Management Advisor Group International, Inc.
Transcript of Management Advisor Group International, Inc.
Fire Department Feasibility Study
July 2016
By:
Management Advisory Group
International, Inc. 13580 Groupe Drive, Suite 200
Woodbridge, VA 22192 (703) 590-7250
Johns Creek, GA
MANAGEMENT ADVISORY GROUP INTERNATIONAL, INC.
LOCAL GOVERNMENT CONSULTING
August 5, 2016
Warren Hutmacher
City Manager
City of Johns Creek
12000 Findley Rd.
Johns Creek, Ga. 30097
Dear Mr. Hutmacher:
Management Advisory Group International, Inc. (MAG) is pleased to present the enclosed draft report to the City of Johns Creek, for a Fire Department Feasibility Study. This report has been a cooperative, yet independent, work effort between the Fire and Rescue Department and Management Advisory Group International, Inc.. We appreciate the hard work of Fire Department staff in providing substantial data and a wide variety of maps based on MAG’s inquiries. On behalf of Chief Neville of MAG and myself, MAG extends its appreciation to all within the City who contributed ideas, feedback, and views on the important services provided by the Johns Creek Fire Department. We look forward to continuing towards finalization of the report.
Sincerely,
Donald C. Long, Ph.D.
President
Management Advisory Group International, Inc.
13580 Groupe Drive, Suite 200
Lake Ridge, VA 22192
(703) 590-7250
Johns Creek, GA
City of Johns Creek, GA
Fire Department Feasibility Study
TABLE OF CONTENTS
Title Page.......................................................................................................................
Letter of Transmittal .....................................................................................................
Table of Contents .............................................................................................................
1.0 Project Goals and Objectives…..……………………....................................................... 1
2.0 Fire Department Current Situation........................................................................ 7
3.0 Findings and Observations…................................................................................. 12
4.0 Options for Review…..…………………...................................................................... 19
5.0 Implementation Schedule.................................................................................... 45
Johns Creek, GA
Management Advisory Group International, Inc. 1
1.0 Project Goals and Objectives
The Request for Proposals indicated several objectives that described the goals and
objectives for this project. They included:
� Perform a comprehensive review of the current service delivery strategy for the provision
of fire and rescue services in the City;
� Review the potential for continued/expanded use of mutual/automatic aid agreements;
� Consider alternate emergency service deployment methods;
� Examine existing fire station locations to include relocating fire station(s), eliminating fire
stations or locating new fire stations;
� Review the use of substations/partnering with existing facilities such as Emory Johns
Creek Hospital; and,
� Review and consider any creative or alternate ideas that would provide a solution to
perceived service delivery inequity.
1.1 Overall Approach
This type of study is best undertaken through a cooperative effort that includes
extensive feedback and discussion of issues, cost factors, and desired outcomes. This has
been accomplished through structured personal interactions with key officials and
personnel, analysis of City provided data and reports, personal survey of the fire, rescue and
emergency medical services environment and Fire Department resources.
Generally, the first portion of the study resulted in a clarif ication of the issues
and existing operations. Subsequent analysis has provided a base of information upon which
recommendations for action are based.
Johns Creek, GA
Management Advisory Group International, Inc. 2
The second major portion of the study has been to create a series of options focusing
on the critical scope of work items for the study. Options are balanced between the desired
level of services and the cost-effectiveness of delivering those services. MAG is sensitive
to the demands of emergency services, the rather unusual traffic conditions and
infrastructure, the unusual number of very large dwellings, and the limitations of public
funding for critical services.
The third major portion of the scope of work has been the preparation of a report that
includes a plan of action and primary fiscal impact anticipated.
Stakeholder Input. MAG received quality information from City officials, Department
management, and personnel. The approach included in-depth interviews and data review
with key individuals in City management, fire administration and operating staff, and others
who would have valuable information to communicate to the study team.
Practical Solutions. Our ultimate goal is to provide you with a series of
recommendations that can be used now and in the future that will serve as a “road map”
for the future. Thus, our approach has concentrated on developing recommendations that
will result in a higher, more evenly distributed, level of service, a safer environment for your
citizens and firefighters, and a maintenance of the current ISO grade or improvement in the
City’s ISO Grade.
Johns Creek, GA
Management Advisory Group International, Inc. 3
1.2 Methodology
PHASE I: INITIATE PROJECT
TASK 1.0: INITIATE PROJECT
Objectives:
• Gain a comprehensive understanding of the project's background, goals, and
expectations. • Identify, in greater detail, specific objectives for the review, and assess how well the
initial work plan would accomplish those objectives. • Collect and review existing operational data, information, agreements, relevant policies
and procedures.
Activities:
1.1 MAG met with City management, project management, key Fire Department staff and
others to establish working relationships, make logistical arrangements, and determine
communication lines.
1.2 We discussed the objectives of the project and identified policy and issue concerns to
be addressed during the review.
1.3 M AG obtained pertinent reports and background materials relevant to the review,
such as: • organization charts and historical staffing data and deployment data; • descriptions of staffing and deployment in meeting service demands; • location and description of facilities and equipment; • description of the current service delivery system and organization; • demographic and other data related to community growth; • capital and operational budgets; • funding data;
• traffic mapping data;
• response time projection data; and,
• demonstrated response time data.
1.4 F inalized: • data collection approach; • interview plan and tentative schedule and interview guide; and, • interim milestones and deliverables.
Result: • Revised project work plan.
Johns Creek, GA
Management Advisory Group International, Inc. 4
PHASE II: OBTAIN STAKEHOLDER INPUT
TASK 2.0: CONDUCT INTERVIEWS
Objectives:
• Discuss expected service levels for services. • Consider views of officials concerning the operations and performance of the services. • Discuss perceived and demonstrated gaps in existing service levels.
Activities:
2.1 Worked with the Project Manager to finalize the interviewee list.
2.2 Drafted an interview guide.
2.3 Established a final interview schedule.
2.4 Conducted interviews as scheduled.
2.5 Analyzed interview results.
Result:
• Feedback on interviews regarding expressed views towards existing programs, service
levels, and perceived strengths and weaknesses, and related issues.
TASK 3.0: CAPTURE INPUT FROM OPERATIONAL PARTICIPANTS
Objectives:
• Identify concerns and satisfactions at the operating department and staff level. • Identify strengths and weaknesses that may exist in the community.
Activities:
3.1 Developed interview questions. Included questions on staffing, operations, facilities,
and service level focused issues.
3.2 Conducted interviews with Fire Department staff at the stations and JCFD Headquarters.
3.3 Reviewed feedback obtained from these interviews.
Johns Creek, GA
Management Advisory Group International, Inc. 5
Result: • Identification of issues raised, with analysis to be used as part of the facilitation
process and development of the draft and final reports.
PHASE III: PREPARE ANALYSES AND DEVELOP CORE STRATEGIES
TASK 4.0: EVALUATE AND PREPARE INITIAL RECOMMENDATIONS
Objectives:
• Build a series of options focused on study objectives.
Activities:
5.1 Reviewed all input and consensus determinations.
5.2 Assessed issues in reference to best practices and desired outcomes.
5.3 Assessed critical operational components in light of data, and interview input.
5.4 Reviewed the services delivery system in context of the environment.
5.5 Provided a draft report on the results of all previous tasks.
Result: • A draft report.
Johns Creek, GA
Management Advisory Group International, Inc. 6
TASK 6.0: PREPARE A FINAL REPORT AND PLAN
Objective:
• Develop a final plan that identifies the critical action steps to ultimately achieve the
recommended outcomes.
Activities:
6.1 Discussed draft report findings and recommendations with appropriate parties.
6.2 Received and reviewed technical feedback on the draft report.
6.3 Made technical adjustments to the draft to produce a final report.
Deliverable: • A final report that recommends action steps needed, to include the specific action
required, the relat ive timing of the action, and any cost impact of each action.
