Mains design guidelines for self-lay organisations … · Mains design guidelines for self-lay...
-
Upload
truongxuyen -
Category
Documents
-
view
219 -
download
0
Transcript of Mains design guidelines for self-lay organisations … · Mains design guidelines for self-lay...
Mains design guidelines for self-lay organisations working in new developmentsDecember 2015
1 Design principles
1.1 Self-lay policy - General information1.2 Point of connection1.3 Routing positioning and location1.4 Depth of mains1.5 Pipe materials, sizing and pressure rating1.6 Jointing1.7 Mains in new development areas1.8 Mains in existing streets1.9 Mains in retail parks and commercial areas1.10 Unadopted roads1.11 Gated developments1.12 Land rights1.13 Water mains in a street1.14 Water mains not in a street1.15 Self-lay in land that is not a street
2 Pressures, flow and sizes 2.1 Design guidance pressure2.2 Design guidance velocity of flow2.3 Design guidance hydraulic gradient2.4 Sizing new mains for domestic premises2.5 Sizing mains for non-domestic and mixed
developments2.6 Managing water quality in new mains
3 Valves and air valves
3.1 Isolating valves3.2 Air Valves
4 Washouts
5 Requirements for service pipes 5.1 Definitions5.2 Conditions for connection5.3 General requirements for service pipes5.4 Service connection arrangements5.5 Standard service connection details
6 Metering 6.1 Temporary supply installation (TBS)6.2 Internal fit metering for flats or multi occupancy premises6.3 Metering standard service connections6.4 Meter specifications6.5 Meter pits6.6 Metering non-standard service connections
7 Fire fighting 7.1 Fire hydrants7.2 Statutory duty7.3 Requirements for firefighting water7.4 Fire sprinkler systems
8 Abandonment and diversion of existing mains
8.1 A development with both a new mains and an
abandoned main8.2 Example of a redeveloped site with a diverted /
abandoned main
9 Tree planting guidance
ContentsIntroduction and contact details
10 Example layouts for new mains and services
10.1 New mains in a shared drive10.2 New mains in a footway10.3 New mains to be installed with a gated
development 10.4 New mains in a commercial area with
an easement
This document aims to help self-lay organisations in designing their own schemes, by making clear our requirements for new pipework and other assets. These will become part of our supply network, often for decades to come. We therefore need to ensure they are fit for purpose and comply with a range of guidelines, explained over the following pages.
Most of the standards we outline below are our own, often based on guidance from the National Joint Utilities Group (NJUG). They also include guidance based on UK legislation. Please note that failure to meet these standards could delay or prevent your approval.
This document should be used in conjunction with our self-lay policy and company-specific addendum to the WRc Code of Practice for the Self-Laying of Water Mains and Services (England and Wales), 2nd edition, 2009. This can be found in the ‘Building and developing’ section of our website, under ‘Self-lay water supply’.
We require developers to make an initial enquiry or a capacity check with us in advance of an application for a new connection to our network. This will help ensure there is sufficient capacity in our water network when it is needed and indicate the potential costs of providing any new capacity or using any previously installed capacity needed for the development.
Completing a capacity check at planning stage will help avoid delays in supplying the site at construction stage.
For further information, including details on pre-development enquiries, please refer to our website or contact us using the details below.
Introduction
Contact detailsThames Water Developer Services2nd Floor WestClearwater Court,Vastern Road,Reading,RG1 8DB
Tel: 0800 009 3921www.thameswater.co.uk Thames Water Utilities Ltd Registered in England and Wales No. 2366661, Registered Office.
All works should comply with BS EN 850 Water Supply, Requirements for Systems and Components Outside Buildings. Design and construction should comply with the current edition of the Civil Engineering Specification for the Water Industry (CESWI). It should also be in line with the National Joint Utilities Group (NJUG) guidelines, Volume 2, available at www.njug.org.uk.
1.1 Self-lay policy – General informationPlease refer to our Self-Lay Policy and Addendum to the WRc Code of Practice, which can be found in the ‘Building and developing’ section of our website, on the page headed ‘Self-lay: How to apply’.
1.2 Point of connection We will determine the point of connection to the existing distribution network. System reinforcement might be required prior to connection depending upon capacity. We will not make the final connection of the self-laid main to the water distribution system until you have provided satisfactory disinfection, pressure test and water sample results.
1.3 Routing positioning and locationWhen deciding on the optimum pipeline route, we will take into account the following factors:
• Hydraulic gradient• Terrain and subterranean conditions• Hazards and obstacles, including
contaminated ground• Existing and future land use• Permanent access• Transport facilities• Utility services
• Agricultural practice• Environmental impact• Industrial and commercial development• County structure plans
On distribution mains, please ensure dead ends do not serve more than 100 properties. They should have a maximum design velocity of 0.6m/s.
Please ensure that all water mains with unrestrained joints have thrust restraint at bends, junctions, line valves and changes in diameter.
Wherever practicable, ensure that distribution mains are located in the footway/verge, in accordance with the NJUG guidelines Volume 1. The pipeline and associated fittings need to allow adequate access from public highways for the equipment and materials necessary to carry out valve operations, inspections, maintenance and emergency repairs, and decommissioning. Service stripsA service strip is a dedicated trench for utilities services in public or private land. The main should be within a service strip provided by the customer. The service strip must be at least 1.8 metres wide – if this width cannot be achieved, we will lay the main in a position which we deem most suitable. Service trenches should be provided within footpaths, roads, or verges.
We sometimes find that the developer provides a service trench in a strip of land situated within the gardens of the new dwellings. Please ensure you avoid this and find a more suitable alternative. Buildings (existing or proposed) should not be situated immediately beside a service strip, as this impedes work to lay the main as well as future maintenance activities.
1. Design principles
Click here
Adoptable vergesAn adoptable verge is a strip of ‘unmade ground’ running parallel to the carriageway/footpath. If a main is to be laid within a verge, the finished surface should not be planted with trees and shrubs.
Third party landThird party land is privately-owned land which requires entry in order to provide a development with water and is not owned by either the local council/highway authority or the applicant. In order to provide a development site with water, it may be necessary to cross land which is under several different ownerships.
You should only consider laying mains within ‘third party land’ as a last resort and should seek an alternative route wherever possible. The general concept of laying mains in private roads is acceptable.
1.4 Depth of mainsDistribution mains should be laid in trenches where there will be a minimum cover of 0.9 metres and maximum cover of 1.2 metres – this is to give any service connection adequate protection from frost (a minimum cover of 750mm).
Every mains design drawing should carry the ‘preferred layout’ template in accordance with NJUG guidelines, which indicates the depth of a water main in conjunction other utilities apparatus. When deciding on the depth of a main, please ensure you consider the weight and frequency of vehicles likely to travel over it.
Please tell us if any new main has to be laid at a reduced depth due to underground obstructions, bridge decking restrictions or any other type of unavoidable obstruction. It is also your responsibility to include the depth of cover of the new main and the depth of cover at the point of connection to the existing main / mains on the ‘as-laid’ drawing.
1.5 Pipe materials, sizing and pressure rating
Choice of materialAll pipes must be marked with the Standard Dimension Ratio. High-performance polyethylene (HPPE) is our preferred material for new mains and
should always be used unless the Soil Analysis Report determines otherwise.
HPPE is identified blue as per NJUG guidelines Volume 2. HPPE pipe is referred to by its external diameter, and should be designed in 90mm, 125mm, 180mm and 250mm, and 355mm mains.
HPPE has a pressure rating of 16 bar and is joined together by ‘butt fusion’ and ‘electro fusion’. Marker tape should be used within the trench in order to provide a means of tracing HPPE pipe. Medium-density polyethylene (MDPE) should be used for should be used for service connection pipes up to and including 63mm.
Neither HPPE mains not MDPE service connections are to be laid in sites which have been deemed contaminated by us following analysis of the customer’s Soil Analysis Report. Wherever contamination is identified, new mains and service connections must be in plastic barrier pipe (up to and including 63mm). Please note that plastic is now our preferred material for barrier pipe.
Ferrous pipe is referred to by its internal diameter and is designed in 100mm, 150mm, 200mm and 300mm sizes. 1.6 JointingButt fusion is our preferred method of jointing plastic pipe, which must be of identical diameter and pressure ratings. Butt fusion can only be carried out outside the trench, and electro fused couplings should therefore be employed where butt fusion is not practicable, i.e. when making the connection from a length of main to a fitting. Electro fusion couplings must be installed wherever the pipe cannot be ‘butt fused’, i.e. at bends, ends, directional changes, and where two sections of main are required to be joined within the trench. They must be HPPE (PE100) and can be black or blue in colour. All electro fusion fittings must incorporate fusion indicators.
Gaskets are rubber rings, which provide a watertight seal within the joint. They provide a flexible joint and are installed within the socket end of the pipe in order to prevent the pipe separating. Gaskets should not be fitted at critical points such as bends, ends or directional changes, which require the installation of anchor gaskets.
1.7 Mains in new development areasWhere the point of entry is less than 10 metres from a water main, service connections can be installed.
Service pipe layout where supply pipe exit is less than 10 metres from a water main
Where points of entry are further than 10 metres from a water main, a new main can be installed.
Mains and service pipe layout where supply pipe exit is more than 10 metres from a water main
Property boundary
Water main
Service pipe
KEY
Shared drive
Communication pipe
Alternative servicepipe route
Property boundary
Water main
Service pipe
KEY
Communication pipe
New main
Shared drive
1.8 Service connections in new streets or a street where a main is not installed
This shows a new development on a new street which has no water main. A new main would need to be installed to allow service connections.
KEY
New developmentboundary
Water main
Communication pipe
New main
Existing carriageway New site road
1.9 Service connections to existing mains
This shows a new development on the same side as an existing water main – therefore no new main needs to be installed.
KEY
Existing water main
Newcommunication pipe
Existingcommunication pipe
Existing carriageway
New property boundary
1.10 New mains in existing streets
This shows a new development on the opposite side to the existing main. In this scenario it can be beneficial to install a new main in order to avoid multiple road crossings.
Example showing where new main would be installed to avoid multiple road crossings
KEY
Existing water main
Newcommunication pipe
New water main
New property boundary
Existingcommunication pipe
Existing carriageway
1.11 Mains in retail parks and commercial areasWherever possible new mains should be located in a road built to an adoptable standard. In retail parks, commercial and industrial areas, it may not always be clear which areas are streets, and there is a particular risk that layouts of buildings, car parks and access roads may be changed without consulting us.
