Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

44
Making the Case for Funding Deferred Maintenance Before it’s Too Late Jim Kadamus – Vice President Sightlines Cuba Plain – Assistant Vice President for Budget Planning and Development University of Missouri System Walt Branson – Vice Chancellor for Finance and Administration Missouri University of Science and Technology Bob Simmons – Associate Vice Chancellor for Administration University of Missouri Kansas City

description

This session provides both a system and campus level perspective as well as a finance and facilities outlook on the problems of deferred maintenance and the strategies to make the case for funding. We will also provide the latest national and regional data on the growing problem of deferred maintenance and the operational implications of not addressing the problem.

Transcript of Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Page 1: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Making the Case for Funding Deferred Maintenance Before it’s 

Too Late

Jim Kadamus – Vice PresidentSightlines

Cuba Plain – Assistant Vice President for Budget Planning and DevelopmentUniversity of Missouri System

Walt Branson – Vice Chancellor for Finance and AdministrationMissouri University of Science and Technology

Bob Simmons – Associate Vice Chancellor for AdministrationUniversity of Missouri Kansas City

Page 2: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Changing the Conversation

SpaceUnderstand how age profile drives capital 

and operational demands

CapitalMultiyear plans that align to mission & 

risk

OperationsImprove 

effectiveness & lower facilities 

overhead impact

Page 3: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Sightlines’ National and Regional Trends

Speaker:Jim Kadamus, Vice President

Company:Sightlines, LLC

Date:October 6, 2014

Page 4: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

CACUBO Region

Included CACUBO States:Illinois, Indiana, Iowa, Kansas, Michigan, Minnesota, Missouri, Nebraska, Ohio, Oklahoma, South Dakota

49 Total Campuses29 Public campuses20 Private campuses342,947,907 Total GSF725,057 Students educated

Purple states: Sightlines & CACUBO membersGrey States: CACUBO but not Sightlines members

Page 5: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Campus Space and Enrollment

0%

1%

2%

3%

4%

5%

6%

7%

8%

9%

2007 2008 2009 2010 2011 2012 2013

Percen

t Cha

nge of Enr

ollm

ent &

 Spa

ce

Growing Campus EnrollmentCACUBO Average within Sightlines Database

Regional Space Growth Regional Enrollment Growth

Page 6: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Campus Space and Enrollment

‐2%

0%

2%

4%

6%

8%

10%

12%

2007 20082009 2010 2011 2012 2013 2007 20082009 2010 2011 2012 2013 2007 20082009 2010 2011 2012 2013

Percen

t Cha

nge of Enr

ollm

ent a

nd Spa

ce

Growing Campus EnrollmentCACUBO Region By Constituent Group

Space Growth Enrollment Growth

Comprehensive Institution Research Institution Small Institution

Page 7: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Database Construction Trends

Pre-War Post-War Modern Complex

0%

2%

4%

6%

8%

10%

12%

0

10

20

30

40

50

60

Tota

l Dat

abas

e G

SF C

onst

ruct

ed (M

illio

ns)

Constructed Space Since 1880

Sightlines Database CACUBO (%)

Page 8: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

The Aging Campus

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

2007 2008 2009 2010 2011 2012 2013 2007 2008 2009 2010 2011 2012 2013

% of Spa

ce

Square Footage by Age CategoryCACUBO Region Renovation Age

Under 10 10 to 25 25 to 50 Over 50

Public Average Private Average

Page 9: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

$0.00

$1.00

$2.00

$3.00

$4.00

$5.00

$6.00

2007 2008 2009 2010 2011 2012 2013 2007 2008 2009 2010 2011 2012 2013

$/GSF

Capital Investment into Existing SpaceCACUBO Region

Annual Capital One‐Time Capital Average

Capital Spending Public vs Private

Public Average Private Average

Page 10: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Facilities Backlogs Continue to Rise

