Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support...

16
Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets University of Oxford May 1-2, 2008
  • date post

    21-Dec-2015
  • Category

    Documents

  • view

    213
  • download

    0

Transcript of Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support...

Page 1: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

Managed by UT-Battellefor the Department of Energy

Review of NFMCC Studies 1 and 2:Target Support Facilities

V.B. Graves

Meeting on High Power Targets

University of Oxford

May 1-2, 2008

Page 2: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

2 Managed by UT-Battellefor the Department of Energy Oxford High Power Target Meeting, 1-2 May 2008

Neutrino Factory Studies

ORNL completed two studies describing support facilities for neutrino factories– 2000, Graphite Target

– 2001, Mercury Jet Target

– Included descriptions of targets, expected radiation, required shielding, remote handling systems, and rough cost estimates

ORNL documents used as contributions to broader scope NFMCC documents

Page 3: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

3 Managed by UT-Battellefor the Department of Energy Oxford High Power Target Meeting, 1-2 May 2008

Study 1 - Carbon Target

16 GeV, 1.5 MW proton beam

1.5 cm diameter, 80 cm long graphite rod inside a helium environment

Target held by two spoke-like graphite supports

15 cm diameter containment tube

20 T magnetic field

Page 4: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

4 Managed by UT-Battellefor the Department of Energy Oxford High Power Target Meeting, 1-2 May 2008

Study 2 – Mercury Jet Target

24 GeV, 1 MW proton beam

1 cm diameter, 30 m/s jet

20 T magnetic field

Removable nozzle assembly inside an iron core

Page 5: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

5 Managed by UT-Battellefor the Department of Energy Oxford High Power Target Meeting, 1-2 May 2008

Study 2 Target-Capture Facility

24 GeV, 1 MW proton beam on Hg target

Upgradeable to 4 MW 20 T target solenoids 1.25 T capture solenoids 5-m steel shield for unlimited

personnel access Facility concept

development– Beam, target parameters– Neutronic analysis– Shielding requirements– Equipment definition– RH requirements, crane

sizing– Cost estimate

Page 6: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

6 Managed by UT-Battellefor the Department of Energy Oxford High Power Target Meeting, 1-2 May 2008

The Target/Capture Facility is 40-m Long

Removable, stacked shielding allows personnel in the crane hall

50-ton crane and bridge manipulator are the primary remote handling tools

2541

610

1760

3560Z=0

SECTION C-C

Shield CRANE HALL

50 Ton

Page 7: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

7 Managed by UT-Battellefor the Department of Energy Oxford High Power Target Meeting, 1-2 May 2008

Hg-Jet Target/Beam Absorber is a Closed Loop System

Hg jet interaction region: r = 5 mm x 30 cm long

110 liters of Hg total volume

V = 30 meters/s

Q = 2.4 liters/s

HG VAPOR TRAP

VAC FILTER

EXHAUST STACK

STORAGE TANK

VENTURI (VELOCITY CONTROL)

MERCURY NOZZLE

BEAM ABSORBER

TRANSFER PUMP

HEAT EXCHANGER

SUMP PUMP

FLOW CONTROL

HOLD-UPTANK

TARGET HOTCELLVENTILATION

Page 8: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

8 Managed by UT-Battellefor the Department of Energy Oxford High Power Target Meeting, 1-2 May 2008

Hg-Target Hot Cell

All components can be remotely replaced

Page 9: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

9 Managed by UT-Battellefor the Department of Energy Oxford High Power Target Meeting, 1-2 May 2008

Maintenance requirements for the target system components

Most of the target system components are life-of-the-facility

Key components are replaced every 2-3 yrs

Component(Class)

Failure Mode Dose Rate

(Rad/h)

Expected Life(yrs)

Replacement Time (days)

Nozzle Insert erosion, embrittled beam window

 >106

 2-3

 11-16

Beryllium Window

 embrittlement

 104 – 105

 2

 7-11

 Isolation Valve

 mechanical

 104 – 105

 5-7

1-2 (plus time for beryllium window

repl.)

Filters saturated Contamination

2 2-3

Pumps, Valves mechanical Contamination

5-7 2-3

Heat Exchanger, Piping, Tanks

 mechanical

Contamination

 > 40

 5-8

* Based on assuming either 12-hour or 8-hour maintenance shifts.