In such areas, we may require an easement to be granted, in order to protect our assets. New water mains should be co-coordinated with other services such as gas, electricity and telecoms, and laid in accordance with Volume 2 of the NJUG guidelines.
An example showing where an easement may be required for a new commercial development
Car parking area Car parking area
Easement
KEY
Existing water main
Service pipe
New water main
Existing carriageway
1.12 Unadopted roads
An adoptable standard footpath is a walkway that is constructed to the standards demanded by a local council or highway authority. The footpath is normally of a minimum width of 1.8 metres. SLOs should only consider laying mains in a footpath narrower than 1.8 metres if it is not used by any other utilities services. If the main is not laid within this footpath, then it should be positioned in the road about one metre from the kerb line.
An adoptable standard road is a carriageway road that is constructed to the standards demanded by a local council or highway authority. The carriageway is normally of a minimum width of 5.5 metres. If the main is not laid within this carriageway, it should be positioned approximately one metre from the kerb line.
1.13 Gated developmentsIf a private road is ‘gated’, it is good practice to install a valve on the main just outside the gate. This will ensure that we can ‘close in’ the main without affecting other customers.
1.14 Land rightsThe Water Industry Act 1991 allows us to lay pipes in streets and private land, and we usually rely on these powers rather than obtaining formal easements. These rights do not apply when the pipes are laid by an SLO. This requirement for land rights should be assessed at design stage and indicated on the approved layout drawings prior to any acceptance of the scheme by the developer. Please ensure you tell us when any proposed land rights are needed so that all required documentation is in place at the earliest possible stage.
Any ‘as laid’ record must be fully in accordance with the planned position of the main that was shown in any notice before the main is connected to our network.
1.15 Water mains in a streetAn adopted footpath is a public walkway which is maintained by the local council or highway authority. The footpath is normally of a minimum width of 1.8 metres. SLOs should only consider laying mains in a footpath narrower than 1.8 metres if it is not used by
any other utilities. If the main is not laid within this footpath, it should be positioned in the road about one metre from the kerb line.
An adopted road is a carriageway which is maintained by the local council or highway authority. The carriageway is normally of a minimum width of 5.5 metres. If the main is not laid within this carriageway, it should be positioned approximately one metre from the kerb line.
1.16 Water mains not in a street Sections 158, 159 and 168 of the Water Industry Act 1991 give us powers to lay mains in streets and private land without obtaining formal easements.
1.17 Self-lay in land that is not a streetWhen mains are self-laid in private land and intended to be subsequently adopted by us, the rights provided by the Water Industry Act 1991 do not apply to SLOs. In such cases, the developer will need to obtain permission from the land owner to install the pipes and then arrange for a deed of easement in favour of Thames Water to be in place before the new mains can be adopted and connected to our network. Any costs incurred in arranging the permissions and subsequent transfers to Thames Water are to be paid by the developer. Advice on all issues concerning pipes in private land should be sought from us.
2.1 Design guidance pressureOur requirements on network pressures are as follows:
• At all times the pressure within the network must be maintained above 1.5 bar. The design of the replaced network must not result in pressures above 10 bar unless previously agreed with us.
• The design must limit the hydraulic level across the area at peak instantaneous flow, to avoid unacceptable pressure changes throughout the day. Hydraulic gradients need to accommodate areas with significant ground level changes or tall buildings.
Please also note that we may require you to install pressure management systems in areas where the static pressures exceeds 5 bar.
2.2 Design guidance velocity of flowThe velocity of flow should be between 0.4m/s and 0.6m/s under average daily operating conditions, and between 0/6m/s and 1.0m/s under peak daily operating conditions, excluding emergency conditions.
2.3 Design guidance hydraulic gradientAny new pipe or network change should be designed so that the hydraulic gradient is typically in the range of 2 to 4 metres per 1000 metres in the proposed main, and in any existing mains that may be influenced by the proposal. However, if downstream pressure is available in sufficient quantity and its reduction is not a concern to us, then a hydraulic gradient not exceeding 10 metres in 1000 metres can be used.
2.4 Sizing new mains for domestic premisesThe following should be used as a guide to the number of residential properties that can be supplied from a new main. These figures are for new mains calculations only and must not be used for service connections.
When a new development has a mixture of houses and flats, the overall demand of the development should be calculated and the mains sized accordingly.
2.5 Sizing mains for non-domestic and mixed demandsWe must carry out the sizing of mains on schemes for non-residential properties, as these need to be modelled, or may have already been modelled. Under the Water Industry Act 1991, we can refuse to supply premises requiring non-domestic use. However, we always look to accommodate customers’ requirements and refusal is only in extreme cases. You must ensure you match our requirements – for example, regarding storage – before we agree to supply the premises.
2.6 Managing water quality in new mainsPlease avoid dead legs wherever possible. New mains should be designed to ensure that the last service connection point is no more than one metre away from any end washout.
Mains should not be laid and commissioned in anticipation of future development, as this would constitute a dead leg. Tees can be installed for future phasing of a development, providing they have a valve and washout on the outlet.
2. Pressures, flow and sizes
Internal diameter Residential properties
75mm 60 houses or 100 flats
100mm 130 houses or 230 flats
150mm 400 houses or 700 flats
200mm 900 houses or 1500 flats
300mm 2600 houses or 4500 flats
3.1 Isolating valvesValves are installed to isolate sections of main and to ensure integrity of supply. A valve is installed on every tee outlet for shutting in and identifying the line of the main. The only exception to this rule is where a tee connection includes a valve fitted either side (in-line), in which case there is no gain achieved by the installation of a valve on the outlet branch.
A valve should be installed along a straight length of new main in order to protect more than 50 properties. A valve should be fitted every 500 metres along a straight length of new main, in order to isolate sections of main for future repair and maintenance purposes.
A valve should also be installed on a main immediately on the public side of any gated private access roads. This will ensure that the main can be ‘closed in’ without affecting other customers. Depending on the size and nature of the proposed new development, and the layout of the existing network, it may be necessary to install new valves either side of the tee connection to ensure integrity of supply.
When installing a valve within a verge or soft ground, the chamber should be adequately supported. This is achieved by providing a one-square-metre layer of concrete to 150mm depth around the chamber, which prevents foliage growing over the chamber and damage to the fitting when operating.Valves should comply with BSEN1563, and internal and external protection must be provided by blue fusion-bonded epoxy powder coating. All valves should be right-hand (clockwise) close only.
3.2 Air valvesAir valves are a means of venting air from the network. They should be installed at points where air can accumulate, such as high points along the route of a new main, bridge crossings and where a main is diverted under an obstruction. An air valve should be installed in conjunction with a tee along the line of a main.
When installing an air valve within a verge or soft ground, the chamber should be adequately supported. This is achieved by providing a one-square-metre layer of concrete to 150mm depth around the chamber, which prevents foliage growing over the chamber and damage to the fitting when operating.
3. Valves
Washouts are installed in order to maintain the integrity of the water supply by providing flushing points.
Combinations of isolation valves and washouts must be provided to enable the isolation and flushing of sections of the main. Washouts must be installed:
• To achieve isolation of a maximum of 500 properties
• At road junctions • At all tees • At a maximum distance of 100 metres apart
A washout must be installed at the end of every leg of main, no more than one metre after the last service connection, in order to prevent the build-up of stagnant water in the main. When connecting a new main between two or more existing mains, washouts should always be installed on the outlet branch of the tee connection point with any existing main. This provides adequate facility for any future disinfection / flushing required across the site.
Please ensure you install washouts and a valve every 500 metres along a straight length of new main, so that sections can be disinfected and flushed following any future repair / maintenance activities. A washout must always be installed next to every closed district boundary valve.
When installing a washout within a verge or soft ground, the chamber should be adequately supported. This is achieved by providing a one-square-metre layer of concrete to 150mm depth around the chamber, which prevents foliage growing over the chamber and damage to the fitting when operating.
4. Washouts
5.1 DefinitionsThe communication pipe is the part of the service pipe owned by us and laid in the same street as the main to which it is connected.
The service pipe connects the water main and the premises being supplied.
The supply pipe is the part of the service pipe belonging to the property owner, and laid within the property boundary.
5.2 Conditions for connectionWe will only connect new pipework to our network once these conditions have been met:• We have received payment for the quotation.• A Water Regulations inspection has taken place
confirming the pipework laid is to the correct standard.
• We have received chlorination results and confirmed that they are acceptable for all supplies with an internal diameter of 50mm and greater.
5.3 General requirements for service pipesServices on non-contaminated sites up to and including 63mm must be made of MDPE (PE80). Services on contaminated sites must be made of barrier pipe.
5.4 Service connection arrangementsWhen a new development is being planned, service connections should be designed in conjunction with both new and existing mains to ensure that services are:
• Laid in a position agreed with Thames Water• Generally perpendicular to the main• Not crossing others’ land• A minimum of 25mm diameter blue PE (or barrier
pipe as required), minimum depth 750mm, maximum depth 1350mm
5. Requirements for service pipes
Property boundary
Supply pipe Communication pipe
Inside stop valve
Internal pipe
Point of entry
Foundations Outside stop valve
Pipework in andaround a typicalhome
5.5 Standard service connection detailsThe service pipe must be installed up to the property boundary. It should be installed at right angles to the distribution main and follow a straight line to the boundary box wherever possible.
All service pipes and meter inlets and outlets must be installed with a minimum cover of 750mm. You must inform us if this cannot be achieved, or if a customer supply pipe is found to be less than 750mm in depth.
The service pipe and supply pipe must be connected with a service adapter at the property boundary.
Where a service has been laid through a duct, the duct must only be used if it is at the correct depth (750mm), and is in line with the customer supply pipe. When installed, the tapping duct and meter box must be in a straight line.
All customer connections to the network must have a means of isolating the customer supply.
6.1 Temporary supply installationWhen designing or setting up a temporary builder’s supply, this diagram shows all the components that need to be in place prior to connecting to the network.
6. Metering
Hose union bib-tap
Insulated pipe-workand fittings securelybracketed to post orbrick wall
Drain tap
Double check valveassembly
In-line stop tap
Insulated ducting
Supply should belaid at minimumdepth of 750mm
Ground level
WRAS approved meterbox located at point ofconnection
Lockable Housing
Property boundary
6.2 Internal fit metering for flats or multi occupancy premisesPlease refer to our internal fit metering guidance leaflet.