$77  $80  $83  $86  $90  $94  $98 

$82  $83  $84  $87  $93  $96  $101 

0%

5%

10%

15%

20%

25%

30%

$0.00

$20.00

$40.00

$60.00

$80.00

$100.00

$120.00

2007 2008 2009 2010 2011 2012 2013 2007 2008 2009 2010 2011 2012 2013

$/GSF

Backlog $/GSFCACUBO Region

Backlog/GSF Percentage Change of Backlog

Public Average Private Average

Page 11: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Facilities Operating Budgets Flat

$3.43 $3.61 $3.59 $3.52 $3.49 $3.56 $3.52

$0.24$0.24 $0.26 $0.27 $0.27 $0.29 $0.30

$0.00

$0.50

$1.00

$1.50

$2.00

$2.50

$3.00

$3.50

$4.00

$4.50

2007 2008 2009 2010 2011 2012 2013

$/GSF

CACUBO Operating Budget Average

Daily Service Planned Maintenance

Page 12: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

$3.44 $3.53 $3.63 $3.54 $3.50 $3.57 $3.57 $3.41$3.70 $3.56 $3.51 $3.47 $3.53 $3.47

$0.23 $0.24$0.26 $0.28 $0.29 $0.33 $0.34

$0.24

$0.24$0.27 $0.26 $0.25 $0.24 $0.26

$0.00

$0.50

$1.00

$1.50

$2.00

$2.50

$3.00

$3.50

$4.00

$4.50

2007 2008 2009 2010 2011 2012 2013 2007 2008 2009 2010 2011 2012 2013

$/GSF

Daily Service Planned Maintenance

$4.39  $4.35 

CACUBO Operating Budgets – Public vs. Private

Operating Budgets 14%+ Short of Inflation

Public Average Private Average

Page 13: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Conclusions

In the CACUBO region, campus enrollment is growing faster than campus space, increasing campus density

Aging facilities are competing with faculty needs and financial aid for funding

Capital funding has only just returned to historic levels following the recession, private universities in the region have surprisingly seen less growth

Backlogs are growing and at public campuses reaching unsustainable levels

Funding for facilities operations have not kept pace with inflation, meaning cuts in staffing and contracts

Page 14: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

University of Missouri SystemSpeaker:Cuba Plain, Assistant Vice President for Budget Planning and Development

Institution:University of Missouri System

Date:October 6, 2014

Page 15: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Land grant institution with four campuses, hospital & clinics, system administration,  

experiment station and farms

24,000 Employees

75,272 Student Headcount58,163 Student FTE

29.5MGSF

1,500+ Buildings

$8.5BFacilities 

Replacement Value

Total Operating Budget:

$3B

System Profile

Page 16: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

34% growth in headcount and 42% growth in FTE students since FY2001

Legislative limits on tuition increases equal to CPI State operating appropriations down almost $30 million since FY2001 in nominal terms

Flat nominal state operating appropriations since 2010 which resulted in a cumulative real loss of $300 million

No new state capital appropriations since FY2008, minimal investment between FY2001 and FY2008

Changes and Challenges

Page 17: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

$0

$50

$100

$150

$200

$250

$300

$350

$400

$450

$500

$550

FY10 FY11 FY12 FY13 FY14

$ in M

illions

Actual Appropriation Received CPI Adjusted Appropriation Cumulative Difference

State Appropriations Over Time

Page 18: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

$0.00

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

$70.00

$80.00

2009 2010 2011 2012 2013

$ in M

illions

UM Annual M&R Spendingby Sightlines

Institutional Recurring Capital One‐time capital Sources

Sightlines Recommended Annual M&R Target

Backlog Stabilized

Backlog Increases

Funding Levels Fall Short

Page 19: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

$0.00

$200.00

$400.00

$600.00

$800.00

$1,000.00

$1,200.00

$1,400.00

FY09 FY13

$ in M

illions

Facilities Needs Backlog by Priority

Critical ‐ Now Urgent < 1Yr Necessary 2‐5 Yr Recommended 6‐10 Yr

$838 M

$1,317 M

Backlog of Need Increased by 57%

Page 20: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

    MU UMKC     S&T UMSL

UM System FCNI Rating of E&G BuildingsPoor Condition Below Average Condition Fair Condition Good Excellent Condition

