling stations will have perimeter
bunding and interception drains to contain oily runoff. Potentially contaminated surface will be
diverted to the TMF and recovered for use as process water; and
Surface water management features such as diversion bunds, oil/water separators, and interception
drains will be checked on a regular basis to ensure their effectiveness.
The management of the refuelling and maintenance of heavy machinery will include:
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-41
Regular maintenance of vehicles and equipment to prevent hydrocarbon leaks in designated areas
where contaminated runoff can be contained (e.g. Mine Services Area); and
Vehicles and equipment and equipment laydown areas will be sealed for overnight / non-operation
parking.
Management measures associated with potential spills or leaks of liquid hazardous materials will include:
Adequate volume of hydrocarbons spill kits (e.g. Sorbex) will be stored in readily accessible locations
where hydrocarbons are stored or handled;
Personnel will be trained in the emergency preparedness and response protocols (refer to ESMMP).
Emergency Preparedness and Response Plans will be prepared for the Project which will detail training
requirements, storage and handling procedures, clean-up material requirements, etc.
Potential input from the truck wash will be managed accordingly:
The truck wash area will be paved, with surface water directed to a collection sump. Hydrocarbon
contaminated sludge from the sump (<10 m3/week) will be volatilised and then buried in a lined
landfill. Treated wastewater (e.g. from oil / water separator at the sump) will be used for dust
suppression on haul roads.
Nutrients and Pathogens
Temporary Construction Phase workforce accommodation and administrative facilities will be designed to
store and / or treat the volume of wastewater generated from kitchen, bathrooms, toilets, etc. A sewage
treatment plant (STP) will treat water from the workforce accommodation camp, Process Plant, and Mine
Services Area. The method of disposal for treated sludge and / or treated water will be managed accordingly:
STP sludge: surplus activated sludge from all sewage treatment plants (calculated as <50 kg/day) will
be solar dried in a lined pond, and then buried in a lined landfill or co-disposed with plant tailings;
STP treated water from accommodation camps (expected to be 50 – 100 m3/day) will be disposed of
via leach drains; and
STP treated water from the Plant Site and Mine Services Area (expected to be 50 – 100 m3/day) will be
disposed of in the TMF and recovered for use as process water.
The CEMP will provide detailed specifications for greywater treatment and sewage containment, treatment
and disposal that ensure effluent meets discharge guidelines and receiving waters meet ambient water
quality guidelines for nutrients and pathogens.
Mine Pit sump water and TMF seepage water will be monitored for nutrient concentrations during operation
to determine if treatment is required prior to the rehabilitation and resumption of discharge from these
facilities. Water will be treated, if required, prior to its release to receiving waters.
Accommodation and additional facilities that may generate nutrients and pathogens (e.g. toilets, kitchens,
etc.) have been designed to ensure containment of potentially contaminated water.
During operation, the measures listed above for Construction Phase erosion and sediment control;
hydrocarbon management and handling measures; and nutrient / pathogens will be implemented with
additional measure incorporated (refer to below) to accommodate specific Project components. Further
detail is provided in Section 9.11, General Waste and Hazardous Materials.
Cyanide and Process Plant Reagents
The Project will adhere to ICMI Cyanide Management Code (Cyanide Code) Principles and Standards of
Practice for Cyanide Transportation, including independent auditing of procedures and Transportation
Verification Protocols; and Cyanide Code Standards of Practice for handling and storage (refer to Section 9.11).
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-42
The Process Plant will incorporate a cyanide destruction circuit to treat slurry from the CIL circuit using the air
/ SO2 process. Cyanide destruction circuit tailings will be pumped to the TMF at a concentration of less than
50 ppm WAD cyanide (as per the ICMI guideline). Supernatant water will be recovered from the TMF and
returned as process water decant to the Plant for storage in the process water tank and reuse. The TMF is
designed, and will be managed, so that it will not discharge to receiving waters during operation.
The Process Plant design incorporates the following measures to account for potential contaminant
discharge of processing reagents:
Materials handling, containment and bunding in all Plant areas will meet the requirements of the
International Cyanide Management Code as well as legislative requirements;
Plant areas subject to potential contamination from chemical or slurry spills will have concrete slabs
and bund. Bunded areas will be equipped with sumps to recover spilled material and rain from slabs;
and
Spillage exceeding the capacity of bunds will report to and HDPE lined event pond, where it will be
pumped back to the Process Plant for reuse or treatment.
As per Section 9.3, the TMF embankment and the southern portion of the TMF will be constructed with an
HDPE liner to minimise the potential for groundwater seepage. A leakage collection system has been
designed to capture TMF seepage for collection in a lined recovery pond. This water will be pumped back to
the TMF and then the Process Plant for reuse as process water.
All process water that may contain cyanide or process reagents (e.g. copper sulphate) will be monitored
throughout operation and prior to Project decommissioning to ensure that surface water discharge will meet
applicable discharge (GRS, 2002; IFC, 2007) and ambient (USEPA, 2009; EU, 2006) water quality guidelines prior
to the resumption of discharge from the Badalla Valley. Water will be treated, if required, prior to its release to
receiving waters.
Piezometers will be installed down-hydraulic gradient from the TMF to monitor groundwater at the following
locations to determine whether remedial works are required:
Approximately 50 metres downstream of the seepage collection sump; and
Approximately 500 metres downstream of the TMF embankment near the Mine Permit boundary.
Badalla Creek will also be monitored to ensure appropriate management of seepage.
Metals and Salinity
Surface water from the WRD and Mine Pit will be captured in the TMF, with TMF water pumped to the Process
Plant for utilisation as process water. Surface water will not be discharged from the TMF to receiving waters
during operation. Seepage from the TMF and / or TMF pipeline will be captured through a leakage recovery
system, contained in a recovery pond, and pumped back to the TMF.
As per Section 9.2 and 9.3, geochemical analyses of waste rock, tailings / ore, and Mine Pit wallrock found each
have a low potential to generate AMD, NMD or sulfate salinity. Surface water will not be discharged from the
Project Footprint during operation. Regular monitoring of water quality and geochemistry (waste rock,
wallrock, and tailings) will be conducted to confirm the risk remains low and to prepare for post-closure
resumption of discharge from the Project Footprint.
Monitoring of TMF seepage quality and quantity during operation will provide data with respect to the likely
behaviour and characteristics of the seepage expected to be generated by the TMF and WRD during
operation and closure. Natural attenuation processes such as microbial uptake and reactive surface adhesion
will be able to be determined by comparing groundwater quality in monitoring bores downstream of the
facility.
All drainage from the WRD, TMF and Mine Pit will be monitored throughout operation and prior to Project
decommissioning to ensure that surface water discharge will meet applicable discharge (GRS, 2002; IFC, 2007)
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-43
and ambient water quality guidelines (USEPA, 2009; EU, 2006) prior to resumption of discharge to Badalla
Valley. Detailed management strategies relevant to mine material geochemistry are discussed in further
detail in Section 9.3.2. Routine water quality monitoring will also be conducted. If the risk is found to increase
during operation, a geochemistry management plan will be developed to ensure that potential impacts
associated with mine material geochemistry post-closure are minimised.
Hydrocarbons
The Process Plant, Mine Services Area, Power Station and WSD pumping facility are designed to minimise the
potential for hydrocarbon discharge to receiving waters. Facilities’ design incorporates primary and
secondary containment for storage and handling areas.
As per the Construction Phase, Emergency Preparedness and Response Plans will be developed that specify
transport, storage, and handling mechanisms; spill prevention and reaction training; and spill clean-up
material requirements (refer to ESMMP, Volume C).
Rehabilitation / Decommissioning / Closure
Salinity and Metals
If discharge occurs from the post mining Mine Pit lake, it may be slightly elevated in salinity and require
treatment such as a designed dilution discharge system or wetland.
There may be an area of groundwater directly under the TMF which will be elevated in some metals and
salinity during the operation and post closure period. During operation this will be managed through
seepage return and groundwater monitoring. The TMF seepage is expected to be relatively low in volume
post closure. The Mine Pit lake and TMF seepage systems will be treated, if required, post closure, to ensure
appropriate ambient water quality is maintained in Badalla Creek.
Erosion and Sediment Transport
As per the Rehabilitation and Conceptual Mine Closure Plan (Volume E), all temporarily disturbed areas will be
rehabilitated and revegetated to create self-sustaining natural ecosystems. Upon successful plant
establishment (i.e. achievement of completion criteria), areas prone to erosion will be minimised. Erosion of
the unsealed road network will provide for an ongoing source of sediment. Roads and associated erosion and
sediment control facilities have been designed to reduce sediment transport to receiving waters.
9.6.3 Residual Impact Assessment
With monitoring and treatment of surface and groundwater in the PDA, the potential for residual impacts for
the majority of potential contaminants is considered low.
The unsealed road network will provide an ongoing source of suspended sediment from erosion during the
rainy season. The responsibility for post-closure maintenance of these roads will be determined during
stakeholder consultation, should the ownership of these assets be transferred to government of local
communities.
The key expected residual impacts related to surface and groundwater quality under normal operating
conditions, and their overall significance for each Project phase, are summarised in Table 9-13. Monitoring will
be required over the mine life to confirm the residual impact predictions, and allow management measures
to be adapted accordingly.
Table 9-13 Summary of key expected pre-mitigation impacts, mitigation measures and residual impacts on
surface and groundwater quality for each Project phase
Receptor / Value
Expected Pre-Mitigation
Impact Significance
Key Management & Mitigation Measures Key Expected Residual Impacts and
Overall Impact Significance
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-44
Receptor / Value
Expected Pre-Mitigation
Impact Significance
Key Management & Mitigation Measures Key Expected Residual Impacts and
Overall Impact Significance
Pre-Construction / Construction
Erosion and Suspended Sediment
MODERATE
Construct site stormwater and sedimentation basin
structures based of hydrological stream order moving
up stream
Develop soil removal mosaic patterns to reduce the
overall area of exposed soil
Use silt fencing and bunding to retain stockpiled soils
MINOR
Some elevation of suspended solids
Erosion and Suspended Sediment
MODERATE
Vegetation clearing restricted to minimum area possible
and vegetation will be preserved in areas where
construction will occur and a later date.
Where feasible, major earthworks and grading
operations will be scheduled for early in the dry season.
Surface water management infrastructure (e.g. cut-off /
diversion drains, velocity dissipation devices, culverts)
will be installed in appropriate locations to minimise and
control surface water flow over disturbed areas.
Vegetation on steep slopes and riparian corridors will be
preserved where possible.
Disturbed land areas progressively rehabilitated when
feasible, with priority rehabilitation and revegetation
undertaken in high risk areas such as steep slopes and
sites close to rivers and creeks.
Roads constructed during the dry season to the extent
possible. Erosion and sediment control facilities for
unsealed roads completed before the onset of the wet
season.
Road design will include a drainage system to channel
water from the road surfaces to outlets with erosion and
sediment control facilities.
Roads constructed with cross-fall slopes of (maximum
3%) to promote rapid drainage from unsealed road
surfaces to avoid scouring.
Drainage from upslope of road surfaces diverted via
roadside drainage channels to culverts with velocity
dissipaters and sediment control at outlets.
Culverts installed at drainage crossings, perpendicular
to the road alignment and implemented with appropriate
slopes to facilitate water and sediment movement with
deposition and consequent culvert blockages.
Permanent structures designed using an average peak
storm recurrence interval of 50 years, and temporary
structures should be designed using an average
MINOR
Some elevated suspended solids expected during large storm events
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-45
Receptor / Value
Expected Pre-Mitigation
Impact Significance
Key Management & Mitigation Measures Key Expected Residual Impacts and
Overall Impact Significance
recurrence interval of two years (24 hour storm events).
Batter slope angles minimised to the extent feasible.
Soil will not be side-cast (pushed) over the crest of the
low side of the road. Excess soil transported to the
topsoil stockpile or temporary stockpiles, with stockpile
locations identified prior to the onset of construction.
Where feasible, vegetation left intact on road verges
and roadside batters to reduce surface flow velocity and
erosive potential.
Operation
Hydrocarbons LOW
All hydrocarbons (e.g. fuels and lubricants) will be
stored in fully bunded areas in the Mine Services Area
and / or applicable vehicle laydown / maintenance
areas;
Vehicle maintenance bays, equipment laydown areas,
and re-fuelling stations will have perimeter bunding and
interception drains to contain oily runoff. Potentially
contaminated surface water in the Badalla catchment
diverted to the TMF and recovered for use as process
water; and
Surface water management features such as diversion
bunds, oil/water separators, and interception drains
checked on a regular basis.
Regular maintenance of vehicles and equipment to
prevent hydrocarbon leaks in designated areas where
contaminated runoff can be contained (e.g. Mine
Services Area); and
Vehicles and equipment and equipment laydown areas
sealed for overnight / non-operation parking.
Adequate volume of hydrocarbons spill kits (e.g.
Sorbex) stored in readily accessible locations where
hydrocarbons are stored or handled;
Construction personnel trained in the emergency
preparedness and response protocols (refer to
ESMMP).
The truck wash area paved, with surface water directed
to a collection sump. Hydrocarbon contaminated sludge
from the sump (<10 m3/week) volatilised and then
buried in a lined landfill. Treated wastewater (e.g. from
oil / water separator at the sump) used for dust
suppression on haul roads.
NEGLIGIBLE
Hydrocarbon contaminated soil from spills will need disposal
Nutrients and Pathogens
MODERATE STP sludge: surplus activated sludge from all sewage
treatment plants (calculated as <50 kg/day) solar dried
NEGLIGIBLE
Low level
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-46
Receptor / Value
Expected Pre-Mitigation
Impact Significance
Key Management & Mitigation Measures Key Expected Residual Impacts and
Overall Impact Significance
in a lined pond, and then buried in a lined landfill or co-
disposed with plant tailings;
STP treated water from accommodation camps
(expected to be 50 – 100 m3/day) disposed of via leach
drains; and
STP treated water from the Plant Site and Mine
Services Area (expected to be 50 – 100 m3/day) will be
disposed of in the TMF and recovered for use as
process water.
groundwater recharge with nutrients
Cyanide and Process Plant Reagents
MODERATE
Materials handling, containment and bunding in all Plant
areas meet the requirements of the International
Cyanide Management Code as well as legislative
requirements;
Plant areas subject to potential contamination from
chemical or slurry spills will have concrete slabs and
bund. Bunded areas equipped with sumps to recover
spilled material and rain from slabs; and
Spillage exceeding the capacity of bunds will report to
and HDPE lined event pond, where it will be pumped
back to the Process Plant for reuse or treatment.
NEGLIGIBLE
Possible transport of CN into TMF seepage requiring treatment
Decommissioning / Closure
Erosion and Suspended Sediment
MODERATE
Restoration of landforms and streamlines undertaken
with revegetation and appropriate sediment and erosion
design prior to flow re-establishment.
MINOR
Some elevation of suspended solids
Salinity and metals
MODERATE
Operation Phase monitoring of TMF seepage and pit
dewatering and pit lake water analysed with surface
water quality modelling to determine if further treatment
is required and if so treatment design parameters for
closure treatment system.
MINOR
Possible low flow elevations of water quality in Badalla Creek
9.7 Soils
9.7.1 Issues and Findings
Site preparation activities (e.g. clearing and grubbing, grading, etc.) and construction of Project components
has the potential to impact soil character (e.g. aeration and moisture holding capacity), topsoil volumes (e.g.
via erosion and sedimentation), and capacity of the landform to promote sustainable plant growth upon
rehabilitation and revegetation during Project decommissioning.
MEC site clearance planning includes excavation, transport, and stockpiling of topsoil and subsoil from
various Project components for utilisation during progressive rehabilitation and for rehabilitation and
revegetation of temporarily disturbed areas during decommissioning and closure (likely the Mine Pit, Process
Plant, WRD, TMF, and WSD).
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-47
In addition, substrate of varying texture (pending Project component) will be required for road construction,
dam construction, TMF liner construction, etc. (e.g. sand, gravel, clay rich substrate). Borrowing for this
material will be conducted within the Project Footprint to the extent possible, but will likely further impact
soil character in the Study Area (within approximately 5km from the PDA) via excavation of current and
additional borrow areas.
The Project Footprint (vegetation clearance area) has been minimised to the extent practicable during Project
design, with the majority of Project components within one small stream catchment (Badalla Valley), limiting
the area of impact. The Project design includes primary and secondary containment areas (concrete bunding,
etc.) in hazardous storage waste storage and handling facilities to protect soil quality in these areas. The
Project will utilise pre-existing (and currently disturbed) quarries to the extent practicable to minimise
potential impacts from borrow activities.
Some potential impacts will have to be managed and mitigated to avoid or minimise impacts during pre-
construction, operation, and decommissioning (refer to below).
Pre-Construction / Construction
Construction activities may impact soils in the PDA in the following respects:
Contaminants: Accidental spillage / leakage of hydrocarbons from vehicles or storage / handling areas
would affect soil and / or water quality. Potential for hazardous materials impacts from the Mine
Services Area, truck wash, etc. are discussed further in Section 9.6 (Surface and Groundwater Quality)
and Section 9.12 (General Waste and Hazardous Materials).
Compaction: The requirement for heavy vehicles / land clearing equipment will compact soil surfaces
during site preparation. For some of the components (e.g. road network, Process Plant and ROM Pad,
Mine Services Area, accommodation camps) the component footprint will require compaction to
support the infrastructure. If unmitigated, compacted soils will inhibit water infiltration, aeration and
the potential for plant establishment following Project closure.
Erosion: Clearing and grubbing vegetation, earthmoving activity, topsoil/subsoil transport, and
topsoil/subsoil stockpiling will promote erosion of soils with wind and water (refer to Section 9.6).
Seed Bank: Excavation and long-term stockpiling of topsoil will likely eliminate the viability of the
seed currently contained therein (pending the respective duration of seed viability for applicable plant
species). The seed bank is however expected to minimise erosion and sediment transport from soil
stockpiles via promotion of plant establishment on long-term stockpiles.
Quarries: Earth-fill borrow material will be required for concrete batching (for facilities construction),
WSD embankment / dam, TMF starter wall construction, and road construction / upgrade activities.
Sand is expected to be hauled to site from a source outside the PDA. Additional borrowing activities
will likely occur on-site, potentially impacting some land at quarry sites for material that cannot be
sourced from the Mine Pit overburden. However, three existing quarries (refer to Figure 9-2) within the
Project Concession Area have been previously disturbed (and not rehabilitated), and are expected to
be utilised for Project borrow requirements, minimising the potential for any additional significant
impacts (refer to below).
General borrow requirements include:
» Sand: It is estimated that approximately 6000 m3 of concrete will be required to construct the
Process Plant, Mine Services Area, Accommodation camp, and various minor facilities. Sand
requirements for concrete are estimated to be 4,950 tonnes. A preliminary review for local sand
availability indicated small quantities of high silt material can be found nearby but are unlikely to
provide the quantities or sand quality needed. As such sand will be sourced from suppliers outside
the PDA.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-48
» Aggregate and rip-rap: there are a number of basalt outcrops in the PDA that may be suitable for
rock extraction and processing. There are three pre-existing quarry sites within the mining lease.
One in particular has been used recently for the recent N7 highway upgrade. This quarry is ready
for immediate use with a loading ramp and laydown area for stockpiling crushed aggregate already
available.
It is envisaged that a contractor with a portable crushing plant will be employed to produce the
required aggregate (6,500 tonnes). Aggregate will be stockpiled at the quarry site and
progressively transferred to the work site over the following seven months.
» Clay-rich material: Engineering grade material will be required for WSD and TMF embankment /
dam construction and for the TMF HDPE liner. It is anticipated that this material will be sourced
from local borrow areas within 2 km of construction activity.
Operation
As per Section 9.6, soil will be susceptible to erosion and sediment transport during operation, but to a lesser
extent than during construction.