6.3 Metering standard service connectionsFor further information, please refer to our Self-Lay Policy and Addendum to the WRc Code of Practice.
6.4 Meter specification• All meters are sourced by us at a cost to the
developer or the SLO.• Concentric 15mm meters are used for external fit
in boundary boxes / manifold boxes.• Internal meters are 20mm in line and are supplied
with a fitting kit.
6.5 Meter pits• Boundary boxes are used to install up to six meters
on pipework entering a property at the same location. A 600mm x 450mm pit will be required for installations of up to six meters if a boundary box cannot be used.
• It must be possible to read the meter from the top of the chamber at ground level. It must also be 300mm to 600mm below ground level.
• Boundary box installations must not sit on any other utilities’ pipes or cables, or any drain or duct.
• Boundary boxes must be Class ‘B’ rated and may be used in areas subject to occasional traffic loading.
• An Atplas box must be used for 25mm and 32mm connections.
6.6 Metering non-standard service connectionsService connections greater than 32mm in diameter are classed as non-standard connections. These may be used to supply a number of individually metered premises or a single premises, where fitted with a bulk meter. The arrangements for metering and their locations are likely to be design-specific and dependent on the construction of the building, the layout of the pipe work and the availability of sufficient space to facilitate the meter installation.
Click here
7.1 Fire hydrantsFire hydrants are installed for the relevant fire authority for the purpose of firefighting. They are water company assets but are the responsibility of the fire authority. Fire hydrants are installed as a requirement under the Fire Services Act 2004.
A fire hydrant is an identical fitting to a washout, but identifiable by its cover marked ‘FH’. Fire hydrant positions are highlighted on the approved drawings and are subject to approval by the fire authority. Fire hydrants must be installed within the footpath every 180 metres along a straight length of main. No property should be more than 90 metres from a hydrant. The hydrant must be installed to the correct specification as detailed on the mains drawing. Its installation details are subjected to an audit checklist.
Hydrants must be compliant with BS750:1984. All hydrants must have a copper alloy (gunmetal) outlet and an automatic frost valve. Hydrants must be of a fixed jumper design.
When installing a hydrant within a verge or soft ground, the chamber should be adequately supported. This is achieved by providing a one-square-metre layer of concrete to 150mm depth around the chamber, which prevents foliage growing over the chamber and damage to the fitting when operating
Hydrants should be located so that fire and rescue services’ fire hoses do not run across dual carriageways or railways during firefighting. Additional hydrants may be needed to avoid this possibility.
7.2 Statutory dutyWe are responsible for contacting and providing the relevant fire and rescue service with all information needed to assess firefighting requirements. The fire and rescue service should respond to us, detailing their requirements, within 42 calendar days of having been provided with all necessary information. We will
then provide drawings for on-site auditing purposes based on the approved water main design, indicating the location of any required firefighting equipment. We may refuse to connect any new mains where the agreed firefighting equipment has not been installed, or where a fire and rescue service has not been given adequate opportunity to provide their requirements.
7.3 Requirements for firefighting waterThe Local Government Association / Water UK national guidance document on the provision of water for firefighting gives guidelines on flow requirements for firefighting as follows:
7.4 Fire sprinker systemsPlease refer to our fire supply policy, available on request.
7. Fire fighting
Type of developmentIdeal required flow (l/s)
Housing (2 floors or fewer) 8
Housing (more than 2 floors) 20-35
Industrial (1 hectare or less) 20
Industrial 1-2 hectares 35
Industrial 2-3 hectares 50
Industrial (more than 3 hectares) 75
Shops, offices, recreation 20-75
Community halls 15
Primary school, health centre (1 floor) 20
Secondary school, health centre (2 or more floors) 35
The Water Industry Act 1991 requires us to alter or remove any pipe or other apparatus if requested to do so by a developer if the land cannot be developed without the required alteration or removal. This requirement does not apply to any pipe or equipment that is located in a street.
We will require advance payment of the estimated reasonable cost of diverting or abandoning any existing mains or associated equipment. This applies to both self- lay and requisition schemes.
8.1 A development with both a new main and an abandoned mainFor this development it was necessary to install a new main for half of the development and also to abandon and divert an existing main to accommodate the new buildings on farm land.
8. Abandonment and diversion of existing mains
148.0m
Playing Field
Sweetapple
Wymans
Cottage
Chapel Cottages
Whipsiderry
1
Bungalow
Rosem
ary
Owl
Cairncot
3
West End
Cottage
West
Cottage
End
Stone Cottage
Lay-by
LB
Overton
Bridge
143.7m
GridCattle
43
1
Old Post Office Cottages
Manor Farm
2
Kimberley
River Kennet
Pond
Footbridge
TCB
FRO
G LAN
E143.6m
The
Withy Bed
New
ton House
The Grange
704
Yew
The
Cot
tage
1
Alma
Cottage
With
y
Cott
Tree
s
Tree
73
Newland
10
Shelter
9
Redlands
Pond
Track
CLOSE
KNIGHTS
SO
UTH
FIE
LD
PEACOCK
WYM
ANS FIELD
KNIG
HTS C
LOSE
FOR
GE LAN
E
FORGE CL
El
Sub Sta
13
Cott
23
12
27
1
1
4
6
2
5
Pear Tree
10
3
26
1
9
68
22
28
6
18
New
2
2
1
5
Houses
67
9
Wits End
4
1
1
6
1
2
2
FH
WO
6" CLASS C
3" (90) SI
3"
FH
(09) (10) 3" PVC
3" SI
WO
FH
FH
WO
3" PVC
(09)
90mm
90mm
90mm
3" PVC
3" (17) P
VC
3" P
VC
3" (90) SI
3" (90) SI
1012
39
5 4
67
8
4
148.0m
Playing Field
Sweetapple
Wymans
Cottage
Chapel Cottages
Whipsiderry
1
Bungalow
Rosem
ary
Owl
Cairncot
3
West End
Cottage
West
Cottage
End
Stone Cottage
LB
GridCattle
43
1
Old Post Office Cottages
Manor Farm
2
Kimberley
River Kennet
FH
WO
3" (90) SI
3"
3" (90) SI
3" (90) SI
90mm HPPE
WO
90mm HPPE
1012
39
5 4
67
8
4
"THRUST BLOCK" (AS REQUIRED)
P 1
P 2
90mm HPPE
WO
WO
1x 32mm MDPE
1x 3
2mm
MDP
E1x
32m
m M
DPE
1x 3
2mm
MD
PE
P 3
P 4
FOR INFORMATION1 WK
(NOT TO SCALE)SITE LOCATION PLAN
1517
09
ROUTE OF NEW MAIN & APPARATUS AS INDICATED
DEPTH OF COVER OF NEW MAIN:
(PLEASE TICK TO CONFIRM)
0.9 OTHER (PLEASE STATE)
DEPTH OF COVER AT CONNECTION POINT TO EXISTING MAIN (POINT 1)
0.9 OTHER (PLEASE STATE)
FULL 'AS LAID' DRAWINGPART ' AS LAID' S DRAWING
YESF/H's PERMANENTLY REINSTATED
CONTRACTOR SIGN OFF:
THAMES WATER SIGN OFF: DATE
AS LAID SIGN OFF
NO N/A
DATE
430
450
600
250
900
960
1255
1550
1720
Carriageway
Tele
com
ms
Wat
er
Gas
Cab
le T
V/c
omm
unic
atio
ns
Ele
c lv
Ele
c hv
Ele
c lv
alt
pos'
n
Dimensions in mm
Bou
ndar
y
1. THE LAYOUT OF MAINS IS GENERALLY IN ACCORDANCE WITH THE'REPORT OF JOINT COMMITTEE ON LOCATION OF UNDERGROUNDSERVICES' PUBLISHED BY THE INSTITUTION OF CIVIL ENGINEERS.
2. THE DIMENSIONS SHOWN REPRESENT THE PREFERRED ARRANGEMENTIN STRAIGHT ROUTES ON RESIDENTIAL ESTATES. VARIATIONS MAY BENECESSARY AT CURVES AND CHANGES OF GRADIENT.
3. THE SPACE ALLOCATED IS CONSIDERED TO BE THE ABSOLUTEMINIMUM AND IN CERTAIN CIRCUMSTANCES E.G. WHERE BOTH HV AND LVCABLES ARE LAID - THE LV CABLE WILL BE LAID IN THE ALTERNATIVE
4. WHERE SERVICES ARE TO BE CONNECTED TO MAINS A MINIMUMDISTANCE OF 2.0M IS REQUIRED BETWEEN THE BUILDING LINE AND THECENTRE LINE OF THE MAIN.
POSITION AND ADDITIONAL WIDTH MAY BE REQUIRED.
MAINS ROUTE
170
2000
295
600
295
690
270
430
350
260280
5. MINIMUM DISTANCE OF ANY WATER SERVICE TO ANY
COVER OF WATER MAINUP TO 12"(300mm) 900mm12"(300mm) TO 24"(600mm) 1100mm
24"(600mm) AND OVER 1200mm
SURFACE/FOUL WATER STRUCTURE IS 300mm.