Deliverables:
• Final Report
Johns Creek, GA
2.0 Fire Department Current Situation
The stated mission of the Fire Department is to:
• Provide high quality advanced life support medical response;
• Rescue individuals from life threatening situations;
• Suppress fires;
• Respond to calls for service;
• Ensure safe buildings, homes and neighborhoods;
• Develop creative, innovative programs that educate the community regarding fire
and life safety; and,
• Support community and citizen events resulting in a safe community for all.
2.1 Station Locations
Fire Department Headquarters is located on the 3rd floor of City Hall at
12000 Findley Road, Suite 380, in Johns Creek. The fire stations are located at: • Fire Station #61 is at 10205 Medlock Bridge Parkway; • Fire Station #62 is at 10925 Rogers Circle; and • Fire Station #63 is at 3165 Old Alabama Road.
2.2 Department Services
The Johns Creek Fire Department provides a diverse set of services to the citizens of the City
of Johns Creek, both emergency and non-emergency. They include:
• Fire Incident Response; • Advanced Life Support Medical Response; • Technical Rescue Response; • Water Rescue Response; • Hazardous Materials Response; • SWAT Medics; • Public Fire & Life Safety Education; • Construction Plan Review; • Fire Prevention Inspections; • Community CPR (Cardio-Pulmonary Resuscitation) Training and Certification; • Charitable Organization Collections; • Toy Drives; • Neighborhood Smoke Detector Blitz and Installation; • Fire Station Blood Pressure Monitoring for the Public; • Child Safety Car Seat Installations; • Fire Origin and Cause Investigations; • Station Visits for the Public and Home and Business Safety Inspections; and, • Community Special Events Participation. 7
Johns Creek, GA
2.3 Department Staffing
Staffing within the Fire Department is as follows:
Headquarters / Administrative Staffing
Fire Chief: (EMT)
Deputy Fire Chief: (Operations) (Paramedic)
Assistant Fire Chief: (Administration) (Paramedic)
Fire Marshal (Division Chief): (EMT)
Support & Technical Services (Division Chief): (EMT)
EMS Coordinator (Lieutenant): (Paramedic)
Fire Inspector / Investigator (Lieutenant): (EMT)
Fire Educator / Inspector (Lieutenant): (Paramedic)
Plan Reviewer (Part-Time):
Executive Assistant:
Administrative Assistant:
10 FT & 1 PT Total
Part-Time Field Operations Staffing
Firefighter II (EMT)
Firefighter II (Paramedic)
Firefighter II (EMT)
Firefighter II (AEMT)
Firefighter II (Paramedic)
Firefighter II (EMT)
Firefighter II (EMT)
7 PT Total
Grand Current Total Staffing = 89 (81 FT & 8 PT)
Staff positions are assigned to the various shifts in the following manner:
8
Johns Creek, GA
Field Operations Current Staffing
Battalion 6 "A" Shift Battalion 6 "B" Shift Battalion 6 "C" Shift
Battalion Chief Battalion Chief: (EMT) Battalion Chief: (Paramedic)
Engine 61 Engine 61 Engine 61
Lieutenant: (Paramedic) Lieutenant: (EMT) Lieutenant: (EMT)
FAO: (EMT) FAO: (EMT) FAO: (EMT)
Firefighter II: (EMT) Firefighter I: (EMT) Firefighter I: (Paramedic)
Firefighter I: Firefighter I: (AEMT) Firefighter II: (EMT)
Truck 61 Truck 61 Truck 61
Captain: (EMT) Captain: (EMT) Captain: (EMT)
FAO: (EMT) FAO: (EMT) FAO: (EMT)
Firefighter II: (EMT) Firefighter II: (AEMT) Firefighter II: (AEMT)
Firefighter I: (Paramedic) Firefighter I: (Paramedic) Vacant
Rescue 61 Rescue 61 Rescue 61
Sergeant: (Paramedic) Sergeant: (Paramedic) Sergeant: (Paramedic)
Firefighter II: (EMT) Firefighter II: (AEMT) Firefighter II: (AEMT)
Engine 62 Engine 62 Engine 62
Captain: (Paramedic) Captain: (EMT) Captain: (Paramedic)
FAO: (EMT) FAO: (EMT) FAO: Robert Jackson (EMT)
Firefighter I: (EMT) Firefighter I: (Paramedic) Firefighter I: (EMT)
Firefighter II: (EMT) Firefighter I: (EMT) Firefighter II: (EMT)
Engine 63 Engine 63 Engine 63
Lieutenant: (EMT) Lieutenant: (Paramedic) Lieutenant: (EMT)
FAO: (EMT) FAO: (EMT) FAO:
Firefghter I: (AEMT) Firefighter II: Firefighter II: (Paramedic)
Firefighter I: (EMT) Firefighter I: (Paramedic) Firefighter II: (EMT)
Truck 63 Truck 63 Truck 63
Captain: (EMT) Captain: (EMT) Captain: (EMT)
FAO: FAO: FAO: (EMT)
Firefighter II: (EMT) Firefighter II: (EMT) Firefighter II: (EMT)
Vacant Vacant Vacant
Rescue 63 Rescue 63 Rescue 63
Sergeant: (Paramedic) Sergeant: (Paramedic) Sergeant: (Paramedic)
Firefighter II: (AEMT) Firefighter II: (EMT) Firefighter II: (AEMT)
24 Total 24 Total 23 Total
Minimum staffing (current 20) represents the minimum number of staff that are assigned
to each shift to ensure that apparatus can be safely deployed. Operations staffing is slightly
greater in order to accommodate “lost” time due to vacations, sick time, and training time.
9
Johns Creek, GA
Management Advisory Group International, Inc.
14 10
2.4 Department Organization
The Fire Department is organized in a relatively traditional manner and with a traditional and
common rank structure.
Johns Creek, GA
Management Advisory Group International, Inc.
14 11
2.5 Apparatus
The Fire Department has three engines (pumpers) and two 100' aerial ladder trucks
(equipped with pumps and hose as well as ground ladders and other typical ladder truck
equipment), in front-line service. The Department also has two (2) transport capable rescues
(sometimes referred to as Quick Response Vehicles or QRVs), which can often respond to
emergencies more quickly than larger equipment.
The QRVs are equipped with 12-lead monitors which monitor heart and lung
conditions and have wired and wireless networking capability to area hospitals, allowing for
monitoring of a patient from the time the first responders in the QRV arrives at the scene of
a medical emergency.
A river rescue boat and a mobile air unit are also part of the department's apparatus.
The Department also has a single reserve engine used in case a front-line apparatus
is disabled.
Johns Creek, GA
Management Advisory Group International, Inc.
14 12
3.0 Findings and Observations
3.1 Current Level of Resources are Inadequate
While MAG finds that the Fire Department appears well managed and operationally
sound, the current John’s Creek Fire Department resources are inadequate to provide an
evenly distributed high level of fire protection and emergency medical service resources to
the majority of the City.
3.2 Issues of Concern to be Addressed
MAG has identified several issues of concern that should be addressed going forward
in the delivery of fire and medical rescue services. They include:
• Inadequate incident command support for shift Battalion Chiefs, thus reducing
incident management effectiveness and heightening firefighter safety issues.
• Large areas of the City of Johns Creek experience extended emergency medical
service response times, thus delaying prompt emergency medical action in those
areas.
• First-response emergency medical service is good only for the southern two-thirds of
the City with time of “arrival on-scene” approximating 6 minutes or less.
• In the northern third, especially in the “shark’s fin” area, prolonged initial emergency
medical response needs improvement to meet generally accepted good practice. The
mutual aid responders often arrive on-scene in the “Shark’s Fin” area after the initial
JCFD unit, which often exceeds 10 minutes. Delayed dispatch procedures seem to be
the most likely cause for the slower than anticipated response time of the mutual-aid
unit.
• Numerous traffic control devices such, as curbed lane dividers, slow emergency
response by requiring units to go to the next break before carrying out a u-turn
toward an incident on the other side of the street.
Johns Creek, GA
Management Advisory Group International, Inc.