During operation, soil will be susceptible to contamination from potential spills of hydrocarbons or other
hazardous materials which would compromise the soil quality and potentially groundwater / aquifers. The
number of facilities potentially susceptible to inadvertent discharge will increase during operation, including
the Process Plant / ROM pad, WRD, Mine Services Area, vehicle laydown areas, Power Station, etc. However,
less construction activity will minimise potential inputs from vehicle leakage and washing.
Closure / Decommissioning
Rehabilitation and closure activities for those facilities identified as ‘Temporary Impact – Rehabilitated to
Natural Ecosystem’ areas will comprise ripping of soil surfaces to remediate compaction, transport of a
suitable volume of subsoil and topsoil, and placement of subsoil / topsoil on components requiring
revegetation.
Minor wind erosion may occur during soil transport. Significant water erosion and sediment transport may
occur during the first few years following planting / seeding of rehabilitated areas. Subsequent losses of
subsoil are expected to abate following successful establishment of vegetation on exposed surfaces.
9.7.2 Avoidance, Mitigation and Management Measures
Avoidance
The Project has been designed to avoid the physical impacts to the natural landscape by reducing the Project
Footprint to the extent practicable.
Minimisation
Pollutant Contamination
The Project requirements for general waste and hazardous materials that may compromise the integrity of
soils in the PDA if improperly managed are detailed in Section 9.12 (General Waste and Hazardous Materials).
In summary, facilities where wastes will be generated, stored, and handled will have primary and secondary
containment (e.g. bunds and sumps for treatment), hazardous and non-hazardous waste have specific
storage, handling and disposal designations, and vehicles will have hydrocarbon spill kits readily available.
Training for spill prevention and clean-up will be specified in the Emergency and Preparedness Response Plans
(refer to ESMMP, Volume C), which will be developed by contractors / the Company prior to the onset of
construction activities.
Where contaminated soils are detected, the soils will be excavated and contaminates volatilised. Residual
material will be buried in a lined landfill.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-49
Minimising Area of Disturbance
Vegetation clearing area (Project Footprint) will be minimised to the extent practicable. Areas identified for
vegetation clearing and earthworks will be clearly demarcated prior to activities, and personnel informed of
the limits of clearing. All clearing and vegetation grubbing shall be conducted during the dry season and
erosion / sediment control facilities implemented prior to the onset of the rainy season.
Stockpile Erosion Control Measures
The following measures are recommended to reduce soil loss for topsoil and subsoil stockpiles:
Site stockpiles in suitable locations, including avoidance of natural drainages and steep slopes;
Divert upstream surface water drainage from stockpiles;
Avoid constructing steep stockpile batters;
Seed long-term stockpiles with native grasses to minimise losses from wind and water erosion; and
Implement silt fences or similar sediment control facilities on downhill side of stockpile areas.
Quarries
Suitable engineering earthworks material for WSD and TMF embankment construction from the Mine Pit
overburden or access road / Process Plant footprints will be utilised to the extent practicable. If these
potential sources cannot supply the required volume, or the material is not of suitable texture, borrow area(s)
and import of sand from outside the Project Footprint will be required.
The Project will utilise previously established borrow pits / quarries to the extent feasible to minimise impacts.
There are three pre-existing quarry sites within the mining lease. One has been used recently for the N7
highway upgrade. This quarry is ready for immediate use with a loading ramp and laydown area for
stockpiling crushed aggregate already available. Aggregate will be stockpiled at the quarry site and
progressively transferred to the work site over the following seven months, minimising Project impacts by
utilising a previously disturbed area.
Management and mitigation measures to minimise additional impacts (e.g. erosion and sedimentation, air
quality, noise, vibration) are provided in the respective sections of this chapter.
Rehabilitation / Decommissioning / Closure
Topsoil and subsoil handling for rehabilitation
Where topographical and soil conditions are appropriate, the top 0.5 metre of topsoil will be stripped from
various facilities’ footprints (e.g. Mine Pit and WRD) following clearing and grubbing of vegetation. Soil will be
excavated and loaded to dump trucks, for transfer to the long-term stockpile locations and subsequent use in
rehabilitation / revegetation activities.
Topsoil and subsoil will be stockpiled separately, with a register of volumes for each to ensure adequate
material is available of Project construction and rehabilitation activities.
Potential short-term stockpile locations should be identified as soon as possible, with some of the following
considerations:
Minimise transport distances;
Utilise planned road network; and
Utilisation of a moderately flat area, with no natural surface water drainages.
A survey for potential topsoil and subsoil stockpile areas is required to ensure capacity is in line with volume
requirements.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-50
The soil character of temporarily impacted areas will be rehabilitated to provide a medium for successful and
sustainable establishment of native vegetation. Greater detail regarding decommissioning / closure
strategies for temporarily impacted areas are provided in the Rehabilitation and Conceptual Mine Closure Plan (Volume E).
In summary, temporarily impacted areas will be rehabilitated via the following procedure:
Where applicable, the facility will be dismantled (and remediated if contaminated), and materials
transported to designated disposal facilities or provided to local communities / government as
needed;
The landform will be graded to match contours of adjacent landforms (with respect to drainage);
Surface soils will be ripped to approximately 1 metre depth to reduce compaction;
Where topsoil was removed during construction, topsoil will be placed and graded to contour to
approximately 0.3m depth (~1.5m depth for TMF) during the dry season;
Native vegetation of local provenance will be planted / seeded early in the rainy season to promote
stability of the landform (in addition to providing viable habitat); and
Planted / seeded areas will be monitored for relative success of plant establishment. Where plant
establishment does not meet Project Success Criteria (refer to Rehabilitation and Conceptual Mine Closure Plan), re-planting or seeding of areas will be conducted until Success Criteria are achieved.
9.7.3 Residual Impact Assessment
Site preparation activities (i.e. clearing of vegetation, earthworks, etc.) will provide substrate for erosion and
sedimentation. Management measures provided in Section 9.6 are expected to minimise erosion and
sedimentation, however some residual impacts during construction are anticipated.
The impacts of erosion and sediment transport will be largely mitigated during operation with the utilisation
of the TMF and event ponds / sediment basins to prevent discharge from Badalla Valley. Erosion of the
unsealed road network will be minimised, though not completely avoided, during operation. A low level of
downstream sedimentation / loss of soil from the PDA is anticipated.
The unsealed road network will remain an active source of low-level soil loss (erosion and sedimentation),
post-closure.
Compacted areas are expected to be mitigated upon closure, with Negligible residual impacts.
The key expected residual impacts related to soil management under normal operating conditions, and their
overall significance for each Project phase, are summarised in Table 9-14. Monitoring will be required over the
mine life to confirm the residual impact predictions, and allow management measures to be adapted
accordingly.
Table 9-14 Summary of key expected pre-mitigation impacts, mitigation measures and residual impacts on soils
for each Project phase
Receptor / Value
Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures Key Expected Residual Impacts and Overall Impact Significance
Pre-Construction / Construction
Erosion and loss of soil resource
MODERATE
Construct site stormwater and sedimentation
structures based of hydrological stream order moving
up stream
Develop soil removal mosaic patterns to reduce the
overall area of exposed soil
MINOR
Some elevation of suspended solids
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-51
Receptor / Value
Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures Key Expected Residual Impacts and Overall Impact Significance
Use silt fencing and bunding to retain stockpiled soils
Operation
Erosion and loss of soil resource
MODERATE
Site stockpiles in suitable locations, including
avoidance of natural drainages and steep slopes
Divert upstream surface water drainage from
stockpiles
Avoid constructing steep stockpile batters
Seed long-term stockpiles with native grasses to
minimise losses from wind and water erosion
Implement silt fences or similar sediment control
facilities on downhill side of stockpile areas
MINOR
Some elevation of suspended solids
Decommissioning / Closure
Erosion and loss of soil resource
MODERATE
Where applicable, the facility will be dismantled (and
remediated if contaminated), and materials
transported to designated disposal facilities or
provided to local communities / government as
needed
The landform graded to match contours of adjacent
landforms (with respect to drainage);
Surface soils ripped to approximately 1 metre depth to
reduce compaction
Where topsoil was removed during construction,
topsoil replaced and graded to contour to
approximately 0.3m depth (~1.5m depth for TMF)
during the dry season
Native vegetation of local provenance planted /
seeded early in the rainy season to promote stability
of the landform
Planted / seeded areas monitored for relative success
of plant establishment
MINOR
Some elevation of suspended solids
9.8 Air Quality
9.8.1 Issues and Findings
Air dispersion modelling was conducted to evaluate the extent of potential Project emissions from the mine
site. Full details of the modelling conducted are provided in the Air Quality, Noise and Vibration Baseline and Project Modelling report (Volume A, Appendix 4).
Due to the local topography surrounding the Mako Gold Project footprint, the CALPUFF model (Version 7.12)
was employed to simulate dispersion as it incorporates calculations to handle multi-level meteorology and
three-dimensional terrain features, and has been adopted by the U.S. Environmental Protection Agency (US
EPA) in its Guideline on Air Quality Models as the preferred model for assessing long range transport of
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-52
pollutants. NASA Space Shuttle Topography Model (SSTM3) radar data was included in the CALPUFF model
for terrain impacts, incorporating surface meteorology data recorded by MEC from the site meteorological
station, while prognostic 2012 meteorological data for the region was produced using the CSIRO TAPM v3
model (‘The Air Pollution Model’, CSIRO 2005). Key modelling outputs are presented in Figure 9-11.
Air quality simulations were compared against the standards for ambient air quality set out in the IFC/World
Bank Group’s Environmental, Health and Safety Guidelines (2007), which are based on the World Health
Organization (WHO) Air Quality Guidelines (2005). The WHO Guidelines consider the potential health impacts
associated with varying concentrations of airborne pollutants. Senegal has also issued a standard for
emissions to air and air quality Norme Sénégalaise NS 05-062 (“Pollution atmosphérique – Norme de rejets”).
Air pollutants such as fugitive dust emissions, measured as particulate matter of varying particle size (e.g.
PM10 and PM2.5); and emissions including carbon monoxide (CO), carbon dioxide (CO2), oxides of nitrogen
(NOx), sulfur dioxide (SO2), ozone (O3) and volatile organic compounds (VOCs) will be emitted during the
Construction and / or Operation Phases. A significant portion of the potential air quality impacts are
minimised via Project design. Project design elements for the Process Plant, Power Station, Mine Pit and WRD
(refer to Operation, Section 9.8.2) will reduce impacts to sensitive receptors to less than significant.
The primary potential air quality impacts likely to arise from the Mako Gold Project, if unmitigated, may
include:
Dust emissions from vehicular and equipment transport on unsealed roads and exposed soils,
particularly given the extensive dry season and Harmattan winds;
Exhaust emissions from fuel combustion in heavy vehicles and plant machinery, including the
generation of CO, SO2, NOx, particulate matter (PM10 and PM2.5) and VOCs; and
Combustion emissions from the Power Station for power generation during Project operation. The use
of diesel will produce emissions of CO, SO2, NOx and particulate matter (PM10 and PM2.5).
Pre-Construction / Construction
During the Pre-Construction / Construction Phase, there will be a number of Project-related emission sources
that may impact local air quality as summarised in Table 9-15
Table 9-15 Project-related air emission sources during the Construction Phase
Emissions source / Project activity Type Emissions intensity Duration / frequency
Fugitive dust emissions from road infrastructure associated with
construction vehicle and material movement on unpaved access
and haul roads within the Project Development Area
Fugitive Major Short-term / daily
Fugitive dust emissions from mechanical disturbance of soil
material associated with earthworks, site preparation, and land
clearing by graders and bulldozers
Fugitive Major Short-term / daily
Wind erosion from freshly exposed areas (e.g. unconsolidated
material stockpiles, topsoil removal, etc.) generating fugitive dust
Fugitive Moderate Short-term / daily
Combustion emissions1 from diesel powered vehicles and plant
machinery, including: particulate matter (PM10 and PM2.5), CO,
NOx, SO2, and VOCs
Fugitive Minor Short-term / daily
Smoke emissions from burning Project wastes comprised of
particulate matter (PM10 & PM2.5) and other air pollutants
Fugitive Moderate Short-term / once-off
Particulate emissions from concrete batching Point
source
Minor Short-term / continuous
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-53
1. The rates of vehicle and plant emissions and potential impact to surrounds would depend on the number, type and condition of
combustion engines used, fuel quality, and intensity of use.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-54
Figure 9-11 Comparison of predicted dispersion of unmitigated PM10 particulate concentrations from all Project
components for construction (top) and operation (bottom). Red contour represents WHO 24-hour criterion (50
micrograms/m3)
Land clearance and earthworks to allow construction of primary Project components will expose moderately
large surface areas to wind erosion / dust generation. Vegetation clearing; topsoil stripping, loading and
transport; earthworks; and topsoil stockpiles will generate dust in the Badalla catchment during the dry
season.
Significant dust emissions during Construction (from the perspective of social receptors) are expected to
result from utilisation of the current road network during the Construction Phase, construction of the Main
Access Road near its intersection with National Route 7, and upgrades to the existing road network.
Unmitigated fugitive dust emission from travel on the unsealed road network and construction / upgrades to
road infrastructure would likely be significant.
The magnitude of air quality impacts for the remainder of parameters listed from combustion of diesel fuel in
vehicles is expected to be relatively low during construction.
Construction Phase impacts to local air quality will be short term, localised and staged over a moderately
short period of time (approximately 20 months). Localised air quality impacts are expected to occur within
approximately 1 km of the construction areas and 200 m of unsealed roads (depending on weather
conditions).
Impacts from Quarry Use
During the Construction Phase, the Project will utilise an existing quarry which is located close to the N7 Road
and the Mine Access Road (the most northern quarry indicated on Figure 4-1). No blasting will be conducted
at the quarry. It is envisaged that a contractor with a portable crushing plant will be employed to produce the
required aggregate (6,500 t) during a day shift only operation over three to six months to produce the
required aggregate. It is expected that the production of aggregate will be a one-off activity which produces
the full Project requirements. Aggregate will be stockpiled at the quarry site and progressively transferred to
the work site.
During active use of this quarry, there is the potential for the extraction of rock and use of the portable
crushing plant to result in dust emissions, though gaseous combustion emissions (SO2, NOx and CO) are
expected to be minimal, associated with generators and vehicle emissions. Potential impacts associated with
dust emissions from quarries will be temporary, and restricted to a three to six month period during the
Construction Phase of the Project. The closest sensitive receptors to the quarry site are:
Road users of the RN7 (closest point of road located 300m from quarry)
Road users of Mine Access Road (closest point of road located 250 from quarry)
Negue Bako and Niemenike are the closest villages to the quarry (closest residences located approximately
2.5 km east of quarry boundary).
Modelling of potential dust emissions from the portable crushing plant used at the quarries was conducted
using the CALPUFF dispersion model to simulate particulates from the quarry. The model predictions
indicated that dust from the quarry will not significantly impact road users on the RN7, Mine Access Road nor
local villages, with predicted maximum concentrations from the single crusher at these receptors being
significantly below national and international particulate criteria. Dust impacts from the quarry are mostly
expected to occur within 200 m of source due to dust fallout, but could extended further in exceptional
conditions such as very high winds, temperature inversions, or very calm conditions where dust build-up can
occur.
Operation
Based on conservative modelling for dust emissions generated by Project activities, international (WHO Air
Quality Guidelines 2005) criteria for air quality may be exceeded in the PDA close to the sources, but are not
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-55
predicted to exceed international criteria at sensitive receptors (Figure 9-11). A more detailed air emissions
inventory is provided the Air Quality, Noise and Vibration Baseline and Project Modelling (Volume A,
Appendix 4).
Mining and processing activities will contribute particulate matter, PM10 and PM2.5 (i.e. the Process Plant,
Petowal Pit, TMF, WRD, ROM Pad stockpiles, and Project Access Roads). In addition, the Power Station will be a
source of stationary combustion emissions during the Operation Phase. Project emission sources are
summarised in Table 9-16 according to emission type, intensity and duration and frequency of emission.
Table 9-16 Project-related air emission sources during Project Operation
Emissions Source / Project Activity Type Emissions
Intensity
Duration /
Frequency
Fugitive dust emission sources from mining and processing activities
including:
Drilling and blasting within the Mine Pit;
Excavating and earthmoving;
Ore processing (crushing and screening), handling (loading,
unloading), conveying, and stockpiling;
Transporting and dumping ore and waste to the processing plant
and WRD on unsealed surfaces; and
Wind erosion from exposed areas (e.g. WRD, soil stockpiles,
ROM stockpiles, and potentially exposed dry tailings in the TMF)
Fugitive Major Ongoing / daily
Stack emissions of CO, SO2, NOx, particulate matter (PM10 and PM2.5) at
the Power Station from diesel combustion.
Point Moderate Continuous
stationary
source
Combustion emissions of CO, SO2, NOx, particulate matter (PM10 and
PM2.5) from mining and processing activities. Such activities include:
Blasting
Drilling with diesel-operated top hammer rigs
Excavating ore by shovels and excavators
Earthmoving ore and wastes using graders and bulldozers
Trucking ore and waste to the processing plant and WRD on
unsealed surfaces
Fugitive Moderate Ongoing / daily
Road fugitive dust emissions from vehicular traffic on unpaved roads,
particularly during dry season.
Fugitive Moderate Ongoing / daily
Combustion emissions of CO, SO2, NOx, particulate matter (PM10 and
PM2.5) from vehicular traffic.
Fugitive Minor Ongoing / daily
Typically, significant impacts would remain close to the ground, particularly in low wind conditions. However,
there will be certain meteorological conditions (i.e. high winds, dry conditions, calm conditions, temperature
inversions) that may lead to dust plumes of particulate matter exceeding applicable WHO and national
standard criteria for PM10 and PM2.5 without proper mitigation. In addition, larger particulates, which do not
pose a health impact, may deposit within a short distance of these sources and may potentially affect
vegetation health.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-56
Major air emission sources identified for each Project component are further discussed in more detail in the
following sub-sections.
Process Plant and ROM Pad
If unmitigated, significant fugitive dust emissions are anticipated from the following sources:
Ore crushing, screening and conveying (on potentially uncovered conveyors) within the three stage
crushing circuit of the Process Plant;
Loading quick lime into the silo storage facility;
Dumping and handling of ore at the ROM Pad and ROM bin; and
Stockpiling ore at the ROM Pad.
Mine Pit
If unmitigated, major fugitive dust sources from the Mine Pit are expected to include:
Excavators loading mined ore into dump trucks; and
Pit blasting to help remove overburden and access targeted ore.
Dust generated from the mining operation will be low in metals due to the geology of the deposit. Silica and
some fibrous minerals such as actinolite are present within the waste and ore material and may be present in
dust at levels that could potentially affect the health of workers if exposure is high.
Waste Rock Dump and TMF
The unloading of waste rock at the WRD and TMF disposal will provide a source for wind erosion from the
facilities which may result in fugitive dust emissions during dry and windy conditions, if unmitigated.
Diesel Power Station
Power during the Operation Phase will be supplied by a 16.2 MW Power Station, comprising of nine 1.8 MW
diesel generators Combustion emissions from this source will include CO, SO2, nitrogen dioxide (NO2), and
particulates (PM10 and PM2.5).
The use of diesel reduces emissions from the Power Station relative to an heavy fuel oil-powered facility by
approximately 30%, and the CALPUFF dispersion models predict that that positioning of the power station at
Badalla Valley also decreases ground-level concentrations of particulates (note that model is sensitive to
emission parameters). The CALPUFF dispersion models predict that assumed emissions of all target species
will not exceed international (WHO) or Senegalese ambient air criteria. However, short individual stacks,
typical of small generators, may produce enhanced ground-level concentrations of emitted pollutants close
to the sources due to reduced dispersion, ground-turbulence and building-wakes (within 200 m). Particulate
matter PM10 concentrations are predicted to fall sharply with distance (due to particulate drop-out) and
ground-level concentrations at receptor villages are predicted to be below 0.5 micrograms/m3.