TRENCH WIDTH
100mm 'BED AND SURROUND' TO MAIN
NOTES:
PREFERRED LAYOUT FOR MAINS IN A 2 METRES WIDE FOOTWAY:
NOMINAL TRENCH WIDTHS TO ALLOW FOR100mm
100mm
DESCRIPTIONREV CHKDRN DATEAPP
SERVICE ORDER No: GRID REF
GRID REF
GRID REF
GRID REF
GRID REF
OPERATION No:
OPERATION No:
OPERATION No:
OPERATION No:
FITTINGS
SCHEDULE OF FITTINGS
POINT NUMBER
ALL FITTINGS,MATERIALS,PIPES & JOINTS ARE TO BE INSTALLED INACCORDANCE WITH "LOT C2 STANDARD NEW MAINS AND CONNECTIONS(APRIL 2010)"
CAD DATE:CAD DATE: CAD :
CTH
AM
ES
WA
TER
UTI
LITI
ES
LTD
(201
3)
CAD PATH: A1
CUSTOMER
MATERIAL: LENGTH:
LINES AND LEVELS CONFIRMED DURING SITE MEETING HELD ON:-
NAME
SIGNATURE
COMPANY
SURVEYORCONTRACTOR
MATERIAL:
MATERIAL: DIA:DIA:
DIA:
LENGTH:LENGTH:
LENGTH:
THIS DRAWING IS BASED ON DEVELOPERS DRAWING No.:
THAMES WATER UTILITIESDEVELOPER SERVICES,CLEARWATER COURT,VASTERN ROAD,
TEL: 0800 009 3921
SITE LOCATION:
READING RG1 8DB
EMAIL: DEVELOPER.SERVICERS@ THAMESWATER.CO.UK
DRAWN BY
SCALE:
SERVICE ORDER :
SELF-LAY No:
REVISION:
SUB CASE No:
SCHEME No:
DESIGN BY
GRID REF:
WPA No:
1
\\Tafiwp02\CFS01_KW-SHARED\NEW Operations\CAD-CLEAN WATER 2015\50077516 MANOR FARM,WEST OVERTON MALBOROUGH,SN8 4ER\WIP 50077516 MANOR FARM,WEST OVERTON MALBOROUGH,SN8 4ER REV 3 09/11/2015 03
1. ALL END WASHOUTS TO BE POSITIONED NO MORE THAN 1m PAST LAST DRAW OFF POINT.2. ALL FIRE HYDRANTS TO BE INSTALLED TO BS750(COPPER/GUNMETAL OUTLET ONLY)3. ALL FITTINGS & CHAMBERS WITH IN VERGES/SOFT GROUND MUST BE ADEQUATELY SUPPORTED BY 1sq m LAYER OF CONCRETE WITH A LAYER OF A393 MESH ON SUITABLE COMPACTED MATERIAL TO A DEPTH OF 150mm.4. ALL 'OPEN ENDED' PIPE WORK FOLLOWING ABANDONMENT OF MAINS,AND REMOVAL OF FITTINGS, (IN OFF-SITE CONDITIONS) MUST BE CAPPED TO ENSURE THERE IS NO INTRUSION OF EARTH ETC,WHICH COULD RESULT IN FUTURE GROUND SUBSIDENCE.5. ALL THRUST BLOCKS MUST BE DETERMINED ON SITE AND CALCULATIONS SUBJECT TO BEARING CAPACITY OF THE SOIL.
6.THE ACTUAL LINE AND DEPTH OF THE MAIN OR PIPE AS SHOWN IS SUBJECT TO VARIATION DUE TO OBSTRUCTIONS.7.IT IS THE CUSTOMER'S RESPONSIBILITY FOR INDICATING THE PLANNED
BOUNDARY LINES AND LEVELS OF ALL ROADS, PATHS, ETC., IN WHICHMAINS ARE TO BE LAID.
SHOULD ANY VARIATION TO THESE LINES OR LEVELS BE MADE WITHOUT THAMES WATER'S CONSENT AFTER THE MAINS HAVE BEEN LAID, THEN THE CUSTOMER WILL BE RESPONSIBLE FOR THE COST OF ANY SUBSEQUENT ALTERATIONS TO OUR APPARATUS.8.DISTANCES TAKE INTO ACCOUNT ANY TOPOGRAPIC VARIANCES.
9.PLEASE NOTE FITTINGS ARE NOT SHOWN TO SCALE.
10.ALL DUCTILE IRON PIPEWORK IS TO BE WRAPPED UNLESS OTHERWISE SPECIFIED.
11.MAINS WILL BE INSTALLED AT A UNIFORM DEPTH WITH THE MINIMUM NUMBER OF BENDS REQUIRED AND TO BE LAID IN A DIRECT ROUTE AS FAR AS PRACTICALLY POSSIBLE.
12.THE POSITION OF ANY BOUNDARY OR APPARATUS SHOWN ON THIS PLANIS GIVEN WITHOUT OBLIGATION AND WARRANTY AND ACCURACYCANNOT BE GUARANTEED. NO LIABILITY OF ANY KIND WHATSOEVER ISACCEPTED BY THAMES WATER FOR ANY ERROR OR OMISSION.
80308336 SU1288567939
ADDED SERVICE CONNECTIONS2 WK 1505
10
NOMINAL TRENCH WIDTHS TO ALLOWFOR NO MORE THAN 100mm 'BED ANDSURROUND' TO THAMES WATER PIPE,UNLESS INSTRUCTED OTHERWISE BYTHAMES WATER
100mm
100mm
CHANGED DESIGN3 WK 1509
11
8.2 Example of a redeveloped site with a diverted/abandoned mainThis is a development where the existing site has been redeveloped. As a result the main in yellow has been abandoned to accommodate new houses that have been built where a road used to be. New mains also had to be installed.
The diagram below sets out the minimum distances that should exist between water mains and certain types of tree. Please ensure you adhere to these distances in order to protect trees from any future maintenance we need to carry out on the main. You should also read the NJUG guidelines Volume 4 for further information.
9. Tree planting guidance
Large growing species
Distance from
pipeline
Poplars and Willows
Large conifers and deciduous forest trees
Scots pineBlack PineCedarLarchAshBeechSycamore
Horse ChestnutSweet ChestnutLondon PlaneHornbeamLime AlderElmOak
ApplePlumCherryLimePear
Dwarf stock fruit trees
Amenity TreesField MapleWild CherryCrab AppleCobnutBirchElder
Ornamental TreesMountain AshWhitebeamCockspur ThornFalse AcaciaLawsons Cypress
Shrub planting bushes
HollyLaurelPrivetRhododendronChristmas TreeDogwoord
SpindleGuelderroseGooseberriesRaspberriesCurrantsRoses
Loganberries
Hedge plants and ground coverHedge plants and where necessary over the pipeline,road and field crossings etc.
Ground coverHawthornSnowberryBlackthorn
BerberisHeathersCotoneaster
10.0m
6.0m
3.0m
1.5m
10.1 New mains in a shared driveIn this example the new mains and communication pipes will be installed within the shared driveway. There is no requirement for an easement as the new main is installed in a street.
10. Example layouts for new mains and services FARLEIGH ROAD
TREES
FORRESTCLOSE
DAM
SON
COLTON ROAD
FRIARS CLOSE
4
7
10
15
17
1
18
3
Pump House
42
6
30
12
(disused)
7
25
2
12
24
30
8
11
28
5
32
22
8
1
22
LB
STALLPITS ROAD
A 42
0
Cattle Grid
Path (um)
33
54
58
47
50
45
57
36
46
52
1
35
35
2
WO
WO
WO
FH
FH
1" EV
4" PVC
3" CI
3" (1988) PVC
4"
3" CI
3" CI
4" CI
FH
FH
3" DI
3" CI
3" DI
WO
P 1 "THRUST BLOCK" (AS REQUIRED)
125m
m H
PPE
WO
90mm HPPE
125mm
HPPE
125mm HPPE
90mm HPPE
90mm HPPE
90mm HPPE
90mm
HPPE
90mm
HPPE
90mm
HPPE
125mm
HPPE
"THRUST BLOCK" (AS REQUIRED)
"THRUST BLOCK" (AS REQUIRED)
WO
WO
WO
P 7
"THRUST BLOCK" (AS REQUIRED)
"THRUST BLOCK" (AS REQUIRED)
WO
WO
WOP 14
6
3
3
2
REMOVE EXISTINGWASHOUT AFTERCHLORINATION
P 14.1
P 14.2
125mm HPPE
"THRUST BLOCK" (AS REQUIRED)
P 7.1
P 1.1SLO TO MAKE THE FINALPIECE THROUGH UNDERTW SUPERVISION
SLO TO MAKE THE FINALPIECE THROUGH UNDERTW SUPERVISION
SLO TO MAKE THE FINALPIECE THROUGH UNDERTW SUPERVISION
125mm
HPPE
125mm
HPPE
Lay-
by
CURTIS ROAD
FARLEIGH ROAD
TREES
FORRESTCLOSE
DAM
SON
COLTON ROAD
FRIARS CLOSE
4
2
7
10
15
17
1
18
Pump House
6
30
12
19
(disused)
7
2
12
24
30
15
8
11
14
28
5
32
17a
22
8
1
1
22
LB
STALLPITS ROAD
A 42
0
Cattle Grid
Path (um)
54
58
47
50
45
57
36
46
52
1
35
2
WO
WO
WO
FH
FH
4" PVC
3" CI
3" (1988) PVC
4"
4"
3" CI
3" CI
3" CI
4" CI
4" CI
FH
FH
3" DI
3" CI
3" DI
FOR INFORMATION1 PB
(NOT TO SCALE)SITE LOCATION PLAN
15
1410
ROUTE OF NEW MAIN & APPARATUS AS INDICATED
DEPTH OF COVER OF NEW MAIN:
(PLEASE TICK TO CONFIRM)
0.9 OTHER (PLEASE STATE)
DEPTH OF COVER AT CONNECTION POINT TO EXISTING MAIN (POINT 1)
0.9 OTHER (PLEASE STATE)
FULL 'AS LAID' DRAWINGPART ' AS LAID' S DRAWING
YESF/H's PERMANENTLY REINSTATED
CONTRACTOR SIGN OFF:
THAMES WATER SIGN OFF: DATE
AS LAID SIGN OFF
NO N/A
DATE
430
450
600
250
900
960
1255
1550
1720
Carriageway
Tele
com
ms
Wat
er
Gas
Cab
le T
V/c
omm
unic
atio
ns
Ele
c lv
Ele
c hv
Ele
c lv
alt
pos'
n
Dimensions in mm
Bou
ndar
y
1. THE LAYOUT OF MAINS IS GENERALLY IN ACCORDANCE WITH THE'REPORT OF JOINT COMMITTEE ON LOCATION OF UNDERGROUNDSERVICES' PUBLISHED BY THE INSTITUTION OF CIVIL ENGINEERS.
2. THE DIMENSIONS SHOWN REPRESENT THE PREFERRED ARRANGEMENTIN STRAIGHT ROUTES ON RESIDENTIAL ESTATES. VARIATIONS MAY BENECESSARY AT CURVES AND CHANGES OF GRADIENT.