14 13
• Other areas in the northern areas needs initial and support structure fire response
improvement, especially in the proximity of:
• Jones and State Bridge Roads intersection
• Jones and Abbots Bridge Roads intersection
• Municipal Court/City Hall
• North of Sergeant Road
• Inadequate staffing at Station 62, thus limiting that station’s interior fire attack and
rescue actions pending arrival of additional resources in order to meet generally
accepted good practice and OSHA regulations (“2in – 2out”).
• There is delayed Truck Company support for Station 62, thus limiting firefighting
effectiveness for that area of the City.
• The current aerial ladder apparatus are ill suited for the Johns Creek environment.
Their design does not allow the mobility required for many development streets and
access roadways which limits utilization of the aerial ladder.
• There is insufficient equipment and long ground ladder capacity on current Truck
Company apparatus, thus limiting fire and rescue activities. The Department lacks
long ground ladder (45-50’) capability limiting certain fire and rescue operations.
• There are an insufficient number of reserve (relief) vehicles to replace vehicles out of
service for maintenance or repair. There is no reserve vehicle for the ladder trucks.
• Fireground training facilities are distant – placing significant restrictions on JCFD
firefighting and rescue workouts.
Johns Creek, GA
Management Advisory Group International, Inc.
14 14
3.3 Johns Creek Fire Department Current Resource Deployment
STATION
APPARATUS DAILY
STAFF
GPM AERIAL COMMENTS
Shift Battalion
Chief: 1
response per
24 hour shift
• Light truck • BC • Inadequate command staff
61:
11 responses
per 24 hour
shift
• Engine
• Truck (Aerial
Quint)
• Rescue
(ambulance)
• LT / FAO /
FF
• CPT / FAO /
FF
• SGT / FF
1500
1500
100’
• Current Truck Company
apparatus not well suited for
John’s Creek.
• Current Rescue apparatus
designed as an ambulance, a
function rarely provided.
62:
1 response per
24 hour shift
• Engine
• Reserve
Engine
• CPT / FAO /
FF
1500 • Current minimum staffing limits
initial interior fire attack and
rescue operations.
63:
7 responses per
24 hour shift
• Engine
• Truck (Aerial
Quint)
• Rescue
(ambulance)
• LT / FAO /
FF
• CPT / FAO /
FF
• SGT / FF
1500
1500
100’
• Current Truck Company
apparatus not well suited for
John’s Creek community.
• Current Rescue apparatus
designed as an ambulance, a
function rarely provided.
Totals I Command
Vehicle
3 Engines
2 Trucks
2 Rescue
Ambulance
1 Reserve
Engine
Min. Staff:
20
7500
1500
2 @100’ 1 Battalion Chief (BC)
3 Captains (CPT)
2 Lieutenants.(LT)
2 Sergeants (SGT)
5 Fire Apparatus Operators (FAO)
7 Firefighters (FF)
Mutual Aid Engine ? ? • Dispatch and staffing issues
make mutual aid response to
Station 61 district problematic
• Alpharetta Engine often does
not reach the “Shark Fin” region
before JCFD units
Johns Creek, GA
Management Advisory Group International, Inc.
14 15
3.4 Review of Mutual Aid
Neither the value nor the limitations of “mutual aid” can be overstated. What is
necessary is that both the value and limitations be fully understood by all parties.
No U.S. fire department is staffed or equipped to successfully control the most
calamitous incident that could befall their community, including the City of New York, the
City of Chicago, the City of Los Angeles or the City of Atlanta.
All communities should have a means of obtaining additional resources in time of
need. There are several forms of mutual aid, or mutual assistance, as it is often termed. The
most prevalent are:
3.4.1 Call When Needed:
This is the most utilized form of mutual-aid used in the U.S. Simply put, an agency
requests another agency to send some type of fire resource to assist in controlling an incident
or providing coverage when the majority or large portion of the requesting agency’s
resources are unavailable for response to emergencies.
The other agency may or may not provide the requested resources, probably
dependent on that agency’s resource status or the situation status in the area for which the
agency is primarily responsible for protecting. It is important to remember that each
agency’s primary responsibility is to the community that fiscally supports them.
It is likely that the requesting agency would not be aware of the requesting agency’s
inability to send assistance until the time of request. The requesting agency then must
request assistance from the next closest agency for which they have an agreement (assuming
there is one).
In some states a coordinating system has been established so that an agency need
only call a single point to request aid to obtain the closest or most appropriate assistance.
Johns Creek, GA
Management Advisory Group International, Inc.
14 16
3.4.2 Automatic-Aid
This often utilized form of mutual aid simply adds another agency’s resource to the
dispatch order for certain, or in some cases all, areas of the community being protected.
It is important to recognize that there is no guarantee that the agency supplying
automatic-aid will be able to send the nearest, or for that matter, any resource to the
requesting agency for the reasons stated above. Hopefully, the requested (supplying) agency
will notify the requesting agency of their inability to supply the request or that the
responding resource will arrive later than expected. However, that notice could be
significantly delayed if the agencies use different dispatch centers.
3.4.3 Contract Aid
Contract aid may not be “mutual aid” in every case. If one party contracts with
another to provide, usually, automatic aid for compensation, typically, in the form of cash,
that is simply “contract aid”. In this case, the warrantee for service is explicitly spelled out
in the contract and there may or may not be fiscal penalties for failing to provide the aid.
Typically, however, there is not a guarantee as to which station or unit (typically the
closest) must respond. So, although one may contract because of the desire to have a certain
unit respond because they are the closest, it is not likely that the contracted agency would
be willing, or even able to provide that sort of guarantee.
In some cases, two agencies will contract to pay each other when mutual aid is
rendered. In this case it can be termed “contracted” mutual aid.
In the specific case of Johns Creek, the utilization of mutual aid to receive credit for a
first-in response of five miles or less, was clearly significantly advantageous to the property
owners (and insurance premium payers) in the “Sharks Fin” area. However, taxpayers
should not be led to believe that this is a “free lunch”.
Johns Creek, GA
Management Advisory Group International, Inc.
14 17
First, “mutual” indicates that in some cases Johns Creek will have one (or more) less
fire company(s) available for Johns Creek needs because JCFD resources will be assisting the
agencies that, on occasion, provide Johns Creek aid.
Second, in practice, the Sharks Fin area, having a mutual fire protection resource
within five miles does not mean Johns Creek is providing that area the same level of service
provided the lower portion of the City. In MAG’s opinion that can only be done with
additional Johns Creek provided resources.
3.5 Review of Potential Relocation of Current Stations
As part of the overall evaluation of resources, station location, and types of apparatus
and deployment issues considered, MAG has reviewed the potential relocation of existing
stations.
3.5.1 Station 61:
Although moving to a site on State Bridge Road, near Johns Creek High School looks
somewhat promising for improving initial response to the west, lack of an obvious suitable
site and impairment of response northerly tarnished this possibility. Moving the station
north on Medlock would improve a problem area in proximity to City Hall and ladder truck
support for station 62, but resulting delays in supporting station 63 would seem to make that
move a net “0” gain. On balance, MAG finds moving station 61 to be unjustified.
3.5.2 Station 62:
The most modern and suitable JCFD station appears to be the site most inappropriate for
the area served. However, the only rationale site (Bell Road / Rogers Bridge Road) that would
improve response to the larger area served would probably result in only slight improvement
and in MAG’s judgment, it is not worth the expense to relocate this station.
Johns Creek, GA
Management Advisory Group International, Inc.
14 18
3.5.3 Station 63:
Moving this station seems the most promising but in MAG’s opinion, is probably not
worth the expense. Establishing a site eastward along Old Alabama Road, toward Jones
Bridge Road, would improve response to the north while maintaining reasonable response
time to the western most part of the City, but is not enough to diminish the need for the
recommended station 64. If, in the future, station modernization becomes feasible, this
move should be considered.
Johns Creek, GA
Management Advisory Group International, Inc.