High concentrations of baseline PM10 have been recorded in the Petowal region, thus cumulative
concentrations may exceed international particulate guidelines when any additional mine-related, processing
and transportation sources are considered.
Project Access Roads and Haul Roads
During Project operation, the use of unpaved road network for trucking mined ore from the Mine Pit to the
ROM Pad and waste rock from the pit to the WRD will create a fugitive dust source if not appropriately
mitigated.
Localised air quality impacts including an increase in ambient levels of fugitive dust and combustion exhaust
emissions will occur within 200 m of the haul roads.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-57
Air quality emissions associated with the use of the Main Access Road will include both exhaust
emissions and dust. This dispersal of dust emissions to areas surrounding the roads and their levels at
sensitive receptors will be dependent on factors such as the distance of the receptors from the road,
topography and prevailing wind conditions. Exhaust emissions are not expected to be significant.
Quarries
No air quality impacts from Project quarries are expected to occur in the Operations or Decommissioning /
Closure Phases, as no use of quarries will be required during these phases.
Decommissioning / Closure
Impacts on air quality during the Decommissioning / Closure phase are expected to be similar to those in the
Construction Phase. Dust and gaseous emissions during decommissioning/closure will primarily be
associated with the removal of site components by trucks, and rehabilitation of site. The ceasing of activities
such as blasting, mining of the pit, processing and Power Station will significantly reduce emissions to air,
relative to operation. Furthermore vegetative cover of open areas is anticipated to be advanced, providing
additional attenuation of fugitive dust to nearby receptors. Some additional temporary dust and vehicle
exhaust emissions associated with truck removal of major plant components and site clearance is anticipated
along the unsealed roads used by the Project.
9.8.2 Avoidance, Mitigation and Management Measures
Avoidance
A significant portion of the potential air quality impacts of the Project have been avoided via the Project
design. As summarised in Table 9-17 a number of specific components of the Project have been designed to
minimise air pollutant emissions.
Table 9-17 Project design measures adopted for managing air quality impacts
Project
Component
Specific Air Quality Abatement Measures Adopted
Power Station Selection of Power Station generators compliant with IFC Ambient Air Guidelines (2007)
Consideration of best industry practice emissions reduction technologies to reduce emissions from diesel
usage, such as:
» Use of low-sulfur/low-emission diesel fuel where available and compatible with generators
» Primary dry methods - low NOx combustion process including: late fuel injection start, high
compression ratio, optimised combustion chamber, optimised fuel injection rate, and suppressed
peak temperatures;
» Secondary methods for flue gas emissions reduction techniques, such as particulate traps, wet or
dry scrubber, electrostatic precipitator (ESP), cyclone or fabric filter (bag house).
» Selective catalytic reduction (SCR) process, which can be added to reduce NOx emissions by 80-
90% using an aqueous reagent of urea or ammonia (catalysts may not be compatible with high-
sulfur-content diesel fuel)
Process Plant
and ROM
Pad
Water sprays, dust collection and wet scrubbing systems to be installed in the crusher, screening circuit
and lime addition to minimise dust emissions from the process plant
Fugitive emissions within the processing area will be contained to the extent practicable by either:
» Enclosing or covering fugitive source emissions such as conveyors, hoppers, bins)
» Increasing and maintaining moisture content in ore-handling areas via water carts to minimise
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-58
Project
Component
Specific Air Quality Abatement Measures Adopted
windblown and traffic generated dust
» Employing air extraction and treatment through a baghouse or cyclone for material handling sources
Project
Access
Roads and
Loading
Areas
Consider sealing the Main Access Road with gravel
Consider using eco suppressants to reduce water use and frequency of application
Mine Pit Apply best practice blasting techniques to minimise dust and gaseous emissions
Waste Rock
Dump Progressively revegetate unused areas of waste rock
Minimisation
The following section outlines the proposed management measures to address air quality and dust impacts
and are generally consistent with those prescribed in the World Bank(WB)/IFC General EHS Guidelines 2007.
The Company will undertake the following management and mitigation measures to minimise potential air
quality impacts associated with earthworks, vehicular movement and exhaust emissions:
Vegetation and topsoil removal will be minimised to the extent practicable for Project construction;
Disturbed areas will be cleared and rehabilitated / revegetated as soon as practicable, thereby limiting
exposure of disturbed surface areas;
Primary dust generating activities will be avoided / mitigated during high winds (e.g. loading, hauling
and dumping of topsoil);
Open burning of waste and vegetation will be restricted or prohibited. It is anticipated that
authorisation will be required prior to burning, if conducted, to limit smoke generation;
Dust containment and suppression controls will be applied where necessary, i.e. during the dry season
and frequency of dust suppression / watering will increase during periods of high risk (e.g. dry and
windy conditions);
Air quality emissions for particulate matter will be monitored at existing dust monitoring stations in
the PDA and near sensitive receptors to evaluate the performance and adequacy of management and
mitigation measures;
Minimising worker exposure to dust through personal protection measures and monitoring the
exposure of workers to dust derived from waste and ore material; and
Village consultations will be undertaken regularly to qualitatively assess the impacts of dust
generation on sensitive receptors. This information will be utilised to improve dust suppression
techniques / frequency.
Additional controls for addressing specific air emission sources are summarised in Table 9-18.
Table 9-18 Air quality mitigation and management controls during Construction
Emissions
Source
Mitigation and Management Controls
Unsealed Mine
Access Road Apply gravel to the Mine Access Road surface if practicable.
Apply water or eco dust suppressants to all unsealed roads and trafficked areas, particularly near
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-59
Emissions
Source
Mitigation and Management Controls
Construction sensitive receptors.
Cover all loose loads on trucks to and from worksites. Securely fix tailgates of road transport trucks
prior to loading and immediately after unloading.
Regularly maintain the Mine Access Road
Implement a speed limit of 50km/hr
Unsealed Project
Access Roads and
Loading Areas
Apply suppressants / water to access roads and loading areas used during the dry season near
sensitive receptors.
Limit driving speed on unsealed access roads, particularly through villages, residences or
environmentally sensitive areas. Enforce a speed limit of 20 km/h through settlement areas.
Seal / apply gravel to all roads where feasible.
Regularly maintain unsealed access roads.
Stockpiles Minimise length of time that topsoil is stockpiled, where practicable.
Plant / revegetate long-term topsoil stockpiles (not used for more than three months).
Rib and roughen smooth surfaces to reduce wind velocity.
Locate stockpiles in areas naturally sheltered from wind, if feasible.
Restrict height of soil stockpiles to the extent practicable (given potential land area restrictions).
Vehicle exhaust
emissions Regularly maintain vehicles.
Prevent overloading of trucks.
Prohibit vehicles from queuing or idling and turn off engines when the vehicle is parked near
sensitive receptors.
Schedule vehicle deliveries to prevent congestion
Use low emission fuels (i.e. containing less than 0.5% sulfur) where available
Consider using low emission diesel engines and/or catalytic convertors for on-site vehicles, trucks,
excavators, etc.
Additional management and mitigation will be required during the Operation Phase to avoid or minimise
adverse impacts to air quality (refer to Table 9-19). Measures listed above for potential impacts during the
Construction Phase will also be employed (where appropriate) during Project operation.
Table 9-19 Additional air quality controls during Project Operation
Emissions
Source
Mitigation and Management Controls
Mining and
processing Disturb only the minimum area necessary for mining.
Locate transfer stations (dumping / loading) in areas sheltered from wind, where possible
Consider water spray systems via computer to site meteorological station, and only activate above
certain temperatures, wind speeds and wind directions to conserve water use, and control dust
suppression.
Drilling and Lower dust aprons during drilling.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-60
Emissions
Source
Mitigation and Management Controls
blasting
Equip drills with dust extraction cyclones or water injection systems.
Use water injection or dust suppression sprays prior to undertaking drilling or blasting when high
levels of dust are being generated.
Stockpiling Maintain water sprays or eco dust suppressants on stockpiles to reduce the risk of airborne dust.
Locate stockpiles in areas sheltered from wind.
Rib and roughen surfaces to increase surface wind friction
Revegetate or cover any unused or exposed areas with wood chippings or grass matting.
Regular maintenance of vehicles and machinery and use of low sulfur diesel and appropriate technologies
(e.g. low emission engines) and filters will help to reduce NOx and SOx emissions and therefore reduce local
air pollution. Excessively dry and dusty roads will be sprayed with water or, more preferably, eco suppressants
to conserve water use, in order to control airborne dust. Vehicle speeds will also be controlled on all access
roads.
Monitoring
Regular air quality monitoring will continue throughout the Project life to confirm the effectiveness of
mitigation measures. To ensure the level of air quality impact remains within acceptable standard levels, an
air quality monitoring plan should be developed for the Project, including:
Continuous monitoring of ambient air concentrations for PM10 and PM2.5, CO, NO2, NOx, and SO2 at
selected locations near the Petowal Mine Pit and villages;
Periodic (monthly) monitoring of dust deposition rates at selected locations near the Petowal Mine Pit
and villages; and
Meteorological monitoring, including temperature, humidity, rainfall, wind speeds and directions.
Rehabilitation / Decommissioning / Closure
Management and mitigation measures to minimise potential impacts during the Construction Phase will be
employed where appropriate during the Decommissioning / Closure phase.
Progressive rehabilitation and revegetation activities will reduce the area of exposed soil with potential to
generate dust emissions over the Project life. Detailed strategies are provided in Volume E, Rehabilitation and Conceptual Mine Closure Plan.
9.8.3 Residual Impact Assessment
During Construction, Negligible air quality impacts from Project works within the PDA for villages and other
sensitive receptors in the surrounding area are expected.
The use of the current unpaved village road network during the Construction Phase will generate significant
particulates if dust suppressant methods are not adopted during the dry season. Localised air quality impacts
are expected to occur within 200 m of unsealed roads (depending on weather conditions). During the dry
season, the villages of Mako and Linguekoto could experience Minor impacts from dust during the upgrade
of Mako-Tambanoumouya road, as their settlement areas are located directly along this road. These impacts
will be short term, localised and vary over time depending on the Project activities undertaken and the
success of the dust suppression measures employed, and will cease once the Main Access Road is completed.
With diligent application of prescribed management measures, dust impacts for other sensitive receptors in
the vicinity of the Project are expected to remain below relevant criteria during the Construction Phase.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-61
In the Operation Phase, there is the potential for Minor dust impacts on sensitive receptors to occur within
approximately 5 km of the PDA during the dry season. These impacts will primarily relate to fugitive dust
emissions from drilling and blasting within the Mine Pit, as well as excavating, earthmoving and processing
(crushers) etc. Combustion emissions from diesel vehicle exhausts, machinery and generators as well as the
operation of the Diesel Power Station may also contribute to Minor impacts.
No significant dust impacts on sensitive receptors are expected from the Main Access Road during the
Operation Phase as no such receptors occur within 200 m of the road. However, receptors and the level of
total impacts will depend greatly on wind direction and other weather conditions. The main recorded local
wind directions are from the East (E) during the dry season (Nov - May), which will reduce impacts on sensitive
receptors as the nearest villages are located to the South and South-East of the Project Footprint. However,
valley regions such as the Gambia and Wayako Valley, are also known to be prone to down-slope flow of cool
air, which can form "valley-winds" which may influence the dispersion of Project emissions, particularly at
night-time.
Negligible air quality impacts are expected to occur for sensitive receptors in the Decommissioning / Closure
Phase. If potential impacts are effectively mitigated, Project related emission sources will be minimised.
The results of air quality monitoring and ongoing village consultations should inform the Project of the
efficacy of dust suppression employed over the Project life. Careful consideration of the rate, timing and
frequency of dust suppression near receptors will be essential for avoiding Moderate or Major residual
impacts for local villages.
With diligent application of prescribed management measures, potential air quality impacts from the
remainder of Project-related emission sources are considered Minor and are expected to remain below
relevant criteria, including World Health Organization (WHO) Air Quality Guidelines 2005 and Norme
Sénégalaise NS 05-062, “Pollution atmosphérique – Norme de rejets.
The key expected residual impacts related to air quality under normal operating conditions, and their overall
significance for each Project phase, are summarised in Table 9-20. Monitoring will be required over the mine
life to confirm the residual impact predictions, and allow management measures to be adapted accordingly.
Table 9-20 Summary of key expected pre-mitigation impacts, mitigation measures and residual impacts on air
quality for each Project phase
Receptor / Value Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and Overall Impact Significance
Pre-Construction / Construction
Air Quality (for Mako and Linguekoto Villages)
MODERATE
The PDA will be enforced, ensuring public access is prohibited
Minimising the size of the Project Footprint
Vegetation and topsoil removal will be minimised to the extent practicable
Disturbed areas will be cleared and rehabilitated / revegetated as soon as practicable
Primary dust generating activities will be avoided/mitigated during high winds
Dust suppression will be used on access roads used during the dry season near sensitive receptors
Enforce a speed limit of 20 km/h
MINOR
Construction and upgrades of the Project Access Roads and utilisation of the current road infrastructure
Fugitive dust emissions from road infrastructure associated with construction vehicle and material movement on unpaved access roads.
Air Quality (for other sensitive receptors in vicinity of Project)
MINOR
NEGLIGIBLE
With diligent application of prescribed management measures, potential air quality impacts are expected to remain below relevant criteria
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-62
Receptor / Value Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and Overall Impact Significance
Pre-Construction / Construction
through settlement areas
Air quality monitoring.
Operation
Air Quality (for receptors within 5 km)
MODERATE
As per Pre-Construction / Construction Phase
MINOR
Fugitive dust emissions from drilling and blasting within the Mine Pit, as well as excavating, earthmoving and processing (crushers) etc.
Dust emissions from vehicular traffic on access roads
Combustion emissions from diesel vehicle exhausts, machinery and generators
Combustion emissions due to the operation of the Diesel Power Station
Volatile emissions from fuel storage
Air Quality (for receptors >5 km)
NEGLIGIBLE
NEGLIGIBLE
With diligent application of prescribed management measures, potential air quality impacts are expected to remain below relevant criteria
Decommissioning / Closure
Air Quality MINOR
As per Pre-Construction / Construction Phase
Restoration activities conducted in accordance with Rehabilitation and Conceptual Mine Closure Plan
Routine checks for compliance
NEGLIGIBLE
With diligent application of prescribed management measures, potential air quality impacts are expected to remain below relevant criteria
9.9 Noise
9.9.1 Issues and Findings
This section considers the potential noise impacts of the Project on the existing acoustic environment.
Details of proposed mitigation and management measures to minimise noise impacts are provided, with
further detail and monitoring strategies presented in the Air Quality, Noise and Vibration Baseline and Project Modelling report (Volume A, Appendix 4).
As the surrounding environment is largely undeveloped (albeit with surrounding villages and agricultural
activities), background noise levels are relatively low, though night-time ambient noise can be relatively high
due to natural insect and wildlife noise. The development of the Mako Gold Project will introduce new
sources of noise and will elevate noise emissions in the PDA and transport routes during the Construction,
Operation and Decommissioning / Closure Phases.
The primary sources of noise from the Mako Gold Project will include:
Transit of vehicles used for construction, transport and mining activities;
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-63
Construction activities, including pile drivers, excavators, dozers, etc. used for earthworks, levelling and
site preparation;
Blasting in the Mine Pit, quarries, and road construction areas;
Ore crushing and ongoing Process Plant operation; and
Power Station.
The significance of noise impacts to the local acoustic environment will depend on a range of factors
including topography, timing of activities conducted, duration of noise emissions, and weather conditions.
Potential noise impacts that may occur during each phase of the Mako Gold Project are assessed for
construction, operation and decommissioning / closure.
The assessment of noise impacts to the surrounding sensitive region was simulated using the Canadian dB
Foresight screening level model (Version 2.05, 2015). The dB Foresight model complies with the International
Standard ISO 9613-2, and considers the following parameters for the noise prediction analysis:
GPS location of each sound source in latitude and longitude;
Ground type (porous, mixed or hard);
Source elevations, height and directivity;
Source mid-band frequencies in Hz;
Physical size of the sources;
Receptor GPS locations, height and elevation;
Terrain;
Attenuation due to natural and man-made barriers;
Air temperature and relative humidity; and
Atmospheric absorption.
Noise attenuation in air is dependent on noise pitch, with low-frequency noise sources (such as blasting and
crushers), propagating farther. Noise propagation is also dependant on the temperature and humidity of the
air, with high temperatures and humidity allowing farther noise propagation. The atmospheric attenuation of
noise sources in dB/km was calculated in standard frequency bands as per ISO 266.
Maps of pre-mitigation modelled noise levels for the PDA and surrounds are presented in Figure 9-12 to
Figure 9-16.
Pre-Construction / Construction
The predominant noise sources during construction will include vehicles / earthmoving equipment, pile
drivers, tippers and backhoe, concrete trucks, and hydraulic excavators. Such emissions are likely to be
associated with the following construction activities:
Clearing, spoil removal, ground surface levelling and site preparation;
Excavation and earthworks;
Drilling and foundation installation;
Erection and commissioning of plant and infrastructure; and
On-site and off-site construction traffic.
Noise impacts from early site preparation and construction activities can vary widely depending on the type
of equipment used and noise produced while existing topography and vegetation provide natural shielding
that may decrease the noise impact from the Project.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-64
Construction Phase noise emissions from the PDA will be temporary (approximately 20 months), localised in
nature, and short-term. Based on the predicted noise levels, in the absence of mitigation Minor night-time
noise impacts from construction activities would be expected to occur for sensitive receptors such as villages
within approximately 5 km from the construction areas within the PDA. It should be noted that the ambient
night-time noise levels recorded in baseline noise surveys in the area are already generally close to that of the
conservative IFC night-time noise criterion 45dB(A), though construction noise may differ from the existing
noise regime.
Noise will occur as a result of construction and upgrades of the Project Access Roads and utilisation of the
current road infrastructure in the Project region. Use of the current road between Mako and Linguekoto for
access to the WSD will be short-term, as the majority of Project personnel will be housed within the PDA and
will utilise the Main Access Road upon its completion which does not pass directly through existing village
settlement areas.
Vehicular traffic on the haul route (National Route 7) will be a source of noise emission, but is not expected to
significantly change ambient conditions as background traffic on the RN7 is typically composed of heavy
vehicles (53%).
Operation
The primary noise impacts of the Project are expected to occur during operation, where blasting, mining and
processing activities as well as truck haulage will likely affect the local ambient acoustic environment. Project
activities with the potential to cause these adverse impacts on the acoustic environment during the
Operation Phase are described below.
Mining and Processing Operations
The principal noise sources for the mining, processing and materials handling activities will be from blasting,
drilling, (further discussed below), loading, hauling and crushing using heavy equipment, including
excavators, dozers, conveyors, haul trucks and diesel-operated top hammer rigs for waste and ore.
Noise emissions from the Mine Pit will vary depending on the amount of shielding provided by the pit walls.
Blasting
Blasting for ore extraction is expected to generate the most significant noise impacts that may exceed noise
standard criteria beyond the immediate mining area. The impact of periodic blasting to the surrounding
acoustic environment is expected to be significant but short-term.
As above, noise emissions from the Mine Pit will vary depending on the amount of shielding provided by the
pit walls. The modelling indicated that the blasting noise emissions were significantly lessened for sensitive
receptors when the existence of the pit was included in the models.
Based on the analyses conducted, blasting from the Petowal deposit may be perceptible at the following
sensitive receptors at the start of the Operation Phase (in the absence of noise attenuation from the pit):
Tambanoumouya (3.0 km from the Mine Pit);
Proposed Operation Accommodation Camp (3.0 km from the Mine Pit).