3. THE SPACE ALLOCATED IS CONSIDERED TO BE THE ABSOLUTEMINIMUM AND IN CERTAIN CIRCUMSTANCES E.G. WHERE BOTH HV AND LVCABLES ARE LAID - THE LV CABLE WILL BE LAID IN THE ALTERNATIVE
4. WHERE SERVICES ARE TO BE CONNECTED TO MAINS A MINIMUMDISTANCE OF 2.0M IS REQUIRED BETWEEN THE BUILDING LINE AND THECENTRE LINE OF THE MAIN.
POSITION AND ADDITIONAL WIDTH MAY BE REQUIRED.
MAINS ROUTE
170
2000
295
600
295
690
270
430
350
260280
5. MINIMUM DISTANCE OF ANY WATER SERVICE TO ANY
COVER OF WATER MAINUP TO 12"(300mm) 900mm12"(300mm) TO 24"(600mm) 1100mm
24"(600mm) AND OVER 1200mm
SURFACE/FOUL WATER STRUCTURE IS 300mm.
TRENCH WIDTH
100mm 'BED AND SURROUND' TO MAIN
NOTES:
PREFERRED LAYOUT FOR MAINS IN A 2 METRES WIDE FOOTWAY:
NOMINAL TRENCH WIDTHS TO ALLOW FOR100mm
100mm
DESCRIPTIONREV CHKDRN DATEAPP
SERVICE ORDER No: GRID REF
GRID REF
GRID REF
GRID REF
GRID REF
OPERATION No:
OPERATION No:
OPERATION No:
OPERATION No:
CAD PATH:
FITTINGS
SCHEDULE OF FITTINGS
POINT NUMBER
ALL FITTINGS,MATERIALS,PIPES & JOINTS ARE TO BE INSTALLED INACCORDANCE WITH "LOT C2 STANDARD NEW MAINS AND CONNECTIONS(APRIL 2010)"
CAD DATE:CAD DATE: CAD :
CTH
AM
ES
WA
TER
UTI
LITI
ES
LTD
(201
3)
A0
CUSTOMER
LINES AND LEVELS CONFIRMED DURING SITE MEETING HELD ON:-
NAME
SIGNATURECOMPANY
SURVEYORCONTRACTOR
THIS DRAWING IS BASED ON DEVELOPERS DRAWING No.:
THAMES WATER UTILITIESDEVELOPER SERVICES,CLEARWATER COURT,VASTERN ROAD,
TEL: 0800 009 3921READING RG1 8DB
EMAIL: DEVELOPER.SERVICES@ THAMESWATER.CO.UK
DRAWN BY
SCALE:
SERVICE ORDER No:
SELF-LAY No:
REVISION:
SUB CASE No:
SCHEME No:
DESIGN BY
GRID REF:
WPA No:
MATERIAL: LENGTH:
MATERIAL:
MATERIAL: DIA:DIA:
DIA:
LENGTH:LENGTH:
LENGTH:
SITE LOCATION:
MATERIAL: DIA: LENGTH:
\\TAFIWP02\CFS01_KW-SHARED\NEW OPERATIONS\CAD-CLEAN WATER 2015\50068879 DAMSON TREE FIELDS,SHRIVENHAM,SN6 8AZ\WIP 50068879 DAMSON TREE FIELDS,SHRIVENHAM,SN6 8AZ REV 2 16/12/2015 02
1. ALL END WASHOUTS TO BE POSITIONED NO MORE THAN 1m PAST LAST DRAW OFF POINT.2. ALL FIRE HYDRANTS TO BE INSTALLED TO BS750(COPPER/GUNMETAL OUTLET ONLY)3. ALL FITTINGS & CHAMBERS WITH IN VERGES/SOFT GROUND MUST BE ADEQUATELY SUPPORTED BY 1sq m LAYER OF CONCRETE WITH A LAYER OF A393 MESH ON SUITABLE COMPACTED MATERIAL TO A DEPTH OF 150mm.4. ALL 'OPEN ENDED' PIPE WORK FOLLOWING ABANDONMENT OF MAINS,AND REMOVAL OF FITTINGS, (IN OFF-SITE CONDITIONS) MUST BE CAPPED TO ENSURE THERE IS NO INTRUSION OF EARTH ETC,WHICH COULD RESULT IN FUTURE GROUND SUBSIDENCE.5. ALL THRUST BLOCKS MUST BE DETERMINED ON SITE AND CALCULATIONS SUBJECT TO BEARING CAPACITY OF THE SOIL.
6.THE ACTUAL LINE AND DEPTH OF THE MAIN OR PIPE AS SHOWN IS SUBJECT TO VARIATION DUE TO OBSTRUCTIONS.7.IT IS THE CUSTOMER'S RESPONSIBILITY FOR INDICATING THE PLANNED
BOUNDARY LINES AND LEVELS OF ALL ROADS, PATHS, ETC., IN WHICHMAINS ARE TO BE LAID.
SHOULD ANY VARIATION TO THESE LINES OR LEVELS BE MADE WITHOUT THAMES WATER'S CONSENT AFTER THE MAINS HAVE BEEN LAID, THEN THE CUSTOMER WILL BE RESPONSIBLE FOR THE COST OF ANY SUBSEQUENT ALTERATIONS TO OUR APPARATUS.8.DISTANCES TAKE INTO ACCOUNT ANY TOPOGRAPIC VARIANCES.
9.PLEASE NOTE FITTINGS ARE NOT SHOWN TO SCALE.
10.ALL DUCTILE IRON PIPEWORK IS TO BE WRAPPED UNLESS OTHERWISE SPECIFIED.11.MAINS WILL BE INSTALLED AT A UNIFORM DEPTH WITH THE MINIMUM NUMBER OF BENDS REQUIRED AND TO BE LAID IN A DIRECT ROUTE AS FAR AS PRACTICALLY POSSIBLE.
12.THE POSITION OF ANY BOUNDARY OR APPARATUS SHOWN ON THIS PLANIS GIVEN WITHOUT OBLIGATION AND WARRANTY AND ACCURACYCANNOT BE GUARANTEED. NO LIABILITY OF ANY KIND WHATSOEVER ISACCEPTED BY THAMES WATER FOR ANY ERROR OR OMISSION.
80279588 SU2330388783
SELF LAY2 WK 15
1612
SELF LAY DRAWING
NOTE:"NON-CONTESTABLE PIPEWORK WILLEND 1.0m INSIDE SITE BOUNDARY"
10.2 New mains in a footwayIn this example the new mains and communication pipes will be installed within the footway. It does not matter whether the footway is adopted or a shared footway as the new main is installed in a street and there is no requirement for an easement.
FH
ZBV499434
DPV499427
ZBV030860
WO
3370
ZBV030576
5092
158
WO
WO
ZBV030582
WOZBV030583
WO
WO
905
WO
590
WO
WO
WO
510
WOWO
904
2286
2287
WO
2289
WO
2288
18"8'' CI 30"
3'' CI
18"
30"
8'' CI
450mm
200mm DI800m
m
800mm
150m
m F
IRE
4"
200mm DI450mm
6"
12"
4" CAST IR
ON
6"
100mm
200mm
4"
150mm
12"
6"
6"
100mm
6"12"
12"
12"
30"
3"
3"
3"
3"
3"
100m
m
WO
ZBV198143
PRV900430PBV760953
WO
DM05303
WO
DM05304
ZBV499953
ZBV030567
FH
FH
800mm450mm
18"
30"
8'' CI
3'' CI
18"
3'' C
I
3"
3" 100mm
4"
FH
4'' CI
100mm ST
30"
Def
CR
Boro Const and Ward Bdy
CR
BS
Post
Post
TCB
Stone
LB
SMILES
LEWISHAM
ROAD
BLACKHEATH RISE
MORDEN HILL
Columbine W
ay
Columbine W
ay
CONINGTON ROAD
PRIN
CES
RIS
E
PLACE
10.8m
16.9m
14.2m
14.5m
14.0m
20.2m
Playground
SM
Play
grou
nd
Car Park
22
2
Hornbuckle
290
Boulton
Aster House
22 to
27
254
13
17
Sub StaEl
1 to
36
7
(PH)
6
7
95
18
Excelsior Gardens
77
1 to 6
Dukes Court
65
292
1
5
12
240
37
59
Lacey House
Pearmain House
27
Arms
23
150
13
Excelsior Gardens
Burn
ett H
ouse
9
16
284
14
140
25
200
69
22
18
Building
Adana
85
5571
41
Rosewood Gardens
13
14
25
1
1
8
39
24
172
28
126
142
1 to 6
43
Sydney
43
House 17
61
218
House
148
186 10
Hall
6
134
1
9
7a
47
Heward Court
2
1 to 6
120
9
63
El Sub Sta
93
22
7
20
13
24
39
17
Darwin House
67
6
16
11
6
2
1
216
132
18
4
16
Pitmaston
11
41
1 to 12
5
7
53
160
4
1 to 8
1 to 12
Mallow Court
House
268
63
28
45
23
FB
69
151
228
1 to 8
79
Superstore
2
33
1
Ravensbourne River
Posts
Subw
ay
TCBsLB
FB
WILLIAM CLOSE
JUNCTION APPROACH
SILK MILLS PATH
9.8m
Car ParkCar Park
El Sub
Sta
6
312
Meml
165
12
Garage
2
2
1 to 6
314
167 to 179
1
7 to
12
13 to
21
Learning Centre322
Station
310
296
PH
1
Lewisham
100
Granville Park Adult
316
War
SL
BS
Russett Way
Weir
8.0m
57
Chenla
Colgate House
Baquba
1036
Building
3
Century House
Nara Building
55
29
1 to 65
Building
1 to 58
5092
590
WO
4" CAST IR
ONColum
bine Way
CONINGTON ROAD
Playground
254
Sub StaEl
284
200
186
1
216
P 1
P 290mm HPPE
"THRUST BLOCK" (AS REQUIRED)
WO
WO
FOR INFORMATION1 WK
(NOT TO SCALE)SITE LOCATION PLAN
1507
07
430
960
1255
1550
1720
Carriageway
Dimensions in mm1. THE LAYOUT OF MAINS IS GENERALLY IN ACCORDANCE WITH THE'REPORT OF JOINT COMMITTEE ON LOCATION OF UNDERGROUNDSERVICES' PUBLISHED BY THE INSTITUTION OF CIVIL ENGINEERS.
2. THE DIMENSIONS SHOWN REPRESENT THE PREFERRED ARRANGEMENTIN STRAIGHT ROUTES ON RESIDENTIAL ESTATES. VARIATIONS MAY BENECESSARY AT CURVES AND CHANGES OF GRADIENT.