Page 10: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

10 Managed by UT-Battellefor the Department of Energy Oxford High Power Target Meeting, 1-2 May 2008

The Target and High Field Solenoids Are Contained in a Common Cryostat

The cryostat is a trunnion-mounted beam that simplifies initial installation of coil modules

The resistive coils and target nozzle are mounted coaxially in the large SC solenoid

Z=0

CRYOSTAT BEAMSUPPORT STRUCTURE(WC/H2O FILLED)

LOWER SEGMENTEXTRA WC SHIELDING Z=610CM

SECTION A-A

MAIN CRYOSTATOUTER BOUNDARY

SUPERCONDUCTINGCOILS

WC SHIELDING BEAM ABSORBERDRAIN LINE

GATEVALVE

MERCURY JET@ 100 MRAD

Page 11: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

11 Managed by UT-Battellefor the Department of Energy Oxford High Power Target Meeting, 1-2 May 2008

Tungsten-Carbide Radiation Shielding Protects the Superconducting Coils

Solenoids are lifetime components

W-C balls are 2-6 mm diam.

Water-cooled flow channels

Stainless steel shell and rib design

TYPICAL SHIELD MODULE CONSTRUCTION

DOUBLE STAINLESSSTEEL WALLS

RADIAL RIBS FORSTUCTURAL SUPPORT

TUNGSTEN CARBIDE

BALLS PACKED AT MAXIMUM DENSITY

WATER LINES FORSUPPLY AND RETURN

Page 12: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

12 Managed by UT-Battellefor the Department of Energy Oxford High Power Target Meeting, 1-2 May 2008

Component Weights and Sizes

Weight and size of major components established the facility dimensions and lifting requirements

Component Outer Diam. (cm) Length (cm) Module Wt. (lb)

Resistive Module 110 180 47,500

Iron Plug - - -

HC1 - - -

HC2 - - -

HC3 - - -

W-C Shield - - -

Main Cryostat + Shield Beam 270 740 73,600

SC1 256 178 61,000

SC2-3 202 183 21,700

2-3 Shield 128 183 59,600

SC4-5 176 351 17,900

4-5 Shield 148 351 86,400

SC6 + Shield 104 50 <4,000

SC7 + Shield 104 185 11,800

SC8 + Shield 104 185 10,800

SC9 + Shield 104 185 9,600

SC10 + Shield 104 185 8,400

SC11 + Shield 104 185 7,700

SC12 + Shield 104 185 6,600

Decay Coils + Shield (6) 87 296 12,600

Page 13: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

13 Managed by UT-Battellefor the Department of Energy Oxford High Power Target Meeting, 1-2 May 2008

The Maintenance Cell isLocated on the Crane Hall Level

Sized for handling cryostat modules

Located above the target hot cell with a hatch access

Staging area for bringing new components into the crane hall

Waste handling area

RAILED CART #1

RAILED CART #2

OVERHEAD HOIST

STORAGE CASTS

STAGING AREA

MAINTENANCE CELL

SECT ION A-A

MANIPULATORSTATION

OPTIONAL MANIPULATORSTATION

SHIELDED CRANEHALL ACCESS

FLOOR PLUGACCESS TO PROCESSHOT CELL

Maintenance Cell Plan View

Page 14: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

14 Managed by UT-Battellefor the Department of Energy Oxford High Power Target Meeting, 1-2 May 2008

Unlimited Personnel Access is Permitted in the Crane Hall

5.2 meters of steel + 30 cm of concrete to limit worker dose to 0.0025 mSv (0.25 mrem/h)

2 meters of steel in the tunnel to meet ground water protection requirements

1642

1220

SECTION B-BDECAY CHANNEL SHIELDING

CRANE HALL

Shield

Page 15: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

15 Managed by UT-Battellefor the Department of Energy Oxford High Power Target Meeting, 1-2 May 2008

R&D Issues Identified

Graphite target– Detailed target design– Beam dump design, incl. coolant connections/piping– Utility connections in target region– Details for helium environment, purge air

Mercury jet target– Thermal mixing of pool by jet– Nozzle erosion

Shielding for high-field solenoids (W-C spheres)– Ball distribution– Pressure drop– Heat transfer coefficient

Page 16: Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.

16 Managed by UT-Battellefor the Department of Energy Oxford High Power Target Meeting, 1-2 May 2008

Summary

Previous studies provided concepts for Target Support Facilities based on graphite and mercury jet targets

A logical method was used to determine facility size– The facilities were based on size and weight of the

solenoids and the radiation shielding that protects the superconducting coils

– Rad shielding was sized to permit unlimited worker access in the crane hall

– The decay channel (tunnel) is shielded to meet ground water protection requirements

Remote handling systems were incorporated into the facility design even at the early conceptual stage