Kerekonko (4.0 km from the Mine Pit);
Chimpanzee Habitat Area (4.3 km from Mine Pit);
Linguekoto (4.5 km from the Mine Pit); and
Dalakoy (4.7 km from the Mine Pit).
Blasting will occur in the daytime, where human activity levels are high. The timing of blasting in the daytime
means that noise levels will not exceed IFC night-time criteria in villages and sensitive receptor areas. The
noise modelling indicated that, in the absence of mitigation, the peak noise levels at Tambanoumouya Village
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-65
will exceed IFC daytime criteria under worst-case atmospheric conditions at the start of the Operation Phase
(in the absence of attenuation from the pit). Daytime noise criteria are not expected to be exceeded at other
villages in the surrounding area pre-mitigation. Following development of the pit, noise levels are not
expected to exceed IFC daytime criteria at any of the sensitive receptors surrounding the PDA. At this stage
of the Project, noise from blasting is expected to only be perceptible for sensitive receptors nearby under
certain atmospheric conditions (inversion, down wind, very high temp/high humidity etc.).
Haul Roads and Mine Access Road
The factors that affect noise emissions from traffic include the volume of traffic, the speed of traffic and the
composition of traffic (number of heavy vehicles versus light vehicles). Generally, heavier traffic volumes,
higher speeds and a larger number of heavy vehicles results in more traffic noise. The dB Foresight screening
model was employed to estimate the traffic-related noise from the Main Access Road. This modelling
indicated that there is the potential for Minor noise impacts on Linguekoto and Tambanoumouya Villages
due to their location less than 1 km from the Main Access Road. Noise impacts from road use during Project
phases will vary depending on the prevailing meteorological conditions and surrounding topography.
Decommissioning / Closure
During the decommissioning/closure phase, the noise impact to the local acoustic environment is expected
to be similar to that generated during the Construction Phase associated with general construction activities.
The predominant sources are expected to be from noise emitting equipment such as combustion engines of
diesel generators, pumps, trucks, dozers, and hydraulic excavators for clearing the site.
Figure 9-12 Pre-mitigation predicted Construction Phase noise in Project Development Area – not including roads.
The units of contour values are dB(A)
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-66
Figure 9-13 Pre-mitigation predicted Operation Phase noise in Project Development Area (including blasting),
prior to pit development. The units of contour values are dB(A)
Figure 9-14 Pre-mitigation predicted Operation Phase noise in Project Development Area (including blasting),
after pit development. The units of contour values are dB(A)
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-67
Figure 9-15 Pre-mitigation predicted “Typical” Operation noise in Project Development Area (without blasting),
after pit development. The units of contour values are dB(A)
Figure 9-16 Pre-mitigation predicted Closure Phase noise in Project Development Area (after pit development).
The units of contour values are dB(A)
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-68
9.9.2 Avoidance, Mitigation and Management Measures
In accordance with the WB/IFC EHS Guidelines – Noise Management 2007, the following control hierarchy will
be adopted for noise mitigation and management, to the extent practicable:
Elimination of the noise source;
Substitution with quieter equipment/process;
Engineering noise controls at the source;
Treatment of the noise propagation path; and
Installation of noise mitigation controls at the receiver.
Avoidance
The Project has been designed to avoid noise impacts, to the extent practicable. The following design
components will significantly reduce potential impacts for sensitive receptors:
The construction of the Main Access Road to connect the Project to RN7, avoiding primary residential
zones, will minimise the impact of noise emissions associated with road traffic.
An exclusion zone (PDA) will prohibit establishment of new settlements near the Project to limit noise
impacts on residential areas;
High noise emission equipment and infrastructure are located as far as practicable from potential
sensitive receptors;
Appropriate technology, that minimises sound emissions have been selected, wherever possible; and
Additional technologies will be selected (refer to Operation, Section 9.9.2) to further mitigate potential
noise impacts.
Minimisation
The following measures will be adopted to avoid potential of nuisance level noise impact:
Major noise emitting site activities will be restricted to daytime hours when human activity levels are
higher;
Operational blasting is planned to occur at 4 pm, when human activity levels are higher and blasting
noise is expected to be less noticeable above background noise levels;
Heavy machinery / equipment and the vehicle fleet will be maintained regularly to ensure they are in
good working order; and
Hearing protection will be provided to Project personnel working in the vicinity of noisy construction
activities (i.e. those generating noise levels greater than 80 dB(A)).
For Project vehicular traffic, additional management measures will be implemented to minimise potential
noise impacts, including:
Heavy vehicles will be restricted to approved construction haul routes only and to daytime utilisation
(to the extent practicable);
Vehicle speed limits will be enforced through village / settlement and environmentally sensitive areas
along transport routes;
The use of air brakes in village / settlement areas will be prohibited; and
Road surfaces will be regularly maintained to minimise surface unevenness, particularly where they
pass through/near residential areas.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-69
During Project operation, measures employed during the Construction Phase will be continued where
appropriate. Additional management and mitigation measures to minimise potential nose impacts during
operation include:
Select equipment with lower sound power levels, whenever possible, in the Project design;
Apply noise reduction, sound insulation and absorption for different equipment and operation;
Ensure the impedance mufflers and vibration insulating base are installed on the air compressors,
blowers and induced fans;
Apply sound insulation covers/barriers where appropriate;
Install high noise equipment (such as crusher) in separate sound insulation areas;
Install silencers for fans;
Install suitable mufflers on engine exhausts and compressor components;
Install acoustic enclosures for equipment casing radiating noise;
Improve the acoustic performance of constructed buildings, apply sound insulation;
Limit the hours of operation for specific pieces of equipment or operation, especially mobile sources
operating through community areas;
Avoid blasting during unfavourable atmospheric conditions (e.g. low level inversions), where possible;
and
Reduce Project traffic through community areas wherever possible.
Refer to Section 9.11 for additional management measures to manage noise impacts from blasting practices.
Rehabilitation / Decommissioning / Closure
Noise impacts to the surrounding environment during Decommissioning / Closure are expected to be very
similar to the Construction Phase, thus the same proposed mitigation and management measures for
Construction are to be employed, where appropriate.
Progressive rehabilitation and revegetation activities will result in natural noise attenuation for sensitive
receptors over the Project life, and particularly during the Decommissioning / Closure Phase when most
revegetation activities will occur. Detailed strategies are provided in Volume E, Rehabilitation and Conceptual Mine Closure Plan.
9.9.3 Residual Impact Assessment
The measures integrated into the Project design will avoid and minimise construction and operational noise
impacts, to the extent practicable. The proposed avoidance, mitigation and management measures for the
Project are expected to be effective at reducing the residual noise impacts on the surrounding environment.
During the Construction Phase, Minor temporary noise impacts for some households directly along the road
in Mako and Linguekoto may occur during the upgrade of Mako-Tambanoumouya road. Utilisation of the
current road infrastructure, while the Main Access Road is constructed, could also result in Minor noise
impacts for these households. With diligent application of prescribed management measures, noise impacts
for other sensitive receptors in the vicinity of the Project are expected to remain below relevant criteria.
During the Operation Phase, if management and mitigation measures are effectively implemented there is
expected to be Negligible noise impact on sensitive receptors surrounding the PDA from Mine Pit blasting,
mining and processing activities. Noise from blasting will occur in the afternoon on days when blasting is
conducted. This noise is likely to be perceptible at most sensitive receptors within 5 km, but is not expected to
exceed daytime noise criteria or result in any significant nuisance noise impacts for local villages.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-70
There is the potential for Minor noise impacts for Linguekoto Village from truck/vehicle use along the Main
Access Road. This village is located approximately 700 m from the closest point of the road. While the Project
traffic volume on the Main Access Road will be greatly reduced in the Decommissioning / Closure Phase,
some Minor impacts from passing vehicles may continue to occur for Linguekoto. Noise impacts during
Project phases at all receptors will vary depending on the prevailing meteorological conditions and
surrounding topography. Four other villages (Tambanoumouya, Wassadou, Dalakoy and Kerekonko) are
located within 1.5 km of the Main Access Road. Monitoring will therefore be required at these villages to
determine if noise impacts occur, and adapt management measures accordingly.
Negligible noise impacts are expected to occur for other sensitive receptors in the broader area surrounding
the Project during the Operation and Decommissioning / Closure Phases.
The key expected residual impacts related to noise under normal operating conditions, and their overall
significance for each Project phase, are summarised in Table 9-21. Monitoring will be required over the mine
life to confirm the residual impact predictions, and allow management measures to be adapted accordingly.
Table 9-21 Summary of key expected pre-mitigation impacts, mitigation measures and residual impacts related to
noise for each Project phase
Receptor / Value Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and Overall Impact Significance
Pre-Construction / Construction
Noise (for Mako and Linguekoto Villages)
MODERATE
The PDA will be enforced, ensuring public access is prohibited
Major noise emitting site construction activities will be restricted to daytime hours when human activity levels are higher
Heavy vehicles will be restricted to approved construction haul routes only and to daytime utilisation (to the extent practicable)
Vehicle speed limits will be enforced through village / settlement and environmentally sensitive areas along transport routes
Road surfaces will be regularly maintained
Noise monitoring.
MINOR
Construction and upgrades of the Project Access Roads and utilisation of the current road infrastructure
Construction Phase noise emissions will be temporary (approximately 18 months), localised in nature, and short-term.
Noise (for other sensitive receptors within 5 km)
MINOR
NEGLIGIBLE
With diligent application of prescribed management measures, potential daytime noise impacts are expected to remain below relevant criteria
Operation
Noise (Linguekoto Village)
MODERATE
As per Pre-Construction / Construction Phase
Noise monitoring
MINOR
Potential for Minor noise impacts from vehicle use on Main Access Road
Noise from blasting is likely to be perceptible, but is not expected to exceed daytime noise criteria or result in any significant nuisance noise impacts
Noise (other sensitive receptors within 5 km)
MINOR
NEGLIGIBLE
With diligent application of prescribed management measures, potential noise impacts are expected to remain below relevant criteria
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-71
Receptor / Value Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and Overall Impact Significance
Pre-Construction / Construction
Noise from blasting is likely to be perceptible, but is not expected to result in any significant nuisance noise impacts
Decommissioning / Closure
Noise (Linguekoto Village)
MODERATE As per Pre-Construction / Construction Phase
Revegetation activities conducted in accordance with Rehabilitation and Conceptual Mine Closure Plan
Routine checks for compliance
MINOR
Potential for Minor noise impacts from occasional vehicle use on Main Access Road
Noise (other sensitive receptors)
NEGLIGIBLE
NEGLIGIBLE
With diligent application of prescribed management measures, potential daytime noise impacts are expected to remain below relevant criteria
9.10 Vibration and Airblast
9.10.1 Issues and Findings
Anticipated vibration levels for airblast and ground vibration from blasting in the Mine Pit were calculated for
the applicable social receptors (local villages and workforce accommodation). Details are provided in the Air Quality, Noise and Vibration Baseline and Project Modelling report (Volume A, Appendix 4).
The impacts from continuous or impulse vibration may be a nuisance for local residents of the region /
additional biological receptors and in extreme cases can compromise the structural integrity of structures.
Both ground-borne and air-borne vibrations will be generated from Project activities during construction,
operation and decommissioning. These will primarily be emitted from:
Heavy vehicle traffic (which varies with speed and surface evenness);
Construction activities (e.g. grading, excavating); and
Blasting in the Mine Pit, quarries, or for road construction.
Vibration impacts to the surrounding physical area are expected to be predominantly short-term and
localised to the construction work areas and the mining and processing area. Potential impacts, if realised, are
expected to be nuisance level for a short duration, associated with blasting activities.
There are no applicable international guidelines or national standards applicable to the Mako Gold Project for
vibration from blasting, nor international guidelines for human comfort level. The Australian Standard
AS2187.2 provides guidelines for blast-induced vibration effects (AS 2187.2 App J, 2006) based on the US
Bureau of Mines USBM RI-8507 and British Standard BS 7385-2 and provides guidelines for assessing airblast
and vibration, including consideration of nuisance level impacts and management. The ESMMP (Volume C)
provides recommendations for Project adoption of appropriate guidelines for vibration.
Pre-Construction / Construction
Mine infrastructure
Ground vibration during construction of mine infrastructure will be localised and the potential impacts are
considered Negligible for the closest receptors. Ground vibration due to pit blasting at Petowal was
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-72
calculated to be imperceptible in the nearest residential areas therefore potential impacts are considered
Negligible.
Transport infrastructure
During road construction and upgrade, nuisance level vibration impacts may occur in areas directly adjacent
the road. A vibratory roller creates typical Peak Particle Velocity (PPV) as follows;
2.4 mm/s at 10 m;
1.2 mm/s at 20 m; and
0.8 mm/s at 30 m from the road.
While this is likely to result in localised vibration impact, this will be temporary and may produce short-term
nuisance level impacts. Vehicle traffic can also result in vibration impacts. The factors that affect vibration
levels from traffic include the composition (heavy vehicle to light vehicle), volume and speed of traffic, road
surface condition and the transmission path (distance, topography between the source and the receiver).
While traffic-related vibration is unlikely to result in structural damage, it may create nuisance impacts.
Vehicle traffic induces vibration in two ways (Hajek et al. 2006):
Ground-borne vibration – caused by the dynamic impact forces of tyres on the pavement or other
surface that can propagate and excite building foundations, resulting in vibrations of building
components; and
Air-borne vibration – caused by low frequency sounds produced by engines and exhaust systems
(primarily associated with large diesel trucks) that can excite building components above ground.
Both types of vibration can be caused by the same vehicle at the same time. The generation of ground-borne
vibration is strongly linked to surface evenness – the more uneven the surface, the greater the ground-
vibration. Heavier vehicles typically produce higher ground-borne and air-borne vibration, and an increase in
the number of heavy vehicles tends to result in more vibration peaks, but not necessarily higher peaks.
Higher speeds increase both ground-borne and air-borne vibrations.
The Peak Particle Velocity or PPV for vehicle traffic can be estimated using a standard curve. For a passing
heavy vehicle (such as those which frequently travel on National Road 7), this curve indicates PPVs of
approximately;
2 mm/s at 5 metres from the road;
1.5 mm/s at 10 metres from the road;
1 mm/s at 15 metres from the road, and
0.2 mm/s at 45 metres from the road
Implementation of management measures for minimising traffic vibration will minimise the overall impact of
vibration from traffic. While uncertainty remains regarding residual vibration impacts from Project vehicles,
the assessment indicates that traffic vibration may be at nuisance levels (using the NSW Vibration Criteria for
residential areas at night) potentially up to 50 m from the Main Access Road and National Route 7.
This is likely an overestimate of expected impacts associated with the Project as this curve is based on
maximum recorded vibrations along a busy highway in the United States. These levels are not considered
sufficient to cause structural damage in the PDA or neighbouring communities.
Operation
During operation, the primary sources of Project related vibration will include:
Blasting in the Mine Pit;
Ore crushing at the ROM Pad; and
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-73
Vehicular traffic.
Blasting during Project operation for ore extraction in the Mine Pit will generate the most vibration impacts,
including airblast and ground vibration. Blasting is an ‘impulsive’ vibration source characterised by a
succession of brief vibration periods that can significantly exceed the background level. The use of explosives
creates airborne pressure fluctuations (airblast) which are audible and can be perceived as ‘noise’ when in the
higher frequency range. At frequencies lower than approximately 20 Hertz, the sound energy is inaudible but
is capable of causing air vibration impacts.
The airblast levels from a blast received at a given location depends on many factors, including:
Charge mass;
Stemming height and type of stemming;
Burden;
Blast hole spacing, blast initiation sequence and timing delay between holes;
Ratio of the blast hole diameter to the burden;
Face height and orientation of face;
Topographic shielding;
Distance from the blast; and
Meteorological conditions.
Airblast vibration impacts were predicted using equations supplied by the US Department of Mines. Given
the distance between Mine Pit, construction area and current residential areas, air vibrations are not likely to
exceed the recommended maximum limit of 120 dB(L) - decibels linear. Airblasts may potentially startle
livestock and wildlife, or rattle windows, and sensitive species may move away from PDA. If managed
appropriately, there are not likely to be any significant impacts from airblast on the residents or structures
within nearby villages.
Ground vibrations as a result of blasting were calculated via an equation provided by the US Dept. of Mines.
According to this equation, ground vibration would be less than 0.1 mm/s beyond 1 km of the Mine Pit. Given
the distance between Mine Pit and current residential areas, ground vibrations as a result of blasting are not
likely to represent any significant impacts to the residents or structures in nearby villages.
Note however that the adopted human comfort level criterion (0.56 mm/s) is estimated to be exceeded
within 500 metres of the blast site, and that the building damage criterion (10 mm/s) is predicted to be
exceeded within approximately 50 metres of the blast site and thus should be considered an exclusion zone
for any site structures. Likewise the 50 metre radius would potentially represent a ground-vibration zone for
unstable rocks and vegetation.
Project related vehicular traffic will continue during operation, but will be confined to the Main Access Road,
WSD Access Road, and auxiliary roads between the Mine Pit, ROM Pad, WSD, Mine Services Area, etc. The
Mako-Tambanoumouya access road parallel to the Gambia (passing through Mako Camp as well as Mako and
Linguekoto Villages) is not expected to be utilised for Project activities during operation. General Project
traffic will not pass close to local villages along the Mako-Tambanoumouya access road, therefore associated
vibration impacts will not occur. Haul trucks may pass individual homes and villages on National Road 7
Traffic vibrations may be an issue up to an maximum distance of 50 m from the road, but would represent
only small percentage of daily vehicular traffic on RN7, and the additional impacts of the Project to existing
vibration levels are likely to be Negligible.
Decommissioning / Closure
During the Decommissioning / Closure Phase, vibration impacts are expected to be Minor and Negligible
outside the immediate work areas. Vibration emissions during decommissioning/closure will primarily be
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-74
associated with trucks and heavy vehicles used for decommissioning and removal of site components, and
rehabilitation of the site.
9.10.2 Avoidance, Mitigation and Management Measures
Avoidance
Project facilities are located at a sufficient distance from local residential areas to avoid potential vibration
impacts from all but airblast vibration from the Mine Pit. The following design components will significantly
reduce potential impacts for sensitive receptors:
The construction of the Main Access Road to connect the Project to RN7, avoiding primary residential
zones, will minimise the impact of vibration emissions associated with road traffic.
An exclusion zone (PDA) will prohibit establishment of new settlements near the Project to limit
vibration impacts on residential areas;
High vibration emission equipment and infrastructure are located as far as practicable from potential
sensitive receptors; and
Appropriate technology that minimises vibration emissions have been selected, wherever possible.
Minimisation
Potential impacts from construction related vibration will be minimised by:
Enforcing speed limits through residential areas;
Ensuring the road infrastructure surface is regularly maintained (particularly through residential areas);
and
Enforcing blast management measures (provided above for the Operation Phase work).
For blasting, the following measures are proposed for managing ground vibrations and air pressure overblast:
Ensure no explosive charge per blast hole exceeds the estimated maximum charge weight per delay;
Detonate only one charge per delay;
Check that the charge is able to break and displace its burden with reasonable ease;
Verify that burden distances are not too small;
Ensure premature ejection of stemming columns does not occur;
Place inter-row delays long enough to give good progressive relief of burden;
Detonate cord trunklines to fire pre-split blasts and ensure these trunklines have a core load of only 5
g/m ad are covered by at least 250 mm of sand or fine screenings; and
Review any reported structural damage from blasting activities.
The Project will undertake regular village consultations over the mine life. A qualitative assessment of
vibration impacts (nuisance level or structural damage) will be conducted via logging complaints as per the
Project Grievance Procedure (refer to ESMMP, Volume C). Such complaints will be reviewed and additional
management measures adopted, where required.
