NYSDOT – M. Ivey AASTHO SCOE – June 9, 2004 1
Maintaining Project Commitments
New York State DOT Perspective
Mary E. Ivey, DirectorEnvironmental Analysis [email protected]
![Page 2: Maintaining Project Commitments](https://reader035.fdocuments.in/reader035/viewer/2022081513/56815b1c550346895dc8cf4e/html5/thumbnails/2.jpg)
NYSDOT – M. Ivey AASHTO SCOE – June 9, 2004 2
Guidance, Tools and Practices in Place
Environmental Policy Environmental
Procedures Manual (EPM) Project Development
Manual (PDM) Environmental Tracking
(E-Track)
![Page 3: Maintaining Project Commitments](https://reader035.fdocuments.in/reader035/viewer/2022081513/56815b1c550346895dc8cf4e/html5/thumbnails/3.jpg)
NYSDOT – M. Ivey AASHTO SCOE – June 9, 2004 3
Guidance, Tools, Practices in Place
Environmental Commitment and Obligations Package for Construction (ECOPAC)
Engineering Instruction - Constructability Review Post-Construction Review Environmental Handbook for Operations
![Page 4: Maintaining Project Commitments](https://reader035.fdocuments.in/reader035/viewer/2022081513/56815b1c550346895dc8cf4e/html5/thumbnails/4.jpg)
NYSDOT – M. Ivey AASHTO SCOE – June 9, 2004 4
Accountability
NYSDOT Internal Environmental Quality Assurance Audit
NYS Department of Environmental Conservation State Environmental Audit
Established Environmental Units in Each Regional Office
Environmental Contacts in Maintenance (MECs) and Construction (CECs) in Regional Offices
![Page 5: Maintaining Project Commitments](https://reader035.fdocuments.in/reader035/viewer/2022081513/56815b1c550346895dc8cf4e/html5/thumbnails/5.jpg)
NYSDOT – M. Ivey AASHTO SCOE – June 9, 2004 5
Meaningful Partnerships - Internal
Environmental Analysis Bureau (EAB) holds regular management meetings with: Design Director Operations Directors (Maintenance, Equipment
Management, Construction) Design Division and FHWA re: Env. Streamlining Regional Environmental Managers
![Page 6: Maintaining Project Commitments](https://reader035.fdocuments.in/reader035/viewer/2022081513/56815b1c550346895dc8cf4e/html5/thumbnails/6.jpg)
NYSDOT – M. Ivey AASHTO SCOE – June 9, 2004 6
Meaningful Partnerships - External
Coordination meetings with Resource and Regulatory Agencies Statewide (Central Office) and regional Meeting at various levels - staff, senior
management and executive Bringing in other partners – Assoc. of General
Contractors (AGC) More outreach to local partners
![Page 7: Maintaining Project Commitments](https://reader035.fdocuments.in/reader035/viewer/2022081513/56815b1c550346895dc8cf4e/html5/thumbnails/7.jpg)
NYSDOT – M. Ivey AASHTO SCOE – June 9, 2004 7
Training
Environmental & Non-Environmental Staff Include External Partners
Resource and Regulatory Agencies Local Entities (DPWs) Transportation Partners (Thruway Authority)
![Page 8: Maintaining Project Commitments](https://reader035.fdocuments.in/reader035/viewer/2022081513/56815b1c550346895dc8cf4e/html5/thumbnails/8.jpg)
NYSDOT – M. Ivey AASHTO SCOE – June 9, 2004 8
Research
Valuable information that leads to better practices and resource management
Builds agency credibility and trust
![Page 9: Maintaining Project Commitments](https://reader035.fdocuments.in/reader035/viewer/2022081513/56815b1c550346895dc8cf4e/html5/thumbnails/9.jpg)
NYSDOT – M. Ivey AASHTO SCOE – June 9, 2004 9
Where Should We Be Going?
Expand E-Track Explore Environmental
Management System (EMS)
Strengthen interaction with Planning, Design, and Construction
Develop performance data and measures - more Quality Assurance
![Page 10: Maintaining Project Commitments](https://reader035.fdocuments.in/reader035/viewer/2022081513/56815b1c550346895dc8cf4e/html5/thumbnails/10.jpg)
NYSDOT – M. Ivey AASHTO SCOE – June 9, 2004 10
Where Should We Be Going?
Make agency re-organization work for us -“Improving Environmental Conditions”
Asset Inventories and Management Efforts Clarity and Consistency in Setting
Environmental Goals Continuous Improvement - learning from one
another
![Page 11: Maintaining Project Commitments](https://reader035.fdocuments.in/reader035/viewer/2022081513/56815b1c550346895dc8cf4e/html5/thumbnails/11.jpg)
NYSDOT – M. Ivey AASHTO SCOE – June 9, 2004 11
The Keys to Success
Agency Environmental Ethic
Genuine Commitment
Open Communication
![Page 12: Maintaining Project Commitments](https://reader035.fdocuments.in/reader035/viewer/2022081513/56815b1c550346895dc8cf4e/html5/thumbnails/12.jpg)
NYSDOT – M. Ivey AASHTO SCOE – June 9, 2004 12
www.dot.state.ny.us/eab/eab.html
![Page 13: Maintaining Project Commitments](https://reader035.fdocuments.in/reader035/viewer/2022081513/56815b1c550346895dc8cf4e/html5/thumbnails/13.jpg)
NYSDOT – M. Ivey AASHTO SCOE – June 9, 2004 13
Thank You!