3. THE SPACE ALLOCATED IS CONSIDERED TO BE THE ABSOLUTEMINIMUM AND IN CERTAIN CIRCUMSTANCES E.G. WHERE BOTH HV AND LVCABLES ARE LAID - THE LV CABLE WILL BE LAID IN THE ALTERNATIVE
4. WHERE SERVICES ARE TO BE CONNECTED TO MAINS A MINIMUMDISTANCE OF 2.0M IS REQUIRED BETWEEN THE BUILDING LINE AND THECENTRE LINE OF THE MAIN.
POSITION AND ADDITIONAL WIDTH MAY BE REQUIRED.
MAINS ROUTE
170
2000
295 295
690
270
430
260280
5. MINIMUM DISTANCE OF ANY WATER SERVICE TO ANY
COVER OF WATER MAINUP TO 12"(300mm) 900mm12"(300mm) TO 24"(600mm) 1100mm
24"(600mm) AND OVER 1200mm
SURFACE/FOUL WATER STRUCTURE IS 300mm.
TRENCH WIDTH
100mm 'BED AND SURROUND' TO MAIN
NOTES:
PREFERRED LAYOUT FOR MAINS IN A 2 METRES WIDE FOOTWAY:
NOMINAL TRENCH WIDTHS TO ALLOW FOR100mm
100mm
ROUTE OF NEW MAIN & APPARATUS AS INDICATED
DEPTH OF COVER OF NEW MAIN:
(PLEASE TICK TO CONFIRM)
0.9 OTHER (PLEASE STATE)
DEPTH OF COVER AT CONNECTION POINT TO EXISTING MAIN (POINT 1)
0.9 OTHER (PLEASE STATE)
FULL 'AS LAID' DRAWINGPART ' AS LAID' S DRAWING
YESF/H's PERMANENTLY REINSTATED
CONTRACTOR SIGN OFF:
THAMES WATER SIGN OFF: DATE
AS LAID SIGN OFF
NO N/A
DATE
DESCRIPTIONREV CHKDRN DATEAPP
SERVICE ORDER No: GRID REF
GRID REF
GRID REF
GRID REF
GRID REF
OPERATION No:
OPERATION No:
OPERATION No:
OPERATION No:
FITTINGS
SCHEDULE OF FITTINGS
POINT NUMBER
CAD DATE:CAD DATE: CAD :CAD PATH:
ALL FITTINGS,MATERIALS,PIPES & JOINTS ARE TO BE INSTALLED INACCORDANCE WITH "LOT C2 STANDARD NEW MAINS AND CONNECTIONS(APRIL 2010)"
CTH
AM
ES
WA
TER
UTI
LITI
ES
LTD
(201
3)
A2
CUSTOMER
MATERIAL: LENGTH:
LINES AND LEVELS CONFIRMED DURING SITE MEETING HELD ON:-
NAME
SIGNATURE
COMPANY
SURVEYORCONTRACTOR
MATERIAL:
MATERIAL: DIA:DIA:
DIA:
LENGTH:LENGTH:
LENGTH:
THIS DRAWING IS BASED ON DEVELOPERS DRAWING No.:
THAMES WATER UTILITIESDEVELOPER SERVICES,CLEARWATER COURT,VASTERN ROAD,
TEL: 0800 009 3921
SITE LOCATION:
READING RG1 8DB
EMAIL: DEVELOPER.SERVICES@ THAMESWATER.CO.UK
DRAWN BY
SCALE:
SERVICE ORDER No:
SELF-LAY No:
REVISION:
SUB CASE No:
SCHEME No:
DESIGN BY
GRID REF:
WPA No:
1
\\Tafiwp02\CFS01_KW-SHARED\NEW Operations\CAD-CLEAN WATER 2015\50060031 ORCHARD GDNS,COLUMBINE WAY,SE13 7LQ\WIP 50060031 ORCHARD GDNS,COLUMBINE WAY,SE13 7LQ REV 1 0107/07/2015
1. ALL END WASHOUTS TO BE POSITIONED NO MORE THAN 1m PAST LAST DRAW OFF POINT.2. ALL FIRE HYDRANTS TO BE INSTALLED TO BS750(COPPER/GUNMETAL OUTLET ONLY)3. ALL FITTINGS & CHAMBERS WITH IN VERGES/SOFT GROUND MUST BE ADEQUATELY SUPPORTED BY 1sq m LAYER OF CONCRETE WITH A LAYER OF A393 MESH ON SUITABLE COMPACTED MATERIAL TO A DEPTH OF 150mm.4. ALL 'OPEN ENDED' PIPE WORK FOLLOWING ABANDONMENT OF MAINS,AND REMOVAL OF FITTINGS, (IN OFF-SITE CONDITIONS) MUST BE CAPPED TO ENSURE THERE IS NO INTRUSION OF EARTH ETC,WHICH COULD RESULT IN FUTURE GROUND SUBSIDENCE.5. ALL THRUST BLOCKS MUST BE DETERMINED ON SITE AND CALCULATIONS SUBJECT TO BEARING CAPACITY OF THE SOIL.
6.THE ACTUAL LINE AND DEPTH OF THE MAIN OR PIPE AS SHOWN IS SUBJECT TO VARIATION DUE TO OBSTRUCTIONS.7.IT IS THE CUSTOMER'S RESPONSIBILITY FOR INDICATING THE PLANNED
BOUNDARY LINES AND LEVELS OF ALL ROADS, PATHS, ETC., IN WHICHMAINS ARE TO BE LAID.
SHOULD ANY VARIATION TO THESE LINES OR LEVELS BE MADE WITHOUT THAMES WATER'S CONSENT AFTER THE MAINS HAVE BEEN LAID, THEN THE CUSTOMER WILL BE RESPONSIBLE FOR THE COST OF ANY SUBSEQUENT ALTERATIONS TO OUR APPARATUS.8.DISTANCES TAKE INTO ACCOUNT ANY TOPOGRAPIC VARIANCES.
9.PLEASE NOTE FITTINGS ARE NOT SHOWN TO SCALE.
10.ALL DUCTILE IRON PIPEWORK IS TO BE WRAPPED UNLESS OTHERWISE SPECIFIED.11.MAINS WILL BE INSTALLED AT A UNIFORM DEPTH WITH THE MINIMUM NUMBER OF BENDS REQUIRED AND TO BE LAID IN A DIRECT ROUTE AS FAR AS PRACTICALLY POSSIBLE.
12.THE POSITION OF ANY BOUNDARY OR APPARATUS SHOWN ON THIS PLANIS GIVEN WITHOUT OBLIGATION AND WARRANTY AND ACCURACYCANNOT BE GUARANTEED. NO LIABILITY OF ANY KIND WHATSOEVER ISACCEPTED BY THAMES WATER FOR ANY ERROR OR OMISSION.
80253611 TQ3816276134
10.3 New mains to be installed within a gated developmentIn this example the new mains and communication pipes will be installed within the private driveway of a gated development. There is no requirement for an easement as the new main is installed in a street. A controlling valve is sited outside the gated area so that the main/services can be isolated without delay if needed.
86.5m
85.3m
81.8m
79.7m
81.1m
83.1m
The Old
26
20
Harcourt Arms
All Saints'
The Old
21
PH
13
Farm
30
17
16
Forge
Pond
Drain
83.6m
FH
FH
3"
4" CAST IRON
4"
86.5m
20
21
PH
FH
4" CAST IRON
P 1
P 2
WO
90mm
BARRIER PIPE
2
2
"THRUST BLOCK" (AS REQUIRED)
FH
4
2
FOR INFORMATION1 WK
(NOT TO SCALE)SITE LOCATION PLAN
1525
09
430
960
1255
1550
1720
Carriageway
Dimensions in mm1. THE LAYOUT OF MAINS IS GENERALLY IN ACCORDANCE WITH THE'REPORT OF JOINT COMMITTEE ON LOCATION OF UNDERGROUNDSERVICES' PUBLISHED BY THE INSTITUTION OF CIVIL ENGINEERS.
2. THE DIMENSIONS SHOWN REPRESENT THE PREFERRED ARRANGEMENTIN STRAIGHT ROUTES ON RESIDENTIAL ESTATES. VARIATIONS MAY BENECESSARY AT CURVES AND CHANGES OF GRADIENT.
3. THE SPACE ALLOCATED IS CONSIDERED TO BE THE ABSOLUTEMINIMUM AND IN CERTAIN CIRCUMSTANCES E.G. WHERE BOTH HV AND LVCABLES ARE LAID - THE LV CABLE WILL BE LAID IN THE ALTERNATIVE
4. WHERE SERVICES ARE TO BE CONNECTED TO MAINS A MINIMUMDISTANCE OF 2.0M IS REQUIRED BETWEEN THE BUILDING LINE AND THECENTRE LINE OF THE MAIN.
POSITION AND ADDITIONAL WIDTH MAY BE REQUIRED.
MAINS ROUTE
170
2000
295 295
690
270
430
260280
5. MINIMUM DISTANCE OF ANY WATER SERVICE TO ANY
COVER OF WATER MAINUP TO 12"(300mm) 900mm12"(300mm) TO 24"(600mm) 1100mm
24"(600mm) AND OVER 1200mm
SURFACE/FOUL WATER STRUCTURE IS 300mm.