Rehabilitation / Decommissioning / Closure
Management for the anticipated vibration levels generated during decommissioning activities will not
require additional management measures.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-75
9.10.3 Residual Impact Assessment
During the Construction Phase, Minor temporary ground vibration impacts for some residences located
directly adjacent to the road in Mako and Linguekoto Villages may occur during the upgrade of Mako-
Tambanoumouya Road. Utilisation of the current road infrastructure while the Main Access Road is
constructed could also result in Minor vibration impacts for these houses.
With appropriate mitigation, there should be only Minor nuisance level impacts associated with airblast from
Mine Pit blasting within approximately 3km, and Negligible impact for receptors beyond this distance. This
impact will progressively decrease as the pit develops, as the pit walls will provide some natural attenuation.
With effective blast management, overall vibration impacts are considered Negligible during Operation.
Negligible vibration impacts are expected to occur for sensitive receptors in the Decommissioning / Closure
Phase, as no blasting will be required and the Mako-Tambanoumouya Road will not be used by Project
vehicles.
The key expected residual impacts related to vibration and airblast under normal operating conditions, and
their overall significance for each Project phase, are summarised in Table 9-22. Monitoring will be required
over the mine life to confirm the residual impact predictions, and allow management measures to be adapted
accordingly.
Table 9-22 Summary of key expected pre-mitigation impacts, mitigation measures and residual impacts related to
vibration and airblast for each Project phase
Receptor / Value
Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and Overall Impact Significance
Pre-Construction / Construction
Vibration and Airblast
(Mako and Linguekoto Villages)
MINOR
The PDA will be enforced, ensuring public access is prohibited
Enforcing speed limits through residential areas
Ensuring the road infrastructure surface is regularly maintained (particularly through residential areas)
Regular village consultation and implementation of Project Grievance Procedure
MINOR
Vibration impacts mostly restricted to the immediate work areas
Minor temporary ground vibration impacts for some residences directly along the road in Mako and Linguekoto may occur during upgrade of Mako-Tambanoumouya road
Utilisation of the current road infrastructure while the Main Access Road is constructed could result in Minor impacts for villages along the Mako-Tambanoumouya road
Vibration and Airblast
(other Project-affected villages)
NEGLIGIBLE
NEGLIGIBLE
Vibration impacts will be Negligible
Negligible impact expected at sensitive receptors
Operation
Vibration and Airblast
(at villages within 3 km)
MODERATE As per Pre-Construction / Construction Phase
For blasting, implement measures for managing ground vibrations and air pressure overblast
MINOR
Airblast vibration from Mine Pit / quarrying blasting is expected to result in Minor nuisance impacts for closest villages. This impact will progressively decrease as the pit develops.
Vibration and Airblast
(other Project-affected villages)
MINOR NEGLIGIBLE
Vibration impacts will be Negligible
Decommissioning / Closure
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-76
Receptor / Value
Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and Overall Impact Significance
Pre-Construction / Construction
Vibration and Airblast
NEGLIGIBLE As per Pre-Construction /
Construction Phase
NEGLIGIBLE
Vibration impacts restricted to the immediate work areas
Negligible impact expected at sensitive receptors
9.11 Flyrock
9.11.1 Issues and Findings
Blasting of ore and rock during the mining process can generate flyrock, rock fragments that may be
propelled through the areas surrounding the blast area, comprising a safety hazard people in proximity to
blasting.
The Company will develop a Blast Management Plan prior to construction that further specifies contractor
requirements. Implementation of the PDA and prohibition from entry to the PDA prior to blasting is
expected to reduce the potential safety hazard associated with flyrock to Negligible.
9.11.2 Avoidance, Mitigation and Management Measures
Avoidance
Blasting may be required for the construction of the access roads within the PDA. Blasting will not be
conducted within 500 m of residential areas. A temporary exclusion zone will be enforced surrounding any
site where blasting will occur. As per the Operation Phase blasting (refer to below), a communication protocol
will be established whereby neighbouring villagers will be informed of the timing of upcoming blasting. The
500 m (radius from the blast site) exclusion zone will be surveyed prior to blasting, and access roads blocked.
A sounding horn will be activated prior to the blast at an agreed-upon interval (in consultation with local
communities).
The following will be considered in selecting the blast contractor:
A licensed and competent blast contractor will be selected that has sound reputation and track record
with respect to blast practices;
Proposed blasting practices will be consistent with industry standards; and
Contractor’s staff are trained and competent and all systems and procedures are strictly followed.
Minimisation
The PDA will be enforced, ensuring access is prohibited (to all but applicable Project personnel) from an
exclusion zone of at least 500 m around the pit to protect people and structures from flyrock. Security
personnel will be employed at key Project access points (road infrastructure) to prohibit access via the most
obvious routes.
Additional measures to minimise potential flyrock impacts during Project operation include:
Blasting will occur only during established daytime hours (e.g. between 7 am to 6 pm);
Blasting will be conducted in favourable weather conditions;
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-77
Blast area exclusion zones will be surveyed prior to blasting to ensure unauthorised people are not
within the potential risk area;
A procedure will be developed for informing villagers / Project personnel of the blasting schedule,
including: signage in villages with blasting dates / times or notification of blasting schedule at least 24
hours in advance of activity, and utilisation of a sounding horn that will warn people in the region of an
impending blast (e.g. sounded 15 minutes in advance of blasting and 5 minutes in advance of blasting)
(refer to ESMMP, Volume C);
Blast pattern designs and powder factors will be evaluated to ensure they are sufficient to provide the
required fragmentation while minimising the potential to cause damage to pit walls and infrastructure;
Flyrock will be visually monitored to confirm that the exclusion zone is sufficient to protect sensitive
receptors (biological and social);
Regularly employ blasting experts to provide audits and advice on general and specific blasting issues;
and
Train Project staff on fly rock safety and conduct a public education program regarding community
safety issues associated with blasting.
The above controls should be considered for inclusion in a Blast Management Plan. This Plan would provide
the detailed management and communication procedures to be employed prior to any blasting to avoid
potential flyrock impacts.
Rehabilitation / Decommissioning / Closure
No blasting is required during Decommissioning/Closure, therefore management measures are not required
for this phase.
9.11.3 Residual Impact Assessment
With strict adherence to flyrock management and mitigation measures detailed above, the expected risks will
be minimised to within acceptable limits.
The key expected residual impacts related to flyrock under normal operating conditions, and their overall
significance for each Project phase, are summarised in Table 9-23. Monitoring will be required over the mine
life to confirm the residual impact predictions, and allow management measures to be adapted accordingly.
Table 9-23 Summary of key expected pre-mitigation impacts, mitigation measures and residual impacts related to
flyrock for each Project phase
Receptor / Value
Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and Overall Impact Significance
Pre-Construction / Construction
Flyrock MINOR
Preparation of Blast Management Plan
The PDA will be enforced, ensuring access is prohibited
Blasting will occur only during established daytime hours
Blasting will be conducted in favourable weather conditions
Blast area exclusion zones will be surveyed prior to blasting to ensure unauthorised people are not within the potential risk area
Flyrock monitoring
NEGLIGIBLE
Management and mitigation measures implemented are expected to reduce the potential safety hazard associated with flyrock to Negligible
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-78
Operation
Flyrock MINOR
As per Pre-Construction / Construction Phase
A procedure will be developed for informing villagers / Project personnel of the blasting schedule
A sounding horn will be activated prior to the blast at an agreed-upon interval (in consultation with local communities)
NEGLIGIBLE
No blasting expected outside of PDA
Prohibition from entry to the PDA prior to blasting is expected to reduce the potential safety hazard associated with flyrock to Negligible
Decommissioning / Closure
Flyrock NEGLIGIBLE None required NEGLIGIBLE
No blasting expected to be required
9.12 General Waste and Hazardous Materials
9.12.1 Issues and Findings
Construction, operation and decommissioning / closure of the Project will require or generate hazardous and
non-hazardous materials. The Project has been designed to specifically address potential risks associated
with hazardous / non-hazardous materials during transport, storage, handling and disposal.
Waste
Potentially hazardous materials that will be stored and handled on site include:
Cyanide (1 tonne bulk bags);
Cyanide reagent packaging (wood and plywood bulk-boxes, < 100 kg/week)
Additional Process Plant reagents (refer to below);
Oils, solvents, and other hydrocarbons (diesel);
Truck wash sludge (<10 m3 per week);
Waste oil (approximately 1,000L/week);
Medical waste including sharps, bandages, etc.; and
Sewage and greywater from kitchens and toilets (refer to Section 9.6).
Non-mining (general non-hazardous) waste materials will be generated via Project construction activities,
administration, procurement and general comp maintenance and operation, including:
Non-toxic solid reagent polypropylene or similar packaging (< 100 kg/week) and grinding media
packaging (200 L steel drums, 50 per week);
Construction material excess (various, approximately 10 tonnes per day), scrap timber (< 2m3 per week),
scrap metals (< 2m3 per week);
Domestic waste (e.g. bottles, cans, plastics,< 2m3 per week);
Putrescible waste (e.g. kitchen waste and food scraps, 250 kg per day);
Liquid reagent packaging (200L plastic drums, 20 per week);
Office waste (e.g. paper, etc., 250 kg per day); and
Other domestic waste (< m3 per week).
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-79
Non-hazardous waste will be handled and disposed of accordingly:
Office waste (~250 kg per week of paper, etc.) will be disposed of in the lined landfill;
Other domestic waste (bottles, cans, plastics (<2 m3 per day), scrap timber (<2 m3 per day), and scrap
metals (<2 m3 per day) will be recycled, with the remainder disposed of in the lined landfill;
Non-toxic solid reagent packaging (< 100 kg per week) will be disposed of in the lined landfill;
200 L steel drums from grinding media packaging (50 per week) will be recycled;
200 L plastic drums (20 per week) will be recycled if possible or disposed of in the lined landfill; and
Cyanide reagent packaging (< 1,000 kg per week of wood and plywood bulk-boxes) will be burned,
with disposal of ash transported to the lined landfill.
Table 9-24 provides an overview of the various types of waste expected to be generated through the Project
activities as well as the preferred method of disposal for each waste stream. The Project will not generate any
radioactive waste.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-80
Table 9-24 Summary of major waste streams
Waste Stream Nature Quantity Method of Disposal in
Order of Preference
LIQUID WASTE
Mine services area
waste water
Truck wash water <50 m3/day Used for dust suppression
on haul roads
Truck wash sludge Hydrocarbon contaminated
sludge from truck wash
sump
<10 m3/week Hydrocarbons to be
returned with recycled oil
products to supplier
Solids disposed of in WRD
or TMF
All water to be directed to
TMF for treatment
Sewage treatment
plant (STP) sludge
Surplus activated sludge
from all sewage treatment
plants
<50 kg/d Direct landfill burial
STP treated water:
accommodation camp
Treated water from camp
sewage treatment plant
50-100 m3/d Leach drains
STP treated water:
plant site and mine
services area
Treated water from plant site
sewage treatment plant
50-100 m3/d Disposal to TMF and
recovered for use as
process water
Waste oil Used lubricating oil etc 1,000 L/week Recycle
SOLID WASTE
Putrescible waste Kitchen waste and food
scraps etc
250 kg/day Landfill
Office waste Paper etc 250 kg/week Landfill
Other domestic waste Bottles, cans, plastics <2 m3/day Recycle
Balance to landfill
Construction waste Various categories 10 t/day Sorted in accordance with
types below and disposed
of in a similar manner
Inert concrete waste Decommissioning of built
infrastructure
6000 m3 Disposal to WRD
Scrap timber Packaging, scrap pallets, off
cuts etc.
<2 m3/week Recycle
Landfill
Scrap metals Scrap equipment and parts,
steel off cuts etc.
<2 m3/week Recycle
Landfill
Non-toxic solid
reagent packaging
Polypropylene or similar
bags
<100 kg/week Landfill
Grinding media
packaging
200L steel drums 50/week Recycle
Liquid reagent
packaging
200L plastic drums 20/week Recycle
Landfill
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-81
Waste Stream Nature Quantity Method of Disposal in
Order of Preference
Cyanide reagent
packaging
Wood and plywood bulk-
boxes
<1,000 kg/week Incineration and dispose of
ashes to landfill
Contaminated soil Contaminated with
chemicals and / or oil spills
<1 m3/week average Disposal to TMF
Volatilise contaminants
then burial in lined landfill
Table 9-25 shows the principal waste disposal routes for different materials.
Table 9-25 Waste disposal routes
Waste classification Example Disposal route
Hazardous - Medical/ biohazard Clinical waste Incineration
Hazardous – high risk Oil filters, waste oily rags Removal of recyclable parts where possible, then incineration. Ash/scrap to lined landfill pit. More detail is provided in the ESMMP
Hazardous – low risk Non-compostable food wastes Lined landfill pit within PDA
Hazardous – low risk Non-recyclable domestic waste and recyclables, including empty bottles, cans, and plastics
Disposed of in off-site landfill pits or recycled wherever possible
Non-hazardous Non-recyclable domestic waste and recyclables, including empty bottles, cans, and plastics
Unlined landfill pit where not recycled or composted
Hazardous Materials and Waste
Sewage Treatment Plant
A Sewage Treatment Plant will be used to treat both waste water and raw sewage from various sources,
including toilets, showers, basins and kitchen facilities.
Both plant and accommodation sites will use a Biological / Aeration based treatment system incorporating
chlorine sterilisation before discharge. Plant water will be disposed of via the tails hopper to the TMF. Camp
water will be disposed of via leach drains. Solids will be disposed of via solar drying and burial in lined landfill,
or sewage truck.
Hazardous Materials
Cyanide
Cyanide may be released to the receiving environment (in gaseous or liquid form) during: transport to the
mine, storage or handling, processing, piping to the TMF, and / or from TMF supernatant water. The potentially
deleterious impacts of cyanide releases (in variable form) are well documented. Potential impacts to aquatic
and terrestrial biology are discussed in the Biological Impacts chapter (Chapter 10) and to human health in
the Social Impacts chapter (Chapter 11).
The toxicity of cyanide depends on the form of cyanide present, ranging from the highly toxic ‘free cyanide’
(CN+HCN) to non-toxic or less-toxic stable strong complexes. The most relevant forms of cyanide with
respect to Project operation may include:
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-82
Hydrogen cyanide (HCN) in gaseous phase, which may result from volatilisation of sodium cyanide at
low pH. HCN is a dangerous gas in a closed system such as the Process Plant. When mixed with water,
sodium cyanide will volatilise at pH < 11;
Free cyanide, potentially derived from dissolution of iron-cyanide complexes that decompose in the
presence of sunlight (releasing free cyanide) in the TMF reservoir;
Weak acid dissociable cyanide (WAD cyanide), ionic complexes of varying stability comprised of
cyanide and one of a number of metals. Various WAD cyanide complexes are relatively unstable (e.g.
copper and zinc) and may release cyanide back to the environment; and
Potential bi-products of cyanide destruction (e.g. Cyanate and Thiocyanate) in the slurry gravitated
from the cyanide destruction circuit (in piping and TMF supernatant water).
Additional sources of potential cyanide release to the environment include: an accidental release during
transport storage and handling; spill or leakage of cyanide solution during preparation and handling; and/or
during piping of slurry to the TMF, posing a threat to water quality and air quality along the transport corridor
and storage complex. Packaging material for NaCn may also be a source.
Reagents
Process Plant reagents (sodium hydroxide, hydrochloric acid, copper sulphate, sodium metabisulphite, leach
aid, calcium carbonate, activated carbon, and flocculent) and their packaging materials are a potential threat
to surface and groundwater quality if released to receiving waters (refer to Section 9.8) and in some cases
may impact air quality if ignited (refer to Section 9.13).
Hydrocarbons
Diesel fuel will be utilised for vehicles / equipment / processing and for the Power Station. Accidental release
of hydrocarbons would potentially impact receiving waters (ground and surface water) and soil substrate.
Hydrocarbons are also a fire hazard (refer to Section 9.13), which threatens Occupational Health and Safety as
well as air quality in general.
Medical Waste
Sharps, bandages, etc. are potential vectors for the spread of disease.
Non-Hazardous Waste
General waste materials generated from mining construction or operation, workforce accommodation camps
and administrative facilities, Process Plant, etc. may physically impact the environment (with potential
biological / social implications), including: contamination of receiving surface and groundwater for
improperly stored or untreated wastes (refer to Section 9.8); increased populations of wildlife due to food
wastes, including rats and other potential vectors for disease; and impaired visual amenity. The non-
hazardous wastes listed in Section 9.12.2 will be generated during Project construction, operation and
closure.
9.12.2 Avoidance, Mitigation and Management Measures
Avoidance and Minimisation
The Process Plant areas and Mine Services Area will be constructed with concrete slabs, primary containment
bunds that can contain at least 110% of the volume of hazardous and non-hazardous materials in the storage
areas, and sump pumps to recover any spilled material.
Spillage in the Process Plant that occurs outside of the Process Plant bunds will report to an event pond
(secondary containment), with water and contaminants reclaimed by a submersible pump.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-83
The amount of cyanide, additional processing reagents, and diesel stored on site will be minimised via
reconciliation of volume requirements. On an instantaneous basis, reagent usage rates of cyanide, elution
and detoxification reagents and diesel flow rates to unit operation will be measured and delivery receipts and
stock takes accounted to ensure adequate but not excessive hazardous materials storage at the Process Plant,
Mine Services Area, vehicle laydown areas, etc.
Cyanide
The Project is designed to avoid potential cyanide releases via the following design elements and
management measures:
Cyanide transport: The Project will adhere to ICMI Cyanide Management Code (Cyanide Code)
Principles and Standards of Practice for cyanide transportation (refer to below), including independent
auditing of procedures, Transportation Verification Protocols);
Storage and handling: The Project will adhere to Cyanide Code Standards of Practice for handling and
storage.
Cyanide destruction: The Process Plant will incorporate a cyanide destruction circuit to treat slurry
from the CIL circuit, gravitated from the carbon safety screen to the cyanide destruction circuit feed
box. Cyanide destruction will be carried out using the air / SO2 process. The cyanide destruction circuit
will comprise two tanks capable of operating in series or parallel. Slurry pH will be adjusted using
caustic solution metered into the circuit. Copper sulphate and sodium metabisulphite solution will be
added to the circuit using dedicated variable speed dosing pumps. Dedicated low pressure blowers
will supply air to the destruction tanks. Cyanide destruction circuit tailings will be pumped to the TMF.
Supernatant water will be recovered from the TMF and returned as process water decant return to the
Plant for storage in the process water tank and reuse;
Piping to the TMF: CIL tailings will be pumped to the TMF. The tailings line will be contained within a
trench to minimise potential contamination from pipe leakage. The route will have a continuous
downhill slope to the TMF with no ‘dead legs’ in the line requiring drain valves and scour pits.
The Company will adhere to the International Cyanide Management Code (a voluntary initiative), including
the following ICMI Principles (ICMI, 2014):
Production: Encourage responsible cyanide manufacturing by purchasing from manufacturers who
operate in a safe and environmentally protective manner;
Transportation: Protect communities and the environment during cyanide transport;
Handling and Storage: Protect workers and the environment during cyanide handling and storage;
Operation: Manage cyanide process solutions and waste streams to protect health and the
environment;
Decommissioning: Protect communities and the environment from cyanide through development
and implementation of decommissioning plans for cyanide facilities;
Worker Safety: Protect workers’ health and safety from exposure to cyanide;
Emergency Response: Protect communities and the environment through the development of
emergency response strategies and capabilities;
Training: Train workers and emergency response personnel to manage cyanide in a safe and
environmentally protective manner; and
Dialogue: Engage in public consultation and disclosure.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-84
Hydrocarbons
Diesel fuel, hydraulic fluids and other hydrocarbons required for vehicle / equipment operation will be
transported, stored and handled to minimise the potential for accidental discharge and to avoid potential for
significant physical impacts (refer to Volume C, ESMMP for greater detail). In summary, the following
measures will be employed:
Vehicle maintenance will be conducted on concrete slabs with diversion drains directing surface flow
to oil / water separators prior to discharge to the surrounding environment;
Hydrocarbons will be stored in primary containment bunds that can accommodate at least 110% of
the volume of hydrocarbons stored on-site;
Hydrocarbon storage areas and vehicle maintenance areas will be stocked with spill clean-up materials
(e.g. Sorbex);
Hydrocarbons storage areas and containers will be labelled, including clearly labelled and displayed
Material Safety Data Sheets (MSDS); and
Personnel will be trained in storage, handling, spill prevent, and spill treatment measures and will be
provided with appropriate personal protective equipment (PPE).