14 19
4.0 Recommendations and Options for Improvement
Most of the options presented in this report for improvement include
recommendations for utilization of a “quint - squad” concept as a means to hold personnel
costs in check. This concept would provide a means to spread a full spectrum of operational
fire – rescue – EMS capability throughout the access challenged community at significantly
less personnel cost than the traditional Engine / Truck Company format.
In typical Quint operations, the Quint functions as an independent unit, equipped to
carry out either Engine or Truck Company functions as the incident requires. However, in
the City’s case, there is a need to maximize the hose load carried, due to the existence of
very long driveways and very large residences, while limiting vehicle length for access
purposes. This would seem to preclude carrying the full load of firefighting and rescue
equipment on a quint.
To meet that space problem, MAG proposes, in essence, to replace the current “rescue”
vehicle” (QRV- an ambulance) with a vehicle with greater equipment storage volume, using
a slightly larger vehicle without patient transport capability (rescue squad). The two units
would function as a single Company except in those few instances where the rescue squad
was dispatched singularly for a limited need EMS call (under current operating procedures a
small percentage of station dispatches).
MAG proposes that the rescue squad would carry the majority of physical rescue and
EMS equipment, with the quint carrying the majority of the firefighting equipment. This
would enable the quint to function in typical instances at fires without the Rescue squad
being in attendance pending arrival of either another station’s rescue squad or the ladder
truck from station 63.
Johns Creek, GA
Management Advisory Group International, Inc.
14 20
The historic, basic emergency resource configuration in the American fire service has
(with many alterations and adjustments) been engine (pumper) and ladder truck (typically
fitted with an aerial ladder device). Essentially, at structure fires, the engine crew applies the
water to the fire, the ladder truck crew forces open locked doors (pry-bars, axes, hydraulic
tools), ventilates noxious gases (powered fans, power saws & axes to open roofs), provides
extensive search and rescue, and carries out salvage duties. This arrangement of resources
has served the USA well for well over a century. However, several relatively recent matters
have caused some rethinking of resource configuration.
First, and probably foremost, is the matter of personnel costs. Firefighter compensation
has dramatically increased over the last several decades making fire protection staffing one
of local governmental agencies most expensive budget items.
Using the engine/truck format necessitates two separate crews, staffing two separate
vehicles. In order for either crew to effectively carry out their function, certain minimum
crew sizes have proven necessary. Because many fires to which a fire department responds,
do not require the truck company support, typically only about one in three or four stations
were equipped with truck companies (typically with engine companies).
The idea of this arrangement of resources being that when encountering a structure fire
requiring truck company operations, the engine company could prepare to enter the building
while awaiting the arrival of the truck company to “open up”. In reality, it is often the case
that truck work is necessary before the engine company can function effectively, however,
staffing additional ladder trucks (not to mention the million dollars or so for the vehicle), for
the majority of agencies, is not fiscally feasible.
Another issue is the reality that most fire agencies, especially those in urban areas are
experiencing fewer structure fires, resulting in a situation where fire agencies now respond
primarily to other than structure fires, e.g. emergency medical emergencies, physical
rescues, auto accidents, etc. This results in the ladder trucks, while becoming more
expensive to staff and purchase, being utilized less and less.
Johns Creek, GA
Management Advisory Group International, Inc.
14 21
This situation has resulted in many agencies experimenting with different ways of
configuring their fire/rescue/emergency medical service resources. These include:
• Use of lighter-weight, less expensive, less heavily staffed, “rescue vehicles”, e.g.
ambulances, panel trucks, pickups, etc. - This has had generally good, but limited
beneficial results (better for EMS, not so good when encountering fire or heavier
rescue situations).
• Cross-staffing of engines and ladder trucks, i.e., depending on the call received, staffing
one or the other. - This has resulted in some very confused responses and, in MAG’s
opinion, is not an effective allocation of resources.
• Task force, i.e. minimally staffing two vehicles that respond in tandem – This provides
great flexibility in capability but has resulted in very expensive vehicles responding to
minor (in terms of resource requirements, e.g. EMS) events and heavier use of said
expensive vehicles resulting in required early replacement of those vehicles. Again, in
MAG’s view, not an effective use of resources.
• Spacing ladder trucks even further apart, - Making their effective arrival even less likely.
• Use of multi-functional vehicles – “quints” – meaning:
•• They are equipped with a large pump (1000-2000 GPM)
•• Carry several different size (diameter) hose (4”-5” for hydrant supply, 3”-1.5” for
fire attack)
•• Have a large water tank (300-500+ gallon)
•• Carry a large array of ground ladders (35’-12’)
•• Are equipped with a powered aerial ladder device (50’-100’)
No knowledgeable party in the fire service would argue that having a quint staffed
with four (4) firefighters arrive at the scene of a structure fire is the equivalent of an engine
and a ladder truck, each staffed with four (or even three) firefighters.
However, it is MAG’s (and others experienced in the fire service) position that having
three (3) properly equipped quints, staffed with four (4) firefighters each, arrive at the scene
at different times, but all within 10-12 minutes, is superior to having two engines, and one
ladder truck arrive within those same time periods.
Johns Creek, GA
Management Advisory Group International, Inc.
14 22
We take that position based on the fact that any one of the three quints can under-
take either engine or ladder truck functions as required by the situation they encounter as
opposed to having engines arrive on scene but being essentially limited to applying water
(and any making straight-forward rescue attempts necessary), while awaiting arrival of the
ladder truck.
One disadvantage of the quint concept is the tendency to over-equip the vehicle,
making it too large to maneuver sufficiently to properly place at the fire scene, e.g. trucks
(quints) 61 and 63.
More recent quint designs have found means around that negative tendency. These
vehicles have in the main limited the length of the aerial ladder (typically 75’), the capacity
of the water tank (typically 300-400 gallons) and the amount of hose carried. These vehicles
have turning radiuses approximating that of an engine (pumper).
In MAG’s view, for use in the Johns Creek environment, the limited aerial ladder
length is more than justified by the ability of these more maneuverable apparatus to be
placed in advantageous firefighting and rescue positions and negotiate Johns Creek traffic.
Because the City is so well provided with fire hydrants, the limited water tank would
not seem to be a significant disadvantage.
But, limited hose capacity is an issue that must be addressed. The very large and
sometimes convoluted residences with very long driveways require extended length of
attack hose availability as well as hydrant supply hose lines
The shorter, more maneuverable quints with which MAG is familiar are not designed,
in MAG’s opinion, with sufficient hose storage capacity to meet Johns Creek needs. To meet
this dilemma MAG proposes allocating to each station housing a quint, a larger capacity
rescue vehicle than the ambulances now in service with the JCFD.
Johns Creek, GA
Management Advisory Group International, Inc.
14 23
Their function would be to respond to EMS calls, as the QRV’s (ambulances) now do, as well
as to fires and to carry rescue, salvage, lighting and other support equipment in order to
provide additional hose capacity space on the quint apparatus.
The quint apparatus proposed by MAG would be equipped to initiate immediate fire
attack in those few instances where the supporting Rescue Squad apparatus did not respond
in tandem. Examples of equipment carried on the Rescue Squad in lieu of the quint would
be:
• Incident scene lighting and large generator
• Salvage equipment (e.g., water & fire resistant covers, sawdust, scoop shovels, brooms)
• Hydraulic tools
• Large powered fans (for noxious gas evacuation)
• Cutting torch
• Air hammer /chisel
The situation where a quint might arrive without an accompanying rescue squad will
occur primarily when the rescue squad is assigned to an emergency medical incident. In that
event, the nearest rescue squad from another station would be dispatched in support. As
well as carrying support equipment for the quints, using the lighter, less expensive rescue
squads for certain EMS dispatches would save wear and tear on the quints and typically make
the quints available for further dispatch more expeditiously at EMS incidents.
The recommended staffing for a quint-equipped station is six (6), with four (4)
personnel on the quint, and two (2) personnel on the rescue squad. The current (and
recommended) staffing for a station housing the engine, truck, rescue configuration is eight
(8), with three (3) personnel on engine and truck, and two (2) personnel on rescue. For
every station configured with quint / rescue squad apparatus as opposed to the engine /
truck / rescue configuration there is a 25% reduction in recommended staffing.