Facilities Condition by Campus

43% 38% 39%

80%

Page 21: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Shaping Campus Policies

Page 22: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Predicting Future Condition

28%26% 27%

41%41%

36%39%

56%

0%

10%

20%

30%

40%

50%

60%

MU UMKC S&T UMSL

FCNI

FY 2014 FCNI INDEX FY 2023 PROJECTED FCNI INDEX

Best Practice ≤ 0.30 FCNI

Page 23: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Potential Funding Sources State Bond Issue

$200 million plan15 Year financing

$17.7 million annual debt service 50/50 Match – Private gifts and State FundingDedicated Recurring State Appropriation Student Facilities Fee

• $300 to $350 annual fee per student FTE

Page 24: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Projected Impact of $200M

Discuss potential spending timeframe for $200M investment

$0.00

$20.00

$40.00

$60.00

$80.00

$100.00

$120.00

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019

$ in M

illions

UM Annual M&R Spendingby Sightlines

Annual M&R Renovation and Other Capital $200M Funding Impact Sightlines Recommended Annual M&R Target

Assuming consistent investment from FY13 and $200M spent over 5 years

Page 25: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Missouri University of Science & Technology

Speaker:Walter Branson, Vice Chancellor for Finance and Administration

Institution:Missouri University of Science and Technology

Date:October 6, 2014

Page 26: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Leader in green:First US university to receive ISO 14001 

certification for environmental managementEnvironmental village

Sightlines member since 2007

2.7M GSF165 

Maintained Acres

8,100 Students

Founded 1870

Campus Profile

Page 27: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Operating Costs by Building Size

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

A B C D M S&T F G H I

GSF

Average Building Size

*Ozanne analytics

$3.00/GSF

$1.00/GSF

STEM focus drive campus profileSmaller Buildings Than Peers

Page 28: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

21%10% 13% 17%

19%28% 24%

25%

41% 42% 43% 29%

20% 20% 19%29%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Missouri S&T FY03 Missouri S&T FY08 Missouri S&T FY13 Peer Average

% of Tot

al Cam

pus GSF

Campus Age by Renovation Age Category

Under 10 10 to 25 25 to 50 Over 50

Renovations and new construction are managing campus ageSpace Profile

Page 29: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Capital ProfileCapital investments falling short of target

$0.00

$5.00

$10.00

$15.00

$20.00

$25.00

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

Total D

ollars in M

illions

Institutional Recurring Capital One‐Time Capital Sources Target Need

Page 30: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

$0.00

$5.00

$10.00

$15.00

$20.00

$25.00

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

Total D

ollars in M

illions

Institutional Recurring Capital One‐Time Capital Sources Infrastructure

Capital ProfileSignificant infrastructure spending for geothermal energy 

Page 31: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

17%

48%

32%

3%

5‐Year Historical Investment Mix

Envelope Systems

Space Safety/Code

0

5

10

15

20

25

30

35

Envelope Systems Space Safety/Code

Years

Average Life Cycle

Spending focused on “bang‐for‐buck” projectsHistoric Spending Mix

Page 32: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

$0

$50

$100

$150

$200

$250

$ in M

illions

Backlog Growth Since FY03

Backlog Maint/ Repair Backlog Modernization Backlog Infrastructure

Recent investment curbs growth in infrastructure, Repair/Maint continues to growTotal Backlog

Page 33: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Balancing Institutional Demands

Page 34: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

University of Missouri – Kansas City

Speaker:Bob SimmonsAssociate Vice Chancellor, Administration

Institution:University of Missouri – Kansas City

Date:October 6, 2014

Page 35: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Engaged and Green:The President’s Higher Education Community Service 

Honor Roll with Distinction.  RecycleMania 2012 Grand Champion Winner.