Waste oils will be collected at source and transferred into secure, bunded tanks. Waste oils tanks will be
periodically collected by the supplier and returned through their logistics chain for recycling.
Additional Process Plant Reagents
The Process Plant will be designed with the following measures to account for potential contaminant
discharge of processing reagents (refer to Section 9.6 for greater detail regarding surface water quality):
Materials handling, containment and bunding in all Plant areas will meet legislative requirements;
Plant areas subject to potential contamination from chemical or slurry spills will have concrete slabs
and bund. Bunded areas will be equipped with sumps to recover spilled material and rain from slabs;
Spillage exceeding the capacity of bunds will report to the HDPE lined event pond; and
Fire water for the process plant will be drawn from the raw water tank (with a reserve of fire water in
the tank always available); an electric fire water delivery pump and back-up diesel driven fire water
pump to convey water; and hydrants and hose reals throughout the Process Plant (including the fuel
and reagent storage areas) to avoid hazardous material air emissions via burning (refer to Section 9.13).
General Management and Mitigation Measures for all Hazardous Materials
Management and mitigation measures for hazardous materials include:
Maintaining an inventory of hazardous material on site;
Construction of an appropriately designed and clearly marked hazardous storage facility;
Provision of protective equipment (i.e. gloves, plastic coveralls, safety glasses and self-contained
respirators) and clean-up materials (e.g. Sorbex);
Clearly labelled and displayed MSDS for all hazardous materials on site;
Comprehensive training for process operators regarding emergency response and the handling,
storage and use of hazardous materials; and
Development of emergency response procedures and training for all Project personnel.
Further detail regarding the management of waste and hazardous materials is provided in the ESMMP
(Volume C). A framework for emergency response procedures is also provided. The Company will develop
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-85
Emergency Preparedness and Response Plans that will provide site-specific management plans, emergency
response protocols, and training requirements.
General (Non-Hazardous) Waste
Waste management at the Project will require the construction of several facilities (e.g. storage and
separation area for recyclables, residue waste landfill for non-recyclables and non-hazardous materials. Inert
construction waste will be disposed of at the WRD.
In general, the Company will handle waste disposal according to the procedures outlined below.
General Procedures
The waste management procedures for the Project will be based on the following hierarchy (in decreasing
order of preference):
1. Minimise the production of waste;
2. Maximise waste recycling and reuse;
3. Treatment of waste; and
4. Ensure safe waste disposal.
The first priority for the management of non-mining wastes generated by the Project will be to reduce the
volume of waste generated, which will be achieved by:
Procuring supplies that produce less waste by virtue of the way they are produced, packaged or
consumed;
Procuring supplies that have been produced from recycled materials, if possible; and
Maximising the efficiency of all on site production processes.
To maximise recycling and reuse, waste will be segregated into different types at the location where they are
generated. Solid waste will be segregated into three categories as follows:
Biodegradable materials – vegetation and food scraps;
Recyclable materials – processed timber; hard plastic; glass; metal; paper and cardboard; and tyres.
(Waste will be further segregated within this category), depending on the requirements of recycling
contractors; and
Non-hazardous residue waste.
Any non-hazardous residue waste that cannot be reused or recycled will be deposited in clearly marked,
general litter bins located around the Project site. The Company will implement an education campaign for
staff and contractors to minimise the generation of litter associated with Project activities.
9.12.3 Residual Impact Assessment
With effective implementation of the management and mitigation measures listed above, it is anticipated
that hazardous materials will not impact the surrounding environment under normal operating conditions.
In addition to the management and mitigation measures listed above, non-hazardous materials management
will require oversight from senior management. With proper disposal, monitoring, and continuous
improvement targets (refer to ESMMP), it is anticipated that impacts from non-hazardous materials will be
Negligible.
The key expected residual impacts related to general waste and hazardous materials under normal operating
conditions, and their overall significance for each Project phase, are summarised in Table 9-26. Monitoring will
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-86
be required over the mine life to assess performance, and allow management measures to be adapted
accordingly.
Table 9-26 Summary of key expected pre-mitigation impacts, mitigation measures and residual impacts related to
general waste and hazardous materials for each Project phase
Receptor / Value
Expected Pre-Mitigation
Impact Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and Overall Impact Significance
Pre-Construction / Construction
General Waste and Hazardous Materials
MINOR
Maintaining an inventory of hazardous material on site
Construction of an appropriately designed and clearly marked hazardous storage facility
Provision of protective equipment and clean-up materials
Clearly labelled and displayed MSDS for all hazardous materials on site
Development of emergency response procedures and training for all Project personnel
Regular monitoring of compliance
NEGLIGIBLE
With effective implementation of the management and mitigation measures listed above, it is anticipated that hazardous materials and other wastes produced will not impact the surrounding environment.
Operation
General Waste and Hazardous Materials
MODERATE
As per Pre-Construction / Construction Phase
Adherence to the International Cyanide Management Code principles and standards of practice
Comprehensive training for process operators regarding emergency response and the handling, storage and use of hazardous materials
NEGLIGIBLE
With effective implementation of the management and mitigation measures listed above, it is anticipated that hazardous materials and other wastes produced will not impact the surrounding environment.
Decommissioning / Closure
General Waste and Hazardous Materials
MINOR As per Pre-Construction /
Construction Phase
NEGLIGIBLE
With effective implementation of the management and mitigation measures listed above, it is anticipated that hazardous materials and other wastes produced will not impact the surrounding environment.
9.13 Accidental Events and Natural Hazards
9.13.1 Issues and Findings
Accidental and natural events that could lead to hazardous discharges or emissions have been considered
throughout the ESIA. While the probability of these occurrences may be low for the majority or all of the
following potential impacts, Project design; management; monitoring; and emergency preparedness and
response procedures / training are required to minimise attendant risk and ensure appropriate action is taken
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-87
in the event of an accident or natural hazard. Table 9-27 provides a summary of key risks and associated
management measures.
Table 9-27 Key Project risks associated with accidental events and natural hazards
Project Facilities (including Pre-construction)
Key Risks
Mine Pit
Pit edge crumble from structural instability leading top subsidence
Pit wall collapse from structural instability
Flyrock
TMF Contamination of surface and groundwater from excessive seepage
Failure of TMF embankment
Sediment Traps Failure of 1.5m embankment releasing sediment-loaded - possibly during a high rainfall event
Process Plant
Cyanide solution spill caused by human error and inadequate management of process water leading to surface and groundwater contamination
Overspill/level indicator malfunction – surface and groundwater contamination from cyanide spill
Mechanical failure / chronic loss of containment leading to cyanide leak
Ore and Waste Rock Haulage Collision with wildlife
WSD Provision of mosquito breeding area with associated increase in malaria incidence
Hazardous Material Storage / Handling
A spill or accidental release of a hazardous substance
Borrow area / Quarry Flyrock
Transportation Road Traffic Accidents – standard collision type accidents
RTAs - explosion or fire with associated secondary risks
The Risk Assessment (ESIA Volume B) provides further detail on each of these risks.
Accidental events and natural hazards may compromise the integrity of Project facilities, potentially resulting
in unanticipated discharge to receiving waters, pollutant emissions to the local atmosphere, landslips, etc.
Management and training requirements are provided in the Mako Gold Project ESMMP (Volume C). In
addition, MEC will develop site-specific Emergency Preparedness and Response Plans for the Mako Gold Project.
Important elements of the Plan includes undertaking regular risk assessment, ensuring adequate emergency
response measures / materials are in place (e.g. water for fire-fighting, spill adsorbent material, etc.), and
training of Project personnel regarding appropriate response to each potential event.
Emergency response to an environmental incident caused by an accidental event or a natural hazard will be
prioritised according to the following sequence:
1. Protection and rescue of human life;
2. Minimisation of the area impacted by the incident;
3. Protection of the environment, plant and property;
4. Rendering the area safe in which the emergency has occurred;
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-88
5. Restoration of all disrupted services; and
6. Decontamination and rehabilitation of the incident scene and surrounding area.
Depending upon the severity of an environmental incident, emergency response may also involve using the
services of, or notifying, the following groups:
Police;
Site medical practitioners;
District and Regional Government;
Village Chiefs and local community;
Department of Civil Protection;
Fire services;
DEEC;
Department of Mines; and
PNNK Authority.
General safeguards that will be adopted and specified in the Emergency and Preparedness Response Plans
include induction training and periodic refresher training for all employees on all aspects of safety, including
site specific rules and emergency situations.
The following sub-sections provide an assessment of specific events and associated safeguards and control
procedures.
Pre-Construction / Construction and Operation
Fuel and chemical leakage or spill
Fuel and chemical spillage may occur during transport, handling, processing, etc. resulting in the release of a
hazardous substance to soil substrate, downstream / down gradient receiving waters, or the atmosphere.
The potential physical impacts to water quality, air quality, soil, and air quality are considered in Section 9.6
(Surface and Groundwater Quality), Section 9.12 (General Waste and Hazardous Materials), and Section 9.8
(Air Quality).
Flooding
Flooding from extreme storm events has the potential to impact the TMF, WSD, and WRD as each facility
intersects ephemeral drainages. The greatest hazard would occur from the failure or over-topping of WSD or
TMF dam structures (and subsequent failure) resulting in release of water and supernatant water (for the TMF)
to the downstream environment. Such failure poses a significant occupational health and safety risk for
construction / operation personnel, local inhabitants of the region, and aquatic / terrestrial ecology. A Dam
Break Consequence Assessment has been conducted for the Project and is appended to the Risk Assessment
(ESIA Volume B).
The Gambia River basin is subject to periodic flooding during the rainy season (refer to ESIA, Chapter 5). As
the majority of Project facilities will be situated outside of the Gambia River flood zone, impacts from Gambia
River flooding would predominantly be unchanged from pre-Project impacts (e.g. existing biological and
social aspects of the region).
However, components of the pumping station for the WSD and segments of the existing road network that
will be utilised during Project construction are situated within the 1000 year average return interval (ARI)
storm event flood area for the Gambia River and may therefore be compromised during an extreme storm
event (pumping station will be located above the 100 year 24 hour ARI storm event flood area. Associated
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-89
potential impacts include erosion of road surfaces and sediment transport to receiving waters for an extreme
flood event. The pump station will be connected to mains power through the Power Station.
Figure 9-17 Estimated flood backflow conditions in Badalla Creek and the Gambia River near the PDA
Fire and Explosion
Mining and ore processing operation, including the improper storage, handling or transport of flammable
substances, can lead to the generation of potentially explosive and/or flammable gas emissions. Potential
impacts may include breakout of fire into surrounding areas, as well as release of significant quantities of air
pollutants and contaminated runoff from burnt areas.
The improper storage, handling or transport of explosives could result in an accidental explosion, potentially
causing loss of life and property damage.
Seismic Risk
A significant earthquake could lead to failure of TMF or WSD dam structures and release of water or tailings to
the downstream environment as well as landslips in the Mine Pit or constructed embankments. Sub-Saharan
Africa is largely a stable intra-plate region characterised by relatively low levels of seismic activity (refer to
Chapter 5) and the PDA is categorised as having a Very Low seismic hazard rating (PGA, 0 – 0.2 m/s2) (Global
Seismic Hazard Assessment Program, 1999).
Failure of Mine Pit walls
While there are no known large scale structures (faults, thrusts, shear zones) likely to affect the deposit, there
is a risk of pit slope instability due to such structures behind the pit wall. In addition, joint sets may be
missing which could impact the kinematic stability of some of the slope bench faces. Impacts would be
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-90
confined to the Mine Pit area, with the greatest risk the occupational health and safety of Project personnel
working in the Mine Pit.
Waste Rock Dump Failure
The geotechnical stability of the WRD is not considered a critical issue due to the proposed low angle slope
design. The stability of the proposed WRD has been assessed under static and seismic loading conditions
using limit equilibrium methods. ‘SLOPE/W’ has been used for the analysis using the Morgenstern-Price
method of limit equilibrium method of analysis (Knight Piesold, 2015g). The modelling results indicate that
the WRD will possess adequate stability for the modelled scenarios and conditions. However, the results
identify that WRD stability is sensitive to the level of the phreatic surface and that drainage measures should
be provided to direct surface water away from the WRD, to reduce water infiltration and to reduce the level of
the phreatic surface that develops.
Dam Failure
A Dam Break Assessment was prepared for the Mako TMF and this resulted in a Dam Failure Consequence
Category of ‘High C’ as per ANCOLD 2012 guidelines. The Project has therefore adopted design criteria for the
TMF based on its Dam Failure Consequence Category. Stability failure due to a seismic event is not likely to
occur during the operating period and in the few years following decommissioning, a nominal period of 15
years. Thereafter the tailing mass will become less susceptible to failure as it consolidates and drains,
therefore resulting in an overall increase in strength.
Harmattan Winds – Dust storms
The Harmattan is a north-easterly wind that blows from the Sahara Desert into the Gulf of Guinea between
November and March, passing over the Project region. On its passage over the desert, the Harmattan picks-
up fine dust (e.g. < 10 µg) and can result in significant dust storms or sandstorms. During extreme events,
public health may be compromised as suspended particulate matter comprises a number of organic and
inorganic constituents, some of which may cause respiratory diseases as well as other health issues.
Drought
Senegal is frequently subjected to drought conditions. The significance of drought in greater Senegal
includes degradation of vegetation (natural ecosystems and agricultural / livestock grazing land), terrestrial
and aquatic biodiversity, and human resource extraction (e.g. agricultural products, NTFP, and water)
including financial implications and famine (refer to Chapter 5). However, the Kedougou region is the wettest
area in Senegal, with a mean annual rainfall of approximately 1,171 mm recorded between 1982 and 2011 in
Kedougou (SRK, 2013). The Project region is less prone to drought conditions and vegetation / habitat and
agricultural plots less likely to suffer significant set-backs.
9.13.2 Avoidance, Mitigation and Management Measures
Avoidance and Minimisation
Fuel and chemical leakage or spill
Project facilities that require storage and handling of hazardous materials (i.e. Process Plant and Rom Pad,
Mine Services Area, Power Station) have been designed with primary and secondary containment systems.
Processes and requirements for storage, handling, emergency preparedness and response (i.e. prevention,
clean-up, training requirements) as well as controls for transport of hazardous liquid materials is provided in
Section 9.12.
Project compliance requirements are also specified in greater detail in the ESMMP (Volume C). The ESMMP
broadly covers the management of potential liquid contaminants, including diesel, process reagents, waste
water, etc. The ESMMP provides requirements for the following categories:
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-91
Primary containment system (i.e. bunding at storage and handling facilities);
Secondary containment systems (i.e. secondary bunds and drainage control);
Containment within operation area (i.e. for spills that occur away from containment structures such
as bunds but within the operation area (e.g. road infrastructure and Mine Pit);
Off-site spill (e.g. spills that occur during transport); and
Non-compliance discharge (i.e. spills that originate from within the Project Footprint and escape the
PDA to receiving environments).
Spill responses are sub-divided into two response categories:
Simple spills of benign chemicals that can be managed immediately by the person present on site
(these do not constitute an environmental emergency); and
More complex spills that may require additional resources or specialist skills for containment and
rehabilitation.
To respond quickly and appropriately to fuel and chemical leaks and spills, the ESMMP provides the
framework for emergency response and the Emergency Preparedness and Response Plans will outline specific
procedures (containment, provision of spill clean-up materials, staff training, and emergency response
protocol) for commonly used fuels and chemicals.
Flooding
The Project Footprint is situated above the Gambia flood zone for the 1000 year average return interval (ARI)
storm event, with the exception of an existing road that will be used during early stages of construction. The
road will be upgraded during early phases of construction, with improved erosion and sediment control
facilities incorporated. Some damage to the unsealed road (and associated erosion and sedimentation) from
an extreme flood event cannot be avoided. The pump station (designed for the 100 year flood level) will be
the subject of further design changes to confirm the final tower height to ensure it can withstand extreme
flood events.
As per Sections 9.2 - 9.4, the WSD and TMF embankments / dams have been designed to withstand
stormwater generated from 100 year 24 hour ARI storm events plus a contingency freeboard of 1m. The WSD
and TMF embankment slopes have been designed for geotechnical stability at full capacity. Spillways will be
constructed to accommodate stormwaters generated for >100 year 24 hour ARI storm events that will
discharge water into the Badalla Creek (TMF) and Kobokou Creek (WSD), to reduce the risk of overtopping.
Seismic events
The Project is committed to ICOLD guidelines with respect to designing the WSD and TMF dams for
geotechnical stability, which accounts for seismicity. ICOLD seismic design and performance criteria consider
various design seismic design criteria for different structures / elements of a large dam Project. Those
considered most relevant to the Mako facilities include:
The Safety Evaluation Earthquake (SEE), which is the earthquake ground motion a dam must be able to
resist without uncontrolled release of the reservoir. The SEE is the governing earthquake ground
motion of the safety assessment and seismic design of the dam and safety-relevant components,
which must be functioning after the SEE. SEE may be determined by assessing the Maximum Credible
Earthquake (MCE) and/or the Maximum Design Earthquake (MDE). Usually the most unfavourable
ground motion parameters are used (for MCE vs. MDE);
MCE is the event which produces the largest ground motion expected at the dam site on the basis of
seismic history and the seismotectonic conditions of the region. It is estimated based on deterministic
earthquake scenarios;
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-92
MDE ground motion parameters are estimated based on a probabilistic seismic hazard analysis, with
mean values of ground motion parameters taken for 10,000 year events (or lesser for smaller dams);
and
Operating Basis Earthquake (OBE), may be expected to occur during the lifetime of the dam. No
damage or loss of service may occur. It has a probability of occurrence of approximately 50% during
the service life of 100 years. The return period is taken as 145 years (ICOLD, 2010). OBE ground motion
parameters are based on probabilistic seismic hazard analysis, with mean values utilised.
For the MCE analysis, the Project assumed that an event of 5.8 ML magnitude could occur at a distance of
250km from the site, which represents the approximate distance to the nearest cluster of historic events.
The design is for the embankments to be stable under design earthquakes up to a design acceleration of
0.03g during operation. The probability of failure is assessed on the basis of failure being the release of
tailings caused by a low probability seismic event. This is considered equivalent to a return period of 1 in
10,000 years or more (Knight Piesold, 2015k).
Mine Pit wall slopes / bench widths and WRD slope angles have considered seismicity into their respective
design. The peak horizontal rock ground motions are 0.03g and 0.10g for the Operating Basis Earthquake
(OBE) and Safety Evaluation Earthquake (SEE) events respectively. The stability of the proposed WRD has
been assessed under static and seismic loading conditions using limit equilibrium methods. The stability of
the WRD was assessed to confirm the factors of safety against shear failure considering long-term drained
conditions and seismic conditions. The desired minimum factor of safety for seismic activity during operation
(OBE) is 1.2 to 1.3 and for seismic activity post closure (SEE) the factor of safety is 1.1 (Knight Piesold, 2015j).