Johns Creek, GA
Management Advisory Group International, Inc.
14 24
In order to retain the availability of a 100’ aerial, in some allocation options presented,
MAG proposes, in most of the options, equipping one station with a 100’ tiller aerial ladder
truck (to improve maneuverability over current 100’ quints), an engine, and a rescue squad.
MAG also is recommending that one of the ambulances replaced by rescue squads be
retained in reserve for those rare (estimated at once a year) incidents where it is desirable
to transport a victim rather than wait for a delayed contract ambulance.
Concerning the City’s ISO grade, any of the options offered should maintain, if not
improve, the City’s ISO grading.
Any significant service level improvement option considered viable by MAG, from a
performance point of view, would require additional costs in the form of personnel,
equipment, and facilities.
Options for consideration are presented below on the following pages:
Johns Creek, GA
Management Advisory Group International, Inc.
14 25
4.1 Option 1:
This option adds an additional fire station (64) in the proximity of Jones Bridge
intersection with Hanstedt Terrace. This option equips that station with quint/squad
apparatus; increases incident command support; replaces station 61’s 100’ quint with a
tiller 100’ aerial and ambulance 61 with a rescue squad; replaces station 62’s single engine
with a quint/squad apparatus; and replaces station 63’s engine, truck, ambulance
apparatus with quint/squad apparatus. This option requires the following significant fiscal
commitments:
Option One: Estimated Costs
Item Estimated Cost
Twenty-eight (28) additional payroll positions &
1.2 FTE overtime costs
$2,628,000.00 (+benefit package) @
$90K/ position
Purchase of one tiller aerial ladder Truck, three
75’ Quint apparatus, and four Rescue squad
apparatus.
$5,100,000
Purchase of property for and design,
construction and furnishing of an additional fire
station.
$1,360,000 (JCFD 1/20/15 estimate)
Purchase of additional necessary
communications equipment.
Undetermined
MAG believes there would be substantial benefits from Option #1, including:
• Initial response times would be significantly improved for large areas of the City,
thus improving emergency medical service in those areas of the City.
• Initial and support firefighting personnel response would be significantly increased,
thus enhancing firefighting and rescue capacity in all areas of the City.
• Incident command support and related administrative functions would be
significantly increased, thus enhancing incident management effectiveness and
firefighter safety.
Johns Creek, GA
Management Advisory Group International, Inc.
14 26
• This option would increase staffing and improve equipment capabilities for Station
62, thus improving firefighting and rescue capabilities for the south-east side of the
City and for the City as a whole.
• Provides “long” ground ladder capability and enlarges equipment storage
compartment space for Truck 63, thus improving firefighting and rescue capabilities.
• Increases aerial ladder truck mobility, thus improving firefighting and rescue
capabilities.
• Increases reserve apparatus fleet, resulting in one reserve Truck, one reserve
Rescue Ambulance and two reserve Engines.
Johns Creek, GA
Management Advisory Group International, Inc.
14 27
JOHN’S CREEK FIRE DEPARTMENT RESOURCE DEPLOYMENT LOG - OPTION 1
STATION APPARATUS DAILY STAFF GPM AERIAL COMMENTS
Shift
Battalion
Chief
• Pickup • BC
• CPT
• Adds incident command support
(Captain)”
61 • Engine
• Truck (tiller aerial)
• Rescue squad
• Reserve
Ambulance
• LT,/ FAO/ FF
• CPT/ FAO /FF
• SGT/ FF
1500
100
• Replaces 100’ Quint with more agile tiller
aerial.
• Increases equipment storage capacity
• Provides long ground ladder capability
(50’)
• Replaces Rescue Ambulance with Rescue
squad
• Retains replaced Rescue Ambulance 63
for reserve
62 • 75’ Quint
• Rescue squad*
• Reserve Engine
• CPT/ FAO/ 2 FF
• SGT/ FF
2000 75’ • Replaces single Engine with 75’ Quint and
Squad
* Increases staffing by 3
• Retains reserve Engine for relief and off-
road response
63 • 75’ Quint
• Rescue squad*
• Reserve Engine
• CPT / FAO / 2 FF
• SGT / FF
2000 75’
• Replaces Engine, 100’ Quint & Rescue
(ambulance) with 75’ Quint and Rescue
squad
• Reduces staff by 2
• Retains replaced Engine for reserve and
off-road response
64 • 75’ Quint
• Rescue squad*
• Reserve Truck
• CPT / FAO / 2 FF
• SGT / FF
2000 75’ • Additional station with 75’ Quint &
Squad.
• Retains replaced 100’ Quint for reserve
Totals I Command Veh.
3 Quints
1 Engine
1 Truck (tiller aerial)
4 Rescue squad
2 Reserve Engines
1 Reserve Truck
1 Reserve Amb.
Minimum Staff 28
7500
1 @100’
3 @75’
1 Battalion Chief (BC)
5 Captains (CPT)
1 Lieutenant.(LT)
4 Sergeants (SGT)
5 Fire Apparatus Operators (FAO)
12 Firefighters (FF)
Mutual
Aid
Engine ? ? • Dispatch and staffing issues make mutual
aid response to Station 61 problematic
• Alpharetta Engine does not often reach
the “Shark Fin” region before JCFD units
Johns Creek, GA
Management Advisory Group International, Inc.
14 28
4.2 Option 2:
This option (#2) also would include the construction, equipping and staffing of an
additional station (#64) in the proximity of Jones Bridge intersection with Hanstedt
Terrace, to meet the resource and deployment needs of the City. The staffing levels
required would be less than Option #1, and the apparatus/equipment needed would be
different, equipping all stations with quint / squads, deleting the 100’ aerial ladder at
station 61. This option requires additional resources and fiscal commitments, including:
Option Two: Estimated Costs
Item Estimated Cost
Twenty-one (21) additional payroll positions & .9
FTE overtime costs
$1,971,000.00 (+ benefit package @
$90K / position)
Purchase of four 75’ Quint apparatus and four (4)
Rescue squad apparatus
$4,800,000
Purchase of property for and design,
construction and furnishing of an additional fire
station
$1,360,000 (JCFD 1/20/15 est.)
Purchase of additional necessary
communications equipment.
Undetermined
MAG believes there would be substantial benefits from this option, including:
• Significantly Improves initial response time for large areas of the City, thus improving
emergency medical service in those areas of the City.
• Significantly increases firefighting personnel response, thus enhancing firefighting
and rescue capacity in all areas of the City.
• Significantly increases incident command support, thus enhancing incident
management effectiveness and firefighter safety.
• Increases staffing and provides limited truck capabilities for Station 62, thus
improving firefighting and rescue capabilities for the south-east side and for the City
as a whole.
Johns Creek, GA
Management Advisory Group International, Inc.
14 29
• Enlarges equipment storage compartment space, thus improving firefighting and
rescue capabilities.
• Increases aerial ladder capability and mobility – improving firefighting and rescue
capabilities (note that while gaining mobility over current deployment, the
Department loses access to a 100’ aerial except in reserve status).
• Increases reserve apparatus fleet, resulting in one reserve Truck one reserve Rescue
Ambulance and two reserve Engines. Increases total pumping capacity.
Johns Creek, GA
Management Advisory Group International, Inc.
14 30
JOHN’S CREEK FIRE DEPARTMENT RESOURCE DEPLOYMENT LOG- Option 2
STATION APPARATUS STAFF GPM AERIAL COMMENTS
Shift
Battalion
Chief
Pickup 1 BC
1 CPT
• Adds incident command support
(Captain)”
61 Quint
Rescue squad*
Reserve Engine
Reserve Ambulance
CPT / FAO / 2
FF
SGT/ FF
2000 75’
• Replaces Engine, 100’ Quint & Rescue
(ambulance) with 75’ Quint and Rescue
squad
• Reduces staff by 2
• Retains replaced Engine for reserve and
off-road response
• Retains replaced Rescue Ambulance for
reserve.