TRENCH WIDTH
100mm 'BED AND SURROUND' TO MAIN
NOTES:
PREFERRED LAYOUT FOR MAINS IN A 2 METRES WIDE FOOTWAY:
NOMINAL TRENCH WIDTHS TO ALLOW FOR100mm
100mm
ROUTE OF NEW MAIN & APPARATUS AS INDICATED
DEPTH OF COVER OF NEW MAIN:
(PLEASE TICK TO CONFIRM)
0.9 OTHER (PLEASE STATE)
DEPTH OF COVER AT CONNECTION POINT TO EXISTING MAIN (POINT 1)
0.9 OTHER (PLEASE STATE)
FULL 'AS LAID' DRAWINGPART ' AS LAID' S DRAWING
YESF/H's PERMANENTLY REINSTATED
CONTRACTOR SIGN OFF:
THAMES WATER SIGN OFF: DATE
AS LAID SIGN OFF
NO N/A
DATE
DESCRIPTIONREV CHKDRN DATEAPP
SERVICE ORDER No: GRID REF
GRID REF
GRID REF
GRID REF
GRID REF
OPERATION No:
OPERATION No:
OPERATION No:
OPERATION No:
FITTINGS
SCHEDULE OF FITTINGS
POINT NUMBER
CAD DATE:CAD DATE: CAD :CAD PATH:
ALL FITTINGS,MATERIALS,PIPES & JOINTS ARE TO BE INSTALLED INACCORDANCE WITH "LOT C2 STANDARD NEW MAINS AND CONNECTIONS(APRIL 2010)"
CTH
AM
ES
WA
TER
UTI
LITI
ES
LTD
(201
3)
A2
CUSTOMER
MATERIAL: LENGTH:
LINES AND LEVELS CONFIRMED DURING SITE MEETING HELD ON:-
NAME
SIGNATURE
COMPANY
SURVEYORCONTRACTOR
MATERIAL:
MATERIAL: DIA:DIA:
DIA:
LENGTH:LENGTH:
LENGTH:
THIS DRAWING IS BASED ON DEVELOPERS DRAWING No.:
THAMES WATER UTILITIESDEVELOPER SERVICES,CLEARWATER COURT,VASTERN ROAD,
TEL: 0800 009 3921
SITE LOCATION:
READING RG1 8DB
EMAIL: DEVELOPER.SERVICES@ THAMESWATER.CO.UK
DRAWN BY
SCALE:
SERVICE ORDER No:
SELF-LAY No:
REVISION:
SUB CASE No:
SCHEME No:
DESIGN BY
GRID REF:
WPA No:
1
S:\NEW Operations\CAD-CLEAN WATER 2015\50071411 BREWERS GARAGE,OXFORD RD,NUNEHAM COURTENAY,OXFORD OX44 9NY\WIP 50071411 BREWERS GARAGE,OXFORD RD,NUNEHAM COURTENAY,OXFORD OX44 9NY REV 2 0304/12/2015
1. ALL END WASHOUTS TO BE POSITIONED NO MORE THAN 1m PAST LAST DRAW OFF POINT.2. ALL FIRE HYDRANTS TO BE INSTALLED TO BS750(COPPER/GUNMETAL OUTLET ONLY)3. ALL FITTINGS & CHAMBERS WITH IN VERGES/SOFT GROUND MUST BE ADEQUATELY SUPPORTED BY 1sq m LAYER OF CONCRETE WITH A LAYER OF A393 MESH ON SUITABLE COMPACTED MATERIAL TO A DEPTH OF 150mm.4. ALL 'OPEN ENDED' PIPE WORK FOLLOWING ABANDONMENT OF MAINS,AND REMOVAL OF FITTINGS, (IN OFF-SITE CONDITIONS) MUST BE CAPPED TO ENSURE THERE IS NO INTRUSION OF EARTH ETC,WHICH COULD RESULT IN FUTURE GROUND SUBSIDENCE.5. ALL THRUST BLOCKS MUST BE DETERMINED ON SITE AND CALCULATIONS SUBJECT TO BEARING CAPACITY OF THE SOIL.
6.THE ACTUAL LINE AND DEPTH OF THE MAIN OR PIPE AS SHOWN IS SUBJECT TO VARIATION DUE TO OBSTRUCTIONS.7.IT IS THE CUSTOMER'S RESPONSIBILITY FOR INDICATING THE PLANNED
BOUNDARY LINES AND LEVELS OF ALL ROADS, PATHS, ETC., IN WHICHMAINS ARE TO BE LAID.
SHOULD ANY VARIATION TO THESE LINES OR LEVELS BE MADE WITHOUT THAMES WATER'S CONSENT AFTER THE MAINS HAVE BEEN LAID, THEN THE CUSTOMER WILL BE RESPONSIBLE FOR THE COST OF ANY SUBSEQUENT ALTERATIONS TO OUR APPARATUS.8.DISTANCES TAKE INTO ACCOUNT ANY TOPOGRAPIC VARIANCES.
9.PLEASE NOTE FITTINGS ARE NOT SHOWN TO SCALE.
10.ALL DUCTILE IRON PIPEWORK IS TO BE WRAPPED UNLESS OTHERWISE SPECIFIED.
11.MAINS WILL BE INSTALLED AT A UNIFORM DEPTH WITH THE MINIMUM NUMBER OF BENDS REQUIRED AND TO BE LAID IN A DIRECT ROUTE AS FAR AS PRACTICALLY POSSIBLE.
12.THE POSITION OF ANY BOUNDARY OR APPARATUS SHOWN ON THIS PLANIS GIVEN WITHOUT OBLIGATION AND WARRANTY AND ACCURACYCANNOT BE GUARANTEED. NO LIABILITY OF ANY KIND WHATSOEVER ISACCEPTED BY THAMES WATER FOR ANY ERROR OR OMISSION.
80310349 SU5521299326
NOMINAL TRENCH WIDTHS TO ALLOWFOR NO MORE THAN 100mm 'BED ANDSURROUND' TO THAMES WATER PIPE,UNLESS INSTRUCTED OTHERWISE BYTHAMES WATER
100mm
100mm
STANDARD PLASTIC PIPEWORK IS NOT PERMITTED FORUNDERGROUND WORK. A SUITABLE MATERIAL SUCH ASCOPPER PIPE (BSEN1057/1996 STANDARD), OR ANAPPROVED 'BARRIER PIPE' MUST BE USED FOR ALLUNDERGROUND PIPEWORK.
REVISED2 PB 1504
12
10.4 New mains in commercial area with an easementIn this example the new main would require an easement to protect our assets from any future changes to the site layout.
FH
WO
100mm Dia Blanking plateAir valve
No. of portsmanifold withService connectionService connection
Temporary washout
Fire Hydrant
Washout
provided by clientDuct to beProposed mainabandonedMain to beExisting main
Closed valveDouble spade valve
Meter
Proposed main indifferent phase
2
Valve
DAV
ENTR
Y R
OAD
94.9m
WB
ETL
El Sub Sta
Drain
Lake
Drain
FH
WO
WO
CONNECTION SPRINKLER
6"
150m
m
150mm
100m
m
150m
m
150mm
150mm
100mm
600m
m
100mm
450mm STRATEGIC
450mm STRATEGIC
450mm
DI
600mm
DI
150mm
100mm
FH
Keep
Cle
ar21
"THRUST BLOCK" (AS REQUIRED)
P 5
P 6
WO
WO
100m
m D
UC
TILE
IRO
N
WO
"THRUST BLOCK" (AS REQUIRED)
P 1
100mm DUCTILE IRON
100mm DUCTILE IRON
P 4
P 3WO"THRUST BLOCK"
(AS REQUIRED)
FH
P 2
MAIN ABANDONED ON
50020981
100mm DUCTILE IRON
100mm DUCTILE IRON
FH
1x32
mm
BAR
RIER
PIP
E
MANAG
EMEN
T SU
ITE
1x63
mm
SPR
INKL
ER
CONN
ECTI
ON
1x 25mm
BARRIER
PIPE FOR BIN STORE
1x 2
5mm
BA
RR
IER
PIP
EFO
R B
IN S
TOR
E
Posts
Tank
Tank
HENNEF
WILDMERE ROAD
DAV
ENTR
Y R
OAD
WAY
El Sub Sta
Industrial Estate
Wildmere
17
10
42
22
Hotel
6
11
3
5
3
WILDMERE ROAD
DAV
ENTR
Y R
OAD
94.9m
WB
ETL
Wildmere
Estate
Industrial
Tank
Tanks
El Sub Sta
CherwellRiver
Drain
Lake
Drain
Tanks
Tanks
WB
El Sub Sta
Silos
Drai
n
A 422
M 40
M 40
ROAD
JUGGLERS CLOSE
WILDMERE CL
WILDMERE
Sub Sta
El
El Sub Sta
Wildmere Industrial
Estate
Tank
1
El Sub StaTank
6
18a
5
WO
125m
m PRIV
ATE
90mm
6"6"
150mm
6" 450mm
150mm
6"
150mm
CONNECTION SPRINKLER
6"
450mm
150mm
90mm
450m
m S
TRAT
EGIC
180mm
600m
m
FH
WO
WO
6"
CONNECTION SPRINKLER
6"
150m
m
150mm
100m
m
150m
m
150mm
150mm
100mm
600m
m
100mm
450mm STRATEGIC
450mm STRATEGIC
450mm
DI
600mm DI
600mm
DI
600mm DI
150mm
100mm
FH
21
"THRUST BLOCK" (AS REQUIRED)
P 5
P 6
100m
m D
UC
TILE
IRO
N
"THRUST BLOCK" (AS REQUIRED)
P 1
100mm DUCTILE IRON
100mm DUCTILE IRON
P 4
P 3"THRUST BLOCK" (AS REQUIRED)
P 2
MAIN ABANDONED ON
50020981
100mm DUCTILE IRON
100mm DUCTILE IRON
1x32
mm
BAR
RIER
PIP
E
MANAG
EMEN
T SU
ITE
1x63
mm
SPR
INKL
ER
CONN
ECTI
ON
1x 25mm
BARRIER
PIPE FOR BIN STORE
1x 2
5mm
BA
RR
IER
PIP
EFO
R B
IN S
TOR
E
FOR INFORMATION1 RA
(NOT TO SCALE)SITE LOCATION PLAN
14
1507
ROUTE OF NEW MAIN & APPARATUS AS INDICATED
DEPTH OF COVER OF NEW MAIN:
(PLEASE TICK TO CONFIRM)
0.9 OTHER (PLEASE STATE)
DEPTH OF COVER AT CONNECTION POINT TO EXISTING MAIN (POINT 1)
0.9 OTHER (PLEASE STATE)
FULL 'AS LAID' DRAWINGPART ' AS LAID' S DRAWING
YESF/H's PERMANENTLY REINSTATED
CONTRACTOR SIGN OFF:
THAMES WATER SIGN OFF: DATE
AS LAID SIGN OFF
NO N/A
DATE
430
450
600
250
900
960
1255
1550
1720
Carriageway
Tele
com
ms
Wat
er
Gas
Cab
le T
V/c
omm
unic
atio
ns
Ele
c lv
Ele
c hv
Ele
c lv
alt
pos'
n
Dimensions in mm
Bou
ndar
y
1. THE LAYOUT OF MAINS IS GENERALLY IN ACCORDANCE WITH THE'REPORT OF JOINT COMMITTEE ON LOCATION OF UNDERGROUNDSERVICES' PUBLISHED BY THE INSTITUTION OF CIVIL ENGINEERS.