Fire
Fire suppression water for the Process Plant and Mine Services Area will be drawn from the raw water tank.
Suctions for other water services fed from the raw water tank will be at an elevated level to ensure a fire water
reserve always remains in the raw water tank. The fire water pumping system will contain an electric jockey
pump to maintain pressure, an electric fire water delivery pump to supply fire water at the required pressure
and flowrate and a diesel driven fire water pump will serve as a backup, automatically starting in the event
that the electric pump fails to maintain pressure in the fire water system. Additional measures include:
Fire hydrants and hose reels will be placed throughout the process plant, power station, fuel storage
areas, and plant offices at intervals that ensure complete coverage in areas where flammable materials
are present;
Operation and transport will avoid petrol and LPG where feasible, limiting risk from explosive materials
to blasting material (dynamite), and diesel fuel;
Appropriate Project personnel will be trained to fight fires (refer to Volume C, ESMMP); and
The explosives storage magazine will be located at least 800 m from all infrastructure and in areas
meeting international standards for fire safety (including fitting flame arresting devices).
Tailings Management Facility Dam Failure
In order to reduce flooding, overtopping and erosion, the TMF will have a stormwater interception and
diversion system. The design will include sufficient freeboard at all times to accommodate the probable
maximum precipitation (PMP) event (476 mm in 24 hours). In the unlikely event that rainfall is greater than
the PMP, or operational errors cause water levels to exceed the available (1m) freeboard, an emergency
spillway will be constructed in the eastern abutment of the TMF embankment in order to protect the integrity
of the facility in the event of emergency overflow. A decant pond will be located downstream of the spillway
to collect process water before it is pumped back to the Process Plant. The TMF embankments / dams have
been designed to store all storm events and annual rainfall sequences to a 1 in 100 year average recurrence
interval (Knight Piesold, 2015f ).
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-93
Pit Wall Failure
Static and kinematic geotechnical analyses have been conducted in order to inform pit wall stability.
Kinematic analyses show that the maximum overall slope angle for the fresh and transition zone is
constrained by the bench and berm geometry, which is based on the requirement for these to minimise
kinematic instability and trap potential rock fall (Coffey, 2015).
If pit slumping and slope failure does occur, the environmental consequences will be physically constrained
by the pit walls.
Waste Rock Dump Failure
The WRD will be constructed from the bottom up so that the toe support is provided to the sections of WRD
located on steeper and higher ground.
The WRD will be compacted at the completion of each lift in order to maintain stability. Each of the
completed lifts of the WRD will be progressively rehabilitated with vegetation throughout the Operation
Phase. This will also help to retain stability.
Drought
Water from the Gambia River will only by pumped to the WRD during rainy season months. The pumping
schedule from the Gambia River should be contingent on river level and not solely the timing of the wet
season months. During significant drought conditions, abstraction rates from the Gambia should be reduced
if the downstream environment would be further affected by pumping.
Dust Storms
Minimising the extent of vegetation clearing, erosion control facilities, progressive rehabilitation, and road
watering (detailed in sections above) will minimise the impact from significant dust storms. Beyond this, the
primary management measures would be covered in Occupational Health and Safety Plans (refer to ESMMP)
to minimise impacts to Project personnel.
9.13.3 Residual Impact Assessment
While the potential for impacts from accidental events and natural hazards cannot be eliminated, the Project
has been designed to avoid or minimise the probability and potentially significant consequences of such an
event. Management and mitigation measures are expected to minimise the associated attendant risks to an
acceptable level.
9.14 Climate and Greenhouse Gases
9.14.1 Issues and Findings
An understanding of climate change trends can provide guidance on predicting future meteorological
conditions in the Mako Gold Project region. The leading international body for climate change assessments is
the Intergovernmental Panel on Climate Change (IPCC), which was established by the United Nations
Environment Program (UNEP) and World Meteorological Organization (WMO) in 1988, to provide clear
scientific views on the current knowledge of climate change. Senegal has been identified as one of the top
three countries in the Sahel region at risk from the effects of climate change (World Bank, 2009).
The scientific community is of the consensus that climate change is caused by increased concentrations of
greenhouse gases in the atmosphere. The Intergovernmental Panel on Climate Change (IPCC), the United
Nations Framework Convention on Climate Change (UNFCCC) and the Kyoto Protocol have been established
to address this issue. Greenhouse gases in this context include carbon dioxide (CO2), methane (CH4), nitrous
oxide (N2O), as well as perfluorocarbons (PFCs) and fluoride gases.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-94
Climate Change is a global issue. Key considerations for Senegal are temperature and rainfall trends, which
are described below.
Mean annual temperatures in Senegal have increased by 0.9°C since 1975 (UNDP 2010);
The mean annual temperature is projected to increase by 1.1 to 3.1°C by the 2060s from current
temperatures, and 1.7 to 4.9°C by the 2090s based on various emissions scenarios;
The projected rate of warming is faster in the interior of Senegal than in the coastal regions;
Rainfall data from Kedougou show a general decrease of approximately -14% over the last century;
Rains have remained steady in Senegal over the past 20 years, but are 15% below the 1920-1969 mean;
Rainfall projections from different models do not agree on the precipitation changes in the region, but
predict general decreases for the wet season of up to -18% for the 21st century;
Heavy rainfall events during the wet season are predicted to increase despite the overall decrease in
annual precipitation; and
General increases in variability and extremes are predicted across the region.
The Republic of Senegal ratified the United Nations Framework Convention on Climate Change (UNFCCC) on
17th October 1994 and ratified the Kyoto Protocol on 20th July 2001. Obligations that come under the
ratifications include undertaking a source and sink greenhouse gas inventory, identifying greenhouse gas
mitigation options, formulating greenhouse gas mitigation strategies and a national implementation plan
that covers all sectors, including energy, industry and transport. Senegal completed its Initial National
Communication (INC) to the UNFCCC in 1997 and the Second National Communication (SNC) in 2010. As of
2015, the SNC report is the most recently reported data on Senegal’s greenhouse gas emissions inventory and
is based on 2000 levels.
Based on the SNC, total greenhouse gas emissions in Senegal in 2000 were estimated at 16,894 kilotonnes
CO2 equivalent. However, some 10,587 kilotonnes of CO2 equivalent is being sequestrated by the forestry
sector (UNFCCC, 2010). The largest emitting sector in Senegal is the energy sector, contributing to 49% of the
country’s total emissions. This is followed by the agriculture sector at 37%, waste at 12%, and 2% from
industrial processes.
The following greenhouse gas assessment for the Mako Gold Project is an initial assessment of the likely
magnitude of emissions from the Project only. The assessment has been based on the methods outlined in
the Greenhouse Gas Protocol: A Corporate Accounting and Report Standard (World Business Council for
Sustainable Development and World Resources Institute, 2004) and 2006 IPCC Guidelines for National
Greenhouse Gas Inventories.
As detailed data for the calculation of greenhouse gas emissions and energy usage was not available at this
stage of the Project, this is considered preliminary assessment and only the potential emissions during the
Operation Phase have been estimated. For the Construction Phase, only potential emissions related to
vegetation clearance are considered (other emission sources during Construction are not included due to
data limitation).
The Project is expected to produce greenhouse gas emissions from the following main sources.
Scope 1 (direct) emissions from:
» Fuel used for Power Station on-site (diesel Power Station);
» Diesel usage for mining activities;
» Supplies transportation to site; and
» Vegetation clearance.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-95
There is not expected to be Scope 2 (indirect) emissions from the consumption of electricity from the grid, as
all electricity will be provided from an on-site Power Station.
Scope 3 emissions are indirect GHG emissions which occur as a result of sources not owned or controlled by
MEC in relation to the Project, for example embodied emissions from material use in the Project, emissions
from equipment delivery to site, and travel emissions of employees to site. Scope 3 emissions are excluded in
this assessment due to data limitation.
The main greenhouse gases produced by the Project are likely to include:
Carbon dioxide (CO2);
Methane (CH4);
Nitrous oxide (N2O);
Sulphur hexafluoride (SF6); and
Hydrofluorocarbons (HFCs).
Industry best practice management will be implemented at the Project site to ensure that greenhouse gas
emissions are minimised through measures such as:
Measure overall greenhouse gas reduction progress and report results;
Promote technical innovation and creativity in low greenhouse gas emissions technologies while
enhancing energy and resource efficiency;
Ensure efficient use of renewable and non-renewable natural resources;
Develop appropriate adaptation strategies specific to each operation; and
Contribute to the sustainable development of local communities and societies in adapting to the
impacts of climate change.
All greenhouse gas emissions associated with the Mako Gold Project are expected to occur as a result of
Scope 1 (direct emissions) from the on-site Power Station, fossil fuel usage in mining activities, and supplies
transportation.
Power will be generated on-site by a dedicated diesel-fuelled project Power Station. The Project is expected
to generate 809,000 tCO2e at a minimum over the Project’s operational life of eight years, or approximately
102,000 tCO2e per annum. The overall emissions increase to approximately 831,000 tCO2e when vegetation
clearing is included.
Table 9-28 illustrates the overall minimum emissions of the Project.
Table 9-28 Initial estimate of the Project’s minimum overall emissions Activities Estimated tonnes of
CO2e per annum ^ Estimated tonnes of CO2e over
8-year operational life ^
Project Construction Phase
Vegetation clearing# – Scope 1
2,810 # 22,500 (other activities during construction is not included at this stage)
Project Operation Phase
Diesel Power Station– Scope 1 81,300 650,000
Diesel Usage for Mining Activities – Scope 1 18,600 149,000
Supplies Transportation to Site – Scope 1 1,250 9,990
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-96
Activities Estimated tonnes of CO2e per annum ^
Estimated tonnes of CO2e over 8-year operational life ^
TOTAL Operation Phase Emissions using Diesel Power Station
102,000 809,000
OVERALL TOTAL Construction and Operation using Diesel Power Station (incl. vegetation clearing)
104,000 831,000
^ Numbers are rounded up to three significant figures.
# This represents the average yearly emissions for land clearing. Note that most likely the majority of emissions due to land clearing would occur
during Pre-Construction and Construction period.
** The emissions here do not consider the effect of revegetation and mine rehabilitation.
A breakdown of the estimated emissions from the Project (based on available data only) is provided in the
sections below.
Pre-Construction / Construction
Only emissions from vegetation clearance are considered for the Construction Phase. Other main emission
sources during Construction that could be included once data becomes available include fossil fuel usage for
construction activities, use of explosives, and transportation of materials to the Project site.
It is expected that approximately 240 ha of natural habitat (IFC, 2012) and 4 ha of modified habitat (IFC, 2012)
will be cleared prior to the construction of the main Project components, Main Access Road, haul road and
pipeline.
For the purpose of estimating the emissions due to vegetation clearing, it is assumed that the area to be
cleared is categorised as “Woodland and Scrub” based on the National Carbon Accounting System Technical
Report No. 17. The woodland and scrub category has the lowest biomass density of the three available
biomass categories, with a density of 51 t/ha. This is expected to be an over-estimate of biomass, however it
represents the closest applicable vegetation category for the emissions estimate.
Based on an estimated area of 240 ha, vegetation type of woodland and scrub, approximately 12,300 tonnes
of biomass would be cleared. Assuming 50% carbon content of the biomass, this translates to approximately
6,120 tonnes of total carbon. Thus assuming all the carbon is converted to carbon dioxide through natural
decomposition (or burning), this equates to approximately 22,500 tCO2e of emissions released during the
vegetation clearing phase.
At the end of the mine life, some of the emissions from vegetation clearing would be offset through native
revegetation and mine site rehabilitation (see Rehabilitation and Conceptual Mine Closure Plan – Volume
E). The assessment here considers the emissions without considering the effect of revegetation and mine
rehabilitation.
Operation
Three emission sources are considered for the Operation Phase, including: fuel usage for electricity
generation (diesel power station), fuel usage for mining activities, and transportation of supplies to site.
Power Station
The diesel Power Station has a maximum capacity at 16.5 MW and a typical continuous load at 9.8 MW.
A typical fuel consumption for a diesel generator at 1.8 MW is estimated at 0.33 L/kWh (Cummins 2660DQLB
Emissions Data Sheet, EDS-1009, 2010). Assuming 24 hours and 365 days operation per year and applying
typical diesel’s energy content of 38.6 GJ/kL (AGDE, 2014) and emission factor of 74,289 kgCO2e/TJ for
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-97
stationary energy (IPCC, 2006), the yearly emissions are estimated at 81,300 tCO2e. Overall emissions during
operational life of 8 years are around 650,000 tCO2e.
Mining Activities
Diesel fuel usage data for mining activities from the Company are provided at 6,000 m3/year. It is assumed
that this amount covers all activities occurring at the mine site. Using the same typical diesel energy content
as above and an emission factor of 80,193 kgCO2e/TJ for a mobile emission source (IPCC, 2006), gives a yearly
emissions estimate of 18,600 tCO2e. Over the 11-year operational period, the total emissions become 205,000
tCO2e.
Supplies Transportation
Transportation of supplies to the Project Site from Dakar (650 km distance) are estimated at three trucks per
day. For an operational period of 365 days per year, this gives a total of 1,095 trucks per year (see Table 9-29).
As truck type data was not available at time of writing, for the purpose of conducting initial assessment, truck
type is assumed to be articulated truck carrying 33 tonnes of goods or less. It is also assumed that there
would be 100% load of supplies from Dakar to Mako and 0% load from Mako to Dakar. Note that this is likely
to result in an over-estimate of GHG emissions from supplies transportation. More accurate estimation should
be calculated once detailed supplies transportation data is available.
The initial emissions estimates were calculated using an emission factor for articulated trucks derived from a
report compiled by UK’s Department for Environment, Food, and Rural Affairs (DEFRA, 2011). DEFRA has
reviewed emissions for different modes of freight transport mechanisms, and developed ranges of emissions
for each mode (including different emission factors for trucks at 100% load and 0% load). This method was
applied due to the unavailability of fossil fuel estimates for the Project. Once the fossil fuel usage data for
supplies transportation becomes available, more accurate estimates will be able to be calculated.
Table 9-29 Initial estimation of greenhouse gas emissions for transportation of supplies
Route Distance
(Km)
Assumed
load of
supplies
No. of
trucks per
day
No. of
trucks per
year
Estimated
tonnes of CO2e
per annum ^
Estimated tonnes of
tCO2e per route over 8-
year operational life ^
Dakar to Mako 650 100% load 3 1,095 748 5,990
Mako to Dakar
(return trip) 650 0% load 3 1,095 501 4,010
TOTAL 1,250 9,990
^ Numbers are rounded up to three significant figures.
Other Emission Sources
There are other emission sources during the Operation Phase that are not considered in this assessment due
to data limitation, such as waste disposal, other fuel usage (i.e. remote generators) and wastewater treatment.
These emission sources are likely to be minor in comparison to the operation’s emissions detailed above.
Decommissioning / Closure
During closure, there will be rehabilitation and revegetation activities as described in Rehabilitation and Conceptual Mine Closure Plan (Volume E). No detailed data on fossil fuel usage during this period is
available at this stage.
The planned revegetation activities indicate that some of the potential emissions due to vegetation clearance
mentioned above would eventually be offset. This should be analysed further once comprehensive data on
planned revegetation activities becomes available.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-98
9.14.2 Avoidance, Mitigation and Management Measures
Minimisation
Prior to construction, an Environmental and Social Management and Monitoring Plan (ESMMP) will be
completed. This plan will outline the necessary strategies, procedures, and reporting requirements in fulfilling
their statutory requirements and voluntary commitments, including greenhouse gas emissions commitments.
The ESMMP includes the following measures:
Maximise efficiency of energy use (type of fuel, lighting, water etc.)
Minimise land clearance to reduce carbon loss;
Maximise absorption/offset of greenhouse gases through revegetation of land during and after mining
(as per the Rehabilitation and Conceptual Mine Closure Plan, Volume E); and
Use best available technology to minimise greenhouse gas emissions at mine site and processing
facility.
During Construction, the Company should implement the measures outlined in the ESMMP’s Greenhouse
Gas Management Plan developed for the Project. Such measures will include:
Follow international industry practices for minimising Project related greenhouse gas emissions,
particularly for major emission sources (on-site Power Station);
Apply appropriate greenhouse gas management measures to all Project-related transport activities;
Integrate energy efficiency principles in building or facility design;
Ensure contractors comply with relevant energy conservation measures outlined in the ESMMP;
Conduct awareness training on energy conservation and greenhouse gas reduction for Project
employees and workforce; and
Establish energy conservation targets for the Project for measuring improvement in greenhouse
intensity of mining operation in accordance with good international industry practices.
During operation, the control procedures for reducing energy and greenhouse gas emissions shown in Table
9-30 should be implemented.
Table 9-30 Greenhouse gas emissions / energy source and control procedures
Source Control Procedures
Heavy equipment
and vehicles
Improve fuel efficiency of all Project vehicles by recording fuel usage and undertaking regular
maintenance;
Maximise the benefits of gravity in movement of material and minimise the need for uphill
movements;
Minimise multiple handling requirements, through optimisation of ore and waste handling processes;
Minimise idling time and distances travelled in vehicles and movement of equipment through active
scheduling;
Where possible, select most fuel efficient vehicles and equipment viable for use on site;
Eliminate unnecessary use and fuel consumption, through the establishment of a central control
system for equipment dispatch;
Regular maintenance of diesel power units;
Optimise operating efficiency of Power Station; and
Consider a visitor area for drivers, to prevent long-time idling of trucks/vehicles
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-99
Source Control Procedures
Energy Usage Consider the use of solar power and biofuels to substitute or augment fossil fuel usage for electricity
generation;
Use of “high-efficiency” motors in equipment that is continuously operated;
Capacitor bank to improve the power factor;
Optimising dewatering and pumping systems to minimise energy use for water management;
Reducing pumping requirements by situating the main mine header tank uphill;
Design and implementation of dust suppression systems that can be switched off when watering is
not required; and
Use efficient and shielded lighting that requires less energy
Rehabilitation / Decommissioning / Closure
During Decommissioning/closure, MEC will continue to implement the measures outlined in the
Rehabilitation and Conceptual Mine Closure Plan (Volume E) (to be developed for the Project). Key
measures to assist in minimising greenhouse gas emissions during rehabilitation and closure activities
include:
Progressively rehabilitating cleared land during operation to ensure that land is revegetated as soon as
possible after mining and waste disposal operation are completed;
Mulch and chip cleared vegetation rather than burn and re-use in rehabilitation;
Consider converting cleared vegetation to biochar and use in rehabilitation; and
Revegetate with native plants such as fast growing bamboo.
9.14.3 Residual Impact Assessment
It is expected that the residual impact of the Project would be Minor provided that the Project follows the
above avoidance, mitigation, and management measures (including those outlined in the ESMMP) and
Rehabilitation and Conceptual Mine Closure Plan, Volume E). By following the above, monitoring of
greenhouse gas emissions are likely to be regularly performed, emissions reduction targets regularly set, and
reduction measures implemented and continually improved to minimise any residual impact that may arise.
The key expected residual impacts related to climate and greenhouse gases under normal operating
conditions, and their overall significance for each Project phase, are summarised in Table 9-31. Monitoring will
be required over the mine life to confirm the residual impact predictions, and allow management measures
to be adapted accordingly.
Table 9-31 Summary of key expected pre-mitigation impacts, mitigation measures and residual impacts related to
climate and greenhouse gas emissions for each Project phase
Receptor / Value Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures Key Expected Residual Impacts and Overall Impact Significance
Pre-Construction / Construction
Climate and Greenhouse Gases – fuel and energy use
MODERATE
Maximise efficiency of energy use (type of
fuel, lighting, water etc.)