62 Quint*
Rescue squad*
Reserve Engine
CPT / FAO / 2
FF
SGT/ FF
2000 75’ • Replaces single Engine with 75’ Quint and
Squad
* Increases staffing by 3
• Retains reserve Engine for relief and off-
road response
63 Quint
Rescue squad*
CPT / FAO / 2
FF
SGT/ FF
2000 75’
• Replaces Engine, 100’ Quint & Rescue
(ambulance) with 75’ Quint and Rescue
squad
• Reduces staff by 2
• Retains replaced Rescue Ambulance for
reserve
64 Quint*
Rescue squad*
Reserve Truck
CPT / FAO / 2
FF
SGT/ FF
2000 75’ • Additional station with 75’ Quint and
Squad.
• Retains replaced 100’ Quint for reserve
Totals I Command Vehicle
4 Quints
4 Rescue squad
2 Reserve Engines
1 Reserve 100’ Quint
1 Reserve
Ambulance
Minimum staff:
26
8000
4-75’ 1 Battalion Chief (BC)
5 Captains (CPT)
4 Sergeants (SGT)
4 Fire Apparatus Operators (FAO)
12 Firefighters (FF)
Mutual Aid Engine ? ? • Dispatch and staffing issues make mutual
aid response to Station 61 district
problematic
• Alpharetta Engine does not often reach
the “Shark Fin” region before JCFD units
Johns Creek, GA
Management Advisory Group International, Inc.
14 31
4.3 Option 3:
This option (#3) would include the construction and staffing of two (2) additional
stations: #64 at the proximity of Jones Bridge intersection with Hanstedt Terrace; and,
#65 at Medlock Bridge Road (near City Hall), to meet the long-term resource and
deployment needs of the City. The apparatus and equipment needed would be different
from other options in that the engine/truck concept is used rather the quint/squad,
thereby significantly increasing staffing requirements (but increasing aerial ladder
capability). This option requires additional resources and fiscal commitments, including:
Option Three: Estimated Costs
Item Estimated Cost
Fifty (50) additional payroll positions & 1.2 FTE
overtime costs
$4,608,000.00 (+ benefit package)
Purchase of three tiller aerial ladder Trucks, and
three (3) Rescue squad apparatus (but of less
capacity than with quint / rescue squad concept)
$4,500,000
Purchase of property for and design,
construction and furnishing of two additional fire
stations
$2,720,000 (JCFD 1/20/15 est.)
Purchase of additional necessary
communications equipment.
Undetermined
MAG believes there would be substantial benefits from this option, including:
• Dramatically Improves initial response time for large areas of the City – improving
emergency medical service in those areas of the City.
• Dramatically firefighting personnel response, thus enhancing firefighting and rescue
capacity in most areas of the City.
• Significantly increases incident command support, thus enhancing incident
management effectiveness and firefighter safety.
Johns Creek, GA
Management Advisory Group International, Inc.
14 32
• Increases staffing for Station 62, thus improving initial fire attack and rescue
capabilities.
• Reduces truck company support time for Station 62
• Greatly increases “long” ground ladder capability and enlarges equipment storage
compartment space, thus improving firefighting and rescue capabilities.
• Greatly increases aerial ladder capability and mobility, thus improving firefighting and
rescue capabilities.
• Greatly Increases aerial ladder availability and mobility, thus improving firefighting
and rescue capabilities.
• Increases reserve apparatus fleet, resulting in one reserve Truck, one reserve
ambulance and one reserve Engines
Johns Creek, GA
Management Advisory Group International, Inc.
14 33
JOHNS CREEK FIRE DEPARTMENT RESOURCE DEPLOYMENT LOG – Option 3
STATION APPARATUS STAFF GPM AERIAL COMMENTS
Shift
Battalion
Chief
Pickup • BC
• CPT
• Adds incident
command support
(Captain)”
61 • Engine
• Truck (tiller aerial)
• Rescue squad
• Reserve Ambulance
• LT,/ FAO/ FF
• CPT / FAO / FF
• SGT/ FF
1500
100
• Replaces 100 Quint
more agile tiller aerial
• Increases equipment
storage capacity
• Provides long ground
ladder capability (50’)
• Replaces Ambulance
with Rescue squad
• Retains replaced
Rescue Ambulance for
reserve
62 • Engine
• Reserve Engine
• CPT / FAO / 2 FF
1500 * Increases staffing by 1
• Retains reserve Engine
63 • Engine
• Truck (tiller aerial)
• Rescue squad
• LT,/ FAO/ FF
• CPT / FAO / FF
• SGT/ FF
1500
100
• Replaces 100 Quint
more agile tiller aerial
• Increases equipment
storage capacity
• Provides long ground
ladder capability (50’)
• Replaces Ambulance
with Rescue squad.
64 • Engine
• Reserve Engine
• Reserve Truck
• CPT / FAO / 2 FF 2000 • Additional station with
Engine only.
• Retain replaced 100’
Quint for reserve.
65 • Engine
• Truck (tiller aerial)
• Rescue Squad
• LT,/ FAO / FF
• CPT / FAO / FF
• SGT/ FF
2000
100 • Replaces 100 Quint
more agile “tiller aerial”.
• Increases equipment
storage capacity
• Provides long ground
ladder capability (50’)
• Replaces Rescue
Ambulance with Rescue
Squad
Johns Creek, GA
Management Advisory Group International, Inc.
14 34
DEPLOYMENT LOG
Option 3
(cont.)
Totals I Command Vehicle
2 Quints
2 Engine
1 Truck (tiller aerial)
3 Rescue squad
2 Reserve Engines
1 Reserve Truck
1 Reserve Ambulance
Minimum Staff: 34
8500
3-100’
1 Battalion Chief (BC)
6 Captains (CPT) 1
3 Lieutenant.(LT) 1
3 Sergeants (SGT) 1
8 Fire Apparatus
Operators (FAO)
13 Firefighters (FF) 4
See Appendix for details
of 75’ Quint and Rescue
squad apparatus
Mutual Aid Engine ? ? • Dispatch and staffing
issues make mutual aid
response to Station 61
district problematic
• Alpharetta Engine does
not often reach the
“Shark Fin” region
before JCFD units.
Johns Creek, GA
Management Advisory Group International, Inc.
14 35
4.4 Option 4:
This option (#4) also would include the construction and staffing of two (2)
additional stations (#64 and #65) to meet the long-term resource and deployment needs
of the City. The staffing levels required would be the same as Option 3 but the apparatus
and equipment needed would be different. This option requires additional resources and
fiscal commitments, including:
• Fifty (50) additional payroll positions & 1.2 FTE overtime costs:
$4,608,000.00 @$90K/ position
• Purchase of a tiller aerial ladder Truck, four (4) Quints and five (5) Rescue squad
apparatus:
$6,300,000.00 (MAG estimate)
• Purchase of property for and design, construction and furnishing of two (2)
additional fire stations
$2,720,000.00 (JCFD 1/20/15 est.)
• Purchase of additional necessary communications equipment: Undetermined
Option Four: Estimated Costs
Item Estimated Cost
Fifty (50) additional payroll positions & 1.2 FTE
overtime costs
$4,608,000.00 @$90K/ position
Purchase of a tiller aerial ladder Truck, four (4)
Quints and five (5) Rescue squad apparatus
$6,300,000
Purchase of property for and design,
construction and furnishing of two (2) additional
fire stations
$2,720,000
Purchase of additional necessary
communications equipment.
Undetermined
Johns Creek, GA
Management Advisory Group International, Inc.
14 36
MAG believes there would be substantial benefits from this option, including:
• Dramatically Improves initial response time for large areas of the City, thus improving
emergency medical service in those areas of the City.
• Dramatically improves firefighting personnel response, thus enhancing firefighting
and rescue capacity in most areas of the City.
