Maintenance
Transcript of Maintenance
Introduction
Maintenance ◦ All activities that maintain facilities and equipment in good working order so that a system can perform as intended
Breakdown maintenance ◦ Reactive approach; dealing with breakdowns or problems when they occur
Preventive maintenance ◦ Proactive approach; reducing breakdowns through a program of lubrication, adjustment, cleaning, inspection, and replacement of worn parts
Maintenance Reasons
Reasons for keeping equipment running
◦ Avoid production disruptions
◦ Not add to production costs
◦ Maintain high quality
◦ Avoid missed delivery dates
Breakdown Consequences
Production capacity is reduced ◦ Orders are delayed
No production ◦ Overhead continues ◦ Cost per unit increases
Quality issues ◦ Product may be damaged
Safety issues ◦ Injury to employees ◦ Injury to customers
Total Maintenance Cost
Breakdown and
repair cost
Optimum Amount of
preventive maintenance
Dem
an
d
Total Cost
Preventive
maintenance cost
Preventive Maintenance
Preventive maintenance: goal is to reduce the incidence of breakdowns or failures in the plant or equipment to avoid the associated costs
Preventive maintenance is periodic ◦ Result of planned inspections
◦ According to calendar
◦ After predetermined number of hours
Frequency of breakdown
If the average cost of a breakdown is $1,000, and the cost of preventative maintenance is $1,250 per month, should use preventive maintenance?
Number of breakdowns 0 1 2 3
Frequency of occurrence .20 .30 .40 .10
Number of
Breakdowns
Frequency of
Occurrence
Expected number of
Breakdowns
0
1
2
3
.20
.30
.40
.10
1.00
0
.30
.80
.30
1.40
Expected cost to repair = 1.4 breakdowns per month X $1000 = $1400
Preventive maintenance = $1250
PM results in savings of $150 per month
Predictive Maintenance
Predictive maintenance ◦ An attempt to determine when best to perform preventive maintenance activities
Total productive maintenance ◦ JIT approach where workers perform preventive maintenance on the machines they operate
Breakdown Programs
Standby or backup equipment that can be quickly pressed into service
Inventories of spare parts that can be installed as needed
Operators who are able to perform minor repairs
Repair people who are well trained and readily available to diagnose and correct problems with equipment
Replacement
Trade-off decisions ◦ Cost of replacement vs cost of continued
maintenance
◦ New equipment with new features vs maintenance
◦ Installation of new equipment may cause disruptions
◦ Training costs of employees on new equipment
◦ Forecasts for demand on equipment may require new equipment capacity
When is it time for replacement?
OEE
The OEE calculation is based on the three OEE Factors: Availability, Performance, and Quality. Here's how each of these factors is calculated.
Availability Availability takes into account Down Time Loss, and is calculated as:
Availability = Operating Time / Planned Production Time
Performance Performance takes into account Speed Loss, and is calculated as:
Performance = Total Pieces / Operating Time) / Ideal Run Rate
Quality Quality takes into account Quality Loss, and is calculated as:
Quality = Good Pieces / Total Pieces
OEE OEE takes into account all three OEE Factors, and is calculated as:
OEE = Availability x Performance x Quality
It is very important to recognize that improving OEE is not the only objective. Take a look at the following data for two production shifts.
Superficially, it may appear that the second shift is performing better than the first, since its OEE is higher. Very few companies, however, would want to trade a 5.0% increase in Availability for a 3.5% decline in Quality
Example OEE Calculation The table below contains hypothetical
shift data, to be used for a complete OEE calculation, starting with the calculation of
the OEE Factors of Availability, Performance, and Quality. Note that the same units of measurement (in this case minutes and pieces) are consistently used throughout the calculations
OEE
Shift Length 8 hours = 480 min.
Short Breaks 2 @ 15 min. = 30 min.
Meal Break 1 @ 30 min. = 30 min.
Down Time 47 minutes
Ideal Run Rate 60 pieces per minute
Total Pieces 19,271 pieces
Reject Pieces 423 pieces
Planned Production Time = [Shift Length - Breaks] = [480 - 60] = 420 minutes Operating Time = [Planned Production Time - Down Time] = [420 - 47] = 373 minutes Good Pieces = [Total Pieces - Reject Pieces] = [19,271 - 423] = 18,848 pieces
Availability=Operating Time / Planned Production Time
373 minutes / 420 minutes=0.8881 (88.81%)
Performance=(Total Pieces / Operating Time) / Ideal Run Rate
(19,271 pieces / 373 minutes) / 60 pieces per minute=0.8611 (86.11%)
Quality=Good Pieces / Total Pieces
0.8881 x 0.8611 x 0.9780=0.7479 (74.79%)
OEE=Availability x Performance x Quality
0.8881 x 0.8611 x 0.9780=0.7479 (74.79%)