Sightlines member since 2007

5.1M GSF149 

Maintained Acres

11,397 Students

Founded 1933

University of Missouri – Kansas City

Page 36: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Changing Campus Density

‐5%

0%

5%

10%

15%

20%

Chan

ge in Den

sity Fac

tor

Density Factor Rate of Change

UMKC Change Peer Change

*Density Factor is measured in Users/100kGSF

2010‐2020 Strategy Statement:By 2020 we will grow enrollment to 20,000 and increase graduation rates 10% by ensuring student success through a small college experience as Kansas City’s community engaged urban research institution, while leveraging our strengths in the visual and performing arts, life and health sciences and entrepreneurship.

Page 37: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

23%10%

18%

21%

45%

46%

14%24%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

UMKC '03 UMKC '13

% of Tot

al Cam

pus GSF

Campus Renovation Age

Under 10 10 to 25 25 to 50 Over 50

Age Shifts over Last 10 Years

Buildings Under 10Little work. “Honeymoon” 

period.Low Risk

Buildings 10 to 25Short life‐cycle needs; primarily space 

renewal.Medium Risk

Buildings 25 to 50Major envelope and mechanical life cycles come 

due.Higher Risk

Buildings over 50Life cycles of major building components are past due.  

Failures are possible.Highest risk

Page 38: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Changing Funding Sources

 $‐

 $10

 $20

 $30

 $40

 $50

 $60

 $70

$ in M

illions

UMKC Capital History ‐ Sources1990 ‐ 2014

State Federal Private Campus Bonds Other (PPP)

As state funding decreases, shifting toward creative use of bond funding

Page 39: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

 $‐

 $2.00

 $4.00

 $6.00

 $8.00

 $10.00

 $12.00

 $14.00

 $16.00

 $18.00

 $20.00

$0.00

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

$70.00

$80.00

$90.00

$100.00

$110.00

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

Capital $

/GSF

Back

log $/GSF

Capital Spending vs. AR Backlog

Backlog Maint/ Repair Capital Spending/GSF

Capital Spending and BacklogLarge infusions of capital have significant impact on backlog

Page 40: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Leaner Budget Than Peers

$0.00

$1.00

$2.00

$3.00

$4.00

$5.00

$6.00

A B C D UMKC F G H I J

$/GSF

Daily Service Daily Service Over Time

Page 41: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

$0.00

$0.20

$0.40

$0.60

$0.80

$1.00

$1.20

$1.40

$1.60

$1.80

A B C D UMKC F G H I J

$ / G

SF

Planned Maintenance 

Planned MaintenanceIncreased PM efforts has improved in‐house PM performance

Institutions ordered by tech rating

$0.13$0.26 $0.27

$0.12

$0.31 $0.29

2011 2012 2013

UMKC PM

In‐HouseExternal

Page 42: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Driving Capital Investment Strategy

Program Value

SAMPLE DATA

Page 43: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Strategies to Address Deferred MaintenanceStrategy 1: Change the conversation throughout higher education. Educate policy makers about the impacts of the space profile, capital plans that are aligned with the institutional mission and risk, and improving operating effectiveness while lowering costs.

Strategy 2: Set capital priorities to address the deferred maintenance needs in aging buildings that are determined to be critical to the mission and programmatic needs of universities. 

Strategy 3: Consider eliminating or replacing aging space with new modern facilities, especially buildings with certain construction vintages where poor quality construction was prevalent. Sometimes less is more when it comes to addressing aging buildings with lots of deferred maintenance. 

Page 44: Making the Case for Funding Deferred Maintenance Before it's Too Late - Sightlines/CACUBO 2014

Strategies to Address Deferred MaintenanceStrategy 4: New construction must support the mission of the university and support the future program needs of each university. 

Strategy 5: Make annual stewardship (keep‐up) investment that addresses building components as they come due a priority at every campus. The more a campus keeps‐up with life cycles as they come due, the less deferred maintenance grows.

Strategy 6: Institute facilities operational practices that are proactive at extending the life cycles of key expensive building components like HVAC, electrical systems and roofs.  Proactive maintenance is not only a good idea when it comes to managing university facilities, it will save money in the long‐run.