• Significantly increases incident command support, thus enhancing incident
management effectiveness and firefighter safety.
• Increases staffing for Station 62, and provides increased truck support thus
improving initial fire attack and rescue capabilities.
• Significantly improves “long” ground ladder capability and enlarges equipment
storage compartment space for Truck 63, thus improving firefighting and rescue
capabilities.
• Dramatically increases aerial ladder capability and mobility, thus improving
firefighting and rescue capabilities.
• Dramatically increases aerial ladder availability, thus improving firefighting and
rescue capabilities. Increases pump capacity by 2000 gpm.
• Increases reserve apparatus fleet, resulting in one reserve Truck, two (2) reserve
Ambulances (replaced 61s & 63s) and two (2) reserve Engines (replaced Engines 61
and 62).
Johns Creek, GA
Management Advisory Group International, Inc.
14 37
JOHNS CREEK FIRE DEPARTMENT RESOURCE DEPLOYMENT LOG – Option 4
STATION APPARATUS STAFF GPM AERIA
L
COMMENTS
Shift
Battalion
Chief
Pickup • BC
• CPT
• Adds “Command Assistant” (Captain)
61 • Engine
• Truck (tiller
aerial)
• Rescue squad
• Reserve
Ambulance
• LT,/ FAO / FF
• CPT / FAO / FF
• SGT/ FF
1500
100
• Replaces 100 Quint more agile “tiller
aerial”.
• Increases equipment storage
capacity
• Provides long ground ladder
capability (50’)
• Replaces Rescue Ambulance with
Rescue squad
• Retains Replaced Rescue Ambulance
for Reserve
62 • Quint
• Rescue squad
• Reserve Engine
• CPT / FAO / 2
FF
• SGT / FF
2000 • Replaces Engine with 75’ Quint and
Rescue squad
* Increases staffing by 3
• Retains Engine for reserve
63 • Quint
• Rescue squad
• CPT / FAO / 2
FF
• SGT / FF
2000 75’
• Replaces Engine, 100’ Quint & Rescue
(ambulance) with 75’ Quint and
Rescue squad
• Reduces staff by 2
64 • Quint
• Rescue squad*
• Reserve Truck
• CPT / FAO / 2
FF
• SGT / FF
2000 75’ • Additional station with 75’ Quint and
Rescue squad.
• Retain replaced 100’ Quint for
reserve
65 • Quint
• Rescue squad
• Reserve Engine
•• CPT / FAO /
2 FF
• SGT / FF
2000
100 • Additional station with 75’ Quint and
Rescue squad.
• Retains Engine for reserve
Totals I Command
Vehicle
4 Quints
1 Engine
1 Trucks (tiller
100’ aerial)
5 Rescue squad
2 Reserve Engines
1 Reserve Truck
1 Reserve
Ambulances
Minimum Staff:
34
9,500
1-100’
4-75’
1 Battalion Chief (BC)
6 Captains (CPT)
1 Lieutenants (LT)
5 Sergeants (SGT)
6 Fire Apparatus Operators (FAO)
15 Firefighters (FF)
See Appendix for details of 75’ Quint
and Rescue squad apparatus
Johns Creek, GA
Management Advisory Group International, Inc.
14 38
DEPLOYMENT
LOG
Option 4
(cont.)
Aid Engine ? ? • Dispatch and staffing issues make
mutual aid response to Station 61
district problematic
• Alpheretta Engine does not often
reach the “Shark Fin” before JCFD
units
Johns Creek, GA
Management Advisory Group International, Inc.
14 39
4.5 Option 5:
This option (#5) also would include the construction and staffing of two (2)
additional stations (#64 and #65). The staffing levels required would be greater than
Options 1,2, or 3, but less than Option #4. This is a quint/squad deployment at four
stations, retaining the single engine deployment at station 62. This option requires
additional resources and fiscal commitments, including:
Option Five: Estimated Costs
Item Estimated Cost
36 additional payroll positions $3,240,000
Purchase of four (4) Quint apparatus and four (4)
Rescue squad apparatus
$4,800,000
Purchase of property for and design,
construction and furnishing of two additional fire
stations.
$2,720,000
Purchase of additional necessary
communications equipment.
Undetermined
MAG believes there would be substantial benefits from this option, including:
• Dramatically improves initial response time for large areas of the City, thus improving
emergency medical service in those areas of the City.
• Dramatically improves firefighting personnel response, thus enhancing firefighting
and rescue capacity in most areas of the City.
• Significantly increases incident command support, thus enhancing incident
management effectiveness and firefighter safety.
• Increases staffing for Station 62, improving initial fire attack and rescue capabilities.
• Improves Truck Company support response time for Station 62, greatly improving
fire attack and rescue capabilities.
Johns Creek, GA
Management Advisory Group International, Inc.
14 40
• Improves “long” ground ladder capability and enlarges equipment storage
compartment space thus improving firefighting and rescue capabilities.
• Increases aerial ladder availability, thus improving firefighting and rescue capabilities
but deletes 100’ aerial.
• Increases reserve apparatus fleet, resulting in one reserve Truck, one reserve Rescue
Ambulance (63s) and two reserve Engines (replaced 61s & Reserve Engine 62).
• Increases total pumping capacity by 2500 GPM.
Johns Creek, GA
Management Advisory Group International, Inc.
14 41
JOHN’S CREEK FIRE DEPARTMENT RESOURCE DEPLOYMENT LOG: Option 5
STATION APPARATUS STAFF GPM AERIAL COMMENTS
Shift
Battalion
Chief
Pickup • BC/
CPT
• Adds “Command Assistant”
(Captain)
61 • Quint
• Rescue squad
• Reserve
Ambulance
• CPT / FAO / 2 FF
• SGT / FF
2000 75’
• Replaces Engine, 100’ Quint &
Rescue (ambulance) with 75’
Quint and Rescue squad
• Reduces staff by 2
• Retains replaced Rescue
ambulance for reserve
62 Engine
Reserve Engine
CPT/ FAO/ 2 FF 1500 * Increases staffing by 1
• Retain reserve (relief) Engine
63 Quint
Rescue squad*
Reserve Engine
CPT / FAO / 2 FF
SGT/ FF
2000 75’
• Replaces Engine, 100’ Quint &
Rescue (ambulance) with 75’
Quint and Rescue squad
• Reduces staff by 2
• Retain replaced Engine for
reserve
64 Quint
Rescue squad*
CPT / FAO / 2 FF
SGT/ FF
2000 75’ • Additional station with 75’
Quint and Rescue squad.
• Retain replaced Engine for
reserve
65 Quint
Rescue squad*
Reserve 100’
Quint
CPT / FAO / 2 FF
SGT/ FF
2000 75’
• Additional station with 75’
Quint and Rescue squad.
• Retain replaced 100’ Quint for
reserve
Totals I Command
Vehicle
4 Quints
1 Engine
4 Rescue squad
2 Reserve
Engines
1 Reserve Truck
1 Reserve
Ambulance
Minimum Staff:
30
9,500
1-100’
3-75’
1 Battalion Chief (BC)
6 Captains (CPT)
4 Sergeants (SGT)
5 Fire Apparatus Operators
(FAO)
14 Firefighters (FF)
See Appendix for details of 75’
Quint and Rescue squad
apparatus
Mutual Aid Engine ? ? • Dispatch and staffing issues
make mutual aid response to
Station 61 district
problematic
• Alpharetta Engine does not
often reach the “Shark Fin”
region before JCFD units
Johns Creek, GA
Management Advisory Group International, Inc.
14 42
4.6 Option 6:
This option (#6) also would also include the construction and staffing of two (2)
additional stations (#64 and #65). The staffing levels required would be greater than
Options #1, or #2, but less than Options #3 and #4. This Option (#6) could be termed the
“total quint/squad concept”. This option requires additional resources, including:
Option Six: Estimated Costs
Item Estimated Cost
Forty-three (43) additional payroll positions & .3
FTE overtime costs
$3,897,000
Purchase, five 75’ Quint apparatus and five (5)
Rescue squad apparatus
$6,000,000
Purchase of property for and design,
construction and furnishing of two additional fire
stations
$2,720,000
Purchase of additional necessary
communications equipment.
