Managed by UT-Battellefor the Department of Energy
Follow-on MERIT Testing at ORNL
Van Graves
2 Managed by UT-Battellefor the Department of Energy MERIT Testing at ORNL
New Capabilities at ORNL
Discussions with Tim Bigelow, ORNL Fusion Energy Division, indicate some existing experimental power supplies will be moved from Y-12 to ORNL
Some of the power supplies will have capability to power MERIT solenoid– 650V peak
– 15,000A pulsed > 5sec
– Voltage and/or current can be controlled by SCR gate waveform control
3 Managed by UT-Battellefor the Department of Energy MERIT Testing at ORNL
7627 Power Supply Building
New building
Final design complete
Located behind 7625
Schedule completion: Sept 2008
Several power supplieswill be installed
Bldg 7625
Bldg 7627
4 Managed by UT-Battellefor the Department of Energy MERIT Testing at ORNL
Bldg 7625
Pit capable of housing MERIT experimental equipment
LN2 dewar in place
20T overhead crane
5 Managed by UT-Battellefor the Department of Energy MERIT Testing at ORNL
Equipment Layout 7627
Vertical field power supplies650V peak
15,000 A pulsed > 5 secVoltage and/or current can be controlled by
SCR gate waveform control
6 Managed by UT-Battellefor the Department of Energy MERIT Testing at ORNL
Comments
Major infrastructure should be available in late 2008, but connection costs may be incurred
Hazard analysis (radiation, Hg, LBE) will have to be performed, but no major obstacles envisioned
Other power supplies will be available (capabilities unknown at this time) that might be useful for other HEP experiments in the future