2. THE DIMENSIONS SHOWN REPRESENT THE PREFERRED ARRANGEMENTIN STRAIGHT ROUTES ON RESIDENTIAL ESTATES. VARIATIONS MAY BENECESSARY AT CURVES AND CHANGES OF GRADIENT.
3. THE SPACE ALLOCATED IS CONSIDERED TO BE THE ABSOLUTEMINIMUM AND IN CERTAIN CIRCUMSTANCES E.G. WHERE BOTH HV AND LVCABLES ARE LAID - THE LV CABLE WILL BE LAID IN THE ALTERNATIVE
4. WHERE SERVICES ARE TO BE CONNECTED TO MAINS A MINIMUMDISTANCE OF 2.0M IS REQUIRED BETWEEN THE BUILDING LINE AND THECENTRE LINE OF THE MAIN.
POSITION AND ADDITIONAL WIDTH MAY BE REQUIRED.
MAINS ROUTE
170
2000
295
600
295
690
270
430
350
260280
5. MINIMUM DISTANCE OF ANY WATER SERVICE TO ANY
COVER OF WATER MAINUP TO 12"(300mm) 900mm12"(300mm) TO 24"(600mm) 1100mm
24"(600mm) AND OVER 1200mm
SURFACE/FOUL WATER STRUCTURE IS 300mm.
TRENCH WIDTH
100mm 'BED AND SURROUND' TO MAIN
NOTES:
PREFERRED LAYOUT FOR MAINS IN A 2 METRES WIDE FOOTWAY:
NOMINAL TRENCH WIDTHS TO ALLOW FOR100mm
100mm
Point 1 All Flanged Tee(150x100mm)1 xFlanged adaptor(100x100mm)2 xAll Flanged Tee(100x100mm)1 xExtension piece(100x100mm)1 xFlanged bend(100mm)4 xValve+Chamber(100mm)1 xTemporary disinfection fittings1 xBlanking plate(100mm)1 xFlanged adaptor(100mm)2 xFlanged socket(100mm)1 xWashout+Chamber(80mm)1 x
DESCRIPTIONREV CHKDRN DATEAPP
SERVICE ORDER No: GRID REF
GRID REF
GRID REF
GRID REF
GRID REF
OPERATION No:
OPERATION No:
OPERATION No:
OPERATION No:
CAD PATH:
FITTINGS
SCHEDULE OF FITTINGS
POINT NUMBER
ALL FITTINGS,MATERIALS,PIPES & JOINTS ARE TO BE INSTALLED INACCORDANCE WITH "LOT C2 STANDARD NEW MAINS AND CONNECTIONS(APRIL 2010)"
CAD DATE:CAD DATE: CAD :
CTH
AM
ES
WA
TER
UTI
LITI
ES
LTD
(201
3)
A0
CUSTOMER
LINES AND LEVELS CONFIRMED DURING SITE MEETING HELD ON:-
NAME
SIGNATURECOMPANY
SURVEYORCONTRACTOR
THIS DRAWING IS BASED ON DEVELOPERS DRAWING No.:
THAMES WATER UTILITIESDEVELOPER SERVICES,CLEARWATER COURT,VASTERN ROAD,
TEL: 0845 850 2777READING RG1 8DB
EMAIL: DEVELOPER.SERVICES@ THAMESWATER.CO.UK
DRAWN BY
SCALE:
SERVICE ORDER No:
SELF-LAY No:
REVISION:
SUB CASE No:
SCHEME No:
DESIGN BY
GRID REF:
WPA No:
MATERIAL: LENGTH:
MATERIAL:
MATERIAL: DIA:DIA:
DIA:
LENGTH:LENGTH:
LENGTH:
SITE LOCATION:
MATERIAL: DIA: LENGTH:
BANBURY GATEWAY,WILDWERE ROAD,
BANBURY, OX16 3XS
100mm 478m
5001616280141494C908132-
446831, 2422451:500 @ A04
P.SABAN 15/07/2014
R.ARNAIZ 15/07/2014XREF 17007-2001 'C' REV 1
S:\CAD DRAWINGS-CLEAN WATER 2014\50016162 BANBURY GATEWAY,WILDMERE ROAD,BANBURY,OX16 3XS\Drawings\WIP 50016162 BANBURY GATEWAY,WILDMERE ROAD,BANBURY,OX16 3XS REV 3 22/09/2015 05
1. ALL END WASHOUTS TO BE POSITIONED NO MORE THAN 1m PAST LAST DRAW OFF POINT.2. ALL FIRE HYDRANTS TO BE INSTALLED TO BS750(COPPER/GUNMETAL OUTLET ONLY)3. ALL FITTINGS & CHAMBERS WITH IN VERGES/SOFT GROUND MUST BE ADEQUATELY SUPPORTED BY 1sq m LAYER OF CONCRETE WITH A LAYER OF A393 MESH ON SUITABLE COMPACTED MATERIAL TO A DEPTH OF 150mm.4. ALL 'OPEN ENDED' PIPE WORK FOLLOWING ABANDONMENT OF MAINS,AND REMOVAL OF FITTINGS, (IN OFF-SITE CONDITIONS) MUST BE CAPPED TO ENSURE THERE IS NO INTRUSION OF EARTH ETC,WHICH COULD RESULT IN FUTURE GROUND SUBSIDENCE.5. ALL THRUST BLOCKS MUST BE DETERMINED ON SITE AND CALCULATIONS SUBJECT TO BEARING CAPACITY OF THE SOIL.
6.THE ACTUAL LINE AND DEPTH OF THE MAIN OR PIPE AS SHOWN IS SUBJECT TO VARIATION DUE TO OBSTRUCTIONS.7.IT IS THE CUSTOMER'S RESPONSIBILITY FOR INDICATING THE PLANNED
BOUNDARY LINES AND LEVELS OF ALL ROADS, PATHS, ETC., IN WHICHMAINS ARE TO BE LAID.
SHOULD ANY VARIATION TO THESE LINES OR LEVELS BE MADE WITHOUT THAMES WATER'S CONSENT AFTER THE MAINS HAVE BEEN LAID, THEN THE CUSTOMER WILL BE RESPONSIBLE FOR THE COST OF ANY SUBSEQUENT ALTERATIONS TO OUR APPARATUS.8.DISTANCES TAKE INTO ACCOUNT ANY TOPOGRAPIC VARIANCES.
9.PLEASE NOTE FITTINGS ARE NOT SHOWN TO SCALE.
10.ALL DUCTILE IRON PIPEWORK IS TO BE WRAPPED UNLESS OTHERWISE SPECIFIED.11.MAINS WILL BE INSTALLED AT A UNIFORM DEPTH WITH THE MINIMUM NUMBER OF BENDS REQUIRED AND TO BE LAID IN A DIRECT ROUTE AS FAR AS PRACTICALLY POSSIBLE.
12.THE POSITION OF ANY BOUNDARY OR APPARATUS SHOWN ON THIS PLANIS GIVEN WITHOUT OBLIGATION AND WARRANTY AND ACCURACYCANNOT BE GUARANTEED. NO LIABILITY OF ANY KIND WHATSOEVER ISACCEPTED BY THAMES WATER FOR ANY ERROR OR OMISSION.
Point 2 Duckfoot bend flanged(80mm)1 xWashout+Chamber(80mm)1 x
Point 3 All Flanged Tee(150x100mm)1 xFlanged adaptor(100mm)2 xAll Flanged Tee(100x100mm)1 xExtension piece(100x100mm)1 xFlanged bend(100mm)4 xValve+Chamber(100mm)1 xTemporary disinfection fittings1 xBlanking plate(100mm)1 xFlanged adaptor(100mm)2 xFlanged socket(100mm)1 xWashout+Chamber(80mm)1 x
80141494 SP4683142245
Point 4 1 xWashout+Chamber(80mm)1 xDuckfoot bend flanged(80mm)
Point 5 All Flanged Tee(150x100mm)1 xFlanged adaptor(100mm)2 xAll Flanged Tee(100x100mm)1 xExtension piece(100x100mm)1 xFlanged bend(100mm)4 xValve+Chamber(100mm)1 xTemporary disinfection fittings1 xBlanking plate(100mm)1 xFlanged adaptor(100mm)2 xFlanged socket(100mm)1 xWashout+Chamber(80mm)1 x
Point 6 1 xWashout+Chamber(80mm)1 xDuckfoot bend flanged(80mm)
Point 1.0 - Point 1.1 1 METRES MP 100 SURFACE B
MAINS LENGTH:
Point 1.1 - Point 2.0 194 METRES MP 100 SURFACE LOPoint 3.0 - Point 3.1 1 METRES MP 100 SURFACE BPoint 3.1 - Point 3.2 7 METRES MP 100 SURFACE CPoint 3.2 - Point 3.3 1 METRES MP 100 SURFACE B
A = UNMADE GROUNDB = EXISTING FOOTPATHC = EXISTING ROAD
BF = BROWNFIELDPM = PART MADE FOOTPATH/ROADLO = LAY ONLY
D = DEVELOPMENT SITE
Point 3.3 - Point 3.4 2 METRES MP 100 SURFACE APoint 3.4 - Point 4.0 92 METRES MP 100 SURFACE LOPoint 5.0 - Point 5.1 30 METRES MP 100 SURFACE APoint 5.1 - Point 5.2 50 METRES MP 100 SURFACE CPoint 5.2 - Point 6.0 100 METRES MP 100 SURFACE LO
STANDARD PLASTIC PIPEWORK IS NOT PERMITTED FORUNDERGROUND WORK. A SUITABLE MATERIAL SUCH ASCOPPER PIPE (BSEN1057/1996 STANDARD), OR ANAPPROVED 'BARRIER PIPE' MUST BE USED FOR ALLUNDERGROUND PIPEWORK.
NOMINAL TRENCH WIDTHS TO ALLOWFOR NO MORE THAN 100mm 'BED ANDSURROUND' TO THAMES WATER PIPE,UNLESS INSTRUCTED OTHERWISE BYTHAMES WATER
100mm
100mm
REVISED MAIN AND SERVICES2 PB 15
2602
REVISED SERVICES3 PB 15
1004
REVISED SERVICES4 WK 15
2209