Undetermined
MAG believes there would be substantial benefits from this option, including:
• Greatly Improves initial response time for large areas of the City, thus improving
emergency medical service in those areas of the City.
• Greatly increases firefighting personnel response, thus enhancing firefighting and
rescue capacity in all areas of the City.
• Significantly increases incident command support, thus enhancing incident
management effectiveness and firefighter safety.
• Greatly improves staffing and improves equipment capabilities for Station 62, thus
improving firefighting and rescue capabilities for that area and for the City as a
whole.
• Greatly enlarges equipment storage compartment space, thus improving
firefighting and rescue capabilities.
Johns Creek, GA
Management Advisory Group International, Inc.
14 43
• Increases aerial ladder capability and mobility, thus improving firefighting and
rescue capabilities (note that while gaining mobility over current deployment, the
Department loses access to a 100’ aerial except in reserve status).
• Increases aerial ladder availability, thus improving firefighting and rescue
capabilities. Increases total pumping capacity by 2500 gpm.
• Increases reserve apparatus fleet, resulting in one reserve Truck one reserve Rescue
Ambulance and two reserve Engines.
Johns Creek, GA
Management Advisory Group International, Inc.
14 44
JOHN’S CREEK FIRE DEPARTMENT RESOURCE DEPLOYMENT LOG: Option 6
STATION APPARATUS STAFF GPM AERIAL COMMENTS
Shift
Battalion
Chief
Pickup 1 BC
1 CPT
• Adds “Command Assistant”
(Captain)
61 Quint
Rescue squad
Reserve Engine
CPT/ FAO/ 2 FF
SGT/ FF
2000 75’
• Replaces Engine, 100’ Quint
& Rescue (ambulance) with
75’ Quint and Rescue squad
• Reduces staff by 2
• Retain replaced Engine for
reserve
62 Quint
Rescue squad
Reserve Engine
CPT / FAO / 2
FF
SGT/ FF
2000 75’
• Replaces Engine with 75’
Quint and Rescue squad
* Increases staffing by 3
• Retain replaced Engine for
reserve
63 Quint
Rescue squad
CPT / FAO / 2
FF
SGT/ FF
2000 75’
• Replaces Engine, 100’ Quint
& Rescue (ambulance) with
75’ Quint and Rescue squad
• Reduces staff by 2
64 Quint
Rescue squad
Reserve 100’ Quint
CPT / FAO / 2
FF
SGT/ FF
2000 75’
• Additional station with 75’
Quint and Rescue squad.
• Retain replaced 100’ Quint
for reserve
65 Quint
Rescue squad
Reserve
Ambulance
CPT / FAO / 2
FF
SGT/ FF
2000 75’
• Additional station with 75’
Quint and Rescue squad.
• Retain replaced Rescue
(ambulance)
Totals 1 Command
Vehicle
5 Quints
5 Squads
2 Reserve Engine
1 Reserve 100’
Quint
1 Reserve
Ambulance
Minimum Staff:
32
10,000
5-75’ 1 Battalion Chief (BC)
6 Captains (CPT)
5 Sergeants (SGT)
5 Fire Apparatus Operators
(FAO)
15 Firefighters (FF)
See Appendix for details of
75’ Quint and Rescue squad
apparatus
Mutual Aid Engine ? ? • Dispatch and staffing issues
make mutual aid response to
Station 61 district
problematic
• Alpharetta Engine does not
often reach the “Shark Fin”
region before JCFD units
Johns Creek, GA
Management Advisory Group International, Inc.
14 45
IMPLEMENTATION SCHEDULE (Option 1)
Phase1
ACTION ANNUAL COST (over current) ONE-TIME COST
• Provide additional staffing to
accommodate increased incident
management support. Increase of
3 Captain positions (1 / shift ).
• $270,000 + benefit package +
overtime costs $81,000 (MAG
estimate)
• Provide additional staffing to
increase minimum staffing from 3
to 4 at Engine 62. Increase of 3
Firefighter positions
• $270,000 + benefit package +
overtime costs $81,000 (MAG
estimate)
• Purchase land for new Fire
Station (64) in the vicinity of
Jones Bridge and Buice Roads
• $200,000 (JCFD estimate
1/20/15)
• Initiate new Fire Station 64
design
• $100,000 (JCFD estimate
1/20/15)
• Initiate detailed design for
Quint, Rescue Squad
• Initiate detailed design and
order new Tiller Ladder Truck, for
Station 61
• Explore aide agreement for new
Forsyth station (north-east of
Johns Creek)
?
Johns Creek, GA
Management Advisory Group International, Inc.
14 46
Phase 2
ACTION ANNUAL COST (over current) ONE-TIME COST
• Construct new Fire Station 64 $1,060,000 (JCFD estimate
1/20/15)
• Begin recruitment process for
additional personnel
• Begin promotional process for
new positions
• Replace Ladder Truck 61 with
Tiller Aerial Ladder Truck (no
change in staffing)
• $1,200,000 – 15 yr. recurring
(MAG estimates)
• Replace ambulance 61 with
Rescue Squad apparatus
• $300,000 – 7 yr. recurring (MAG
estimate)
Phase 3
ACTION ANNUAL COST (over current) ONE-TIME COST
• Place Station 64 in operation
with Quint and Squad. Minimum
staffing: Captain, Fire Apparatus
Operator, Sergeant, and 3 Fire
Fighters.
• Station Equipment
• Quint and Rescue Squad
apparatus
• $1,890,000 + benefit package +
overtime costs $81,000 (MAG
estimate)
• $100,000 (MAG estimate)
• $1,200,000 – 15 & 7 year
recurring (MAG estimate)
• Implement Quint / Squad
concept at Fire Station 63.
Minimum staffing: Captain, Fire
Apparatus Operator, Sergeant,
and 3 Fire Fighters. (station staff
reduction: 3 Lts, 3 FAOs).
• Reduction of $ 630,000 +
benefits + overtime costs
$27,000 (MAG estimate)
Johns Creek, GA
Management Advisory Group International, Inc.
14 47
Phase 4
ACTION ANNUAL COST (over current) ONE-TIME COST
• Implement Quint / Squad
concept at Fire Station 62.
Minimum staffing: Captain, Fire
Apparatus Operator, Sergeant,
and 3 Fire Fighters. (3 additional
staff over current, 2 over Phase
1)
Over current
• $900,000 + benefit package +
overtime costs $162,000
(MAG estimate)
Over Phase 1
• $630,000 + benefit package +
overtime cost $27,000 (MAG
estimate)
• $1,200,000 - 15 & 7 year
recurring (MAG estimate)
Phase 5
ACTION ANNUAL COST (over current) ONE-TIME COST
Review Forsyth aide experience
to determine need for new
Station at or near intersection of
Medlock Bridge Road and East
Johns Crossing.
Assuming need for additional
station :
• Purchase land for new Fire
Station (65) in the vicinity of
Jones Bridge and Buice Roads
$400,000 (MAG estimate)
• Initiate new Fire Station 64
design
• $150,000 (JCFD estimate
1/20/15)
Phase 6
ACTION ANNUAL COST (over current) ONE-TIME COST
• Construct new Fire Station 65 $2,000,000 (MAG estimate)
Johns Creek, GA
Management Advisory Group International, Inc.
14 48
Phase 7
ACTION ANNUAL COST (over current) ONE-TIME COST
• Place Station 65 in operation
with Quint and Squad. Minimum
staffing: Captain, Fire Apparatus
Operator, Sergeant, and 3 Fire
Fighters.
• Station Equipment
• Quint and Rescue Squad
apparatus
• $1,890,000 + benefit package +
overtime costs $81,000 (MAG
estimate)
• $110,000 (MAG estimate)
• $1,500,000 – 15 & 7 year
recurring (MAG estimate)