Follow international industry practices for
minimising Project related greenhouse gas
emissions, particularly for major emission
MINOR
Greenhouse gas emissions will occur due to mining activities
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-100
Receptor / Value Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures Key Expected Residual Impacts and Overall Impact Significance
sources (on-site Power Station)
Apply appropriate greenhouse gas
management measures to all Project-related
transport activities.
Integrate energy efficiency principles in
building or facility design.
Ensure contractors comply with relevant
measures outlined in the ESMMP to be
prepared for the Mako Project.
Establish energy conservation targets for the
Project for measuring improvement in
greenhouse intensity of mining operation in
accordance with good international industry
practices.
Climate and Greenhouse Gases – Vegetation Clearing
MODERATE
Minimise land clearance to reduce carbon
loss.
Mulch and chip cleared vegetation rather than
burn and re-use in rehabilitation.
Maximise absorption/offset of greenhouse
gases through revegetation of land during and
after mining (as per the Rehabilitation and
Conceptual Mine Closure Plan, Volume E).
MINOR
Reduction in air pollution due to smoke
Additional mulch to ensure revegetation success
Removal of vegetation during mining
Operation
Climate and Greenhouse Gases - Heavy equipment and vehicles
MODERATE
Where possible, select most fuel efficient
vehicles and equipment viable for use on site
Maximise the benefits of gravity in movement
of material and minimise the need for uphill
movements.
Minimise multiple handling requirements,
through optimisation of ore and waste
handling processes.
MINOR
Greenhouse gases will be generated through fuel use
Cost of fuel can be minimised through materials handling efficiency
Climate and Greenhouse Gases - Energy Usage
MODERATE
Use best available technology to minimise
greenhouse gas emissions at mine site and
processing facility.
Consider use of renewable energy such as
wind, solar and biofuels to substitute or
augment fossil fuel usage for electricity
generation.
MINOR
Energy use will contribute to greenhouse gas production
Climate and Greenhouse Gases – Vegetation Clearing
MODERATE
Progressively rehabilitating cleared land
during operation to ensure that land is
revegetated as soon as possible after mining
and waste disposal operations are completed.
MINOR
Native vegetation will be removed to undertake mining
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-101
Receptor / Value Expected Pre-Mitigation Impact
Significance
Key Management & Mitigation Measures Key Expected Residual Impacts and Overall Impact Significance
Decommissioning / Closure
Climate and Greenhouse Gases – Vegetation Clearing
MINOR
Restoration activities conducted in accordance with Rehabilitation and Conceptual Mine Closure Plan
Revegetate with native plants such as fast
growing bamboo.
NEGLIGIBLE
Fast re-vegetation restores carbon sink and improves water quality outcomes
9.15 Visual Amenity
9.15.1 Issues and Findings
Assessment of the potential Project related impacts to the baseline visual amenity within and in proximity to
the PDA during construction, operation and decommissioning / closure involved:
Photographic surveys of potential impact sites and sensitive receptors during wet and dry seasons
(2014) to determine line-of-site from Project components; and
Computer simulations of predicted visual impacts of the Project from sensitive receptor locations
(viewshed analysis).
The viewshed analysis was conducted using Geographic Information System (GIS) software. A 3-dimensional
terrain model of the area was produced with the major features of the proposed Project Footprint overlaid on
the surface terrain to predict the approximate visibility of Project components for potential receptor sites (e.g.
local communities and PNNK).
The viewshed analysis considered line-of-site to primary Project components (e.g. Mine Pit; WRD; Process
Plant and ROM Pad; TMF; WSD; Power Station, Main Access Road and night-lighting for components) while the
overall impact assessment considered additional elements, including upgrade of the existing Mako-
Tambanoumouya Road (paralleling the Gambia River), additional vehicles in the Project region, skyglow from
night-works, etc.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-102
Figure 9-18 3D Terrain model with Project components and potentially sensitive receptors
The primary and ancillary components of the Mako Gold Project are located at a moderate distance from the
nearest potentially sensitive receptors (i.e. villages and PNNK). Many of the components (e.g. the TMF, the
majority of the WRD and Mine Pit) are located within Badalla Valley, where topographic relief will shield the
areas from direct line of site. The impacts to visual amenity are expected to be low for most receptors, though
may be Moderate for villages with direct line of site to the WRD and Process Plant / Power Station.
The viewshed analysis (Figure 9-14), identifies areas that are visible from the location of the proposed Project
component. Some of the components will become progressively less visible throughout operation (i.e. the
Mine Pit), while the remainder will be rehabilitated and revegetated during Project operation (WRD) and
following Project decommissioning (with the exception of the main access road and workforce
accommodation).
Pre-Construction / Construction
Due to the topography of the PDA (i.e. topographic relief and shielding), visual amenity for various receptors
will vary during construction, with potential for direct line-of-site to one or more of the following for the
communities / PNNK receptors identified in Figure 9.13:
Badalla Valley vegetation clearance (e.g. Mine Pit, WRD) and construction (TMF);
Process Plant, ROM Pad, and Power Station vegetation clearance area and facilities’ construction;
WSD embankment and Main Access road construction;
Mako to Tambanoumouya road upgrade (paralleling the Gambia River); and
Increased Project-related traffic, including associated dust emissions during the dry season (particularly
for Access Road upgrade and Main Access Road Construction near National Route 7.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-103
Visual modification during construction and the potential severity of impacts to visual amenity for local
receptors are provided in Table 9-32. Potential impacts were determined via GIS viewshed analysis developed
from photographs (refer to Figure 9-14) and simulated viewshed analyses (refer to Table 9-32). The potential
impact of visual modification is expected to be less during the wet season due to the increased presence of
vegetation and the screening that it provides.
Table 9-32 Pre-Construction and Construction Phase visual impact assessment
Site Name Construction / Visual Modification Potential Impact
Tambanoumouya WRD and Pit vegetation clearance MODERATE
Kerekonko WRD and Pit vegetation clearance MODERATE
PNNK (eastern limit) WRD and Pit vegetation clearance LOW
Linguekoto Construction Access Road Upgrade, Traffic, Dust LOW
Dalakoy Process Plant, Power Station and WSD Construction (potentially) LOW
Wassadou Process Plant and Power Station Construction LOW
Mako Construction Access Road Upgrade, Traffic and Dust LOW
Niemenike/National Route 7 Main Access Road Construction, Traffic and Dust LOW
Badian (Maragoukoto) Mako Camp NEGLIGIBLE
Sekoto NA NEGLIGIBLE
Tomboronkoto NA NEGLIGIBLE
Operation
Visual amenity during operation will also vary for receptors due to local topographic features and distance
from operation. The context of visual amenity impact will change for respective receptors (compared to
Construction Phase) as night-time operation (and associated lighting) will be introduced, whilst road
construction, vegetative clearance, and use of the Temporary Construction Access Road will cease or be
significantly reduced. The primary potential impacts to visual amenity are provided below, with an
assessment of these impacts for applicable receptors provided in Table 9-33, visual viewshed analysis ( Figure
9-19) and viewshed simulation for the select villages is provided in Table 9-35.
Night-lighting – It is anticipated that the Project will be in operation for 24 hours per day, with the
main components illuminated for safety. The lack of electricity in the area is such that the PDA is
currently isolated from the effects of night lighting. Direct line-of-site to Project associated night-
lighting is likely for residents of Tambanoumouya, Kerekonko, and potentially Dalakoy as well as for
southern portions of the PNNK (e.g. PNNK 1 in Figure 9-18).
Skyglow - Though a lesser impact than direct view of night-lighting, indirect light may be visible for
the majority of villages within proximity of the PDA. Skyglow (a brightening of the night sky above the
Project) varies with changes in humidity, cloud cover, dust concentration and light output.
Badalla Valley Project Components – Though the Mine Pit footprint is located on the crest of the
ridge line and hence is currently visible by a number of the surrounding villages, the majority of the
facility will not be within line-of-site (subsurface). The WRD and TMF will become progressively more
visible throughout operation. The GIS viewshed analyses predict that the most affected sensitive
receptors are likely to be Kerekonko, Tambanoumouya and Dalakoy. These villages are within a few km
of the WRD and have relatively unimpeded views of the Badalla Valley.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-104
Process Plant, Power Station and ROM Pad – As these facilities straddle the ridgeline of the Badalla
Valley, they will be visible to more receptors than for Badalla Valley Project facilities. Lighting (if
applicable) would provide direct and indirect impacts after nightfall. These facilities will be visible for
Tambanoumouya, Kerekonko, Dalakoy, and Wassadou.
WSD and Main Access Road – The Main Access Road and WSD road, cutting across the foot of the hill
may, will be constructed within a relatively undisturbed setting. These components will be visually
prominent until a moderate level of vegetation cover is established at their margins. Vegetative
screening will incrementally increase as forest tree cover re-establishes on the foot-slopes of the road
cutting. Sections of the Main Access Road will be visible in Linguekoto, Dalakoy and Wassadou. These
components are not expected to impact visual amenity to a great extent.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-105
Figure 9-19 GIS Viewshed Analysis for Project Components
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-106
Table 9-33 Operation Phase Visual Impact Assessment
Site Name Distance
From Pit
Visual Modification Impact
Assessment
Tambanoumouya 3.0 km WRD, Lighting and Skyglow MODERATE
Kerekonko 4.0 km WRD, Process Plant, Lighting and Skyglow MODERATE
PNNK (southern portion) 4.3 km WRD, Lighting and Skyglow MODERATE
Linguekoto 4.5 km Mako Camp and Skyglow LOW
Dalakoy 4.7 km Process Plant and Skyglow LOW
Wassadou 5.2 km Process Plant and Skyglow LOW
Niemenike/National Route 7 9.0 km Access Road. Traffic LOW
Badian (Maragoukoto) 7.4 km Skyglow NEGLIGIBLE
Mako 8.6 km Skyglow NEGLIGIBLE
Sekoto 14.4 km Skyglow NEGLIGIBLE
Tomboronkoto 17 km Skyglow NEGLIGIBLE
The following simulated views of Project components are displayed from a vantage point of 100 m above
ground level in respective village locations (the images increasingly blur when simulating closer to the
ground). The view of Project facilities presented in these simulations is therefore less impeded by
topographic relief than will be the case from a ground-level perspective. Impacts to visual amenity are
therefore expected to be less than that represented in Table 9-34.
Table 9-34 Simulated Views of Project Components from 100 m Elevation above Receptors
Receptor Simulated View (from 100m above receptor)
Tambanoumouya
(viewing north-
west)
Tambanoumouya
(viewing east)
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-107
Receptor Simulated View (from 100m above receptor)
Kerekonko
(viewing north)
Dalakoy
(viewing north)
Linguekoto
(viewing north-
west)
Linguekoto
(viewing north-
east)
Wassadou
(viewing north-
east)
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-108
Receptor Simulated View (from 100m above receptor)
Badian (viewing
west)
Mako (viewing
southwest)
Decommissioning / Closure
Impacts to visual amenity associated with decommissioning / closure are expected to be limited to dust
generation associated with landform rehabilitation (topsoil application and re-contouring) and equipment
operation necessary for decommissioning of facilities. Facilities to be rehabilitated are > 3 km from the
nearest village, therefore visible impacts are expected to be Minor to Negligible (refer to Table 9-35).
Progressive rehabilitation and revegetation during operation (e.g. WRD) and full-scale rehabilitation and
revegetation of the remainder of the temporarily disturbed areas (refer to Section 9.1) will incrementally
improve the visual amenity of the Project Footprint. The view from the PNNK will gradually improve as the
WRD is rehabilitated and the post-closure impact is expected to be Negligible. Though some landforms will
differ from their pre-Project morphology, provision of natural ecosystems during the five-year closure period
is a primary objective of the Rehabilitation and Conceptual Mine Closure Plan (Volume E).
Table 9-35 Post-Closure Visual Impact Assessment
Site Name Distance
From Pit
Visual Modification Impact
Assessment
Tambanoumouya 3.0 km Upper Pit rim LOW
Kerekonko 4.0 km Upper Pit rim LOW
PNNK (southern portion) 4.3 km Rehabilitated WRD NEGLIGIBLE
Linguekoto 4.5 km NA NEGLIGIBLE
Dalakoy 4.7 km NA NEGLIGIBLE
Wassadou 5.2 km NA NEGLIGIBLE
Badian (Maragoukoto) 7.4 km NA NEGLIGIBLE
Mako 8.6 km NA NEGLIGIBLE
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-109
Site Name Distance
From Pit
Visual Modification Impact
Assessment
Niemenike/National Route 7 9.0 km Rehabilitated WRD NEGLIGIBLE
Sekoto 14.4 km NA NEGLIGIBLE
Tomboronkoto 17 km NA NEGLIGIBLE
9.15.2 Avoidance, Mitigation and Management Measures
Avoidance
The following will be adopted by the Company to reduce Project related impacts to visual amenity during
operation:
Lighting design will incorporate the minimum wattage required for a safe working environment;
Lights will be pointed downward and toward operational areas, minimising light egress.
Shielded lighting will be utilised to minimise night-time light egress from operational areas and
skyglow.
Low-visibility fencing will be utilised to the extent practicable (such as wire mesh, rather than palisade
or solid fence structures);
Non-reflective surfaces for incorporated into roofing, fencing and building design.
Signage will be restricted to the minimum required with due consideration to safety; and
Visual barriers will be evaluated for implementation, such as tree or bamboo planting (e.g. around Mine
Pit perimeter that does not require access) to reduce potential impacts on visual amenity.
Minimisation
The Company will adopt the following measures to minimise impacts to visual amenity of the PDA (and
surrounds) during construction:
Vegetation clearance will be restricted to the minimum extent practicable for Project construction;
Cleared areas around facilities will be progressively rehabilitated and revegetated to the extent
practicable as soon as respective areas are no longer required for construction / operation;
Dust suppression (water spray) will be actively implemented on the unsealed road network during the
dry season (refer to Section 9.8 and Chapter 11), particularly near sensitive receptors;
Project structures will be painted in muted colours in keeping with the local area and vegetation;
Construction sites will be well maintained and kept tidy;
Physical barriers such as earth/rock banks or vegetation will be considered for concealing Project
components to the extent feasible;
Long-term soil stockpiles will be planted / seeded with grasses or similarly fast growing vegetation;
Where relevant, visual amenity management and mitigation measures will be incorporated into the
Construction and Environmental Management Plan(CEMP); and
A Grievance Mechanism will be established to provide a means for responding to stakeholder
concerns.
Rehabilitation / Decommissioning / Closure
As per the Rehabilitation and Conceptual Mine Closure Plan (Volume E), disturbed areas will be
progressively rehabilitated throughout Project operation. For example, the WRD will be revegetated from the
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-110
bottom upward throughout operation and is expected to be revegetated in advance of Project closure (as
waste disposal will cease after the sixth year of operation).
Temporarily disturbed areas (e.g. WRD, TMF, Process Plant and ROM Pad, Power Station, WSD, etc.) will be
rehabilitated and revegetated during Project closure to provide self-sustaining natural ecosystems similar to
the surrounding environment. After decommissioning / contouring landforms; Tree savannah, Wooded
savannah, or Shrub savannah vegetative communities will be established (refer to Rehabilitation and Conceptual Mine Closure Plan, Volume E). Though the shape of some landforms will change (e.g. WRD and
TMF), the habitat quality (and visual amenity) will increasingly improve following Project decommissioning
until these facilities blend with their surroundings. Given the high rainfall and tropical climate of the region,
regeneration of the savannah is expected to be fairly rapid, though tree growth may require some time to
achieve pre-Project character.
The Mine Pit, workforce accommodation facilities and the majority of road infrastructure will remain following
Project closure. As vegetation establishes around remaining facilities, the visual amenity will incrementally
improve.
9.15.3 Residual Impact Assessment
During construction, there may be moderate impacts on visual amenity for the villages of Tambanoumouya
and Kerekonko and eastern limit of PNNK, with direct line-of-site to some of the Badalla Valley vegetation
clearance and Process Plant construction area. There may also be a moderate impact on the village of
Linguekoto, with exposure to road upgrade work and increased vehicular travel (and dust) associated with
upgrade of the existing Access Road from Mako to Tambanoumoya, paralleling the Gambia River. Given the
distance and topographic shielding for much of the PDA, management measures are expected to reduce
impacts to visual amenity to a Minor or Negligible level of impact for the remainder of the receptors during
construction.
During operation, there may be Moderate impacts on the visual amenity for Tambanoumouya and Kerekonko
as well as the eastern limit of the PNNK. The WRD will become progressively more visible and night-lighting
may be directly visible from the Badalla Valley and the ridgeline separating Badalla / Wayako Valleys. Given
the topographic shielding, distance to the PDA, and management / mitigation measures, Minor to Negligible
level impacts to visual amenity are anticipated for the remainder of receptors in proximity to the PDA (i.e.
within 20 km) during operation, with the primary impact expected to be skyglow. Measures to reduce egress
of light from night-time work areas during operation will significantly reduce this potential impact.
Post-closure, rehabilitation and revegetation activities will progressively return the visual amenity of
temporarily disturbed areas to pre-Project conditions (refer to Figure 9-20). The Mine Pit (a permanently
impacted facility) will likely not be visible for local communities (sub-surface with vegetative buffer for the Pit
rim). Residual impacts to visual amenity will include the existence of the Main Access Road and workforce
accommodation facilities, which are considered low to Negligible impacts.
The key expected residual impacts related to visual amenity under normal operating conditions, and their
overall significance for each Project phase, are summarised in Table 9-36. Monitoring will be required over the
mine life to confirm the residual impact predictions, and allow management measures to be adapted
accordingly.
Table 9-36 Summary of key expected pre-mitigation impacts, mitigation measures and residual impacts on visual
amenity for each Project phase
Receptor / Value Expected Pre-Mitigation Impact Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and
Overall Impact Significance
Pre-Construction / Construction
Visual Amenity MODERATE Vegetation clearance
restricted to the minimum extent practicable for Project
MINOR
Visual impacts are Minor in specific view
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-111
Receptor / Value Expected Pre-Mitigation Impact Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and
Overall Impact Significance
Pre-Construction / Construction
construction
Cleared areas around facilities progressively rehabilitated and revegetated to the extent practicable as soon as respective areas are no longer required for construction / operation
Project structures painted in muted colours in keeping with the local area and vegetation
Construction sites well maintained and kept tidy
Physical barriers such as earth/rock banks or vegetation considered for concealing Project components to the extent feasible
Where relevant, visual amenity management and mitigation measures incorporated into the CEMP
Routine checks for compliance
fields
Operation
Visual Amenity MODERATE
Lighting design will incorporate the minimum wattage required for a safe working environment
Lights pointed downward and toward operational areas, minimising light egress
Shielded lighting utilised to minimise night-time light egress from operational areas and skyglow
Low-visibility fencing will be utilised to the extent practicable (such as wire mesh, rather than palisade or solid fence structures)
Visual barriers evaluated for implementation, such as tree or bamboo planting (e.g. around Mine Pit perimeter that does not require access) to reduce potential impacts on visual amenity
Routine checks for
MINOR
Progressive habitat restoration will reduce overall impacts in the Operation Phase
Use of screening vegetation to reduce visibility of large mine structures
Large structures will be visible from specific view fields
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-112
Receptor / Value Expected Pre-Mitigation Impact Significance
Key Management & Mitigation Measures
Key Expected Residual Impacts and
Overall Impact Significance
Pre-Construction / Construction
compliance
Decommissioning / Closure
Visual Amenity MODERATE
Restoration activities conducted in accordance with Rehabilitation and Conceptual Mine Closure Plan
Use of selected native and endemic vegetation for revegetation of site areas
Use of fast growing vegetation to reduce visual impacts of closure as quickly as possible
Routine checks for compliance
MINOR
Habitat restoration will reduce overall visual impacts Post-Closure
Some areas of permanent vegetation loss will remain (e.g. pit and TMF)
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 9-113
Figure 9-20 Mako Gold Project Post-Closure